The EngineeringToolBox.com
As we donot have the pipe lay out drawing the Bend and valve Loss is taken approximately 3 mtrs
Staction lift 0 mts
Total Head
Specified Data
C = Hazen-Williams roughness constant New GI Pipe 120
Q = volume flow (gal/min) UK Gal/Min 1408.44
dh = inside or hydraulic diameter (inches) 15.75
The EngineeringToolBox.com
As we donot have the pipe lay out drawing the Bend and valve Loss is taken approximately 10 mtrs
Hence. A total head of 113 mtrs as per your calculation is more than adequate.