Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Unit 11 Project Scheduling and PERTCPM
Structure
11.1. Introduction
11.2. Basic difference between PERT and CPM
11.2.1 PERT
11.2.2 CPM
11.2.3 Project scheduling by PERTCPM
11.3. PERT / CPM network components and precedence relationship
11.3.1 Critical Path Calculations
11.3.2 Determination of the Critical Path
11.3.3 Determination of Floats
11.4. Project Management – PERT
11.5. Summary
Terminal Questions
Answers to SAQs and TQs
11.1. Introduction
A project such as construction of a bridge, highway, power plant, repair and maintenance of an oil
refinery or an air plane design, development and marketing a new product, research and
development etc., may be defined as a collection of interrelated activities (or tasks) which must
be completed in a specified time according to a specified sequence and require resources such
as personnel, money, materials, facilities etc.
The growing complexities of today’s projects had demanded more systematic and more effective
planning techniques with the objective of optimizing the efficiency of executing the project.
Efficiency here implies effecting the utmost reduction in the time required to complete the project
while accounting for the economic feasibility of using available resources.
Project management has evolved as a new field with the development of two analytic techniques
for planning, scheduling and controlling projects. These are the Critical Path Method (CPM) and
the Project Evaluation and Review Technique (PERT). PERT and CPM are basically time
oriented methods in the sense that they both lead to the determination of a time schedule.
Sikkim Manipal University 182
Operations Research Unit 11
Learning Objectives:
After studying this unit, you should be able to understand the following
1. What is a project?
2. What is project management?
3. Application of PERT / CPM method to network analysis
11.2. Basic difference between PERT and CPM
Though there are no essential differences between PERT and CPM as both of them share in
common the determination of a critical path and are based on the network representation of
activities and their scheduling that determines the most critical activities to be controlled so as to
meet the completion date of the project.
11.2.1 PERT
1. Since PERT was developed in connection with an R and D work, therefore it had to cope with
the uncertainties which are associated with R and D activities. In PERT, total project duration
is regarded as a random variable and therefore associated probabilities are calculated so as
to characterise it.
2. It is an eventoriented network because in the analysis of network emphasis is given an important
stages of completion of task rather than the activities required to be performed to reach to a
particular event or task.
3. PERT is normally used for projects involving activities of nonrepetitive nature in which time
estimates are uncertain.
4. It helps in pinpointing critical areas in a project so that necessary adjustment can be made to
meet the scheduled completion date of the project.
11.2.2 CPM
1. Since CPM was developed in connection with a construction project which consisted of
routine tasks whose resources requirement and duration was known with certainty, therefore
it is basically deterministic.
2. CPM is suitable for establishing a tradeoff for optimum balancing between schedule time and
cost of the project.
3. CPM is used for projects involving activities of repetitive nature.
Sikkim Manipal University 183
Operations Research Unit 11
11.2.3 Project scheduling by PERTCPM
It consists of three basic phases: planning, scheduling and controlling.
1. Project Planning: The various steps involved during this phase are given below:
i) Identify various activities (task or work elements) to be performed in the project.
ii) Determining requirement of resources such as men, materials, machines etc., for carrying
out activities listed above.
iii) Estimating costs and times for various activities.
iv) Specifying the interrelationship among various activities.
v) Developing a network diagram showing the sequential interrelationships between the
various activities.
2. Scheduling: Once the planning phase is over, scheduling of the project, is when each of the
activities required to be performed, is taken up. The various steps involved during this phase
are listed below:
1. Estimating the durations of activities, taking into considerations the resources required for
these execution in most economic manner.
2. Based on these time estimates, preparing a time chart showing the start and finish times
for each activity, and hence calculation of total project duration by applying network
analysis techniques such as forward (backward) pass and floats calculation; identifying
the critical path; carrying out resource smoothing (or levelling) exercise for critical or
scarce resources including recosting of the schedule taking into account resource
constraints.
Self Assessment Questions 1
Verify whether the following statements are True or False
1. Project consists of interrelated activities.
2. Project activities are to be completed in a specified time according to specified sequence.
3. PERT and CPM identifies non critical activities.
4. PERT is activity oriented network.
Sikkim Manipal University 184
Operations Research Unit 11
5. CPM is used for projects that are repetitive in nature.
a) Events: An event represents a point in time that signifies the completion of some activities
and the beginning of new ones. The beginning and end points of an activity are thus
described by 2 events usually known as the Tail and head events. Events are commonly
represented by circles (nodes) in the network diagram. They do not consume time and
Resource
b) Activities: Activities of the network represent project operations or task to be conducted. An
arrow is commonly used to represent an activity, with its head indicating the direction of
progress in the project. Activities originating from a certain event cannot start until the
activities terminating at the same event have been completed. They consume time and
Resource.
Events in the network diagram are identified by numbers. Numbers are given to events such that
arrow head number must be greater than arrow tail number.
Activity
i J
Starting event Completion Event
Fig. 9.1
Sikkim Manipal University 185
Operations Research Unit 11
Figure 9.2 shows another example, where activities (1, 3) and (2, 3) must be completed before
activity (3, 4) can start.
1
3 4
2
Fig. 9.2
The rules for constructing the arrow diagram are as follows:
1. Each activity is represented by one and only one arrow in the network.
2. No two activities can be identified by the same head and tail events.
3. To ensure the correct precedence relationship in the arrow diagram, the following questions
must be answered as every activity is added to the network:
a) What activities must be completed immediately before these activity can start ?
b) What activities must follow this activity ?
c) What activity must occur concurrently with this activity ?
This rule is selfexplanatory. It actually allows for checking (and rechecking) the precedence
relationships as one progresses in the development of the network.
Example 1: Construct the arrow diagram comprising activities A, B, C …….. and L such that the
following relationships are satisfied:
1) A, B and C the first activities of the project, can start simultaneously.
2) A and B precede D.
3) B precedes E, F and H.
4) F and C precede G.
5) E and H precede I and J.
6) C, D, F and J precede K.
7) K precedes L.
8) I, G and L are the terminal activities of the project.
Sikkim Manipal University 186
Operations Research Unit 11
Fig. 9.3
The dummy activities D1 and D2 are used (dotted lines) to establish correct precedence
relationships. D3 is used to identify activities E and H with unique end events. The events of the
project are numbered such that their ascending order indicates the direction of the progress in the
project.
Note: A dummy activity in a project network analysis has zero duration.
11.3.1. Critical Path Calculations
The application of PERT/CPM should ultimately yield a schedule specifying the start and
completion time of each activity. The arrow diagram is the first step towards achieving that goal.
The start and completion times are calculated directly on the arrow diagrams using simple
arithmetic. The end result is to classify the activities as critical or non critical. An activity is said
to be critical if a delay in the start of the course makes a delay in the completion time of the entire
project. A noncritical activity is such that the time between its earliest start and its latest
completion time is longer than its actual duration. A noncritical activity is said to have a slack or
float time.
11.3.2. Determination of the Critical Path
A critical path defines a chain of critical activities that connects the start and end events of the
arrow diagram. In other words, the critical path identifies all the critical activities of the project.
The critical path calculations include two phases. The first phase is called the Forward Pass
where all calculations begin from the start node and move to the end node. At each node a
number is computed representing the earliest occurrence time of the corresponding event. These
Sikkim Manipal University 187
Operations Research Unit 11
numbers are shown in squares . In forward pass we note the number of heads joining the event.
We take the maximum earliest timing through these heads.The second phase called the
Backwards Pass, begins calculations from the “end” node and moves to the “start” node. The
number computed at each node is shown in a triangle D near end point which represent the latest
occurrence time of the corresponding event. Consider the forward pass In backward pass we see
the number of tails and take minimum value through these tails.
With the computation of all ESj, the forward pass calculations are completed. The backward pass
starts from the “end” event. The objective of this phase to calculate LCi, the latest completion
time for all the activities coming into the event i. Thus if i = n is the end event LCn = ESn initiates
the backward pass.
In general for any node i, LCi = min {LCjDij} for all defined activities are calculated, which ends
the calculation of backward pass.
The critical path activities can now be identified by using the results of the forward and backward
passes. An activity (i, j) lies on the critical path if it satisfies the following conditions.
A) ESI = LCi
B) ESJ = LCJ
C) ESJESI = LCJLCI = DiJ
These conditions actually indicate that there is no float or slack time between the earliest stand
and the latest start of the activity. Thus the activity must critical. In the arrow diagram these are
characterised by numbers in and D are the same at each of the head and tail events and the
difference between the number in (or D) at the head event and the number in (or D) at the tail
event in equal to the duration of the Activity.
Thus we will get a critical path, which is chain of connected activities, which spans the network
form start to end.
Sikkim Manipal University 188
Operations Research Unit 11
Example 2: Consider a network which stands from node 1 and terminate at node 6, the time
required to perform each activity is indicated on the arrows.
Fig. 9.4
Let us start with forward pass with ESi = 0.
Since there is only one incoming activity (1, 2) to event 2 with D12 = 3.
ES2 = ES1+ DS2 = 0+3=3.
Let us consider the end 3, since there only one incoming activity (2, 3) to event 3, with D23 = 3.
ES3 = ES2+ D23 = 3+3 = 6.
To obtain ES4, since there are two activities A (3, 4) and (2,4 ) to the event 4 with D24 = 2 and D34
= 0.
ES4= maxi=2, 3 { ESi + De4}
= max { ES2 +D24, ES3 + D34}
= max {3+2, 6+0} = 6
Similary ES5 = 13 and ES6 = 19
Which completed first phase.
In the second phase we have
LC6= 19 = ES6
LC5 = 196 = 13
LC4= minJ = 5, 6 {LCJ – D4J} = 6
LC3 = 6, LC2 = 3 and LC1 = 0
\ activities (1, 2), (2, 3) (3, 4) (4, 5) (5, 6) are critical and (2, 4) (4, 6), (3, 6), are noncritical.
Sikkim Manipal University 189
Operations Research Unit 11
Thus the activities (1, 2) (2, 3 ) (3, 4) (4, 5) and (5, 6) define the critical path which is the shortest
possible time to complete the project.
11.3.3. Determination of Floats
Following the determination of the critical path, the floats for the noncritical activities must be
computed. Note that for the critical activities this float is zero. Before showing how floats are
determined, it is necessary to define two new times that are associated with each activity. There
are Latest Start (LS) and the Earliest Completion (EC) times, which are defined activity (i, J) by
LSeJ= LCJ – DiJ
and ECeJ = ESi + DiJ
There are two important types of floats namely, Total Float (TF) and Free Float (FF). The total
float TFiJ for activity (i, J) is the difference between the maximum time available to perform the
activity (= LCJ – ESi) and its duration (= DiJ )
That is,
The free float is defined by assuming that all the activities start as early as possible. In this case
FFiJ for activity (i, J) is the excess of available time (= ESi – ESi) over its deviation (= DiJ );
that is, FFiJ = ESi – ESi = DiJ .
Note that only for a critical activity must have zero total float. The free float must also be zero
when the total float is zero. The converse is not true, that is in the sense that a noncritical
activity may have zero free floats.
Let us consider the example taken before the critical path calculations together with the floats for
the noncritical activities can be summarized in the convenient form shown in the following table:
Sikkim Manipal University 190
Operations Research Unit 11
Earliest Latest
Activit Table Free
Duration Start Completio Start Completio
y Float Float
DiJ ES n LS n
(i J) i ij TFiJ FFiJ
ECiJ DLCJ
(1, 2) 3 0 3 0 3 0* 0
(2, 3) 3 3 6 3 6 0* 0
(2, 4) 2 3 5 4 6 1 1
(3, 4) 0 6 6 6 6 0* 0
(3, 5) 3 6 9 10 13 4 4
(3, 6) 2 6 8 17 19 11 11
(4, 5) 7 6 13 6 13 0* 0
(4, 6) 5 6 11 14 19 8 8
(5, 6) 6 13 19 13 19 0* 0
Note: Total float = ESij = LFij ESij
Free float = Total float Head slack
* Critical activity *
Example 3: A project consists of a series of tasks A, B, C, – D, – E, F, G, H, I with the following
relationships. (W < X,Y means X and Y cannot starts until W is completed, X,Y < W means W
cannot start until both X and Y are completed). With this notation construct the network diagram
having the following constraints A < D, E; B, D < F; C < G, B < H; F,G < I.
Find also the minimum time of completion of the project, the critical path, and the total floats of
each task, when the time (in days) of completion of each task is as follows:
Task: A B C D E F G H I
Time: 23 8 20 16 24 18 19 4 10
Fig. 9.5
Sikkim Manipal University 191
Operations Research Unit 11
Self Assessment Questions 2
Fill in the blanks
1. Events do not consume ________ and _________.
2. Arrow’s head number is _________ than its tail number.
3. Dummy activity in network is introduced t keep proper _________ relationship.
4. Critical path calculation include both _________ and _________.
11.4 Project Management – PERT
Probability and Cost Consideration in Project Scheduling
The analysis in CPM does not take into the case where time estimates for the different activities
are probabilistic. Also it does not consider explicitly the cost of schedules. Here we will consider
both probability and cost aspects in project scheduling.
Probability considerations are incorporated in project scheduling by assuming that the time
estimate for each activity is based on 3 different values. They are –
a = The optimistsic time, which will be required if the execution of the project goes extremely
well.
b = The pessimistic time, which will be required if everything goes bad.
Sikkim Manipal University 192
Operations Research Unit 11
m = The most likely time, which will be required if execution is normal.
a + b
The most likely estimate m need not coincide with midpoint of a and b. Then the
2
a + b
expected duration of each activity D can be obtained as the mean of and 2 m. i.e.
2
a + b
+ 2 m
2 a + b + 4 m
D= = .
3 6
This estimate can be used to study the single estimate D in the critical path calculation.
The variance of each activity denoted by V is defined by
2
b - a ö
variance V = æç ÷ .
è 6 ø
The earliest expected times for the node i denoted by E(mi) for each node i is obtained by
taking the sum of expected times of all activities leading to the node i, when more than one
activity leads to a node i, then greatest of all E(mi) is chosen . Let mi be the earliest occurrence
time of the event i, we can consider mi as a random variable. Assuming that all activities of the
network are statistical independent, we can calculate the mean and the variance of the mi as
follows E{mi } = ESI and Var{mi } = å V k . Where K defines the activities along the largest path
k
leading to i.
For the latest expected time, we consider the last node. Now for each path move backwords,
is defined.
Note: The probability distribution of times for completing an event can be approximated by the
normal distribution due to central limit theorem.
Since mi represents the earliest occurrence time, event will meet a certain schedule time STi
(specified by an analyst) with probability
æ m - E ( m ) ST - E ( m ) ö
Pr (mi £ STi) = Pr ç i i £ i i ÷
ç ÷
è V ( mi ) V ( mi ) ø
= Pr (Z £ Ki)
Sikkim Manipal University 193
Operations Research Unit 11
ST i - E ( mi )
where Z ~N(01) and Ki = . It is common practice to compute the probability that event i
V ( mi )
will occur no later than its LCe such probability will then represent the chance that the succeeding
events will occur within the (ESe, LCe) duration.
Example 4: A project is represented by the network shown below and has the following data.
Task A B C D E F G H I
Optimistic Time 5 18 26 16 15 6 7 7 3
Pessimistic Time 10 22 40 20 25 12 12 9 5
Most Likely Time 8 20 33 18 20 9 10 8 4
Determine the following:
a) Expected task time and their variance.
b) The earliest and latest expected times to reach each event.
c) The critical path.
Fig. 9.6
d) The probability of an event occurring at the proposed completion data if the original contract
time of completing the project is 41.5 weeks.
e) The duration of the project that will have 96% channel of being completed.
Solution:
a) Using the formula we can calculate expected activity times and variance in the following table
2
D = 1 ( a + b + 4 m ) V = æç b - a ö÷
6 è 6 ø
Sikkim Manipal University 194
Operations Research Unit 11
b)
Activity a B m v
12 5 10 8 78 0.696
13 18 22 20 2000 0.444
14 26 40 33 330 5.429
25 16 20 18 180 0.443
26 15 25 20 200 2.780
36 6 12 9 90 1.000
47 7 12 10 98 0.694
57 7 9 8 80 0.111
67 3 5 4 40 0.111
Forward Pass:
E1 = 0 E2 = 7.8 E 3 = 20 E4 = 33 E5 = 258 E6 = 29 E7 = 42.8
Backward Pass:
L7 = 42.8 L6 = 38.8 L5 = 34.8 L4 = 33.0 L3 = 29.8 L2 = 16.8 L1 = 0.
The Evalues and Lvalues are shown in Fig.
Fig. 9.7
c) The critical path is shown by thick line in fig. The critical path is 147 and the earliest
completion time for the project is 42.8 weeks.
d) The last event 7 will occur only after 42.8 weeks. For this we require only the duration of
critical activities. This will help us in calculating the standard duration of the last event.
Expected length of critical path = 33+9.8 = 42.8
Variance of article path length = 5.429+0.694 = 6.123
Sikkim Manipal University 195
Operations Research Unit 11
Probability of meeting the schedule time is given by Pi (Z £ Ki) =
Pi (Z – 0.52) = 0.30 (From normal distribution table)
Thus the probability that the project can be completed in less than or equal to 41.5 weeks is
0.30. In other words probably that the project will get delayed beyond 41.5 weeks is 0.70.
e) Given that P (Z £ Ki) = 0.95. But Z0.9S = 1.6 u, from normal distribution table. Then 1.6 u =
ST i - E ( m i ) ST i - 42 . 8
is 1 . 6 u = or
V ( m i ) 2 . 47
Sji = 1.64´2.47+42.8 = 46.85 weeks.
Self Assessment Questions 3
I) True or False
1) In a project network, a sequence of activities may form a loop.
2) A critical activity must have its total and free floats equal to zero.
3) A noncritical activity cannot have zero total float.
4) The critical path of project network represents the minimum duration needed to complete
the network.
5) A network may include more than one critical path.
11.5. Summary
Critical Path computations are quite simple, yet they provide valuable information that
simplifies the scheduling of complex projects. The result is that PERTCPM techniques
enjoy tremendous popularity among practitioners in the field. The usefulness of the
techniques is further enhanced by the availability of specialized computer systems for
executing, analyzing and controlling network projects.
Terminal Questions
1. Write down the basic difference between PERT and CPM.
2. Explain Project Management (PERT)
3. A project has 10 activities. The following table shows the information about the activities.
Sikkim Manipal University 196
Operations Research Unit 11
E A 3
F C 3
G D 5
H B, D, E 5
I H 2
J I, G, F 3
a. Draw the network
b. Find the project duration
c. Identify the CPM
d. Prepare the schedule
4. A small project consisting of eight activities has the following characteristics:
TIME ESTIMATES (IN WEEKS)
Activity Preceding activity Most optimistic Most likely time Most pessimistic
time (a) (m) time (b)
A None 2 4 12
B None 10 12 26
C A 8 9 10
D A 10 15 20
E A 7 7.5 11
F B, C 9 9 9
G D 3 3.5 7
H E, F, G 5 5 5
a. Draw the PERT network for the project.
b. Determine the critical path.
c. If a 30week deadline is imposed, what is the probability that the project will be finished within
the time limit?
d. If the project manager wants to be 99% sure that the project is completed on this schedule
date, how many weeks before that date should he start the project work?
Answers To Self Assessment Questions
Self Assessment Questions 1
1. True 2. True 3. True 4. False 5. True
Self Assessment Questions 2
1. Time, resource
2. Greater than
Sikkim Manipal University 197
Operations Research Unit 11
3. Precedence
4. Forward pass & backward pass
Self Assessment Questions 3
1) False 2) True 3) True 4) True 5) False
Answer for Terminal Questions
1. Refer to Section 11.2
2. Refer to Section 11.4
3. b) 20 weeks c) A – D – H – I J
4. b) A – D – G – H c) 0.6591 d) 34.7 weeks
Sikkim Manipal University 198