Sei sulla pagina 1di 2

Action Plan [Project Name]

SAC Manual Action Plan Project Manager: Krista McBride Last Updated:11/01/10

Task Baseline Actual Baseline Actual Baseline Actual Labor


ID Task Name Start Start Finish Finish Labor Labor Remaining
1 Research 11-Oct 18-Oct 4-Nov 15
2 Evaluate time frame 30-Oct 31-Oct 5
3 Prepare Litature Review 2-Nov 14-Nov 20
4 Evaluate manual designs 15-Nov 19-Nov 10
5 Speak with stakeholders for their opinions 22-Nov 24-Nov 5
6 Development of strategic goals 24-Nov 28-Nov 3
7 Internal assessment 24-Nov 28-Nov 3
8 Create a workable outline 24-Nov 28-Nov 2
9 Determine section titles 29-Nov 3-Dec 2
10 Design the overall layout
11 Explore cover designs
12 Development of formulation for each strategic goal
13 Create the first draft
14 Applying motivational elements
15 Provide a document that provides future additions to the manual
16 Create a table of contents
17 Revise the rough draft
18 Make alterations to the workable outline (if needed)
19 Revise the finished rough draft and prepare for implementation
20 Show final product to stakeholders
21 Pass onto the next head of the SAC

Fast Foundation for Project Management - Action Plan


1 of 2
Reference The Fast Forward MBA in Project Management, Chapters 6-8
Action Plan [Project Name]

SAC Manual Action Plan


Last Updated:11/01/10

Task
ID Task Name Comments
1 Research
2 Evaluate time frame
3 Prepare Litature Review
4 Evaluate manual designs
5 Speak with stakeholders for their opinions
6 Development of strategic goals
7 Internal assessment
8 Create a workable outline
9 Determine section titles
10 Design the overall layout
11 Explore cover designs
12 Development of formulation for each strategic goal
13 Create the first draft
14 Applying motivational elements
15 Provide a document that provides future additions to the manual
16 Create a table of contents
17 Revise the rough draft
18 Make alterations to the workable outline (if needed)
19 Revise the finished rough draft and prepare for implementation
20 Show final product to stakeholders
21 Pass onto the next head of the SAC

Fast Foundation for Project Management - Action Plan


2 of 2
Reference The Fast Forward MBA in Project Management, Chapters 6-8