Factory Rehabilitation Schedule

Manpower
Required
Apr-11 May-11
Responsible Days
Sr # Work To Do Date From Date To
Head Unskill- Required
Skilled 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
ed

1 Machinery Layout Fahim 1 1 26-Apr-11 26-Apr-11

Estimate Of Electrical / Wiring


2 Fahim 1 2 27-Apr-11 28-Apr-11
work

Estimate Of Labour
Accommodation Building In New
3 Fahim 2 28-Apr-11 29-Apr-11
Plot And Approval From Head
Office

4 Arrival Of Machines From IIL Ijaz-Ul-Haq 1 30-Apr-11 30-Apr-11

Unloading / Placing Of Machines


5 Fahim 2 5 7 2-May-11 8-May-11
At Factory

Construction Of Building For


6 Fahim 25 2-May-11 26-May-11
Labour

7 Power Connection Of Machines Fahim 2 2 5 10-May-11 14-May-11

Coils & Ba'rs For Testing Of CNC


8 Ijaz-Ul-Haq 5 9-May-11 13-May-11
Machine

Fixing Problems Of CNC


9 Asif-Fahim 2 15 13-May-11 27-May-11
Machines

Construction Of Wall Of CNC


10 Fahim 5 27-May-11 31-May-11
Machine Hall (East Side)