Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
This model ('the Model') has been built to assess the economic cost of the selected technologies
on a case by case basis. The purpose of this modelling is to provide estimates of the
relative cost of electricity generation technologies under different scenarios and assumptions to
inform policy analysis. The outputs do not represent a government view on the relative costs
of the technologies. The modelling is based on levelised costs and is not intended to predict
specific private sector investment decisions or to rank different generation technologies
In regard to nuclear decommissioning and waste disposal details of the work programme and
timetable to establish arrangements for dealing with the costs of decommissioning and waste
from nuclear new build will be published by the time of the White Paper. The Government has not
taken a position on how these arrangements should be designed. For the purposes of the Model
assumptions have been made which in no way prejudice the outcome of work to determine the
arrangements for dealing with the costs of decommissioning and waste from nuclear new build.
The Model has been constructed for a specific purpose and is not intended
for distribution to third parties. Third parties who obtain copies of the Model
should be aware of the following:
· the Model may not be suitable for purposes, other than the specific purpose
for which it was designed, and the interests of third parties may not have
been anticipated;
· the Model was not intended for use by third parties and may not be designed
so that it can be readily operated in a correct manner by such parties;
· material events may have occurred since completion which are not reflected in the Model;
· whilst the Model has been tested, this may not provide an appropriate degree of assurance
for all possible uses of the Model
Input_Main
Input_Main
Main Input Sheet Coal
Main Input Sheet Coal
[General & Plant Specific]
- Input Data - [General & Plant Specific]
Index Operation
Index Operation
Graph data
Graph data
Plant Performance
Power Revenue
Opex: Volume Related
Pre-development &
Pre-development &
construction
construction Margins
- Calculation Section -
Decommissioning
Decommissioning Finance
Finance
Interest During Construction
Interest During Construction
Waste
Waste
Levelised Cost
Levelised Cost
Disclaimer
Disclaimer
Summary
Plant Design Pulverised Fuel (ASC) with FGD Plant Total Capacity (MW) 500
Kind First of a kind Net Efficiency (HHV) (Average during operation) 43.4%
Assumptions Data Availability (Average) 90.0%
Construction Period (years) 4
Plant Life (years) 50
Capital Cost (£/kW) 918
Construction Commences 1-Jan-2011 O&M Cost (£/kW) 17
Operation Commences 1-Jan-2015 Decommissioning Fund (£m) PV 0
Avge Annual Decomm. Contribution (£m) Over Operational Life 0.0
Avge Annual Waste Contribution (£m) Over 40 Years 0.0
Master Check OK 0
Cost of Generation
LC (£/MWh)
Type Design FOAK NOAK
Levelised Cost
Nuclear PWR 1 37.51 31.24
Coal Pulverised Fuel (ASC) with FGD 26.14 22.20
Coal Pulverised Fuel (ASC) with FGD with CCS 40.78 36.92
Coal IGCC 29.37 25.41
Coal IGCC with CCS 44.77 40.93
Gas CCGT 34.57 34.26
Gas CCGT with CCS 47.93 47.63
Wind Onshore Wind (80MW) 55.15 54.93
Wind Offshore Wind (100MW) 83.15 82.93
Retrofit Coal
Pulverised Fuel (ASC) with Retrofit FGD with CCS 35.69 31.36
Model Check: OK
Coal
All Values in £m Unless Otherwise Indicated / Yearly Basis
Annual Period Starting
Annual Period Ending
Operating Year No
Operation Year Flag
Operational Flag
Proportion in Year Operation
LEVELISED COSTS
Power Production Total
Power Output, Net (TWh) 197
Operating Costs
Total Fuel Costs 1,564
Fixed O&M Cost 425
Variable O&M Costs 217
Emissions Costs 0
Additional Insurance Costs 0
Additional Security Costs 0
Waste Fund 0
Decommissioning Fund 0
Capital Costs
Predevelopment Costs 0
Construction Costs 2,633
Total
Levelised Cost £/MWh
Fuel 7.9
Fuel Delivery 1.6
Fixed O&M 2.2
Variable O&M 1.1
Emissions Costs 0.0
Additional Insurance Costs 0.0
Additional Security Costs 0.0
Waste Fund 0.0
Decommissioning 0.0
Predevelopment Costs 0.0
Construction Costs 13.3
Storage (pertaining to Carbon Sequestration) 0.0
Model Check: OK
Coal
All Values in £m Unless Otherwise Indicated / Yearly Basis
Annual Period Starting
Annual Period Ending
Operating Year No
Operation Year Flag
Operational Flag
Proportion in Year Operation
Graphs
80.00
4,000
70.00 3,500
60.00 3,000
50.00 2,500
GWh
40.00 2,000
30.00 1,500
1,000
20.00
500
10.00
0
0.00 2008 2012 2016 2020 2024 2028 2032 2036 2040 2044 2048 2052 2056 2060 2064 2068 2072 2076 208
Pulverised Fuel (ASC) with FGD with CCS CCGT with CCS 2006 2010 2014 2018 2022 2026 2030 2034 2038 2042 2046 2050 2054 2058 2062 2066 2070 2074 2078
PWR 1 IGCC with CCS Offshore Wind (100MW)
Gross Energy Generated Fuel Consumption (GWht), Net
Column AA Column AD (before auxiliary deductions)
70.0% 1 0.9
1 0.8
60.0%
1 0.7
50.0% 1 0.6
0 0.5
40.0%
£m
£m
%
0 0.4
30.0%
0 0.3
20.0% 0 0.2
0 0.1
10.0%
0 0
0.0% 2009 2015 2021 2027 2033 2039 2045 2051 2057 2063 2069 2075 2081 2087
2008 2012 2016 2020 2024 2028 2032 2036 2040 2044 2048 2052 2056 2060 2064 2068 2072 2076 2080 2006 2012 2018 2024 2030 2036 2042 2048 2054 2060 2066 2072 2078 2084 2090
2006 2010 2014 2018 2022 2026 2030 2034 2038 2042 2046 2050 2054 2058 2062 2066 2070 2074 2078
Decommissioning Fund Decommissioning Waste Contributions
Power / Fuel Margin (%) - Non- Operating Margin (%) - Non- Contributions
Escalated Escalated
0.9
0.8
0.7
0.6
0.5
£m
0.4
0.3
0.2
0.1
0
2087
84 2090
Graphs
Model Check: OK
Pulverised Fuel Coal
LC (£/MWh)
Sensitivity Comment SensitivityType SensitivityValue FOAK NOAK
Model Check: OK
Pulverised Fuel Coal
LC (£/MWh)
Sensitivity Comment SensitivityType SensitivityValue FOAK
General Information
Project Base Data (I)
Project Developer DTI
Project Name Pulverised Fuel Coal
Financial Model Version Version 2006
Financial Model Type New Build Evaluation Model
Market Price Forecasts Based on (source) DTI projections April 2006
Calculation Model Manual
Reactor Design
Pulverised Fuel (ASC) with FGD
Kind
First of a kind
Assumptions
Data
Conversion Factors
Summary Sheet Unit 1,000
Timing
Key Dates / Time Periods Unit
Financial close 1-Jan-2007
Financial close (to closest year) 1-Jan-2007
Prelicensing Period (months) 0 (years) 0 (days) 0
Site Specific Licensing Period (months) 24 (years) 2 (days) 730
Public Enquiry Period (months) 24 (years) 2 (days) 730
Pre-development Period - Subtotal (months) 48 (years) 4
Pre-development Period (NOAK Adjustment) (months) 0 (years) 0
Total Pre-development Period (including NOAK) (months) 48 (years) 4.0
Calculation Flags
Proportion of Period in Pre-development 0% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0%
Pre-development Year Flag - 1 2 3 4 - - - - - - - -
Pre-development Days in Period 0 364 366 365 365 1 0 0 0 0 0 0 0
Pre-development Phase Flag 0 1 1 1 1 0 0 0 0 0 0 0 0
Proportion of Period in Construction 0% 0% 0% 0% 0% 100% 100% 100% 100% 0% 0% 0% 0%
Construction Period Year Flag - - - - - 1 2 3 4 - - - -
Construction Days in Period 0 0 0 0 0 364 366 365 365 1 0 0 0
Construction Phase Flag 0 0 0 0 0 1 1 1 1 0 0 0 0
Construction Start Flag 0 0 0 0 0 1 0 0 0 0 0 0 0
Project Finance Period Year Flag - - - - - 1 2 3 4 5 6 - -
Project Finance Phase Flag 0 0 0 0 0 1 1 1 1 1 1 0 0
Proportion of Period in Operation 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 100% 100% 100%
Operation Year Flag - - - - - - - - - 1 2 3 4
Operation Days in Period 0 0 0 0 0 0 0 0 0 364 366 365 365
Operational Phase Flag 0 0 0 0 0 0 0 0 0 1 1 1 1
Start of Operational Phase Flag 0 0 0 0 0 0 0 0 0 1 0 0 0
End of Operational Phase Flag 0 0 0 0 0 0 0 0 0 0 0 0 0
Construction / Operation Phase Flag 0 0 0 0 0 1 1 1 1 1 1 1 1
Proportion of Period in Waste Storage 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Waste Disposal Spend Flag 0 0 0 0 0 0 0 0 0 0 0 0 0
Waste Disposal Phase Flag 0 0 0 0 0 0 0 0 0 0 0 0 0
Proportion of Period in Decommissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Decommissioning Days in Period 0 0 0 0 0 0 0 0 0 0 0 0 0
Decommissioning Phase Flag 0 0 0 0 0 0 0 0 0 0 0 0 0
Decommissioning Year Flag 0 0 0 0 0 0 0 0 0 0 0 0 0
Plant Data II
Gross to Net efficiency factor (HHV/LHV) 1.05
Output Degradation 100%
Heat Rate Degradation 100%
Run In Period (years) 2
Availability (first X years) 90%
Availability (thereafter) 90%
Pre-development Costs
Pre-development Cost (£'000) Data Tax ded'ble
Prelicensing - cost 0 0%
Technical including design selection 0 0%
Regulatory including licensing and EIA 0 50%
Regulatory - public enquiry - cost 0 50% Non-sensitised
Total Pre-development Costs 0 0
Construction Costs
Construction Cost Data
Capital cost (£/kW) 918
Capital Cost (£'000) 459,000
Infrastructure Cost (£/kW) 0
Waste Disposal Cost (£/kW) 0
Land - acquisition cost 0
Working Capital 31-Dec-2006 31-Dec-2007 31-Dec-2008 31-Dec-2009 31-Dec-2010 31-Dec-2011 31-Dec-2012 31-Dec-2013 31-Dec-2014 31-Dec-2015 31-Dec-2016 31-Dec-2017 31-Dec-2018
Circulation Time of Accounts Receivable (Days) 30 30 30 30 30 30 30 30 30 30 30 30 30
Circulation Time of Accounts & Bills Payable (Days) 30 30 30 30 30 30 30 30 30 30 30 30 30
Contract Data
Contract Period / Years 0.0
Minimum Take-or-Pay Contract Amount (million tonnes / therms) 0.0
Max Contract Amount (million tonnes /therms) 0.0
Contract Price (£/tonne or p/therm) 0.0
Contract Lifetime
Power Purchase Agreement (PPA) Period / Years 0
Power Price Scenarios (£/MWh) 31-Dec-2006 31-Dec-2007 31-Dec-2008 31-Dec-2009 31-Dec-2010 31-Dec-2011 31-Dec-2012 31-Dec-2013 31-Dec-2014 31-Dec-2015 31-Dec-2016 31-Dec-2017 31-Dec-2018
PPA Price 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Power Price Scenarios (£/MWh) 31-Dec-2006 31-Dec-2007 31-Dec-2008 31-Dec-2009 31-Dec-2010 31-Dec-2011 31-Dec-2012 31-Dec-2013 31-Dec-2014 31-Dec-2015 31-Dec-2016 31-Dec-2017 31-Dec-2018
1 Low 20.92 20.92 20.92 20.92 20.92 20.92 20.92 20.92 20.92 20.92 20.92 20.92 20.92
2 Central 26.15 26.15 26.15 26.15 26.15 26.15 26.15 26.15 26.15 26.15 26.15 26.15 26.15
3 High 55.00 55.00 55.00 55.00 55.00 55.00 55.00 55.00 55.00 55.00 55.00 55.00 55.00
4 XXX
5 XXX
Selected Option
2 Central
Central 26.15 26.15 26.15 26.15 26.15 26.15 26.15 26.15 26.15 26.15 26.15 26.15 26.15
Emissions Data
Emissions - Operation (base plant) tCO2e/MWh 0.728
Emissions - Operation (base plant with CCS) tCO2e/MWh 0.728
31-Dec-2006 31-Dec-2007 31-Dec-2008 31-Dec-2009 31-Dec-2010 31-Dec-2011 31-Dec-2012 31-Dec-2013 31-Dec-2014 31-Dec-2015 31-Dec-2016 31-Dec-2017 31-Dec-2018
EU ETS Trading Flag 0 or 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Carbon Cost Scenarios (£/tCO2e) 31-Dec-2006 31-Dec-2007 31-Dec-2008 31-Dec-2009 31-Dec-2010 31-Dec-2011 31-Dec-2012 31-Dec-2013 31-Dec-2014 31-Dec-2015 31-Dec-2016 31-Dec-2017 31-Dec-2018
1 Low 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00
2 Central 17.00 17.00 17.00 17.00 17.00 17.00 17.00 17.00 17.00 17.00 17.00 17.00 17.00
3 High 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00
4 Assume no carbon price post 2012 6.92 6.92 6.92 6.92 6.92 6.92 6.92 0.00 0.00 0.00 0.00 0.00 0.00
Selected Option
4 Assume no carbon price post 2012
Assume no carbon price post 2012 6.92 6.92 6.92 6.92 6.92 6.92 6.92 0.00 0.00 0.00 0.00 0.00 0.00
Renewable Obligation Certificate Scenarios (£/MWh) 31-Dec-2006 31-Dec-2007 31-Dec-2008 31-Dec-2009 31-Dec-2010 31-Dec-2011 31-Dec-2012 31-Dec-2013 31-Dec-2014 31-Dec-2015 31-Dec-2016 31-Dec-2017 31-Dec-2018
1 Low 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00
2 Central
3 High
Selected Option
1 Low Low 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00
31-Dec-2006 31-Dec-2007 31-Dec-2008 31-Dec-2009 31-Dec-2010 31-Dec-2011 31-Dec-2012 31-Dec-2013 31-Dec-2014 31-Dec-2015 31-Dec-2016 31-Dec-2017 31-Dec-2018
Climate Change Levy Flag 0 or 1 0 0 0 0 0 0 0 0 0 0 0 0 0
Climate Change Levy Scenarios (£/MWh) 31-Dec-2006 31-Dec-2007 31-Dec-2008 31-Dec-2009 31-Dec-2010 31-Dec-2011 31-Dec-2012 31-Dec-2013 31-Dec-2014 31-Dec-2015 31-Dec-2016 31-Dec-2017 31-Dec-2018
1 Low 3.44 3.44 3.44 3.44 3.44 3.44 3.44 3.44 3.44 3.44 3.44 3.44 3.44
2 Central
3 High
Selected Option
1 Low Low 3.44 3.44 3.44 3.44 3.44 3.44 3.44 3.44 3.44 3.44 3.44 3.44 3.44
31-Dec-2006 31-Dec-2007 31-Dec-2008 31-Dec-2009 31-Dec-2010 31-Dec-2011 31-Dec-2012 31-Dec-2013 31-Dec-2014 31-Dec-2015 31-Dec-2016 31-Dec-2017 31-Dec-2018
Recycling Benefit Flag 0 or 1 0 0 0 0 0 0 0 0 0 0 0 0 0
Recycling Benefit Scenarios (£/MWh) 31-Dec-2006 31-Dec-2007 31-Dec-2008 31-Dec-2009 31-Dec-2010 31-Dec-2011 31-Dec-2012 31-Dec-2013 31-Dec-2014 31-Dec-2015 31-Dec-2016 31-Dec-2017 31-Dec-2018
1 Low 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00
2 Central 6.00 6.00 6.00 6.00 6.00 6.00 6.00 6.00 6.00 6.00 6.00 6.00 6.00
3 High 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00
Selected Option
1 Low Low 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00
Capital Allowances %
Industrial Buildings Allowances (SL Basis) 85% 4%
Write Down Allowances (Reducing Balance) 15% 6%
Dividends
Dividends Payable Even If No P&L Reserves n/a 2
No
Financing
Pre-Development %
Debt 0%
Equity 100%
Total Capital 100.0%
Project Finance %
Debt 70.00%
Equity 30.00%
Total Capital 100.0%
Construction Financing
Financing Date, Year 2011
Maturity, Yrs 6
Risk Free Interest Rate / LIBOR 4.26%
Debt Margin Rate 2.00%
Arranging Fees (% of debt) 1.80%
Tolerance on Arrangement Fee Convergence check 0.01
Loan Type
1 Structured Repayment
Structured Repayment 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.0% 0.0%
Structure %
Senior Debt 70%
Junior Debt 0%
Equity 30%
Total Capital 100.0%
Refinancing Yes 1
Refinancing Takes Place, Date 2017 Senior Debt Profile
Senior Debt Amortised Bullet Check
Senior Debt Maturity, Yrs 20 90% 10% 100.0%
Senior Debt Margin Rate 2.00%
Arranging Fees (% of debt) 100.00%
Junior Debt Junior Debt Profile
Junior Debt Maturity Period After Senior Debt (years) 2 Amortised Bullet Check
Junior Debt Maturity, Yrs 22 0% 100% 100.0%
Junior Debt Margin Rate 1.50%
Arranging Fees (% of debt) 2.50%
Interest on Cash
Interest on Cash 2.00%
Rates / Valuation
Levelised Discount Rate ( LC_WACC) 10 10.00%
General Information
Selected Option
1 First of a kind
First of a kind
Assumptions
1 Data
2 Redpoint
3 Spare2
Timing
Key Dates / Time Periods Unit Data Unit Data Unit
Financial close 1-Jan-2007 1-Jan-2007
Prelicensing Period (months) - (years) 0 (days) 0 (months) 0 (years) 0 (days) 0 (months)
Site Specific Licensing Period (months) 24 (years) 2 (days) 730 (months) 24 (years) 2 (days) 730 (months)
Public Enquiry Period (months) 24 (years) 2 (days) 730 (months) 24 (years) 2 (days) 730 (months)
Pre-development Period - Subtotal (months) 48 (years) 4 (months) 48 (years) 4 (months)
Pre-development Period (NAOK Adjustment) (months) - (years) 0 (months) - (years) 0 (months)
Total Pre-development Period (including NAOK) (months) 48 (years) 4 (months) 48 (years) 4 (months)
Construction Start Date 1-Jan-2011 1-Jan-2011
Construction Period (months) 48 (years) 4.0 (months) 48 (years) 4 (months)
Commercial Operation Start Date 1-Jan-2015 1-Jan-2015
Plant Operating Period (years) 50 (years) 50 (years)
Commericial Operation End Date 1-Jan-2065 1-Jan-2065
Decommissioning Cooldown (years) - (years) 0 (years)
Decommissioning Start Date 1-Jan-2065 1-Jan-2065
Decommissioning Period (months) 12 (years) 1 (months) 12 (years) 1 (months)
Decommissioning End Date 1-Jan-2066 1-Jan-2066
31-Dec-2006 31-Dec-2007 31-Dec-2008 31-Dec-2009 31-Dec-2010 31-Dec-2011 31-Dec-2012 31-Dec-2013 31-Dec-2014 31-Dec-2015 31-Dec-2016 31-Dec-2017
Pre-development Distribution 100.0% 0% 25% 25% 25% 25% 0% 0% 0% 0% 0% 0% 0%
Capex Distribution 100.0% 0% 0% 0% 0% 0% 15% 24% 42% 19% 0% 0% 0%
Plant Data II
Gross to Net efficiency factor (LHV/HHV) 1.05
Output Degradation 100.0%
Heat Rate Degradation 100.0%
Data Redpoint Spare2
Run In Period (years) 2 2 2 -
Availability (first X years) 90% 90% 90% 0%
Availability thereafter 90% 90% 90% 0%
31-Dec-2018 31-Dec-2019 31-Dec-2020 31-Dec-2021 31-Dec-2022 31-Dec-2023 31-Dec-2024 31-Dec-2025 31-Dec-2026 31-Dec-2027 31-Dec-2028 31-Dec-2029 31-Dec-2030 31-Dec-2031 31-Dec-2032 31-Dec-2033 31-Dec-2034
0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Construction Costs
Construction Cost Data Data Redpoint Spare2
Capital cost (£/kW) 918 918 882 -
Waste Disposal Cost (£/kW) - 0 0 0
Infrastructure Cost (£/kW) - - - -
Capital Cost (£'000) 459,000 459,000 441,000 0
Working Capital
Circulation Time of Accounts Receivable (Days) 30 30 30 30 30 30 30 30 30 30 30 30
Circulation Time of Accounts & Bills Payable (Days) 30 30 30 30 30 30 30 30 30 30 30 30
Coal Cost Scenarios £/tonne 31-Dec-2006 31-Dec-2007 31-Dec-2008 31-Dec-2009 31-Dec-2010 31-Dec-2011 31-Dec-2012 31-Dec-2013 31-Dec-2014 31-Dec-2015 31-Dec-2016 31-Dec-2017
1 Coal Central Case - DTI July 2006 33.00 31.54 30.08 28.62 27.16 26.94 26.73 26.51 26.29 26.08 25.86 25.65
2 Coal Low Case - DTI July 2006 31.82 28.66 25.40 22.24 18.97 18.56 18.16 17.65 17.24 16.83 16.32 15.91
3 Coal High Case - DTI July 2006 35.00 35.58 36.17 36.75 36.52 36.52 36.52 36.52 36.52 36.52 36.52 36.52
4 Coal - Markal price 30.50 30.50 30.50 30.50 30.50 30.50 30.50 30.50 30.50 30.50 30.50 30.50
5 XXX
6 XXX
7 XXX
8 XXX
9 XXX 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Selected Option
1 Coal Central Case - DTI July 2006
Coal Central Case - DTI July 2006 33.00 31.54 30.08 28.62 27.16 26.94 26.73 26.51 26.29 26.08 25.86 25.65
Contract Price (£/MWh) 31-Dec-2006 31-Dec-2007 31-Dec-2008 31-Dec-2009 31-Dec-2010 31-Dec-2011 31-Dec-2012 31-Dec-2013 31-Dec-2014 31-Dec-2015 31-Dec-2016 31-Dec-2017
Power Purchase Agreement (PPA) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Emissions
Emissions - Operation Data Data Redpoint Spare2
CO2 - base plant tCO2e/MWh 0.728 0.728 0.753 #DIV/0!
CO2 - base plant with CCS tCO2e/MWh 0.728 0.728 0.753 #DIV/0!
30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30
30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30
31-Dec-2018 31-Dec-2019 31-Dec-2020 31-Dec-2021 31-Dec-2022 31-Dec-2023 31-Dec-2024 31-Dec-2025 31-Dec-2026 31-Dec-2027 31-Dec-2028 31-Dec-2029 31-Dec-2030 31-Dec-2031 31-Dec-2032 31-Dec-2033 31-Dec-2034
25.43 25.22 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00
15.50 14.99 14.59 14.59 14.59 14.59 14.59 14.59 14.59 14.59 14.59 14.59 14.59 14.59 14.59 14.59 14.59
36.52 36.52 36.52 36.52 36.52 36.52 36.52 36.52 36.52 36.52 36.52 36.52 36.52 36.52 36.52 36.52 36.52
30.50 30.50 30.50 30.50 30.50 30.50 30.50 30.50 30.50 30.50 30.50 30.50 30.50 30.50 30.50 30.50 30.50
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
25.43 25.22 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00
31-Dec-2018 31-Dec-2019 31-Dec-2020 31-Dec-2021 31-Dec-2022 31-Dec-2023 31-Dec-2024 31-Dec-2025 31-Dec-2026 31-Dec-2027 31-Dec-2028 31-Dec-2029 31-Dec-2030 31-Dec-2031 31-Dec-2032 31-Dec-2033 31-Dec-2034
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Decommissioning Costs
Decomissioning Cost ('000) Data Data Redpoint Spare2
Capital cost (£/kW) - - - -
Total Decommissioning Costs 0 0 0 0
Spare2 %
85.0% 4.0%
15.0% 6.0%
Pre-development
Pre-development Cost
Pre-development Total
Prelicensing - cost 0 0 0 0 0 0 0 0 0 0
Technical including design selection 0 0 0 0 0 0 0 0 0 0
Regulatory including licensing and EIA 0 0 0 0 0 0 0 0 0 0
Regulatory - public enquiry - cost 0 0 0 0 0 0 0 0 0 0
Escalated
Prelicensing - cost 0 0 0 0 0 0 0 0 0 0
Technical including design selection 0 0 0 0 0 0 0 0 0 0
Regulatory including licensing and EIA 0 0 0 0 0 0 0 0 0 0
Regulatory - public enquiry - cost 0 0 0 0 0 0 0 0 0 0
Construction
Construction Cost
Pre-development
Pre-development Cost
Pre-development Total
Prelicensing - cost 0 0 0 0 0 0 0 0 0 0
Technical including design selection 0 0 0 0 0 0 0 0 0 0
Regulatory including licensing and EIA 0 0 0 0 0 0 0 0 0 0
Regulatory - public enquiry - cost 0 0 0 0 0 0 0 0 0 0
Escalated
Prelicensing - cost 0 0 0 0 0 0 0 0 0 0
Technical including design selection 0 0 0 0 0 0 0 0 0 0
Regulatory including licensing and EIA 0 0 0 0 0 0 0 0 0 0
Regulatory - public enquiry - cost 0 0 0 0 0 0 0 0 0 0
Construction
Construction Cost
Pre-development
Pre-development Cost
Pre-development Total
Prelicensing - cost 0 0 0 0 0 0 0 0 0 0
Technical including design selection 0 0 0 0 0 0 0 0 0 0
Regulatory including licensing and EIA 0 0 0 0 0 0 0 0 0 0
Regulatory - public enquiry - cost 0 0 0 0 0 0 0 0 0 0
Escalated
Prelicensing - cost 0 0 0 0 0 0 0 0 0 0
Technical including design selection 0 0 0 0 0 0 0 0 0 0
Regulatory including licensing and EIA 0 0 0 0 0 0 0 0 0 0
Regulatory - public enquiry - cost 0 0 0 0 0 0 0 0 0 0
Construction
Construction Cost
Pre-development
Pre-development Cost
Pre-development Total
Prelicensing - cost 0 0 0
Technical including design selection 0 0 0
Regulatory including licensing and EIA 0 0 0
Regulatory - public enquiry - cost 0 0 0
Escalated
Prelicensing - cost 0 0 0
Technical including design selection 0 0 0
Regulatory including licensing and EIA 0 0 0
Regulatory - public enquiry - cost 0 0 0
Construction
Construction Cost
Power Production
PLANT PERFORMANCE
Average during
Power Generation operation
Gross Plant Output (MW) MWe 0 0 0 0 0 0 0 0
Output Degradation 100.0% % 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
Net Plant Output (MW) MWe 0 0 0 0 0 0 0 0
Auxiliary Power Requirement % 1.8% 1.8% 1.8% 1.8% 1.8% 1.8% 1.8% 1.8%
Average during
Fuel Consumption Total operation
Gross Efficiency % 45.6% % 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
Net Efficiency % 43.4% % 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
Fuel Consumption (MWht), Gross 454,147,105 9,082,942 MWht 0 0 0 0 0 0 0 0
Heat Rate Degradation % 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
Fuel Consumption (MWht), Net 454,147,105 9,082,942 MWht 0 0 0 0 0 0 0 0
Power Production
PLANT PERFORMANCE
Average during
Power Generation operation
Gross Plant Output (MW) MWe 0 500 500 500 500 500 500 500
Output Degradation 100.0% % 0.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
Net Plant Output (MW) MWe 0 500 500 500 500 500 500 500
Available Operating Hours during the Period Hours 0 8,736 8,784 8,760 8,760 8,760 8,784 8,760
Overall Availability Total 90.0% % 0.0% 90.0% 90.0% 90.0% 90.0% 90.0% 90.0% 90.0%
Gross Energy Generated (before auxiliary deductions) 197,229,600 MWhe 0 3,931,200 3,952,800 3,942,000 3,942,000 3,942,000 3,952,800 3,942,000
Auxiliary Power Requirement % 1.8% 1.8% 1.8% 1.8% 1.8% 1.8% 1.8% 1.8%
Gross Energy Generated (before auxiliary deductions) 197,229,600 3,944,592 MWhe 0 3,931,200 3,952,800 3,942,000 3,942,000 3,942,000 3,952,800 3,942,000
Energy Sent Out 193,679,467 3,873,589 MWhe 0 3,860,438 3,881,650 3,871,044 3,871,044 3,871,044 3,881,650 3,871,044
Average during
Fuel Consumption Total operation
Gross Efficiency % 45.6% % 0.0% 45.6% 45.6% 45.6% 45.6% 45.6% 45.6% 45.6%
Net Efficiency % 43.4% % 0.0% 43.4% 43.4% 43.4% 43.4% 43.4% 43.4% 43.4%
Fuel Consumption (MWht), Gross 454,147,105 9,082,942 MWht 0 9,052,105 9,101,842 9,076,974 9,076,974 9,076,974 9,101,842 9,076,974
Heat Rate Degradation % 0.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
Fuel Consumption (MWht), Net 454,147,105 9,082,942 MWht 0 9,052,105 9,101,842 9,076,974 9,076,974 9,076,974 9,101,842 9,076,974
Power Production
PLANT PERFORMANCE
Average during
Power Generation operation
Gross Plant Output (MW) MWe 500 500 500 500 500 500 500 500
Output Degradation 100.0% % 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
Net Plant Output (MW) MWe 500 500 500 500 500 500 500 500
Available Operating Hours during the Period Hours 8,760 8,760 8,784 8,760 8,760 8,760 8,784 8,760
Overall Availability Total 90.0% % 90.0% 90.0% 90.0% 90.0% 90.0% 90.0% 90.0% 90.0%
Gross Energy Generated (before auxiliary deductions) 197,229,600 MWhe 3,942,000 3,942,000 3,952,800 3,942,000 3,942,000 3,942,000 3,952,800 3,942,000
Auxiliary Power Requirement % 1.8% 1.8% 1.8% 1.8% 1.8% 1.8% 1.8% 1.8%
Gross Energy Generated (before auxiliary deductions) 197,229,600 3,944,592 MWhe 3,942,000 3,942,000 3,952,800 3,942,000 3,942,000 3,942,000 3,952,800 3,942,000
Energy Sent Out 193,679,467 3,873,589 MWhe 3,871,044 3,871,044 3,881,650 3,871,044 3,871,044 3,871,044 3,881,650 3,871,044
Average during
Fuel Consumption Total operation
Gross Efficiency % 45.6% % 45.6% 45.6% 45.6% 45.6% 45.6% 45.6% 45.6% 45.6%
Net Efficiency % 43.4% % 43.4% 43.4% 43.4% 43.4% 43.4% 43.4% 43.4% 43.4%
Fuel Consumption (MWht), Gross 454,147,105 9,082,942 MWht 9,076,974 9,076,974 9,101,842 9,076,974 9,076,974 9,076,974 9,101,842 9,076,974
Heat Rate Degradation % 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
Fuel Consumption (MWht), Net 454,147,105 9,082,942 MWht 9,076,974 9,076,974 9,101,842 9,076,974 9,076,974 9,076,974 9,101,842 9,076,974
Power Production
PLANT PERFORMANCE
Average during
Power Generation operation
Gross Plant Output (MW) MWe 500 500 500 500
Output Degradation 100.0% % 100.0% 100.0% 100.0% 100.0%
Net Plant Output (MW) MWe 500 500 500 500
Available Operating Hours during the Period Hours 8,760 8,760 8,784 8,760
Overall Availability Total 90.0% % 90.0% 90.0% 90.0% 90.0%
Gross Energy Generated (before auxiliary deductions) 197,229,600 MWhe 3,942,000 3,942,000 3,952,800 3,942,000
Gross Energy Generated (before auxiliary deductions) 197,229,600 3,944,592 MWhe 3,942,000 3,942,000 3,952,800 3,942,000
Energy Sent Out 193,679,467 3,873,589 MWhe 3,871,044 3,871,044 3,881,650 3,871,044
Average during
Fuel Consumption Total operation
Gross Efficiency % 45.6% % 45.6% 45.6% 45.6% 45.6%
Net Efficiency % 43.4% % 43.4% 43.4% 43.4% 43.4%
Fuel Consumption (MWht), Gross 454,147,105 9,082,942 MWht 9,076,974 9,076,974 9,101,842 9,076,974
Heat Rate Degradation % 100.0% 100.0% 100.0% 100.0%
Fuel Consumption (MWht), Net 454,147,105 9,082,942 MWht 9,076,974 9,076,974 9,101,842 9,076,974
Decommissioning
Decommissioning
Decommissioning
Decommissioning
Decommissioning
Waste Disposal
Waste Disposal
Waste Disposal
Waste Disposal
Waste Disposal
Finance
CONSTRUCTION FINANCING
Senior Debt I
Balance b/f Total 0 0 0 0 0 0
Debt Drawdown - Principal 395,536 0 0 0 0 0 56,714
Debt Drawdown - Arrangement Fee 8,254 0 0 0 0 0 8,254
Total Loan Amount before Repayments 0 0 0 0 0 64,968
Interest capitalised 63,015 0 0 0 0 0 4,067
Senior Debt I Special Repayments 0 0 0 0 0 0 0
Senior Debt I Repayments (466,806) 0 0 0 0 0 0
Finance
CONSTRUCTION FINANCING
Senior Debt I
Balance b/f Total 69,035 172,432 361,376
Debt Drawdown - Principal 395,536 93,238 167,654 77,929
Debt Drawdown - Arrangement Fee 8,254 0 0 0
Total Loan Amount before Repayments 162,274 340,086 439,305
Interest capitalised 63,015 10,158 21,289 27,500
Senior Debt I Special Repayments 0 0 0 0
Senior Debt I Repayments (466,806) 0 0 0
Finance
CONSTRUCTION FINANCING
Senior Debt I
Balance b/f Total 466,806 466,806 466,806 0 0 0 0
Debt Drawdown - Principal 395,536 0 0 0 0 0 0 0
Debt Drawdown - Arrangement Fee 8,254 0 0 0 0 0 0 0
Total Loan Amount before Repayments 466,806 466,806 466,806 0 0 0 0
Interest capitalised 63,015 0 0 0 0 0 0 0
Senior Debt I Special Repayments 0 0 0 0 0 0 0 0
Senior Debt I Repayments (466,806) 0 0 (466,806) 0 0 0 0
Finance
CONSTRUCTION FINANCING
Senior Debt I
Balance b/f Total 0 0 0 0 0 0
Debt Drawdown - Principal 395,536 0 0 0 0 0 0
Debt Drawdown - Arrangement Fee 8,254 0 0 0 0 0 0
Total Loan Amount before Repayments 0 0 0 0 0 0
Interest capitalised 63,015 0 0 0 0 0 0
Senior Debt I Special Repayments 0 0 0 0 0 0 0
Senior Debt I Repayments (466,806) 0 0 0 0 0 0
Balance c/f 0 0 0 0 0 0 0
Check 0
Indexation
INDICES
INDEX VALUES
Indeces / I (2006)
RPI 2.75% 2.75% 2.75% 2.75% 2.75% 2.75% 2.75% 2.75% 2.75%
INDEX FACTORS
Indexation
INDICES
INDEX VALUES
Indeces / I (2006)
RPI 2.75% 2.75% 2.75% 2.75% 2.75% 2.75% 2.75% 2.75% 2.75%
INDEX FACTORS
Indexation
INDICES
INDEX VALUES
Indeces / I (2006)
RPI 2.75% 2.75% 2.75% 2.75% 2.75% 2.75% 2.75% 2.75% 2.75%
INDEX FACTORS
Indexation
INDICES
INDEX VALUES
Indeces / I (2006)
RPI 2.75% 2.75%
INDEX FACTORS
Version 2006
0
Preparation Date:
Report W/sheet
0 1 2 3 4 5 6 7 8 9
(L)and /
Name Area Name Worksheet Zoom HorizCenter? VertiCenter? CenterHeader LeftFooter CenterFooter
(P)ortrait
RightFooter
FALSE
FALSE
FALSE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE