3) According to the CERC Norms, what percentage of the Power Plant Cost do the
spares account for in a coal based plant?
a) 4%
b) 2.5%
c) 3%
d) 5%
5) What is the percentage of Escalation in the O&M expenses of a Power Plant each
year?
a) 3%
b) 3.5%
c) 4%
d) 5%
8) The following Inputs are required before issue of Notice Inviting Tender for a
Package except one. Which is that?
a) Finalization of Specification
b) Finalization of NIT Cost Estimate
c) Finalization of Financing Agencies
d) Finalization of Qualifying requirements
10) Arrange the following elements of the Project Cycle in the right order:
- Project Appraisal
- Feasibility Analysis
- Negotiation
- Project Selection
a) A-B-C-D
b) B-A-C-D
c) B-A-D-C
d) A-B-D-C
12) What is the Discount Factor used in the levelization of Cost of Energy?
a) 10%
b) 4%
c) 5%
d) 12%
15) The new Gazette notification of MOEF dated _______gives the Approval of
Terms Of Reference (TOR) for EIA study:-
a) 14.09.06
b) 14.08.06
c) 18.09.07
d) 19.04.06
18) The Patwaris come into play at which stage of the Project management?
a) Infrastructure Planning
b) Infrastructure Development
c) Land Acquisition
d) Infrastructure: Accomodation
19) Notification of which section/s is issued by the revenue Department during Land
Acquisition?
a) Section 9
b) Section 11
c) Section 6 & 17
d) Section 4
26) What is the Gap between Site leveling and the start of civil work of foundations?
a) 4 months
b) 6 months
c) 5 months
d) 9 months
27) How far should be the Thermal Power Plant from archaeological, historical,
cultural, religious or tourist importance and defence installations?
a) 5 kms
b) 10 kms
c) 25 kms
d) 50 kms
28) For a 2000 MW power plant how many acres area is required for Township?
a) 100
b) 150
c) 250
d) 350
29) How many cusecs of Cooling Water is generally required for a 1300 MW Power
Plant?
a) 18
b) 25
c) 30
d) 35
30) Geological and seismotechtonic set-up of the site covers an area of not less than -
_______ radius around the project site.
a) 80 km
b) 100 km
c) 150 km
d) 200 km
32) Deemed Export Benefits come under which chapter of foreign Trade Policy?
a) 7 (f)
b) 7 (d)
c) 8 (d)
d) 8 (f)
34) Which of the following clearances is not required for a Hydro Project?
a) Ministry of Environment & Forests
b) Ministry of Social Justice and Tribal Affairs
c) CEA
d) SLC
35) How many projects have been approved by NTPC Board under Navratna Powers?
a) 18
b) 19
c) 20
d) 21
ANSWER KEY
1-C
2-A
3-B
4-C
5-C
6-B
7-D
8-C
9-B
10-C
11-C
12-D
13-B
14-C
15-A
16-B
17-D
18-C
19-D
20-A
21-C
22-B
23-C
24-B
25-A
26-C
27-B
28-C
29-D
30-C
31-D
32-D
33-C
34-D
35-C