ST. AUGUSTINE
2010
ii
Abstract
Table of Contents
Abstract.............................................................................................................................ii
List of Figures...................................................................................................................v
List of Tables...................................................................................................................vi
Chapter 1 - Introduction...................................................................................................vii
Chapter 2 - Literature Review..........................................................................................ix
2.1 Overview of the Current Public Procurement Process...........................................ix
2.1.1 Definition of Public Procurement....................................................................ix
2.1.2 The Evolution of the Legislative and Regulatory Framework..........................x
2.1.3 Current Procurement Practice observed by the Central Tenders Board.......xiii
Chapter 3 - Discussion of the Principal Challenges to the Development of Efficient
Procurement Processes in the Public Sector in Trinidad and Tobago...........................xvii
3.1 Design and Build Procurement System...............................................................xvii
3.1.1 Challenges Faced by the Adoption of a Design and Build Procurement
System......................................................................................................................xx
3.1.2 Recommendations to Combat Challenges of Design/Build Approach..........xxi
3.1.3 Performance Based Contracts ......................................................................xxii
3.1.4 External Consultancy Services....................................................................xxiii
3.2 Alleged Corruption in All Stages of the Procurement Process..........................xxiii
3.2.1 How corruption operates in the Public Procurement Process.......................xxv
3.2.2 Mitigation Strategies for Corruption in Public Procurement.....................xxviii
3.3 Presence of Foreign Contractors.....................................................................xxxviii
3.3.1 Chinese Experience in Trinidad and Tobago...........................................xxxviii
3.3.2 Local Contractor Praised................................................................................xli
3.3.3 Recommendations...........................................................................................xli
3.4 Public Sector Procurement Process......................................................................xlv
3.4.1 Deficiencies in the Legal and Regulatory Framework..................................xlv
3.4.2 Absence of Uniformity in the Tendering Process.........................................xlvi
3.4.3 Human Resource Limitations......................................................................xlvii
iv
List of Figures
List of Tables
Table 3.1: Corruption Related Risks at each stage of the Procurement Process...........xxv
vii
Chapter 1 - Introduction
Public contracting is the main way a government operates and public money is spent. A
contract is a binding agreement or business arrangement for the supply of goods or services.
Examples include the purchase of office supplies for a governmental office and the contracting
for the design of a complex concession system for an airport. These contracts are meant to buy or
produce goods or services that benefit citizens directly, for example the construction of a road or
a sewage system. Others benefits citizens indirectly, such as the contracting out of consultancy
states and in national governments. While national level procurement can be bigger in terms of
value per contract, local government contracting is significant in terms of the number of
processes and their impact. The term procurement is often used in this field. Procurement refers
to the acquisition of goods and services by any individual or organization (public, private and
international).
An efficient public procurement process is one that always seeks to deliver value for money,
accountability and transparency to the client. However, this is not the situation in today’s public
procurement system within Trinidad and Tobago. Currently, the region of Trinidad and Tobago
is faced with numerous challenges which hinder and stifle the development efficient procurement
processes in the public sector. These challenges include but not limited to the following:
3. Funding
This report discusses the principal challenges and attempts to provide solutions,
recommendations and strategies to combat these challenges. The challenges that were considered
to be of utter importance included nos. 2, 3,4,5,7 and 9 from the listed previously stated. These
were considered to be principal challenges because these issues are currently plaguing society
and most prevalent in Trinidad and Tobago’ public procurement system. The construction sector
of Trinidad and Tobago can be considered as the most severe pathogen to these hosts of public
procurement challenges.
ix
legislative and regulatory framework behind public procurement in Trinidad and Tobago and
provide a synopsis of the procurement cycle observed by the Central Tenders Board.
Procurement can be defined as the acquisition of goods and services including the
undertaking of works and consultancy services for use by the client organization. Procurement is
therefore a comprehensive process that includes inter-alia design, publicity, tendering, receiving,
opening and evaluation of offers, award and signing of contract, guarantees, installation, testing
and start up operation, service and maintenance (Central Tenders Board n.d.).
utilization of public money imposes on all agents a duty of care in the public
interest and a duty to safeguard and ensure the attainment of value for
money. The utilization of public money also demands that such utilization
x
will be undertaken only for the purposes intended and authorized. Public
services. This means that the legal framework will apply not only to
During the period 1956 to 1960, there was a significant increase in Public
The Cost Accounting Division in the Ministry of Finance was the agency charged with the
responsibility of spending public funds and is therefore accountable to the population for such
expenditure. The majority of this expenditure involves the procurement of goods and services.
Approximately 75% of the Budget allowances for this procurement are through the Tendering
Process.
The Central Tenders Board was therefore established by Act No. 22 of 1961 to ensure that
the proper procedures are followed to obtain the most suitable supplies and services from
xi
available resources. The Central Tenders Board forms an integral part of the Financial
Government Ministries, Departments and certain Statutory Bodies. The Central Tenders
procurement system.
on its own behalf. This reflected a major shift in policy on the role of the CTB
CTB.
arms, ammunition, and equipment for the Defense Force and the Protective
Services.
the removal of some earlier established statutory bodies from the purview of
the CTB. The CTB now has an exceedingly diminished role as compared to
1961.
xiii
Note: The text highlighted in red for steps 5 & 6 indicates the alteration to the Procurement
cycle to represent Selective Tendering
The following is a synopsis of the Procurement Method observed by the Central Tenders Board
• The Client Ministry or Department conducts a needs assessment, reconciling its needs
with available funding. A Bid Package is subsequently prepared and submitted to the
• Upon receipt of the bid package, the Central Tenders Board reviews the documents and
ensures that they conform to the Central Tenders Board Regulations and Procedures.
• Once all documentation received from the Client Ministry is reviewed and found to be
within the proper procedures, the Central Tenders Board invites bids/tenders publicly or
selectively.
• Tenders are invited publicly by advertising tender notices locally, in the press and in at
least two (2) newspapers of wide circulation; and internationally, in reputable Journals
and the Development Business Forum. Tenders are also published on the Central Tenders
Board’s Website.
• Tenders are invited selectively from a shortlist of registered contractors, consultants and
• Tenders received are opened publicly on the closing date of the tender and are forwarded
• The Central Tenders Board then reviews the evaluation reports prepared by the team. The
evaluation team may also be required to provide explanations of aspects of their report.
• The Award of Contract is subsequently decided upon by the Central Tenders Board. In
• Letters of Acceptance are issued to successful bidders by the Central Tenders Board
Division.
xv
• In the case of major projects, the form of contract Agreement is prepared by the Chief
State Solicitor’s Office who formally arranges the execution of the contract Agreement
• All Contracts awarded are published monthly by the Central Tenders Board in the
Trinidad and Tobago Gazette and on the organization’s website. Copies of the Contracts
However, the Central Tenders Board may become involved in this stage of the process
only if called upon to resolve a dispute or approve a variation to the contract outside of
• A report is submitted to the Central Tenders Board, upon completion of the contract,
which in turn authorizes the release of performance bonds and the refund of deposits. The
• Tender committees within the Client Ministries or Departments may act for the Central
Tenders Board within limits, as provided by the Central Tenders Board Ordinance (No.
Tenders Board and follow the procedures of the Division. In cases where the value of the
acquisition is below a certain limit, the committee has the ability to award the contract.
• Permanent Secretaries and Departmental Heads can also procure goods and services
below a certain financial limit. All financial limits are defined in the Regulations, Rules
• Most statutory bodies, all State-owned enterprises and NIPDEC are fully responsible for
• State enterprises are required to invite a representative of the Central Tenders Board to sit
on panels considering Tenders above a certain level. The award of contracts by these
Ministry of Finance.
xvii
processes in the public sector in Trinidad and Tobago. Recommendations for overcoming these
Currently there is battle looming in the industry over the concept of design/build as the
preferred building construction delivery method. This method challenges what we have come to
accept as the norm, which is the system of design/ bid/ build or client design and tender where
the latter process involves the client hiring the architect and the architect assembles the design
team of engineers and quantity surveyors together. They prepare a preliminary design and cost
estimates in accordance with the client’s brief and instructions, and contractors are then invited
to tender.
This method of delivery for construction projects has been around since the 1500s with the
master carpenter/master-builder having full responsibility for the design and construction of
building projects. However, around the eighteenth century, the professional class of architects
and engineers replaced the master carpenter or master-builder of earlier times. The architect
eventually became the client representative taking charge of projects from conception to
completion including the outfitting of most projects with requisite furnishing. The system of
However, this process became very adversarial and confrontational between the owner, designer
and contractor - with much time and money being spent on litigation and or the avoidance of
litigation when projects failed to meet budgetary and completion schedules (Joseph 2008).
These failures were due to a number of factors, the main ones being:
i. The inability of the architect and quantity surveyor to keep current with construction cost.
ii. Incomplete design at the tender stage, resulting in final construction drawings that varied
greatly, both in scope and specifications, from the preliminary tender documents.
iii. Client change orders during the construction stage, resulting in completed work having to
problem, originates from a lack of meaningful communication between the client, the
architect and the contractor. Proper communication would allow for value engineering
vi. Adversarial relationships between all parties resulting from some or all of the above.
The design/build method as we know it today was reintroduced to reduce the adversarial
relationship and increase the efficiency and cost effectiveness of construction project delivery by
having a single entity take responsibility for the entire project. This is actually nothing new to
the construction sector here in Trinidad and Tobago. This procurement system is one where a
single contract is awarded for the design and construction of the work to be performed. It
suggests that the client enters into contract with one agency for the complete delivery of the
project. This system is also referred to as a turnkey system or package deal (see Figure 3.2).
xix
Design
Client
Construct
Design
Client
Construct
i. It facilitates greater unity between the two functions. It allows the design process to be
carried out just ahead of the construction process and therefore result in less time for the
project.
ii. It removes the adversarial relationship which could arise in the traditional procurement
system.
iv. This system is highly economic hence this leads to greater savings and a lower contract
price.
xx
The design and build approach is usually adopted by the government for the procurement
of large projects. As evidence suggests, this leads to improved project outcomes but it prohibits
an experienced local firm from acting as the main contractor due to capacity constraints (mainly
financial) and an inability to carry the additional risks. In most cases when this occurs, the local
firms and enterprises are used as subcontractors to subcontract sections of the work or to procure
supplies. The widespread subcontracting of local firms has a negative impact on the development
of an efficient procurement system within the public sector (Wells and Hawkins 2008).
3.1.1.2 Corruption
In the case of the design-build procurement method, the occurrence of corruption is likely
to increase because the entire process, as compared with that of the more traditional methods, is
less transparent with fewer opportunities for oversight by independent supervisors. The selection
‘beauty parade’ because there is a variety of criteria such as design, cost, schedule, quality,
experience and financial resources that can be easily manipulated under the guise of a
supposedly transparent process to achieve any desired result. Whereas in the traditional methods,
the project stages such as pre-design, design, financing, planning and construction are
project stages are reduced from five to three, or even less, thereby reducing transparency and
Corruption is another factor that contributes to the degradation of an efficient public procurement
The fact there is an absence of independent scrutiny and supervision on the contractor
within a design and build system creates a source of concern. It raises curiosity towards the
integrity and quality of the design, the selection and use of materials and the general quality of
the works. Another area of concern deals with the liability of the design and build contractor.
While it does appear that the contractor should be liable for the design and construction, the
question rests with how will the client establish what is the nature and extent of the damage or
fault and hence the liability, particularly when these faults are not immediately apparent. The
concealing of faults and poor quality designs originating from the utilization of the design and
build approach in public procurement certainly affects the efficiency of the process (Suite n.d.).
This section attempts to describe possible solutions to the problems encountered by the
design and build approach currently used by the Government of Trinidad and Tobago for the
In the case where local firms may be prohibited from acting as the main contractor as
seen in the design and build approach, a modification to this system can utilized as another
innovative way of creating opportunities for small contractors on a sizeable project. This
modification involves the formation of a joint venture (see Figure 3.2) between foreign
contractors and local contractors. An example of this system exists where the foreign firm is
xxii
employed as the management contractor and the local firm as the labour contractor. This
appointed to execute and supervise the work, with supervision assistance form the district
councils. The IEF signed a contract for the works with the tender board and then contracted
small scale labour-based contractors to carry out the work. A total of 47 labour based contractors
were employed on the project and together they built 700km of gravel roads in five years at a
This joint venture system is also depicted in the water projects in Trinidad and Tobago
where Mekorot Development and Enterprise Ltd. From Israel will work with the Water and
Sewerage Authority of Trinidad and Tobago to develop, plan and build projects worth $100
million. The work includes a project to improve the drinking water supply system, the overall
supply management, and upgrading water treatment plants. Mekorot Development and
Enterprise is already active in Trinidad. Last September, the company signed a consultancy and
training agreement with WASA, and in November an agreement was signed for developing
Performance-based contracts (1) describe the work in terms of what is to be the required
output rather than how the work is to be accomplished; (2) place the responsibility for quality
performance on the contractor; and (3) stipulate formal and measurable performance standards,
the public procurement process as they expand the range of acceptable solutions and permit the
inclusion of indigenous technologies. They are also seen as having potential to reduce corruption
In order to reduce the occurrence of flaws in publicly procured projects, the client i.e. the
advice from a consultancy agency to vet the design and monitor the construction phase.
Experts identify procurement as one of the areas most prone to corruption in the construction,
• harms companies that produce goods and services as it increases operation costs,
• leads to a distortion of fair competition, the waste of scare resources and the neglect of
• can give rise to massive market inefficiencies and, in the extreme, lead to the destruction
• can add 20-25% to the costs of government procurement and frequently result in inferior
Contracting is the main way a government operates and public money is spent. In this sense,
contracts are the vehicles for implementing public policy. A significant portion of
construction, health and education expenditure goes to procurement or contracts for goods
determining factor in policy and project efficiency (Trinidad and Tobago Transparency
Institute 2008).
and is the conduit through which billions of dollars enter the national
not typical because we rely less on aid than most other developing countries.
US$14,000.00, the highest in the region, mainly due to the income derived
been developed over the years more from self regulation than from
procurement has been one of the more fertile grounds for corruption locally
(Hart 2008).
Corruption in public procurement can take the form of bribery, extortion, deception
(fraud) or simple abuse. The risks of corruption in public contracting can be more easily
understood in relation to each stage of a contracting process. Most contracting processes broadly
follow the same steps. It is generally believed that the risk of corruption is especially high during
the evaluation phase of a contracting process, when offers are studied in order to select the
contractor. But the risks are not limited to this phase. Corruption can occur even before a
contracting process starts, when decisions are taken about what to contract. Some projects start
off ear-marked for award to a particular party. There is also room for abuse once the contracting
process has finished and the contractor has been selected. Underperformance, contract
renegotiation, change orders, over-billing, and non compliance are just some of the forms of
The table below synthesizes some of the corruption related risks at each stage of the process:
Table 3.1: Corruption Related Risks at each stage of the Procurement Process
Evaluation criteria are not set from the start or are not objective,
thereby making them prone to abuse
Stage C: Contracting process
Description Main risks (examples)
A contracting process opens. It Invitation to tender (an open bid) is not publicised, thereby restricting
should take place according to the number of bidders that participate;
what method the law determines
be used to receive proposals When short-lists are used, companies bribe to be included or to gain
(e.g. open bidding system) or access to them;
evaluate contractors (e.g. single
source) Invitation to tender is publicised but very little time is given to
present offers, making it difficult for bidders without prior knowledge
of the contract to present bids;
Contract awards are not publicised (nor the grounds for the decision).
Stage E: Contract implementation and supervision
Description Main risks (examples)
xxvii
The contract is signed with the Contract changes and renegotiations after the award are of a nature
selected bidder or contractor that changes the substance of the contract itself;
Additional Risks
Additional risks are created by confusing or contradictory legislation. In some cases, for
example, donor and credit agencies require their procurement procedures to be used instead of
national procedures. In some cases, this has been helpful; but in others, requirements for
transparency are higher under national legislation. In this case, an important tool to prevent
corruption is lost. An additional burden is created if the local implementation agency is not
familiarized with the donor or credit agency's guidelines, or if it has to simultaneously handle
Research has told us that corruption in procurement takes place because of - and is
Size
Bribes are often calculated as percentages of the total sum, representing a proportional
relationship. Hence, the more money involved the more reason to demand a bribe.
Mystification
The more high technology involved, or seemingly involved, the more attractive the
project will be to the potential beneficiaries. This kind of "mystification" reduces the risk of
xxviii
being criticized for paying too much. (For example: How many people can say whether a
particular fighter aircraft should have cost $21million rather than $23million?)
Immediacy
The term of office may be brief to many politicians, but also to officials. From this it
follows that the most attractive projects are those in which the full purchase price, or at least a
Discretion
The discretionary authority of public officials often represents a golden opportunity to obtain
bribes. Discretionary power is at its greatest when the public demand and the public preferences
are delegated to the public agent and defined during a bilateral bargaining process. Then the civil
servant is choosing the private part, while price and other contract conditions are the result of the
• Confidential information
global consensus on the need to curb corruption that encompasses companies, governments,
donors and credit agencies and civil society organizations around the world.
xxix
For many years, it was believed that the only way to fight corruption in public contracting
was through law enforcement and control. While this is clearly necessary, it often comes too late,
after the damage has been caused. More importantly, corrupt behaviour should be prevented by
giving those involved in contracting the opportunity to avoid it and the pressure to do so.
Contracting processes need to be permanently monitored. Supervision and control play a key role
since good rules are necessary but not always enough to curb corruption. It is also important to
have clear and publicly available procedures and to have regular audits by external parties (U4
Good rules, transparency and monitoring are three elements that help to prevent corruption.
• In the case of absent rules or rules which can be manipulated to one's advantage, donors
should assist governments in elaborating and enforcing procurement laws and procedural
• These procurement rules should at least minimize confidentiality, state open bidding from
bidding documents, procedures, evaluations and awards are publicly and timely available.
They should also establish administrative review systems, foster objective evaluation
criteria and provide structures for it. These rules should ensure that the different
different offices, committees and individuals, each with the appropriate expertise and
systems, including online systems, where information can be shared with auditors,
complainants and the general public. Tools for improving electronic procurement systems
transparency and accountability, facilitates oversight and citizen participation, and brings
legitimacy to governmental decisions. Rules that follow these principles also provide a
• Written procurement procedures should outline the whole process, using explicit criteria
to award contracts.
• Rules are not enough, however, and law enforcement mechanisms are often weak.
Monitoring by local experts and independent oversight agencies can help make existing
norms effective. Civil society also has an important role to play in monitoring.
governments, companies, donors and civil society. Monitoring should also include an
• Donors can also promote integrity in the private sector, e.g. through information
campaigns for small and medium sized businesses. It is the latter who lose out in corrupt
xxxi
procurement deals as larger firms can more easily afford to position themselves vis-à-vis
decision-makers.
system. Some tools that help to correct these inefficiencies may also prevent corruption and vice
versa. But this is not always the case. For example, speeding up the procurement process may
increase the risks of corruption if transparency and accountability are not assured. Conversely, a
delays. This means that a careful consideration of impact and implementation should be
multi-party evaluation committees, rotation principles for procurement officials and the
establishment of accountability and report procedures, are key in fighting corruption. Incentives
promoting 'good behaviour' for individuals are also needed, such as the performance-based staff
incentive structures. Systems usually plan punishment for 'bad behaviour', but experience proves
that rewards for good behaviour can motivate individuals. The development of codes of conduct
Competitive bidding includes a good public procurement system that can ensure fair
competition and best value for money. There is also broad agreement about the main elements in
• Documents that clearly set out the needs, describe the bidding process and contract terms
and conditions, and give the criteria for choosing the winner
xxxii
• Submission of secret sealed bids that are opened in the presence of the bidders at a
• Award of the contract to the bidder complying with all requirements and offering the best
Research has demonstrated that the fight against corruption must start with an explicit
commitment by the prime leadership of the country. Ending the pettier forms of corruption in the
An anti-corruption reform of the public procurement system depends on the political will
to disclose the state budgets, to extend the obligation to keep accounts, to establish external
monitoring systems and to improve public access to bureaucratic and political information.
Because the challenge in the arrangement of corrupt agreements is often the search for a
connections, and further increase the transaction costs of corruption. Rotation of public officials
It is important to make the underlying rules as clear and simple as possible, so that people
know what an honest system is supposed to produce. Uncertain and variable rules tend to create
discretionary authority among public officials should for instance also be made accessible to
ordinary people.
The goods procured should be "simplified". Anti-corruption benefits are just one of
"state-of-the-art" products. The state administration should apply private market prices as
benchmarks and specify their requirements in terms of standard off-the-shelf items. This would
In particular construction, but to a certain extent also procurement, tend to become much
more expensive than envisaged in the first plans. This is a global problem.
Accordingly, the way additional work is specified in the contract is important. Does such
out by the same enterprise? The latter might end up in a monopoly price if not prices of
supplementary work are determined in advance. And what is the definition of supplementary
work? These questions should be clearly answered in the procurement contract, while decisions
to change or supplement the project should be monitored with caution by officials external to the
3.2.2.8 Inspection
All kinds of procurement decisions have to be monitored in some way. For discretional
procurement decisions this represents a certain challenge. While elements like technical value,
times of execution, costs of utilization to some extent can be monitored objectively; there will
often remain an aspect of evaluation that is clearly individual. Also to enable inspection of these
judgments, specific objectives are the solution. When significant problems arise during
Rules to ensure integrity make it easier for public officials to renounce corruption. Codes
of conduct are a "compulsory" part of any procuring institution. However, they should not just
remain on the paper, but characterize all forms of bureaucratic activity. A step in that direction
would be to include ethical standards in the legal framework. Codes of conduct are supposed to
serve as an obstacle for private interests to interfere with those of the government. Important
elements are the way gifts and personal benefits should be treated; forms of communication and
association with external agents involved in administrative cases; what to do when fraud or
corruption is discovered among colleagues; and what to do when uncertainty about these issues
arises.
3.2.2.10 Competition
are one element, but also monopoly providers of public services can be problematic. In a given
example where the office issuing drivers licenses frequently demands bribes, even when you
have all papers in perfect order, an idea could be to establish other public offices with the same
xxxv
authority. That way you could address the office which doesn't add the extra price the bribe
money incurs. Competition in the provision of public services has in some cases been forwarded
as a possible solution.
The following three anti-corruption tools have been developed by – or their development
facilitated by- Transparency International (Trinidad and Tobago Transparency Institute 2008)
Integrity Pact
The Integrity Pact (IP) is aimed at preventing corruption in public contracting. It consists
of a process that includes an agreement (entered into before bids are invited) between a
government or a government department (at the federal, national or local level) and all pre-
qualified bidders for a public contract. It contains rights and obligations to the effect that neither
side will: pay, offer, demand or accept bribes; collude with competitors to obtain the contract; or
engage in such abuses while carrying out the contract. The IP also introduces a monitoring
Through the use of the IP, governments are able to reduce the high cost of corruption in
major project can go a long way to restoring public confidence in a country’s public procurement
processes.
The IP has shown itself to be adaptable to many legal settings and flexible in its
application. In the case of Trinidad and Tobago, no new legislation is required for its
introduction. Obviously, the legal requirement will vary from country to country and that would
need to be examined locally. So far, the IP has been successfully introduced in about 20
xxxvi
countries around the world with some major success reported. Regrettably, despite lobbying by
TTTI, the government of Trinidad and Tobago is yet to use the IP on any of its projects.
Anti-Corruption Forums
sector anti-corruption alliance between the infrastructure industry (represented by business and
professional associations and companies) and civil society (represented by TI and other
organisations with particular interest in the infrastructure sector). The forum agrees and promotes
anti-corruption actions in the infrastructure sector and liaises as necessary with government and
alliance of TI’s UK chapter with business associations, professional institutions and companies
with interests in the domestic and international infrastructure, construction and engineering
sectors. Over 1,000 UK companies and 200,000 engineers and construction managers are
The purpose of the UK ACF is to promote industry-led actions which can help eliminate
corruption. The members believe that corruption can only be eliminated if governments,
financiers, business and professional associations, and companies working in these sectors co-
which impact on all project phases, on all major participants and at a number of contractual
levels.
The developers of PACS have started from the premise that corruption on construction
projects is a complex problem. It may occur in the form of bribery, extortion, fraud or collusion.
It can take place during any phase of a project, including project identification, planning,
financing, design, tender, execution, operation and maintenance. In each project phase,
corruption may involve any one or more of the participants i.e. government, state enterprises,
partners, and agents. It may occur at any level of the contractual structure.
• templates that provide the tools by which the measures recommended in the PACS
a) assess its existing project anti-corruption measures against the PACS Standards;
b) modify its existing measures in accordance with the PACS Standards; and/or
c) use some or all of the PACS Templates, appropriately customised, in order to implement
In most developing countries the construction sector plays an important role in the developmental
process. Developed countries can also derive the benefits of the construction industry. Construction is a
major consumer of products from the primary sector as well as the manufacturing sector. The
The sheer size of the market in construction presents significant opportunities for competent firms
and individuals no matter where they are based or their size, provided they have the necessary interest,
opportunity and support. However, like in other countries, regional firms must receive support politically
It is claimed that firms within the Caribbean Community (CARICOM) are not as competitive as
they should be against firms from other parts of the world. However a significant number of professionals
in the region are of the opinion this may not always have to do with elements of industry efficiency per se
and that the support, subsidies and incentives (albeit often hidden) available to foreign firms create unfair
terms of trade and are largely responsible for the imbalances in ‘competitiveness’ as measured by winning
international competitively bid contracts. The region is also faced with the phenomenon of cheap labour
The Chinese presence began elsewhere in the region. Their presence was evident with the design
and construction of the sporting facilities for the hosting of the Cricket World Cup matches. The Chinese
construction company – Shanghai Construction, was introduced to Trinidad and Tobago with the design
and construction of the Prime Minister’s residence and diplomatic centre at cost of nearly TT$150
million. It has since expanded further locally with the design and construction of cultural centres
in Port of Spain and San Fernando and government office buildings and even houses in Tobago.
In some cases, the Government of China has financed these projects at concessionary terms.
xxxix
There has been at least one report in the local press that a private developer was also using
‘Chinese labour’.
Several issues arise from this development in the region. Issues that relate to the
importation of a foreign design style and culture, the displacement of local consultants,
contractors and labour, the importation of materials that are usually available locally, the use of
materials that may not satisfy local construction codes, the absence of independent supervision
and certification of the designs and construction works, that the Chinese are supposed to be
delivering projects much faster and more economically than local contractors (Lewis and Imbert
n.d.).
Lack of Transparency
The Chinese projects fail the ‘transparency’ test because the details of the contractual
arrangements between government and the Chinese contractors are being treated like state
secrets. There has been no disclosure to the public, or to Parliament, of the contract terms.
Generally, there has been no consultation by government on the proposed plans. The designs of
the Cultural Centres in T&T have been finalized without design inputs from the facilities
intended users. After much lobbying, very limited consultation took place, after the fact, and
resulted in delays to the projects because of the resulting need to go back to the drawing board.
In the case of the Prime Minister’s Residence and Diplomatic Centre, no stakeholder
Lack of Accountability
The Chinese projects fail the ‘accountability’ test because there is no overseeing of the
contractor’s work by independent competent local professionals. In the case of the the Prime
xl
Minister’s Residence and Diplomatic Centre, there was an electricity outage during the first
function, the tour by media and special guests. If press reports are correct, the outage was the
result of the electrical design and installation not meeting the standards of local codes. Further,
the Electrical Stand-by Generator is reported to have failed to operate as intended because of
design faults.
It is impossible to determine whether Trinidad and Tobago is receiving value for money
from the Chinese awarded projects, simply due to the lack of information. It can be deemed that
they fail to deliver value for money. This conclusion can be drawn from the following
observations:
• Firstly, in most cases, the Chinese contractors are not made to tender in competition with
local or regional contractors, therefore, no one is sure if contracts are awarded for the best
price. The international norm is that competitive tendering is a prerequisite for ensuring
value for money and every credible funding agency such as the World Bank etc. insist on
• Secondly, an important part of the ‘value for money’ equation which has not been met is
the transfer of technology from the foreigners to locals. There was a failure in the
appointment of local understudies on any of these projects. Therefore, when the Chinese
labourers depart, Trinidad and Tobago may be left in a situation where we may
knowledge with the locals. Further, maintenance of the buildings will require the
sourcing of materials and equipment that are not readily available in the local market.
xli
These two issues have raised concern as to whether the Chinese contractors are receiving
preferential treatment not enjoyed by local contractors (Trinidad and Tobago Transparency
Institute 2008).
It can be concluded that the high influx of foreign contractors stifles the expansion of local content.
This means that it reduces the chances for local people to earn income through employment on the
construction site or in the supply industries. It also reduces the opportunities for local businesses as
contractors, subcontractors, producers or suppliers of material and equipment and increased local
knowledge and skills. Procuring services and goods from local contractors and suppliers and using
techniques adapted to the local resource endowment, will generate income locally and make a substantial
The reputation of local contractors in Trinidad and Tobago is at such a deplorable state
that when a local contractor succeeds to deliver a project on time, their performance is well
recognized and appraised. According to the article “Local contractor praised” dated 22nd
September 2009, a local contractor Sharoz Enterprises Lrd. was commended by the Minister of
Legal Affairs for delivering of St. Mary’s Primary School on time and within budget despite
Government’s preference for foreign contractors (Bethel 2009). This gesture by the Government
indicates the extent at which the potential of local contractors is viewed by the public.
3.3.3 Recommendations
The following describes recommendations and alternatives that should be introduced into the
• Avoid combination/multi-stage contracts, which make them too big for local firms, for example,
financing, construction and installation works as in major turnkey contracts. Disaggregate very
• Established protocols for consortia of local firms and joint ventures between local and foreign
firms for adequate technology transfer and equitable sharing of risk, responsibility and profits.
• Review pre-qualification criteria, particularly the weighting given to ‘local experience’, which
should be significant.
• Promote the use of uniform standards and specifications relevant to the region. Legislation is
• Facilitate access by local firms to funds to enable interest rate equalization and in the provision of
insurance and bonds to alleviate disadvantages of the small size of the economy and firms.
• Address the issue of unfair tax concessions for foreign consultants and contractors.
• Restrict the right to Commercial Presence by a foreign firm when this can be shown to be
Local firms need to collaborate, as consortia or joint ventures where appropriate, with other firms to gain
Institutional Strengthening
• Local associations need institutional support for the further development of the professional
resources.
• There is a need for an agreed standard for accrediting skilled artisans, tradesmen and craftsmen.
This is the responsibility of the Caribbean Association of National Training Agencies (CANTA).
• There should be mandatory local registration of all professionals and firms as a precondition for
• For regional equivalency and reciprocity, it is necessary that similar registration legislation be
• The Caribbean Accreditation Council for Engineering and Technology (CACET) should be
• There is a need for a system for reciprocal recognition of similarly registered and licensed
• To facilitate and encourage information flow through the local sector, especially documentation
• To carry out further studies into the performance of the construction sector for baseline data on
construction costs, educational and training programmes and human resources in the various
categories of skills.
• To initiate a process whereby Governments, developmental and lending agencies would provide
• To establish and maintain an up-to-date website on the Caribbean Single Market and Economy
and trade negotiations and agreements and their implications for the regional industry.
The Government of Trinidad and Tobago adopted a meticulous tendering process for the
procurement of the Interchange Project along the Uriah Butler Highway. This strategy involved a
delay in the process of approximately six months to allow local contractors to participate in the
project by entering into joint ventures with their foreign counterparts. This effort to include the
local content into the project proved useless because not a single local contractor submitted a bid.
After considerable due diligence and independent verification a contract was signed with foreign
contractor Vinci. Although this attempt was not successful, this strategy can be adopted for
future projects as a method for improving the efficiency of public procurement (Tack Chan
2009).
xlv
Since as early as 1987 there have been several attempts to reform the current public procurement
process. Weaknesses in this process include (Ministry of Finance of Trinidad and TObago 2005):
procuring agency of the State, while at the same time limiting its activities
and services are made at step 1 of the procurement cycle. These decisions
permeate the process and affect the award of the contract. In law, the CTB
has no direct involvement in the design of the Terms of Reference (TOR), nor
the preparation of Requests For Proposal (RFPs), nor the monitoring or the
execution of the contract. Further, after the award of a contract, all matters
that are dealt with fall within the domain of contract law to which the CTB
cannot be a party.
Even within its realm of responsibility, the CTB in many cases refers
delayed.
Some contractors, suppliers and consultants share the view that there
necessary to go back and forth from CTB to client. They argue that the
resultant delays affect tender prices and more often than not justify price
increases since the validity period of three months expires before a contract
is awarded.
(DFC), Build Own Lease Transfer (BOLT) and Build Own Operate Transfer
(BOOT) are used to shorten the procurement cycle. The Ordinance does not
State-owned enterprises and NIPDEC are fully responsible for their own
unnecessary parallel systems. While the CTB has striven for uniformity in the
tendering process, in practice this uniformity has not been achieved. The net
The current staffing and training of the CTB’s personnel constrains the
Currently, the office of the Chief State Solicitor prepares all major
staffed nor structured to deal efficiently with the volume and complexity of
selected State-owned enterprises under Section 20A (1) (c) of the Ordinance
thereby bypassing the regulatory oversight of the CTB. In most cases, these
contract and award sub-contracts using their own procurement rules and
procedures.
The CTB does not have the authority to regulate. The regulatory
and ensure compliance with the rules and procedures for the award and
Although the CTB receives and acts upon supplier complaints with
Each procurement agency keeps its own register for inviting bids, and
opportunities, the publication and status of bids and awards, or the progress
of major projects.
suppliers do not believe that they are being fairly considered in the tendering
process. There are concerns that some SOEs negate fair competition by the
such records and the maintenance period that is applicable to all procuring
practices;
the economic concerns, identify with the public interest, and impact the
is outlined below.
means the attainment of the best combination of price and quality to meet
procurement attains the best quality of property and services for the price
that is paid, or the lowest price for the acceptable quality of property and
services. It does not necessarily result in the lowest priced goods available or
the absolute highest quality available. It is the best combination of price and
quality to meet the particular need. An assessment of Value for Money must
take into account not only the immediate cost of property and services
payment;
and quality.
3.4.1.2 Transparency
rules and decision-making criteria. Bids are opened publicly and all decisions
are fully recorded and published. The public is therefore able to debate the
documents;
liv
letters of invitation
3.4.1.3 Accountability
of buying agencies are not only clearly identified but are held directly
Government, Parliament and the public. In conducting their duties, they are
reflect the policies and principles that are specified. In addition, they are
subject to heavy penalties and personal liability if the policies and principles
The UNCITRAL model law typifies this model. It prescribes in detail for
transactions that reflect the principles of value for money and good
sophisticated version of the current model of the CTB Ordinance. Like the
changing environment.
Generally the provisions in the UNCITRAL Model Law treat in detail with
the responsibility of these institutions. The law does not explicitly adopt the
core principles of value for money, transparency and accountability nor does
it explicitly draw the link between procurement and policy objectives. The
The conceptual basis of the legal framework of this model is the ethical
use of public money and public property by an agency within the prescribed
contracting;
process;
cycle;
ethics;
process.
lviii
3.4.3.1 Introduction
current system have led to the need to regulate procurement in new ways.
Tobago must therefore acknowledge the increasing use of these bodies and
achieve. The framework must reflect the various objectives and the relative
need to
for Value for Money – which by definition encompasses efficient and effective
delivery of the property and services for which public money is spent. It is
ultimately liable.
In addition, public accountability may exist for private money where that
money is used for a public purpose even though the spender may be a
The test lies not with the mode of incorporation or even the extent of
The proposed new procurement regime must deal therefore with all
components of the public procurement cycle and affect all involved in public
This Model addresses many of the weaknesses with the current system:
lxi
by the public;
guidelines;
3.5 Funding
Funding is one of the difficulties encountered by local enterprises (many of which are
small) in accessing the public procurement market. These include the high fixed costs of access
(regulation and prequalification costs), the high costs of tender information, the policy of
bundling contracts which favours large firms and financial constraints. The most critical
constraint to local construction firms winning contracts is lack of access to capital, particularly
working capital. One of the key advantages of Chinese contractors in construction markets is
their ready access to cheap finance from state owned banks. Foreign contractors often get tax
concessions on imported materials and equipment, concessions which are denied to domestic contractors,
particularly in construction. In a recent study, Ghana contractors complained of having to pay import
duties and VAT on metal framework imported from Spain, while foreign contractors can bring in such
lxii
items duty free (Wells and Hawkins 2008). The above factors combine to ensure that providers of
construction services from the least developed countries are often unable to compete for projects in their
own home markets. While supply side assistance is also needed, the fact remains that lack of access to the
market is the most critical factor inhibiting the development and growth of many small local producers.
3.5.1 Recommendations
The following list includes solutions that Government can adopt in order to get more local
• Lowering the cost of accessing tender information by either charging for the cost of
Government should also consider separating the purchase of materials from the provision
of labour services as this may give better outcomes in terms of utilizing local contractors and
suppliers. It would open up the public procurement market to the large number of labour
contractors who do not have the capital and are not willing to take the risk of supplying
materials. At the same time it would give the client greater control over the source and quality of
materials. This approach, however, requires strict controls on the purchasing, storing and issuing
of materials.
lxiii
and familiarity with new technology required for Mega projects is as a result of the level of
procurement experience and expertise in local actors. A quick review of Trinidad and Tobago’s
current local environment reveals that in this very heated construction industry with demand
exceeding supply for construction services there exists a high mobility of critical resources
(professionals, skilled and unskilled labour moving from company to company) and low
Local contractors in Trinidad and Tobago currently exhibit the following features which prove to
• Lack of expertise in certain specialized fields e.g. hotel renovations, smart buildings
3.6.1 Registration
A possibility exists that the local contractors are not familiar with the registration process
which ,may discourage local contractors and suppliers from tendering for public projects, This
dilemma is due to the absence of a system to efficiently provide suppliers of property and
3.6.2 Management
A failure of local contractors to adopt project management best practices can result in
foreign contractors being favoured by the Government. There practices mainly focus on efficient
resource and time management. It is known that local contractors in Trinidad and Tobago are
always busy, their resources are stretched and they fail to keep project delivery schedules and
cost overruns. Misuse or failure to implement project management strategies can result in poor
3.6.3 Labour
Mainly in the construction sector there is a shortage of labour, this problem poses a
disadvantageous situation to local contractors in that they stand the chance of being offered a
Britain’s Major Projects Association (MPA) defines major projects as “those which require
knowledge, skills or resources that exceed what is readily or conventionally available to the key
participants” (major Projects Association 2008). It is with this stipulation that the Government is
forced to procure mega-projects to foreign contractors since local contractors fail to posses the
required set of skills and knowledge for handling this type of project. Some recent mega-projects that
2. Outdoor stage at the St Ann’s residence of the prime minister – $10 million
• Vinci Construction:
• Genivar:
3.6.5 Recommendations
The following include strategies that can be adopted to improve the skills and competence of
• Government can devise a plan for the transfer of technology and building skills from the
• Benchmarking – In cases where a similar project exists in the world, the Government can
find out about the experience of those that have done it before; what worked; what failed
and why.
to tender invitation
process
• Establishment of programmes that enforce the use of project management best practices
Chapter 4 - Conclusion
The analysis of the challenges faced by the current public procurement system in Trinidad
and Tobago revealed its weaknesses and it also addressed possible outcomes. It was noticed that
there is a high level of integration and overlapping of the challenges and the recommendations
for one particular challenge may in fact eliminate the occurrence of another. For instance, the
presence of foreign contractors is highly related to the fact that local contractors are unable to
fund projects. Therefore, a solution to the funding issue will reduce the need for foreign
contractors which can further lead to a boost in the local content of Trinidad and Tobago and the
References
Archibald, Hart. Victor. "Procurement Practices in the Public Construction Sector." 2009.
Barkat, Amiram. "Mekorot and Yossi Maiman team for Trinidad water projects." 2010.
http://archive.globes.co.il/searchgl/The%20joint%20venture%20will%20develop,%20plan
%20and%20build%20water_s_hd_2L34oC38vDbmnC30mDJGuEJaqBcXqRMm0.html
(accessed April 20, 2010).
Bethel, Camille. "Local contractor praised." Trinidad Express, September 22, 2009.
Central Tenders Board. "Central Tenders Board of Trinidad and Tobago." In Central Tenders
Board of Trinidad and Tobago Information Booklet, 14.
Gumbs-Sandiford, and Anika. "It's open corruption." Trinidad Guardian, March 28, 2010.
Hart, Victor. Integrity in Public Procurement - Anti-Corruption Tools for Construction Projects.
Trinidad and Tobago Transparency Institute, 2008.
Lewis, T.A., and C.A.C. Imbert. "Policy Imperatives for CARICOM Trade in Construction
Services."
http://www.caricom.org/jsp/single_market/services_regime/concept_paper_construction.pdf
(accessed April 20, 2010).
Ministry of Finance of Trinidad and TObago. "Reform of the Public Sector Procurement
Regime." 2005.
Suite, Winston H.E. "Evolving Contract Procurement Systems, Pitfalls, Challenges and
Opportunities."
Tack Chan, CLint. "Foreign contractors coming to TT." Newsday, May 2, 2009.
Wells, Jill, and John Hawkins. Increasing local content in the procurement of infrastructure
projects in low income countries. Briefing note, Institute of Civil Engineers, 2008.