UB ENGINEERING LTD.

ID Task Name Duration Start Finish Predecessors Responsible Individual


Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 Appointment of Project 23 days Mon Fri 3/18/11 G.M. Bapat
Manager 2/21/11 Appointment of Project Manager

2 Town Planning Approval 20 days Mon Tue Patankar/Acidwala/Pansambal


2/21/11 3/15/11 Town Planning Approval
3 Tender Opening 1 day Sat 2/26/11 Sat 2/26/11 Hemal/Gurudas Rao
Tender Opening
4 Comparative Chart Final 5 days Mon Fri 3/4/11 3 Gurudas Rao/Vishal Jindal
2/28/11 Comparative Chart Final
5 Finalize and award 4 days Mon 3/7/11 Thu 4 UBEL
contract 3/10/11 Finalize and award contract
6 Factory Drawings Final 1 day Mon Mon Architect/UBEL/Ostan
Discussions 2/28/11 2/28/11 Factory Drawings Final Discussions
7 Prepare final drawings 8 days Tue 3/1/11 Wed 3/9/11 6 Architect
Prepare final drawings
8 Submit final drawings for 1 day Thu Thu 7 Architect
factory build 3/10/11 3/10/11 Submit final drawings for factory build
9 Initial Equity Infusion 11 days Wed 3/2/11 Mon Mahesh Sabnis
3/14/11 Initial Equity Infusion
10 Gram Panchayat NOC 3 days Fri 2/25/11 Mon Patankar/Hemal
2/28/11 Gram Panchayat NOC
11 Apply for MSEB 1 day Tue 3/1/11 Tue 3/1/11 10 Pansambal/Patankar
Permissions Apply for MSEB Permissions
12 Construction Start 1 day Fri 4/1/11 Fri 4/1/11 10,9,2 Contractor
Construction Start
13 Construction Complete 196 Sat 4/2/11 Wed 12 Contractor Construction Complete
days 11/16/11

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project1
Progress Rolled Up Milestone Group By Summary
Date: Fri 3/4/11
Milestone Rolled Up Progress Deadline
Summary Split

Page 1