Sei sulla pagina 1di 1

M/s.

Vinayaka Construction
Bangalore

Item Rate labour charges for Civil works Dt:29/12/2008

Sl Particulars Unit Rate


1 Earth work excavation Cft 5.00
2 1:4:8 concrete in formation 3” to 4” thick Cft 6.00
3 RCC in footing & pedestal column concrete Cft 6.00
4 Column concrete Cft 12.00
5 Roof & Beam concreteing Cft 7.50
6 BBM in 9” thick Sft 6.00
7 BBM in 4.5” thick Sft 5.00
8 Door & window fixing Each 200.00
9 Chajja Concreting Sft 6.00
10 Staircase step concreting Cft 12.00
11 Ceiling plastering including cleaning & paper removing Sft 5.50
12 Wall plastering Sft 5.00
13 Column plastering Sft 10.00
14 Beam Plastering Sft 10.00
15 Chajja bottom & top plastering Sft 10.00
16 Extermal plastering with sponge finish Sft 7.00
17 Chicken mesh coats rough & finishing (2 side Measurement) Sft 15.00
18 Hacking RCC surface + scafolding Sft 2.00
19 Hollow block 8”, 6”, 4” Sft 6.00
20 PCC Flagging including finish Sft 6.00
21 Starter Each 100.00
22 Stone masonry above floor level fill plinth Cft 6.00
23 Stone masonry below floor level Cft 6.00
24 Dressed stone masonty Cft 10.00
25 Solid block 4”,6”,8” thick Sft 6.00
Weather proof course including lifting material and finishing the
26 same Sft 15.00
27 Soling for footing Cft 6.00

Watch man salary Rs 500 per month including Sunday curing