Re: SAP MM MRP  

  Reply
Posted: Sep 3, 2009 6:33 AM   in response to: kirumoha

Hi,

Following steps need to be follow for configuring MRP

1. Plant Parameters for MRP (SPRO)


2. MRP type (MM)
3. MRP controller (MM)
4. Procurement Type(MM)
5. Special Procurement Type if applicable (MM)
6. Lot Sizing Procedure (MM)
7. Scheduling Margin Key(MM)
8. Scheduling Parameters for planned orders through (SPRO)

Detail:

1. Activate Plant Parameters for MRP(in SPRO)


2. MRP Type Customization(E.g, PD, M1,M2,, -in SPRO - But need not suposed to do without
client's permission)
3. MRP Controller (in SPRO)
4. Production Scheduler Profile (in SPRO)
5. Order type Dependent Paremeters(in SPRO)
6. Plant Parematers(in SPRO)
7. Scheduling Parameters(in SPRO)

Important T-Codes - OPL8,OPJH,OPKP

Note: Go to SPRO, select reference IMG,

Select Production - Material Requirements Planning, Here you will get all the details about the setting
for MRP

by

Hi,

Following steps need to be follow for configuring MRP

1. Plant Parameters for MRP (SPRO)


2. MRP type (MM)
3. MRP controller (MM)
4. Procurement Type(MM)
5. Special Procurement Type if applicable (MM)
6. Lot Sizing Procedure (MM)
7. Scheduling Margin Key(MM)
8. Scheduling Parameters for planned orders through (SPRO)

Detail:

1. Activate Plant Parameters for MRP(in SPRO)


2. MRP Type Customization(E.g, PD, M1,M2,, -in SPRO - But need not suposed to do without
client's permission)
3. MRP Controller (in SPRO)
4. Production Scheduler Profile (in SPRO)
5. Order type Dependent Paremeters(in SPRO)
6. Plant Parematers(in SPRO)
7. Scheduling Parameters(in SPRO)
Important T-Codes - OPL8,OPJH,OPKP

Note: Go to SPRO, select reference IMG,