Rev. No 0 1 2 3 4 5 6 7 8
Date 24.11.2009
This document as seen on ENKA Electronic Document Management System is the current and valid version. Hard
copies, unless stamped as “CONTROLLED COPY” should be treated as “INFORMATION ONLY”.
TABLE OF CONTENTS
1. INTRODUCTION
2. DEFINITIONS
2.1 Manhour
2.1.1 Spent Manhour
2.1.2 Planned Unit Manhour
2.1.3 Earned Manhour
2.1.4 Planned Manhour
2.2 Performance Factor
2.3 Physical % Complete
2.4 Construction Schedule
3. QUANTITY and UNIT RATE REPORT
3.1 Setting up
3.2 Man‐Hours
3.3 Physical % Complete
3.4 Performance Factor (P.F.)
4. WEEKLY CONSTRUCTION PROGRESS SUMMARY REPORT
4.1 Environmental, Health & Safety
4.2 Weather Reports
4.3 Construction Progress
4.4 Project Milestones
4.5 Procurement Status
4.6 Labour Force
4.7 Key Progress Evaluators
4.8 Area of Concern
4.9 Progress Highlights
YAJVA POWER PLANT PROJECT
PLANNING DEPARTMENT PROCEDURE
WEEKLY REPORTS
Doc.: . Rev.: 000 Date : 24.11.2009 Page : 3 / 14
1. INTRODUCTION
This procedure defines the weekly planning reporting systems for ENKA projects and
provides a guideline for the methodology and format of the weekly planning reports.
2. DEFINITIONS
2.1 Man-hour
One “man-hour” is one hour of one worker. If one worker can pour one 1 m3 concrete in 15
hours, then 1 m3 can poured in 15 man-hours. Theoretically, with three workers working, one
m3 conrete can be poured in five hours.
Spent man-hour is the actual man-hour spent on site during the execution of any given
activity.
“Planned unit man hour” is defined at the beginning of the Project, and provides the man-
hours required to perform of one unit of any given activity.
actual quantity
Formula 2.1.3
P. F.
Formula 2.2
Performance factor displays how efficiently the workforce is used while executing an activity.
If P.F. > 1 , the actual manpower spent is more efficient than planned
If P.F. < 1 , the actual manpower spent is less efficient than planned
Physical % complete = WF1 x AQ1 / WF1 x TQ1 + WF2 x AQ2 / WF2 x TQ2 + …… WFn x AQn / WFn x TQn
Formula 2.3
2.4 Construction Schedule
The Construction schedule is prepared based work activities, work sequence, quantities, and
resources. There should be a certain logic defining the work sequence, the quantities and
planned unit man-hours as well machinery and equipment shall define the duration of the
activities. There are also other elements of the construction schedule such as deliverables of
the owner, engineering, and procurement constraints etc. The Construction schedule shall be
prepared in a planning tool, either in Primavera or MS Project.
Quantity and unit rate report is prepared on the basis of installed quantity, and man-hours,
and it displays the comparison between what is planned and what the current situation is
(ahead & behind) in addition it monitors performance factor of each line of work.
• Physical % Complete: as explained above in item no: 2.3, all major activities and overall
physical % completions are calculated as per installed quantities.
• Man-hours: in this section, earned, planned and spent man-hours are calculated. As per the
calculations explained above (formula 2.1.3 , formula 2.1.4), earned and planned man-hours
are calculated, spent man-hours are taken from H.R. department reports. The HR department
reports shall be checked thoroughly. The planning engineers need to verify the installed
quantity as well.
• Performance Factor (P.F.): in Q.U.R.R. performance factor is monitored both on weekly and
cumulative up to date basis. P.F. is calculated and monitored as per formula 2.2.
3.1 Setting Up
To prepare Q.U.R.R,
a. Quantities for each activity.
b. Planned unit man-hour
c. Actual Quantities
d. Spent man-hours
are required.
YAJVA POWER PLANT PROJECT
PLANNING DEPARTMENT PROCEDURE
WEEKLY REPORTS
Doc.: . Rev.: 000 Date : 24.11.2009 Page : 6 / 14
After having all quantities and all man-hours ready, construction scheulde shall be prepared
as described in 2.4 in a planning tool, either Primavera and and for Q.U.R.R. preparation
purposes, previously calculated man-hours and/or the quantities must be distributed on a
weekly basis as per the schedule in another sheet as shown below,
Figure 3.1
3.2.1 Forecasted (or Planned) man-hour: Calculated total forecasted man-hours should be
punched to Q.U.R.R. (E column Table 3.1)
quantity overall
Formula 3.2.1
3.2.2 Earned man-hour up to date: from actual quantities (up to date) and planned unit man-
hours, earned man-hour is calculated and punched to Q.U.R.R. (F column)
3.2.3 Planned man-hour up to date: from construction schedule and planned unit man-hour,
planned man-hour up to date is calculated and punched to Q.U.R.R. (G Column);
quantity up to date
Formula 3.2.3
3.2.4 Spent man-hour up to date: spent man hour for activity should be taken from H.R.
department reports up to date and punched to Q.U.R.R. (H column)
YAJVA POWER PLANT PROJECT
PLANNING DEPARTMENT PROCEDURE
WEEKLY REPORTS
Doc.: . Rev.: 000 Date : 24.11.2009 Page : 8 / 14
3.2.5 Earned man-hour this week: actual quantity the reporting week shall be punched to
Q.U.R.R. (I Column)
3.2.6 Planned man-hour this week: the reporting weeks planned man-hour shall be punched to
Q.U.R.R. (J Column)
3.2.7 Spent man-hour this week: spent man-hour of each activity should be taken from H.R.
department reports for reporting week and punched to Q.U.R.R.(K Column)
Above mentioned 7 man-hours will display if the project is on schedule or not, how efficiently
workforces are used while executing an activity.
3.3.1 Planned up to date (Column A Table 3.1) : shows % planned complete up to date
3.3.2 Actual up to date (Column B Table 3.1) : shows % actual complete up to date
3.3.3 Planned this week (Column C Table 3.1) : shows % planned complete this week
3.3.4 Actual this week (Column D Table 3.1 : shows % actual complete this week
From the calculated spent and earned man-hours, performance factor is calculated as per
formula 2.2. In Q.U.R.R. “Performance Factor” consist of 2 parts;
Performance Factor up to date (Column L Table 3.1) : shows how efficiently workforces are
used up to date while executing an activity
YAJVA POWER PLANT PROJECT
PLANNING DEPARTMENT PROCEDURE
WEEKLY REPORTS
Doc.: . Rev.: 000 Date : 24.11.2009 Page : 9 / 14
Performance Factor up to date (Column M Table 3.1) : shows how efficiently workforces are
used within reporting week while executing an activity.
4.1 Environmental, Health & Safety : Here Lost Time Accidents (LTA) (Includes Fatalities),
total man hours up to date / this week (including productive, unproductive, indirect, staff
and all third party labor working on site), and total man hours w/o LTA up to date / this
week are reported.
Figure 4.1
4.4 Project Milestones: Forecasted and actual status of the selected milestones shall be
reported in this section.
YAJVA POWER PLANT PROJECT
PLANNING DEPARTMENT PROCEDURE
WEEKLY REPORTS
Doc.: . Rev.: 000 Date : 24.11.2009 Page : 10 / 14
4.5 Procurement status: Major deliveries within the reporting week, 4 months major deliveries
and purchase status are reported.
4.6 Labor status: Forecasted and actual; direct, indirect, unproductive, subcontractor, and etc.
comparisons are reported.
4.7 Key Progress Evaluators: Forecasted and actual status of the major materials are
reported in quantities.
4.8 Areas of concerns: The concerns that are effecting the progress are reported in this
section.
4.9 Progress Highlights: the major progress activities achived within the reporting week and
planned to be executed in the next reporting week is reported in this section.
YAJVA POWER PLANT PROJECT
PLANNING DEPARTMENT PROCEDURE
WEEKLY REPORTS
Doc.: . Rev.: 000 Date : 24.11.2009 Page : 11 / 14
ATTACHMENT A
Quantity and Unit Rate Report
YAJVA
A POWER
R PLANT PROJECT
P
PLANNING DEPAR
RTMENT PROCEDDURE
WEEKL
LY REPORT
TS
Doc.: . Rev.: 000 Datte : 24.11.2009
9 Pag
ge : 12 / 14
YAJVA POWER PLANT PROJECT
PLANNING DEPARTMENT PROCEDURE
WEEKLY REPORTS
Doc.: . Rev.: 000 Date : 24.11.2009 Page : 13 / 14
ATTACHMENT B
Weekly Construction Progress Summary Report
YAJVA POWER PLANT PROJECT