Projek Penyelenggaraan Lebuhraya Berhad

Traffic Safety Unit


Northern Region -Tsu Project -Weekly Progress Report ( 10/2010 - 08/3/2010 - 14/3/2010 )

Item no Project Title Location Client

1 P.S.O Km 128.10 Nb UEMC


2 P.S.O Km 127.10 Sb UEMC
3 Pavement Repair Km 129.60 Nb Propel - Ed
4 Pavement Repair Km 133.00 Nb Propel - Ed
5 Pavement Repair Km 136.00 Nb Propel - Ed
6 Pavement Repair Km 140.00 Nb Propel - Ed
7 Pavement Repair Km 145.00 Nb Propel - Ed
8 Pavement Repair Km 150.00 Sb Propel - Ed
9 P.S.O - Survey Km 153.00 Nb UEMC
10 Railling Inspection Sec N4 & Sec N5 Propel - Nbd
11 Installation For Wire Rope Sec N3 MRSB
12 Penang Bride Widenning Penang Bridge UEMC
13 P.S.O Km 259.00 Nb UEMC
14 P.S.O Km 229.00 Sb UEMC
15 Pedestrian Bridge Km 191.90 BB Bumi Aman
16 Package 5 Jelapang UEMC
17 Slope Rehab@ Rock Fence Km 263.90 Sb Impian Khidmat Sb
18 Slope Rehab@ Rock Fence Km 258,10 Sb Nce Conctructions

Prepared By
ARH - TSU - NR
/3/2010 - 14/3/2010 )

Start Date Completion Date Status Manpower Remarks


Driver Workers
1/9/2009 In progress 1 3 Section N3
1/9/2010 In progress 2 6 Section N3
2/1/2010 In progress Section N3
3/1/2010 10/2/2010 In progress Section N3
1/11/2009 In progress 1 5 Section N3
1/11/2009 10/2/2010 In progress 4 Section N3
1/11/2009 In progress 1 8 Section N3
1/11/2009 10/2/2010 In progress 1 3 Section N3
1/1/2010 10/2/2010 In progress 1 3 Section N3
3/1/2010 25/2/2010 In progress Section N3
3/2/2010 23/2/2010 In progress 1 3 Section N3
2006 In progress 3 6 Penang Bridge
1/7/2009 In progress 2 12 Section N5
1/9/2009 In progress 2 6 Section N5
10/11/2009 In progress 1 6 Section N4
2006 In progress 2 5 Section C1 & N5
3/3/2010 In progress 1 2 Section N5
11/3/2010 In progress 1 2 Section N5