AHMEDABAD BUS RAPID TRANSIT SYSTEM - "JANMARG"

PACKAGE 04 - PIRANA - DANILIMDA - MANINAGAR & DANILIMDA - CHANDOLA - NAROL -12.0 kM


RATE ANALYSIS FOR NP4 300 MM DIA RCC HUME PIPE

Sr.No Particulers Unit Rate Quantity Amount Remarks


1 NP4 600 DIA Rmt 1488.00 BOQ ITEM P-04
A Material Component

Concrete M-35 per Rmt Cum 3304.000 0.183 604.632 S.OR. 2005-2006

Steel per Rmt MT 29.000 0.012 0.347 S.OR. 2005-2006


Total 604.979
B Labour Component 883.021

2 NP4 300 DIA


C Material Component
Concrete M-35 per Rmt Cum 3304.000 0.043 142.072 S.OR. 2005-2006
Steel per Rmt MT 29.000 0.003 0.101 S.OR. 2005-2006
Total 142.173
D Labour Component 883.021

Total cost (C+D) 1025.194

Add tender premium 24.315 % 249.276


Cost of 300 MM DIA NP4 Pipe per Rmt 1274.470
AHMEDABAD BUS RAPID TRANSIT SYSTEM - "JANMARG"
PACKAGE 04 - PIRANA - DANILIMDA - MANINAGAR & DANILIMDA - CHANDOLA - NAROL -12.0 kM
RATE ANALYSIS FOR NP4 450 MM DIA RCC HUME PIPE

Sr.No Particulers Unit Rate Quantity Amount Remarks


1 NP4 600 DIA Rmt 1488.00 BOQ ITEM P-04
A Material Component

Concrete M-35 per Rmt Cum 3304.000 0.183 604.632 S.OR. 2005-2006

Steel per Rmt MT 29.000 0.012 0.347 S.OR. 2005-2006


Total 604.979
B Labour Component 883.021

2 NP4 450 DIA


C Material Component
Concrete M-35 per Rmt Cum 3304.000 0.124 409.696 S.OR. 2005-2006
Steel per Rmt MT 29.000 0.005 0.135 S.OR. 2005-2006
Total 409.831
D Labour Component 883.021

Total cost (C+D) 1292.852

Add tender premium 24.315 % 314.357


Cost of 450 MM DIA NP4 Pipe per Rmt 1607.209
Concrete quantity of NP-4 pipe

NP4 600 DIA


A-1 3.14/4 0.77 0.77 0.47
A-2 3.14/4 0.60 0.60 0.28
0.183 0.183

NP4 450 DIA


A-1 3.14/4 0.60 0.60 0.28
A-2 3.14/4 0.45 0.45 0.16
0.124 0.124

NP4 450 DIA


A-1 3.14/4 0.38 0.38 0.11
A-2 3.14/4 0.45 0.45 0.07
0.043 0.043

Bags per cum Consumption


M-25 9 450.00
M-35 10 500.00

Diff of cement consumption 1.00 Bags


Basic rate of cement 210.00 Bags
Total amount of cement 210.00 per Cum

Rate of M-25 3094.00 per Cum

Hence rate of M-35 3304.00 per Cum


0.38

0.38
Providing and casting in situ
precast controlled cement
concrete M.350 for
Prestressed concrete work
Cu.M 500-00