Parbati - II Project (Himachal Pradesh)

Features

SALIENT FEATURES
Location Distt. Kullu, Himachal Pradesh.
Approach Nearest Rail Head - Kiratpur & Nearest Airport - Bhunter.
Capacity 4x200 MW
Annual Generation 3108.66 MU (90% dependable year)
Project Cost Rs.3919.59 Crores (December 2001 price level)
H.P., Delhi, J&K, Punjab, Haryana, Rajasthan, U.P & Union
Beneficiary States
Territory of Chandigarh.
Year of Commissioning/Completion
March 2013 (As per MOU 2010-11)
Schedule

TECHNICAL FEATURES
 85 m high concrete Gravity dam.
 130 m high, 17m Dia Orifice type surge shaft.
 6 m dia 31.52 km long Head race tunnel.
 2 pressure shafts each of 1546 m length & 3.5 m dia.
 4 nos. Tail Race Channels 60m long 5 m x 4.5 m each.
 Surface power house containing 4 Pelton Turbine Generating units of  200 MW each.
 400 KV GIS Surface Switchyard with 2 out going 400 KV feeders.

 
Parbati - II Project
Introduction

The Parbati Hydroelectric Project (Stage-II) is a run-of-the-river scheme proposed to harness hydro
potential of the lower reaches of the river Parbati, The proposed scheme is 'inter basin transfer' type.
The river is proposed to be diverted at Village Pulga in Parbati valley and the Power House shall be
located at village Suind in Sainj valley. Thus a gross head of 862m between Pulga and Suind will be
utilized for generating 800MW power. The diverted discharge of the river Parbati has been further
augmented by diverting the discharge of various nallahs falling along the HRT alignment.
 