Sei sulla pagina 1di 40

CONSTRUCTION

OF
CROSS COUNTRY
PIPELINES

By: G. K. IYER (AGM.)

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Delivering excellence through people
Slide Number- 1 of 50
CROSS COUNTRY PIPELINE WORKS
„ OVERVIEW
„ MAIN PURPOSE
TRANSPORTATION OF MATERIAL/PRODUCT
- PIPELINE FOR GAS E.G. NATURAL GAS; LPG; LNG ETC.
- PIPELINE FOR LIQUIDS E.G. CRUDE OIL / PETROLEUM PRODUCT; WATER ETC.
- PIPELINE FOR SOLIDS E.G. IRON ORE ETC.

„ TYPES OF PIPELINE
- OFFSHORE SUBMARINE PIPELINE: LAID ON SEA-BED
- ONSHORE CROSS COUNTRY PIPELINE: LAID 1MTR UNDERGROUND

„ SOME MAJOR ADVANTAGES


- LOW COST OF TRANSPORTATION & ACCESSIBILITY TO REMOTE AREAS
- LESS TIME TAKEN FOR TRANSPORATION
„ SOME DISADVANTAGES
- HIGH INITIAL COST
- DEAD STOCK / INVENTORY IN PIPELINE
CONSTRUCTION OF CROSS COUNTRY PIPELINES
Engineers India Ltd – Delivering excellence through people
Slide Number - 2 of 50
CROSS COUNTRY PIPELINE WORKS
„ SOME OF THE MAJOR PIPELINES UNDERTAKEN BY EIL
1. 1986 – 36”/18” x 1800 Kms: HBJ (HAZIRA-BIJAIPUR-JAGDISHPUR) GAS P/L OF M/s GAIL
2. 1996 – 22”/14”/10” x 1450 Kms: KBPL (KANDLA-BHATINDA) PRODUCT P/L OF M/s IOCL
3. 1997 – 36” x 505 Kms: GREP (HBJ UP-GRADATION) GAS P/L OF M/s GAIL
4. 1998, 2003, 2007 – 18”/14” x ~1200 Kms: MMPL PH-1,2 &3 (MUMBAI-MANMAD-INDORE-
DELHI) PRODUCT P/L OF M/s BPCL
5. 2000 – 16” x 1269 Kms: JLPL (JAMNAGAR-LONI) LPG P/L OF M/s GAIL
6. 2002 – 16”/14” x 220 Kms: VSPL (VIJAIWADA-SECUNDRABAD) PRODUCT P/L OF M/s HPCL
7. 2002 – 18”/14” x 289 Kms: CKPL (COCHIN-KARUR) PRODUCT P/L OF M/s PETRONET LTD.
8. 2003 – 24”/24” x 380 Kms: MBPL (MANGLORE-BANGLORE) PRODUCT P/L OF M/s HPCL
9. 2003 – 12”/10” x 600 Kms: VSPL (VIZAG-SECUNDRABAD) LPG P/L OF M/s GAIL
10. 2004 – 42” x 610 Kms: DVPL (DAHEJ-VIJAIPUR) GAS P/L OF M/s GAIL
11. 2006 – 18” x 1037 Kms: MDPL (MUNDRA-DELHI) PRODUCT P/L OF M/s HPCL
12. 2006 – 14”/12” x 343 Kms: PSPL (PUNE-SHOLAPUR) PRODUCT P/L OF M/s HPCL
13. 2007 – 16” x 401 Kms: NSPL (NUMALIGARH-SILIGURI) PRODUCT P/L OF M/s OIL
14. DPPL PH-1&2 (DHABOL-PUNE) GAS P/L OF M/s GAIL PH-2 IN PROGRESS
15. VBPL (VADINAR-BINA) CRUDE OIL P/L OF M/s BORL IN PROGRESS
16. VDBPL (VIJAIPUR-DADRI-BAWANA) GAS P/L OF M/s GAIL IN PROGRESS
17. MBPL (MUNDRA-BHATINDA) CRUDE OIL P/L OF M/s HMPL IN PROGRESS
18. BKPL (BINA-KOTA) PRODUCT P/L OF M/s BPCL IN PROGRESS
CONSTRUCTION OF CROSS COUNTRY PIPELINES
Engineers India Ltd – Delivering excellence through people
Slide Number - 3 of 50
CROSS COUNTRY PIPELINE WORKS
VADINAR – BINA CRUDE PIPELINE PROJECT : 24” DIA x 931 KMS., API – 5L X70 GR., CAPACITY - 6 MMPTA

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - 4 of 50
CROSS COUNTRY PIPELINE WORKS
VADINAR – BINA CRUDE PIPELINE PROJECT : 24” DIA x 931 KMS., API – 5L X70 GR., CAPACITY - 6 MMPTA

RT- BINA

IP2-SANDAVATA

IPS2- BEWARI

IP1 -SIDHASAR

IPS1- THAMNA SP5-


208 KMS.
SP4-
DT-VADINAR SP1- SP2- SP3- 219 KMS.
160 KMS. 199 KMS. 145 KMS.

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - 5 of 50
CROSS COUNTRY PIPELINE WORKS

I. CONSTRUCTION METHODOLOGY

II. TYPE OF CONSTRUCTION EQUIPMENTS

III. TYPES OF CONTRACTORS REQUIRED FOR


CONSTRUCTION OF PIPELINES

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - 6 of 50
CROSS COUNTRY PIPELINE WORKS

I. CONSTRUCTION METHODOLOGY

ƒ QA/QC, CODES, SPECN., & HSE REQUIREMENTS

ƒ LINEPIPES COATING AT YARD & DUMPSITE

ƒ LAYING OF PIPELINE

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - 7 of 50
CROSS COUNTRY PIPELINE WORKS
„ QA/QC IN PIPELINE

‹ Review & Approval of Contractor’s QAP for all activities

‹ Review & Approval of Contractor’s Inspection & Test Plans (ITP’s)


with reference to standard ITP’s of EIL before start of work

‹ Review & Approval of Job Procedures & Inspection Formats


based on ITP’s for all Pipeline activities

‹ Quality Audits & Resolution of Non Conformances (NC’s)


observed during execution of work & quality audits

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - 8 of 50
CROSS COUNTRY PIPELINE WORKS
„ CODES & STANDARDS
Following are the reference/codes followed during Line-pipe Coating & Laying of Pipeline:

1. DIN 30670 : 3LPE Coating of Line-pipes

2. AWWA 203 : Coal Tar Enamel Coating of Line-pipes

3. API 1104 : Welding of Pipeline & Related Activities

4. API 1105 : Construction Practices for Oil & Products Pipelines

5. ASME B 31.4 : Pipeline Transportation System for Liquid Hydrocarbon

6. ASME B 31.8 : Gas Transmission and Distribution Piping System

7. OISD B 141 : Design and construction requirements for cross-country


Hydro-carbon Pipelines

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - 9 of 50
CROSS COUNTRY PIPELINE WORKS
‰ RELEVANT EIL SPECN. & STANDARDS

Following are the relevant EIL Specification & Standards for Coating & Laying of Pipeline:
1. 6-71-0001 : Standard specification for Line pipes, Valves, Fittings,
to 6-71-0040 Scrapper Launcher / Receiver, Pig signaller etc.
2. 6-71-0041 : Standard specification for 3LPE Coating
3. 6-71-0042 : Standard specification for CTE Coating Onshore Pipeline.
4. 6-71-0044 : Standard specification for Field Jt. Coating Onshore Pipeline.
5. 6-71-0046 : Standard specification for Conc. Coating Onshore Pipeline.
6. 6-71-0051 : Standard specification for Pipeline Construction (Onshore)
7. 6-71-0052 : Standard specification for Pipeline Construction, Road, Rail,
Minor Water Crossings
8. 6-71-0053 : Standard specification for Major Water Crossings (Conventional)
9. 6-71-0054 : Standard specification for Pipeline River Crossings by HDD
10. 6-71-0055 : Standard specification for Hydro-testing of Onshore Pipelines
11. 6-71-0057 : Standard specification for Pipeline Markers
12. 6-82-1901 : Standard Inspection & Test Plans (ITP’s) for Pipeline Activities
to 6-82-1925

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - 10 of 50
CROSS COUNTRY PIPELINE WORKS
‰ HSE IN PIPELINE

ƒ Review of contractors’ HSE plan & documents with reference to


EIL specification no. 6-82-0001, Rev-4.

ƒ Construction hazards identification & mitigation measures

ƒ Ensuring compliance to HSE requirements by contractors

ƒ First-Aid & Fire fighting facilities

ƒ HSE promotion activities

ƒ HSE Reporting including statistics

ƒ HSE Audits & Resolution of Non-conformances

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - 11 of 50
CROSS COUNTRY PIPELINE WORKS
„ LINEPIPE COATING AT YARD

„ TYPES OF EXTERNAL YARD COATING


- 3 LAYER POLYETHELENE (3LPE) COATING / FBE COATING
- COAL TAR ENAMEL (CTE) COATING

„ 3LPE COATING / ONE LAYER FBE COATING


-1st LAYER: FUSION BONDED EPOXY – 50 MICRONS (200 TO 300 MICRONS - FBE COATING)
- 2nd LAYER: SIDE EXTRUSION ADHESIVE (LDPE) – 200 TO 300 MICRONS
-3rd LAYER: SIDE EXTRUSION POLYETHELENE (LDPE / MDPE / HDPE) - > 2 MM

„ CTE COATING (HOT APPLIED)


- 1st COAT: COAL TAR PRIMER – 50 TO 75 MICRONS
- 2nd COAT: 1st HOT COAL TAR ENAMEL LAYER WITH INNER WRAP– > 1 MM
- 3rd COAT: 2nd HOT COAL TAR ENAMEL LAYER WITH INNER WRAP– > 1 MM
- FINAL COAT: COAL TAR IMPREGNATED OUTER WRAP – 600 TO 750 MICRONS

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - 12 of 50
CROSS COUNTRY PIPELINE WORKS
„ LINEPIPE COATING AT YARD Contd…

„ COATING PROCESS:
1) BARE PIPES VISUAL INSPECTION 2) SHOTBLASTING AND VISUAL INSPECTION
- PIPE NO., HEAT NO., LENGTH, DIA, THK ETC. - ROUGHNESS CHECK ON BODY
- BEVEL & BODY DAMAGES E.G. DENTS, GOUGES ETC. - BODY DENTS & GOUGES

BARE PIPES STACKING YARD SHOT BLASTING OF PIPES

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - 13 of 50
CROSS COUNTRY PIPELINE WORKS
„ LINEPIPE COATING AT YARD Contd…

„ COATING PROCESS:
3) PRE-HEATING OF PIPES & PRIMER / EPOXY APPLICATION (PIPES TO BE PREHEATED TO 200 0 C BY
INDUCTION COIL/ GAS OVEN)
- CHECK FOR PIPE TEMP BY DIGITAL TEMPERATURE GUAGE & UNIFORM SPRAY
SPRAY OF EPOXY ON PIPE

BARE PIPES PRE HEATING

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - 14 of 50
CROSS COUNTRY PIPELINE WORKS
„ LINEPIPE COATING AT YARD Contd…

„ COATING PROCESS:
4) COATING APPLICATION
- CHECK TEMP OF EXTRUDERS, PE FILM, ADHESIVE FILM, COAL TAR ENAMEL
ENAMEL ETC.

INNER/OUTER WRAP & COAL


ADHESIVE & PE APPLICATION
TAR ENAMEL APPLICATION

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - 15 of 50
CROSS COUNTRY PIPELINE WORKS
„ LINEPIPE COATING AT YARD Contd…

„ COATING PROCESS:
5) COOLING OF COATED PIPES IN COOLING TUNNEL & VISUAL INSPECTION OF COATED PIPES
- CHECK COOLING WATER TEMP, VISUAL DAMAGE TO COATING, COATING THK. ETC.

COATED PIPE COOLING TUNNEL 3LPE COATING THICKNESS CHECK CTE COATING THICKNESS CHECK

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - 16 of 50
CROSS COUNTRY PIPELINE WORKS
„ LINEPIPE COATING AT YARD Contd…

„ COATING PROCESS:
6) HOLIDAY TESTING, REPAIR OF COATING & TESTING
- CHECK FOR HOLIDAY AT 25KV FOR 3LPE COATING & 15KV FOR CTE COATING
COATING
- MARK PIPES FOR TESTING E.G. PEEL TEST, AP TEST, IMPACT TEST ETC.
ETC. & COATING REPAIR

RING HOLIDAY TESTING MARKING OF TESTING

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - 17 of 50
CROSS COUNTRY PIPELINE WORKS
„ LINEPIPE COATING AT YARD Contd…

„ COATING PROCESS:
7) EXTERNAL PAINTING (IF REQD) AND STACKING IN YARD
- THK OF PAINT, MARKING ON COATING PIPES, COATING ACCEPTANCE NO., ROW HEIGHT ETC.

COATED PIPES EXTERNAL


COATED PIPES STACKING YARD
PAINTING

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - 18 of 50
CROSS COUNTRY PIPELINE WORKS
„ DUMP SITES FOR STORAGE OF COATED PIPES
„ ACQUIRING OF LAND & DEVELOPMENT OF DUMP SITE
- GRADING OF LAND, PROVIDING TEMPORARY FENCING, BARRIER GATE , GUARD
GUARD ROOM AND SECURITY
- PROVIDING INTERNAL ROADS (WBM) FOR TRAILER MOVEMENT & AREA LIGHTING
LIGHTING WITH DG SET
- PROVIDING SAND ROWS FOR STACKING OF COATED PIPES

„ HANDLING OF COATED PIPES


- ADEQUATE CRANES WITH PADDED HOOKS FOR UNLOADING / LOADING OF COATED
COATED PIPES IN TRAILERS
- STACKING OF COATED PIPES ON SAND ROWS
- HOLIDAY CHECK AND VISUAL CHECK INCLUDING GUAGE PLATE PULL TEST BEFORE DESPATCH TO SITE

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - 19 of 50
CROSS COUNTRY PIPELINE WORKS
„ PIPELINE LAYING ACTIVITIES:

‹ ROU SURVEY
‹ ROU CLEARING AND GRADING
‹ STRINGING
‹ TRENCHING
‹ BENDING
‹ WELDING
‹ FIELD JOINT COATING
‹ LOWERING
‹ BACKFILLING
‹ CROSSING
‹ TIE-INS
‹ HYDROTESTING
‹ PIPELINE MARKERS, CLEAN UP & RESTORATION
‹ STATION WORKS
‹ MAGNETIC PIGGING & EGP – PRE COMMISSIONING ACTIVITY

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - ___of 50
CROSS COUNTRY PIPELINE WORKS
„ PIPELINE LAYING ACTIVITIES..Contd.:
„ ROU SURVEY
ƒ Installation of Bench Marks, Turning Points
ƒ Stake markers in center line of pipeline at a distance of max.100m for centre line and for
horizontal bends10 m. and reference point for same
ƒ Stake two ROU markers at least at every 100m, Painted in red and numbers in white in
direction of flow.
ƒ Chainage markers at every 250 m
„ ROU CLEARING & GRADING
ƒ All obstacles causing hindrance in construction / laying pipeline are removed.
ƒ Entire ROU is Graded for movement of equipments and vehicle.
ƒ Temporary approaches/bridges, if required, are constructed for movement of equipments,
vehicles & personnel’s
„ STRINGING
ƒ Stringing shall be done after blasting & trenching when ROU is in rocky area .
ƒ Coated Pipes shall be strung on approved soft earth/sand filled bag and wedge in such a
way that bottom of coated Pipe remain above ground
ƒ Pipes shall be supported at minimum two locations
ƒ Pipe number, Heat number, coat number & length shall be transferred and recorded in
serial order
CONSTRUCTION OF CROSS COUNTRY PIPELINES
Engineers India Ltd – Delivering excellence through people
Slide Number - ___of 50
CROSS COUNTRY PIPELINE WORKS
ROU CLEARING & GRADING AND PIPELINE STRINGING ACTIVITY

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - ___of 50
CROSS COUNTRY PIPELINE WORKS
„ PIPELINE LAYING ACTIVITIES ..Contd.:
„ TRENCHING
ƒ Trench excavation is carried out along staked centerline of Pipeline
ƒ The width of excavation for trench shall be minimum (pipe diameter plus 200mm either side)
ƒ Depth of trench shall be as specified (Normal= 1M; Road= 1.2M; River= 1.5M; Rly.= 1.7M etc)
ƒ In case of trenching in rocky areas, blasting is performed with the guidelines /Safety Rules
of Chief Controller of explosives, Nagpur.
ƒ In case where rock/gravel or murrum/hard soil is encountered in the bottom of trench,
padding material (minimum compacted thickness of 150 mm) shall be provided.
ƒ When up-floating of the pipeline after backfilling is anticipated, antibuoyancy measures are
provided in such areas e.g. weighing by applying continuous concrete, installing saddle
weights etc.
„ BENDING
ƒ For changes in vertical & horizontal alignment, pre-fabricated cold field bends are provided
ƒ Over-bends are made in a manner that centre of bend clears the highest point of trench
bottom. Sag bends shall fit the bottom of the trench. Side bends shall have specified
clearance to the outside wall of trench.
ƒ The radius of cold field bends shall not be more than 40 times the dia. of pipe (for 18” inch
and above) and 30 times the dia. of pipe (for 18” inch below).
ƒ Pipes with longitudinal welds are bent a way that weld lies in the plane passing through the
neutral axis of bend
CONSTRUCTION OF CROSS COUNTRY PIPELINES
Engineers India Ltd – Delivering excellence through people
Slide Number - ___of 50
CROSS COUNTRY PIPELINE WORKS
PIPELINE TRENCHING ACTIVITY

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - ___of 50
CROSS COUNTRY PIPELINE WORKS
PIPELINE BENDING ACTIVITY

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - ___of 50
CROSS COUNTRY PIPELINE WORKS
„ PIPELINE LAYING ACTIVITIES.. Contd.:
„ WELDING
ƒ Welding Procedure Specification (WPS) to be followed for the welding is qualified and the
Procedure qualification record (PQR) is approved before start of welding. Approved brand of
electrodes are used for welding. Physical properties of the weld produced by an electrode
shall not be less than minimum value of base metal. Electrode qualification and batch record
are maintained.
ƒ Each pipe shall be thoroughly checked internally & externally for visual defect/ damage and
cleaned internally by compressed air blowing.
ƒ Damaged end shall be cut and re-bevelled with beveling machine. All new bevels shall be 100%
dye penetrant /MPI tested and Ultrasonically tested for any lamination.
ƒ Use of internal clamp is mandatory for pipe dia.> 10”. Except tie in joints, fitting etc. In such
case external clamps are used.
ƒ Each joint shall bear an identification number which shall be followed for NDT
ƒ The number of welders, and welding sequence, speed etc. should be similar to that of adopted
in approved welding procedure
ƒ Radiography examination of 100 % girth weld is carried out. Weld shall meet the requirement
of API 1104. In addition 100% ultrasonic inspection is required for critical weld joints i.e. tie in,
welding of valves etc. joints which have not undergone pressure testing i.e. GOLDEN TIE-Ins.
ƒ Repair is limited to maximum 30% of the weld length. Weld containing cracks shall be cut and
re-bevelled to make a joint.
ƒ Destructive testing of weld joints are done for 0.1% of the total numbers of welds completed.
CONSTRUCTION OF CROSS COUNTRY PIPELINES
Engineers India Ltd – Delivering excellence through people
Slide Number - ___of 50
CROSS COUNTRY PIPELINE WORKS
PIPELINE MAINLINE WELDING ACTIVITY

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - ___of 50
CROSS COUNTRY PIPELINE WORKS
AUTOMATIC WELDING CREW FOR MAINLINE JOINT MANUAL WELDING OF MAINLINE JOINT

AUTOMATIC WELDING OF MAINLINE JOINT AUTO UT OF MAINLINE JOINT

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - ___of 50
CROSS COUNTRY PIPELINE WORKS
„ PIPELINE LAYING ACTIVITIES.. Contd.:
„ FIELD JOINT COATING

ƒ The cut-back areas of Coated Pipes where weld joints are made are to be Coated by Field
Joint Coating.
ƒ Field joint coating material is heat shrinkable wraparound sleeve used as anticorrosion
coating of buried onshore pipeline.
ƒ Sleeve consist of radiation cross-linked, thermally stabilized, ultraviolet resistant semi-
rigid polyolefin backing with a uniform thickness of high shear strength thermoplastic/co-
melt adhesive
ƒ The joint coating system shall consist of a solvent free epoxy primer applied to the pipe
surface prior to sleeve application. The surface area is blast cleaned to SA-2.5 followed by
Pre-heating of pipe surface, application of epoxy primer and application of sleeve by heat
shrinking.
ƒ Each sleeve joint is inspected by means of a full circle holiday detector set to DC voltage
at 25 KV (Pipe surface temperature below 50 degree Celsius) and thickness of sleeve
checked.
ƒ One out of 50 joints coating or one coating out of every day production shall be tested to
establish peel strength on steel and factory applied coating.

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - ___of 50
CROSS COUNTRY PIPELINE WORKS
PIPELINE FIELD JOINT COATING ACTIVITY

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - ___of 50
CROSS COUNTRY PIPELINE WORKS
„ PIPELINE LAYING ACTIVITIES.. Contd.:
„ LOWERING

ƒ Lowering shall commence after inspection of trench. Trench bottom shall be free from
pipe supports, stones, roots, debris, stakes, and rigid material. Padding shall be provided
in rocky/ murram area.

ƒ Lowering shall commence as soon as possible after completion of joint coating, Before
lowering in, complete check by a full circle holiday detector for pipe coating and field joint
coating at 15 KV is carried out (Speed 300mm /sec). Any damage shall be repaired.
Support/ skid points shall be thoroughly checked.

ƒ The pipeline must be laid without interruption for the whole or the length of section
available

ƒ Ends of the lowered pipeline section shall be closed with night cap to prevent ingress of
water, mud etc.

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - ___of 50
CROSS COUNTRY PIPELINE WORKS
PIPELINE HOLIDAY AND LOWERING ACTIVITY

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - ___of 50
CROSS COUNTRY PIPELINE WORKS
„ PIPELINE LAYING ACTIVITIES.. Contd.:
„ BACKFILLING
ƒ Backfilling shall be carried out immediately after pipeline lowering in trench after
inspection, so as to provide a natural anchorage for the pipeline, thus avoiding long
exposure of coating to high temperature, damaging action of adverse weather conditions,
sliding down of trench sides and pipeline movement in the trench.
ƒ Backfill material shall not contain any extraneous material or hard lumps of soil which can
damage pipeline or coating or leave the voids in backfilled trench.
ƒ After placing of initial backfill, proper compaction shall be done. The surplus material
shall be crowned (300 mm) directly over trench and adjacent excavated area on both side
of trench.
ƒ If trench are excavated in steep area where the slope is more than 10%, slope breakers
shall be installed to prevent erosion of backfill. Stabilization of backfill shall be done in
sandy area to have consolidated cover over the pipeline.
„ CROSSINGS
ƒ Cased & Un-cased crossings for Roads & Railways
ƒ Open cut & Horizontal Directional Drilling (HDD) for Minor & Major River Crossing
„ TIE-INs
ƒ The unconnected sections of the lowered pipeline sections at various locations have to be
welded, coated and backfilled to make the sections ready for post installation hydro test .
ƒ If a pup piece cannot be avoided for tie in, the minimum 1.0 m length shall be added.
CONSTRUCTION OF CROSS COUNTRY PIPELINES
Engineers India Ltd – Delivering excellence through people
Slide Number - ___of 50
CROSS COUNTRY PIPELINE WORKS
PADDING & BACKFILLING BOARING FOR CASED CROSSING

TIE-IN IN PROGRESS

TIE-IN WELDING IN PROGRESS


CONSTRUCTION OF CROSS COUNTRY PIPELINES
Engineers India Ltd – Delivering excellence through people
Slide Number - ___of 50
CROSS COUNTRY PIPELINE WORKS
„ PIPELINE LAYING ACTIVITIES.. Contd.:
„ HYDRO-TESTING
ƒ Hydrostatic test is performed on entire length of the pipeline. The maximum permitted length
is 50 Kms. Hydrostatic test diagrams indicating number of test sections and minimum and
maximum test pressure in each test section are prepared before performing hydrostatic test.

ƒ Hydrostatic test commence only after completion of all welding works so as to avoid/
minimize untested hydro-test joints/ Golden joints.

ƒ Hydro test includes all those sections which are tested earlier for Road, rail road crossings,
major water crossings etc.

ƒ Duration of hydrostatic test is minimum 24 hours after thermal stabilization. Hydro-static test
pressure for pipeline handling hydrocarbon in gaseous phase is 1.25 times the design
pressure in pipeline located in Class-1 & 2 locations and 1.4 times the design pressure if
pipeline located in Class-3 & 4 locations.

ƒ Before water filling, pipeline shall be cleaned with air driven pigs with spring loaded brushes
and chiseled to remove all mill scale, rust, sand etc. from the internal pipe section.

ƒ After successful cleaning and acceptance, gauging is carried out using gauging pig.

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - ___of 50
CROSS COUNTRY PIPELINE WORKS
„ PIPELINE LAYING ACTIVITIES.. Contd.:
„ HYDRO-TESTING..Contd,
ƒ After acceptance of gauging operation, un-inhabited water is pumped into the section using
four cup batching pigs which are launched at specific intervals.

ƒ After water filling operation, thermal equilibrium between pipeline and environment shall be
checked with thermocouples installed on the pipeline.

ƒ After thermal stabilization pressurization is carried out in cycles of 50% test pressure & 75%
test pressure and held for 1 hour at each test pressure and depressurized to zero pressure and
then pressurized to final test pressure. During each test pressure, two test shall be carried out
for calculation of air volume in the pipeline under test and on acceptance of air volume test the
section is held for 24 hours at Final test pressure and pressure and temperature recorded on
chart.

ƒ The hydrostatic test shall be considered positive if pressure has kept a constant value
throughout the test duration, except for change due to temperature effects. The pressure value
thus added shall be compared with initial value and the test shall be considered as acceptable
if the difference is less than or equal to 0.3 bar.

ƒ After positive test results, test shall be terminated . The pipeline shall be depressurized at
constant rate. Dewatering shall be carried out by using four cup pigs driven by compressed air.
Foam pigs shall be passed to complete the dewatering.
CONSTRUCTION OF CROSS COUNTRY PIPELINES
Engineers India Ltd – Delivering excellence through people
Slide Number - ___of 50
CROSS COUNTRY PIPELINE WORKS
„ PIPELINE ACTIVITIES Contd.:
„ PIPELINE MARKERS, CLEAN-UP AND RESTORATION
ƒ Following type of markers shall be fabricated and installed along the pipeline route such
that they do not cause any hindrance to the regular land user or traffic
− Aerial Markers : At every 5 Kms.
− Kilometer Markers : At every 1 Km. & as per Alignment sheet
− Pipeline Warning Markers : At Road / Railway / River Crossings & Stations / Terminals
− ROU Boundary Markers : At every 750 Mtrs. & as per Alignment sheet
− Direction Markers : At significant turning points
− Navigational Markers : At bank of Navigational Course
− OFC Markers : At OFC Joints

ƒ ROU and all sites used for construction of pipeline , water crossing and other structures
shall be restored as per satisfaction of authority having jurisdiction over it.
ƒ Damages to roads, bridges, fences etc. damaged during construction shall be restored to
original.
ƒ The bed of water course shall be restore to the original level. The banks and any
excavated area shall be restored to original levels . The banks shall also be stabilized.
ƒ On completion of clean-up, the ROU shall be restored to such stable and usable condition
as may be reasonably consistent with the condition of the ROU prior to laying the
pipeline. The release note from the land owner s regarding satisfactory indemnification
and restoration of land shall be obtained from land owner.

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - ___of 50
CROSS COUNTRY PIPELINE WORKS
„ PIPELINE ACTIVITIES Contd.:
„ SV / IP / DT, PS & RT STATION WORKS
ƒ Sectionalizing Valve (SV) are installed at regular intervals (around 25 to 40 Kms.) to isolate
pipeline section during emergencies like leakage in pipeline as per statutory requirements.
An SV station is installed at such locations having a unmanned control room with a guard
room and boundary wall. A lockable grill cage is provided over the Sectionalizing Valve
installation including piping and instrumentation to prevent tampering by unauthorized
persons and ensuring safety of pipeline operations.

ƒ Intermediate Pigging (IP) stations are installed at regular intervals (as per design ~ 150
Kms.) having a Pig Launcher and a Pig Receiver with Control room, Sump tank, Basket
Filters, guard room, boundary wall etc. to facilitate pigging of pipeline during routine
Operation and Maintenance.

ƒ Dispatch Terminal (DT), Pump Station (PS) & Receipt Terminals are provided at start,
intermediate & end locations of the Pipeline to facilitate handling and pumping of the
product through the pipeline. It comprises of Pig Launcher / Pig Receiver with Control
room, Mainline & Booster Pumps (DT/PS), Sump tank, Basket Filters, guard room, Firewater
system, boundary wall etc.

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - ___of 50
CROSS COUNTRY PIPELINE WORKS
TYPICAL SECTIONALIZING VALVE (SV) STATION

CONSTRUCTION OF CROSS COUNTRY PIPELINES


Engineers India Ltd – Delivering excellence through people
Slide Number - ___of 50
CROSS COUNTRY PIPELINE WORKS
„ PIPELINE ACTIVITIES Contd.:
„ MAGNETIC PIGGING & ELECTRONIC GEOMETRY PIGGING (EGP):
Pre Commissioning Activity
ƒ This is a part of pre-commissioning activity, which ensures that there is no deformity in
pipeline. This is done prior to filling the line with product.

ƒ Magnetic PIG loaded with high capacity magnets spread uniformly with high density
polythene four cup PIG is launched to remove ferrous debris, mill scale, electrode pieces
etc. The accumulated weight of this ferrous debris is checked after running the PIG through
pipeline section. When the collected weight of ferrous debris is within limit for specific
length of pipeline section, the line is ready for launching EGP tool.

ƒ After successful completion of magnetic pig run EGP tool is launched. This tool is mounted
with battery operated battery device, which gives the reduction in pipeline Dia. at specific
location in electronic form.

ƒ Any defect /deformity more than 3% of internal diameter of pipe (dent or ovality) is
physically verified at site. Defect of more than 5% internal diameter of pipe are repaired by
cutting the suitable length of pipe and re-welding and accepted after radiography.