Sei sulla pagina 1di 5

For the questions 1, 2, 3, 4, 5 draw a A - O - A diagram, find EST, EFT, LST, LFT of all the activities, calculate T

QUESTION 1
activity preceeding activity hours
a - 6
b - 8
c a 6
d a 12
e a 2
f c 8
g c 10
h c 10
i b,d 2
j f,j 4
k e,h,g,k 10
l e,h,g,k 30
m l 10
n m 8

QUESTION 2

PRECEE
JOB JOB DAYS TIME in days DING
ACTIVITY

a 13 -
b 8 a
c 10 b
d 9 c
e 11 b
f 10 e
g 8 d,f
h 6 e
i 7 h
j 14 g,i
k 18 j

QUESTION 3
duration
activity precedence
in days
a - 6
b - 5
c b 2
d c 2
e a,d 2
f d 1
g a,d 6
h e 5
i g,h 6
j i 2
k g,h 4
l j,k 3
m l 1

Question 4

expected
activity preceding activity timein
months
a - 12
b a 1
c a 6
d c 2
e b 1
f d,e 2
g d,e 4
h g half
i f 4
j i 1
k h,j 2
l k 1
m k 1
n m half
o l,n half
p o 1

QUESTION 5

expected
Activity predecessors duration
[days]
a - 2
b a 6
c b 12
d b 8
e c 6
f c 4
g c 3
h e,f,g 10
i h 9
j d,i 6
k j 3
l k 2
m l 1

QUESTION 6
[duration in days]
most
activity predecessor activity optimistic Pessimistic
likely
a - 5 4 6
b - 12 8 16
c a 5 4 12
d b 3 1 5
e d,a 2 2 2
f b 5 4 6
g c,e,f 14 10 18
h g 20 18 34

1) Draw a network for this project and find the critical path.what is the expected length of the critical path .what is th
2) WHAT IS THE PROBABILITY THAT THE LENGTH OF THE CRITICAL PATH DOES NOT EXCEED 60 DAYS

QUESTION 1 Pg 516 Q4,JK SHARMA


QUESTION2 Pg 522 Q9 JK SHARMA
QUESTION 3 Pg 556 Q13 JK SHARMA
QUESTION4 Pg 556 Q14 JK SHARMA
QUESTION5 Pg 557 Q16 JK SHARMA
QUESTION6 Pg 562 Q25 JK SHARMA
activities, calculate T E,TL of all the events.Identify Critical Path and estimate Earliest completion Time of the project.
ength of the critical path .what is the variance of the length of the critical path
DOES NOT EXCEED 60 DAYS

Potrebbero piacerti anche