PROJECT PANEL LOCATION

PANEL NAME DB-G BRANCH CIRCUIT PANEL BOARD SCHEDULE

PHASE AND VOLTAGE 3 PHASE,4W & G, 380 V/220 V


FEEDING SOURCE
LOAD DESCRIPTION
CONNECTED LOAD PER

S.OUTLET-COMPUTER STATION
DEMAND LOAD PER PHASE, VA
PHASE, VA

S.OUTLET-DATA & SECURITY


RATING OF INCOMER(MAIN

LOAD PER UNIT, VA


S.OUTLET-GENERAL USE
MCB TRIP RTG IN AMPS

CONDUIT SIZE, MM
CIRCUIT NUMBER

WIRE SIZE, MM2

WATER HEATER

HAND DRYER
FCU-HEATER

NOT IN USE

NOT IN USE

NOT IN USE

NOT IN USE

NOT IN USE

NOT IN USE

NOT IN USE

NOT IN USE

NOT IN USE
BREAKER)

LIGHTING
POLE, NO.

FCU-FAN

COOKER
REMARKS

A B C A B C

1 20 3X4 20 1 10 100 1000 900

2 20 3X4 20 1 10 100 1000 900

3 20 3X4 20 1 10 100 1000 900

4 20 3X4 20 1 10 100 1000 900

5 20 3X4 20 1 10 100 1000 900

6 20 3X4 20 1 10 100 1000 900

7 0 0

8 0 0

9 0 0

10 0 0

11 0 0

12 0 0

13 0 0

14 0 0

15 0 0

16 0 0

17 0 0

18 0 0

19 0 0

20 0 0

21 0 0

22 0 0
100 A MCB

23 0 0

24 0 0

25 0 0

26 0 0

27 0 0

28 0 0

29 0 0

30 0 0

31 0 0

32 0 0

33 0 0

34 0 0

35 0 0

36 0 0

37 0 0

38 0 0

39 0 0

40 0 0

41 0 0

42 0 0

43 0 0

44 0 0

45 0 0

46 0 0

47 0 0

48 0 0

TOTAL 2000 2000 2000 1800 1800 1800

TOTAL DEMAND PER PHASE INCLUDING 20


2160 2160 2160
% FUTURE LOAD

MAXIMUM DEMAND PER PHASE AFTER


2052 2052 2052
APPLYING SIMULTANEITY FACTOR

FEEDING CABLE SIZE-4 WIRE & GROUND CONDUIT SIZE, MM


S.OUTLET-DATA &

WATER HEATER
GENERAL USE

HAND DRYER
FCU-HEATER
COMPUTER

NOT IN USE

NOT IN USE

NOT IN USE

NOT IN USE

NOT IN USE

NOT IN USE

NOT IN USE

NOT IN USE

NOT IN USE
S.OUTLET-
S.OUTLET-

SECURITY
LIGHTING

STATION
FCU-FAN

COOKER

LOAD DESCRIPTION

UTILIZATION(DEMAND) FACTORS 0.9 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0

FREQUENCY 60 HZ.
TOTAL CONNECTED LOAD (KVA) 6.00 CURRENT (A) 9
MOUNTING SURFACE/RECESS

TOTAL DEMAND LOAD CONSIDERING


5.40 CURRENT (A) 8
UTILIZATION FACTORS (KVA)

TOTAL DEMAND LOAD+20 % FUTURE


6.48 CURRENT (A) 10
LOAD (KVA)
VOLTAGE (V) 380
PANEL SHORT
10 (kA)
CIRCUIT LEVEL
SIMULTANEITY FACTOR 0.95

MAXIMUM DEMAND AFTER


APPLYING SIMULTANEITY 6.16 CURRENT (A) 9
FACTOR(KVA)