PROCEDURE CHECKLIST FOR FM200 INSTALLATION

SITE: ROOM:

1. Smoke ionization detector integrity test

2. Sounder/flasher triggers

3. Smoke optical detector integrity test

4. 24Vdc fire bell triggers

5. After 30sec 24V is read on the auxiliary port of the activator

6. Breaking the MCP triggers the sounder/flasher

7. Gas cylinder normally charged

8. Installations neatly done

System checklist integrity completed.


Remarks:
……………………………………………………………………………………………………………………………
…………………………………………………………………………………………………………..
CLIENT CONTRACTOR SUBCON

Company: …………………………. …………………………… ………………………….


Staff Name:……………………….. …………………………… ..………………………..
Sign/Date:…………………………. …………………………… ………………………….

Hello Bola,
Ijebu Ode BSC Status is as follows
 
1. BSC offline commisioning has been done for 400TRX
2. Transmission link between BSC (B4015) and backbone (B5993) have been established
3. Currently the circuit between BSC-B4015 and lekki datacenter is being connected and loopback being done to
determine the E1's
4. Remaining Abis cables  are being terminated
 