OBRAS PEQUEÑAS

CIMIENTOS
HORMIGON CLASE H5
170 Kg cem./m3

Tabla de cálculo

Sector Largo (m) Ancho (m) Espesor (m) Volumen (m3) Sacos cem. Grava (m3)
1 8.3 1 1 8.30 33.20 6.31
2 75 0.6 0.9 40.50 162.00 30.78
3 150 0.6 0.8 72.00 288.00 54.72
4 0.00 0.00 0.00
5 0.00 0.00 0.00
6 0.00 0.00 0.00
7 0.00 0.00 0.00
8 0.00 0.00 0.00
9 0.00 0.00 0.00
10 0.00 0.00 0.00
TOTAL 483.20 91.81
Arena (m3)
4.81
23.49
41.76
0.00
0.00
0.00
0.00
0.00
0.00
0.00
70.06
OBRAS PEQUEÑAS

SOBRECIMIENTOS (sin armadura)


HORMIGON CLASE H-10
212,5 Kg cem./m3

Tabla de cálculo

Sector Largo (m) Ancho (m) Espesor (m) Volumen (m3) Sacos cem. Grava (m3)
1 1.1 1 1 1.10 5.50 0.83
2 0.00 0.00 0.00
3 0.00 0.00 0.00
4 0.00 0.00 0.00
5 0.00 0.00 0.00
6 0.00 0.00 0.00
7 0.00 0.00 0.00
8 0.00 0.00 0.00
9 0.00 0.00 0.00
10 0.00 0.00 0.00
TOTAL 5.50 0.83
Arena (m3)
0.64
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.64
OBRAS PEQUEÑAS

RADIER
HORMIGON CLASE H-15
255 Kg cem./m3

Tabla de cálculo

Sector Largo (m) Ancho (m) Espesor (m) Volumen (m3) Sacos cem. Grava (m3)
1 62 1 0.08 4.96 29.76 3.67
2 90 1 0.07 6.30 37.80 4.66
3 3 4 0.05 0.60 3.60 0.44
4 9 2 0.07 1.26 7.56 0.93
5 0.00 0.00 0.00
6 0.00 0.00 0.00
7 0.00 0.00 0.00
8 0.00 0.00 0.00
9 0.00 0.00 0.00
10 0.00 0.00 0.00
TOTAL 78.72 9.71
Arena (m3)
2.88
3.65
0.35
0.73
0.00
0.00
0.00
0.00
0.00
0.00
7.61
OBRAS PEQUEÑAS

PAVIMENTO
HORMIGON CLASE H-30
370 Kg cem./m3

Tabla de cálculo

Sector Largo (m) Ancho (m) Espesor (m) Volumen (m3) Sacos cem. Grava (m3)
1 3 5 0.08 1.20 10.44 0.84
2 0.00 0.00 0.00
3 0.00 0.00 0.00
4 0.00 0.00 0.00
5 0.00 0.00 0.00
6 0.00 0.00 0.00
7 0.00 0.00 0.00
8 0.00 0.00 0.00
9 0.00 0.00 0.00
10 0.00 0.00 0.00
TOTAL 10.44 0.84
Arena (m3)
0.68
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.68
OBRAS PEQUEÑAS

PILARES, CADENAS, LOSAS Y SOBRECIMIENTOS (armados)


HORMIGON CLASE H-20
297,5 Kg cem./m3

Tabla de cálculo

Sector Largo (m) Ancho (m) Espesor (m) Volumen (m3) Sacos cem. Grava (m3)
1 4 1 1 4.00 28.00 2.80
2 0.00 0.00 0.00
3 0.00 0.00 0.00
4 0.00 0.00 0.00
5 0.00 0.00 0.00
6 0.00 0.00 0.00
7 0.00 0.00 0.00
8 0.00 0.00 0.00
9 0.00 0.00 0.00
10 0.00 0.00 0.00
TOTAL 28.00 2.80

PILARES, CADENAS, LOSAS Y SOBRECIMIENTOS (delgados)


HORMIGON CLASE H-20
310 Kg cem./m3

Tabla de cálculo

Sector Largo (m) Ancho (m) Espesor (m) Volumen (m3) Sacos cem. Grava (m3)
1 3 5 0.08 1.20 8.76 0.74
2 0.00 0.00 0.00
3 0.00 0.00 0.00
4 0.00 0.00 0.00
5 0.00 0.00 0.00
6 0.00 0.00 0.00
7 0.00 0.00 0.00
8 0.00 0.00 0.00
9 0.00 0.00 0.00
10 0.00 0.00 0.00
TOTAL 8.76 0.74
Arena (m3)
2.24
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
2.24

Arena (m3)
0.70
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.70
OBRAS PEQUEÑAS

ESTUCOS EXTERIORES
ZONA SECA 1:4

Tabla de cálculo

Sector Espesor (m) Largo (m) Ancho (m) Volumen (m3) Sacos cem. Arena (m3)
1 0.00 0.00 0.00
2 0.00 0.00 0.00
3 0.00 0.00 0.00
4 0.00 0.00 0.00
5 0.00 0.00 0.00
6 0.00 0.00 0.00
7 0.00 0.00 0.00
8 0.00 0.00 0.00
9 0.00 0.00 0.00
10 0.00 0.00 0.00
TOTAL 0.00 0.00

ESTUCOS EXTERIORES
ZONA LLUVIOSA 1:3

Tabla de cálculo

Sector Espesor (m) Largo (m) Ancho (m) Volumen (m3) Sacos cem. Arena (m3)
1 0.025 1 80 2.00 18.80 1.98
2 0.00 0.00 0.00
3 0.00 0.00 0.00
4 0.00 0.00 0.00
5 0.00 0.00 0.00
6 0.00 0.00 0.00
7 0.00 0.00 0.00
8 0.00 0.00 0.00
9 0.00 0.00 0.00
10 0.00 0.00 0.00
TOTAL 18.80 1.98

ESTUCOS INTERIORES
ZONA SECA 1:5

Tabla de cálculo
Sector Espesor (m) Largo (m) Ancho (m) Volumen (m3) Sacos cem. Arena (m3)
1 1.4 1 1 1.40 8.96 1.55
2 0.00 0.00 0.00
3 0.00 0.00 0.00
4 0.00 0.00 0.00
5 0.00 0.00 0.00
6 0.00 0.00 0.00
7 0.00 0.00 0.00
8 0.00 0.00 0.00
9 0.00 0.00 0.00
10 0.00 0.00 0.00
TOTAL 8.96 1.55

ESTUCOS INTERIORES
ZONA HUMEDA 1:4

Tabla de cálculo

Sector Espesor (m) Largo (m) Ancho (m) Volumen (m3) Sacos cem. Arena (m3)
1 0.025 80 1 2.00 15.20 2.14
2 0.00 0.00 0.00
3 0.00 0.00 0.00
4 0.00 0.00 0.00
5 0.00 0.00 0.00
6 0.00 0.00 0.00
7 0.00 0.00 0.00
8 0.00 0.00 0.00
9 0.00 0.00 0.00
10 0.00 0.00 0.00
TOTAL 15.20 2.14
Aditivo (kg)
56.60
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
56.60
Aditivo (kg)
53.40
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
53.40
OBRAS PEQUEÑAS

MUROS, PILARES, CADENAS


297,5 Kg cem./m3

Tabla de cálculo

Sector Largo (m) Ancho (m) Espesor (m) Volumen (m3) Sacos cem. Grava (m3)
1 1960 1.2 0.07 164.640 1152.480 115.248
2 0.000 0.000 0.000
3 0.000 0.000 0.000
4 0.000 0.000 0.000
5 0.000 0.000 0.000
6 0.000 0.000 0.000
7 0.000 0.000 0.000
8 0.000 0.000 0.000
9 0.000 0.000 0.000
10 0.000 0.000 0.000
TOTAL 1152.480 115.248
Arena (m3) Agua (Aprox.)
74.911 21.897
0.000 0.000
0.000 0.000
0.000 0.000
0.000 0.000
0.000 0.000
0.000 0.000
0.000 0.000
0.000 0.000
0.000 0.000
74.911 21.897
OBRAS PEQUEÑAS

EMPLANTILLADOS
170 Kg cem./m3

Tabla de cálculo

Sector Largo (m) Ancho (m) Espesor (m)Volumen (m3) Sacos cem. Grava (m3) Arena (m3)
1 0.324 1 1 0.324 1.296 0.227 0.168
2 180 0.6 0.05 5.400 21.600 4.104 3.132
3 0.000 0.000 0.000 0.000
4 0.000 0.000 0.000 0.000
5 0.000 0.000 0.000 0.000
6 0.000 0.000 0.000 0.000
7 0.000 0.000 0.000 0.000
8 0.000 0.000 0.000 0.000
9 0.000 0.000 0.000 0.000
10 0.000 0.000 0.000 0.000
TOTAL 22.896 4.331 3.300
Agua (Aprox.)
0.040
12.528
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
12.568
OBRAS PEQUEÑAS

MORTERO DE PEGA
ALBAÑILERIA DE LADRILLO PRENSADO 1:3

Tabla de cálculo

Sector Largo (m) Ancho (m) Area (m2) Ladrillo Fiscal (un) Cem. (sacos) Arena (m3)
1 9.5 1 9.5 342 5.42 0.57
2 0 0 0.00 0.00
3 0 0 0.00 0.00
4 0 0 0.00 0.00
5 0 0 0.00 0.00
6 0 0 0.00 0.00
7 0 0 0.00 0.00
8 0 0 0.00 0.00
9 0 0 0.00 0.00
10 0 0 0.00 0.00
TOTAL 342 5.42 0.57

MORTERO DE PEGA
ALBAÑILERIA DE BLOQUE DE CEMENTO 1:3

Tabla de cálculo

Sector Largo (m) Ancho (m) Area (m2) Bloque (un) Cem. (sacos) Arena (m3)
1 3 5 15 188 3.60 0.36
2 0 0 0.00 0.00
3 0 0 0.00 0.00
4 0 0 0.00 0.00
5 0 0 0.00 0.00
6 0 0 0.00 0.00
7 0 0 0.00 0.00
8 0 0 0.00 0.00
9 0 0 0.00 0.00
10 0 0 0.00 0.00
TOTAL 188 3.60 0.36

MORTERO DE PEGA
ALBAÑILERIA DE LADRILLO ARTESANAL 1:4
Tabla de cálculo

Sector Largo (m) Ancho (m) Area (m2) Ladrillo artesanal (un) Cem. (sacos) Arena (m3)
1 55.6 1 55.6 2002 27.80 3.89
2 0 0 0.00 0.00
3 0 0 0.00 0.00
4 0 0 0.00 0.00
5 0 0 0.00 0.00
6 0 0 0.00 0.00
7 0 0 0.00 0.00
8 0 0 0.00 0.00
9 0 0 0.00 0.00
10 0 0 0.00 0.00
TOTAL 2002 27.80 3.89