Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
CCPM
Yasuaki Yamamoto
TAKAGI CO.,LTD
Plastic Mold Manufacturing Dept. Manufacturing Division
19 th May, 2016
Yasuaki Yamamoto
1990 ()
2012 ()
TOC20157
CCPM
yamamoto16@takagi.co.jp
Agenda
1. Company Overview
2. Background
3. Problem & Solution
4. Challenges
5. Results
6. Next Steps
7. Lessons Learned
www.tocpractice.com
Company Overview
www.tocpractice.com
Business Overview
Water
Purifier
Business
Watering
Business
Dies
&
Molds
1961
7,800
www.tocpractice.com
Customer Profile
Mold Manufacturing Business
Medical 1%
Sales
Building
Material
Others
2%
16%
Consumer
Electrics
3%
Automobile
35%
Commodity
10%
Internal
33%
www.tocpractice.com
Mold Manufacturing
Closed
Open
Fixed side
Moveable side
Molded
item
Assembly
Parts
Production
www.tocpractice.com
Process Flow
Delivery
Inspection
Adjust
TRY
Adjust
TRY
Assembly
Design
Order
received
Quotation
Parts Production
Business Needs
Increase Throughput (TP)
Implementation Timeline
2015
1
Jan
2
Feb
3
Mar
4
Apr
5
May
6
Jun
Concerto
Go-live
&
WIP
WIP
Reduction
7
Jul
8
Aug
9
Sep
10
Oct
Concerto
Go-live
Management
Debriefing
PJ
Task
Mgmt
Impl
PJ
Ctrl
Impl
&
CRS &
Solution
Design
Mfg. CCPM
Duration:
10w
www.tocpractice.com
11
Nov
WIP
WIP
Redu Task
ction Mgmt
Impl
Design CCPM
Duration:
4w
10
12
Dec
1st
TRY
Project A
Parts Production
Project B
Assembly
2nd
TRY
Short works
Adjust
2
Adjust
1
1st
TRY
Parts Production
Processing
Assembly
Assembly
Modify
C
Adjust
1
Repair
D
Short works
11
Problem Structure
Need to show
progress
Switch to another
task while waiting
input/decision/help
Wait time
Multitasking
Task/project duration
takes longer
Suddenly
adjustment
instruction comes
in after TRY
(Short work)
High WIP
Fixed schedule
www.tocpractice.com
12
Direction of Solution
What to change?
High WIP
Resource concentration
Fixed Schedule
Local and unclear priority
www.tocpractice.com
Full-Kit
Dont start tasks unless
preparation is completed
13
Project
Short
Work
Project Level Limit WIP by phase, and release projects by one-out & one-in
Parts Production
Phase
One-in
Assembly Phase
One-out
www.tocpractice.com
Workstream 1
Fixed side
Workstream 2
Moveable side
Workstream 3
Slide etc.
Fixed side
Moveable
side
Slide etc.
14
Machining
Electricdischarging
Machining
Process Flow
Fixed side
Moveable side
Slide etc.
Fixed side
Moveable side
Slide etc.
www.tocpractice.com
WIP = 3
Resources spread thin
No dependency among 3 workstreams
WIP = 2
Resourced concentrated
Strategically made dependency
between work-streams
15
Original schedule
(Date-driven)
Resolved resource
Low WIP & resource
contention
concentrated schedule
(but delayed)
www.tocpractice.com
16
Parts Production
One-in
Phase
Project completed
Assembly Phase
One-in
OK
One-out
One-out
Customer
Assessment
FK
1
FK
2
NG
Adjustment
WIQ1
WIQ2
Value
Short
work
One-in
Short work
One-out
FK
WIQ3
www.tocpractice.com
WIP = 5
17
www.tocpractice.com
18
Premachining
Machining
Electricdischarging
Machining
FK1
Assembly
FK
2
TRY
FK2
()
(T1)
(
)
(
)
(S)
www.tocpractice.com
19
D
E
D
C
www.tocpractice.com
20
Interruption
Interruption
Parts
Production
TRY
Assembly
Resource Concentration
Parts Production
Assembly
TRY
Assy
TRY
Project Buffer
Target
date
Milestone
Buffer
TRY
date
www.tocpractice.com
21
Operations Review
24:00
Buffer Recovery
Actions
Corrective
Actions/Change
Policy
Daily
www.tocpractice.com
Weekly
Monthly
22
Executive
Resources
www.tocpractice.com
Escalation
Task Mgr
Full-kit
Meeting
Escalation
Project Mgr/
Short work Mgr
Resource Mgr
Project Mgr
Escalation
Escalation
Resource Mgr
Executive
Operation
Review
Buffer
Recovery
Meeting
30min/mo
15min/wk
30min/wk
Task Mgr
Task
Update
Meeting
10min/day
Worker
Worker
Worker
Worker
Worker
23
Challenges
Scope of Projects & Measurements
We have defined our management scope & measurements with the view of
what is our responsibility as managers instead of controllable
Manage Work In Queue (WIQ) and release orders with earlier due dates
www.tocpractice.com
24
Result:
Production Cycle Time Reduction
Project Overall CT
Production CT
www.tocpractice.com
25
Result:
Increased Throughput
Project TP
Production TP
www.tocpractice.com
26
Results Summary
Before
Target
After
% Var.
(2015/7-12)
60d
45d
48d
20%
22.4d
11d
15d*
33%
Throughput
4/month
5.3/month
5.3/month
33%
This figure was achieved although average project size was 26% bigger than baseline.
20%
33%
reduced
60
d
48
d
Days
www.tocpractice.com
Throughput
33%
reduced
22
d
15
Days
increased
5.3
27
Employees Voice
What Went Well:
As workload situation and Projects progress can be recognized at a glance,
necessary information is shared between sales, design, and manufacturing.
By limiting number of projects, we can concentrate one mold production.
My role became clear.
We changed our mind for seeking faster production and setup.
Multi-skill development enhanced.
It seems that uptime of machines went up.
Areas For Improvement:
Feel lack of resources.
More workload required for managing execution.
Overtime is unavoidable when multiple molds should be delivered on same DD.
More amount of short works than expected, big urgent load
because of increased completion rate of projects?
Still have some difficulties to assign resources based on work priority.
28
Next Steps
Better management for short works
Applying CCPM to Mold Design division
Better Subcontract management
Further shrink of project overall cycle time
www.tocpractice.com
29
Applying CCPM to
Mold Design Div.
BackgroundTP of Mold Mfg. increased. For that, Mold Design Div. increased the release rate
of projects and increased in TP of Design as well, however had caused high WIP and longer CT.
ImplementationInvolved outsourcing resources in China, and implemented the CCPMs
three rules within one month
Achieved BenefitsCapability was expanded as design cycle times are shortened.
Significant reduction of delays. Manageability improved.
Before
Target
After
% Var.
(2016/3-4)
21d
10d
9d
57%
57%
reduced
21d
9d
Days
www.tocpractice.com
30
Lessons Learned
Management is important!!
Corrective actions to solve raised issues
Before) Leave everything to workers (noninterference)
New) Managers should interference when needed
31
www.tocpractice.com
32