Sei sulla pagina 1di 20

SCHEME

UDP-78 YR/2015-16

NAME OF WORK
Constructing CC road in various areas @ Anklav under UDP-78
(package-1)

CONSULTANT
INFINITE CIVIL SOLUTIONS PVT. LTD.
AHMEDABAD
Mob. : 99250 30601

INFINITE CIVIL SOLUTIONS PVT. LTD.

ISSUED TO: ___________________________________________________


CLIENT / OWNER NAME:
Anklav Nagar Palika , Anklav

Constructing CC road in various areas @ Anklav under UDP-78


(package-1)

YEAR 2016-2017

ISSUED BY
Date

:
:

________________________________

Consultant :
Infinite Civil Solutions Pvt. Ltd.
Infinite House, F.P. 25, Nr. Aditya Elegance, CIMS Hospital
road, Ahmedabad.
Mobile-9925030601

INFINITE CIVIL SOLUTIONS PVT. LTD.

Notice Inviting On-line Tender


Department Name

Nagarpalika

IFB No / Tender Notice No.

2/2016-2017

Name of Project

UDP-78 YR/2015-16

Name of Work

Constructing CC road in various areas @ Anklav under


UDP-78 (package-1)

Estimated Contract Value (INR)

4181550.78

Period Of Completion(in Months)

3 Month

Bidding Type

Open

Joint Venture

Not Applicable

Rebate

Not Applicable

Bid Document Fee :

Rs. 5000.00

Bid Document Fee Payable To :

Chief Officer Anklav Nagar Seva Sadan

Bid Security/EMD (INR) :

Rs. 42000.00

Bid Security/EMD In Favour Of :

Chief Officer Anklav Nagar Seva Sadan

Bid Document Downloading End


Date

24/06/2016

Pre Bid Meeting

21/06/2016

Last Date & Time for Receipt of


Bids

24/06/2016

Bid Validity Period

120 Days

Remarks

Physical submission of Tender fee, EMD and other


documents up to date 29/06/2016 in the office of Chief
Officer Anklav Nagar Seva Sadan during office hours.

Preliminary Stage

30/06/2016

12 :00 Hrs.

Pre-qualification Stage

30/06/2016

14 :00 Hrs.

Commercial Stage

30/06/2016

15 :00 Hrs.

INFINITE CIVIL SOLUTIONS PVT. LTD.

18 :00 Hrs.

18 :00 Hrs.

To,
The Chief officer
Anklav Nagar Palika , Anklav.
Dist. : Anand

Name of Work: Constructing CC road in various areas @ Anklav under UDP-78(package-1)

Dear Sir,
I/We am/are submitting here with the tender for the above duly filled and Signed amounting to Rs
_______________ (in words)__________________________including contingencies.
I/We have studied the drawings, conditions of tender specifications and willing to abide by the terms and
conditions mentioned.
I / We here by deposit the sum of Rs 42000.00 (Rupees Fourty Two thousand ) to 1 % (One percent ) of the
total cost as Earnest Money deposit by D.D./ F.D.R. NO._____________ Dated __________________in
favors of CHIEF OFFICER, ANKLAV NAGAR SEVA SADAN, ANKLAV.

Your Faithfully,
Dated signature of Contractor
Date:
Name:
Address:

INFINITE CIVIL SOLUTIONS PVT. LTD.

Qualification Criteria
1. No conditional tender shall be accepted.
2. The last date of accepting the tender is as per online Tender Notice.
3. The Consultant as well as the committee of Nagarpalika reserves the right to reject any tenders.
4. Contractor shall make and shall bear the running charges etc.
5. Site and drawing must be inspected before tendering.
6. Contractor should submit minimum two similar type of Govt.s work completion certificate (Form
3A) of same amount in last three years.
7. Contractor should have registration of required class with R&B or Govt. as contractor & registered
under special road category with R&B.
8. Submit Nationalize banks solvency certificate of current financial year of 20% value of tender cost.
9. Submit EPF No, service tax no, sales tax no & other required registration for contract work as per
Govts norms.
10. No rate escalation will be given in any case i.e. no star rate will be given. Civil supply cement will
be given on contractors demand & advance payment via Demand draft from contractor in the
name of civil supply dept.
11. RMC plant concrete is necessary for speedy & good quality work due to Monsoon.
12. Contractor who failed to match the above T&C will be liable to reject or disqualify

Dated Stamp & sign. Of Contractor


Checked by

ENGINEER
Anklav Nagar
palika

CONSULTANT

INFINITE CIVIL SOLUTIONS PVT. LTD.

ICSPL

CHAIRMAN
Anklav
Nagarpalika

CHIEF OFFICER
Anklav
Nagarpalika

NAME OF WORK: Constructing CC road in various areas @ Anklav under UDP-78(package-1).

TERMS OF PAYMENT
Defect Liability Period

24 Months (one year)

Period of Final Measurement

One Month

Date of Commencement

Date of Work Order

Time Limit

3 (six) Months

Liquidated Damages

Rs. 500.00 Per Day/As per Govt. norms.

Interim Certificate

Rs. As per work wise terms.

Retention (Interest Free)

(1)

Value of Work for

1 % As Earnest money

(With tender D.D./F.D.R.)


(2)

1.5 % Payable on acceptance of Tender

(3)

2.5 % from bills

Income Tax

2.24 % (Form bills) / As per Government Rules.

Testing Charges

1 % (From Bills)

Performance guarantee Money

5 % (From Bill) (will be released after

completion

of defect liability period)

Installment after virtual completion

5 % (Five Percent)

Period of Honoring Interim Certificate

15 (Fifteen) Days

Dated Sign of Contractor

INFINITE CIVIL SOLUTIONS PVT. LTD.

APPENDIX
Defects Liability Period

24 Months (one year)

Period of Final Measurement

One Month

Date of Commencement

Date of Work Order

Time Limit

3 (six) Months

Estimated cost

Rs 4181550.78

Earnest money deposit

Rs 42000.00 by DD/F.D.R. only in favor of The

Chief
Retention (Interest Free)

Officer, Nagar Palika Anklav.


:

(1)
(2)
(3)

1 % As Earnest money
(With tender D.D./F.D.R.)
1.5 % Payable on acceptance of Tender
2.5 % from running bills

Liquidated damages/ performance


Guaranty money

5 % (From bills)

24/06/2016

Document by R.P.A.D. only

29/06/2016

Insurance and compensation

By contractor.

Last date of online submission the


tender
Last date of receiving sealed tender

Of worksite & workers


++

Date:

INFINITE CIVIL SOLUTIONS PVT. LTD.

Sign of Contractor

GENERAL CONDITION OF CONTRACT


1.

The contractor shall have to attach a list of works executed so far.

2.

The quality and nature of all the materials to be used shall b according
to the specifications. The samples of these materials shall have to be
approved by the consultant before ordering them.

3.

Proper arrangements for the labours and workmen for all different types
of work shall be made by the contractor.

4.

The contractor shall bring to the Engineers or consultant knowledge in


writing for any extra terms during the works before execution and it
shall be charged reasonably according to the present market rates in
case of dispute consultant decision shall be final to both the parties
without appeal.

5.

The Contractor shall have to pay all the charges livable by authorities
concerned in connection with the work.

6.

the contractor shall have to deposit an amount stated in the appendix


(Rupees thirty one thousand against EMD) with the owner bearing no
interest as security for the due exaction of the work and completion of
the contract. The same will be returned to the contractor after one
month of the date of completion of the work.

7.

The owner will be at liberty to cancel some of the item from the contract
and hand over to some other contractor approved by the Engineer and
Consultant.

8.

The contractor shall be responsible for all damage to property and for
injury caused by the work or workmen or person. Animals or things
and to the supervisory staff of the Owner, Engineer & Contractor and to
the authorized visitors to the site. He shall offset any insurance
necessary, and hold the owner entirely fee from all responsibility.

INFINITE CIVIL SOLUTIONS PVT. LTD.

9.

The contractor will at his own expenses clear the site, set out all work
and provide all necessary labour, page, string, etc. to enable Engineer &
consultant to check all setting out contractor will correct all errors.

10.

The contractor shall have to enclose a Nationalize bank F.D.R.


amounting to 1 % of the cost of tender as Earnest money deposit in
favor of chief officer, Anklav Ngarpalika.

11.

Defect liability period will be of 24 month. i.e. 5% P.G.MONEY will be


released after 24 month. if there is any damage occurs, contractor
should have repaired immediately on his own cost. If he fails to do so
Nagar Palika will repair on behalf of the contractor and deduct the same
from P.G MONEY. Defect liability period will be after completion of
work.

12.

The contractor shall have to give binding for completing the work as per
specification & verbal instruction of the engineer to owner on a required
stamp paper.

13.

Contractor shall have to finish up the work within the stipulated time
limit it the contractor fails to do so, then the Engineer and owner are at
liberty to executer the work at the risk and cost of the contractor after
issuing the notice will in advance.

14.

Contractor shall have to provide all facilities to laborers as required


under labour Act. Of Government.

15.

The contractor shall have to keep First Aid Box on site.

16.

Necessary warning signal and caution boards shall have to be provide


the maintained by the contractor in order to avoid unexpected accident.

17.

The contractor shall not assign the agreement for sublet any portion of
the work without written consent of the Engineer.

INFINITE CIVIL SOLUTIONS PVT. LTD.

18.

The contractor shall have to engage an authoresss agent who may be


quite conversant with the technical supervision and to whom Engineer
or owner may pass instruction for work.

19.

No compensation shall be paid to the contractors for any bad quality of


work or workmanship rejected by the consultant.

20.

The water used in the work shall be drinkable and it should provided by
the contractor.

21.

The contractor shall on the request of the Engineer immediately dismiss


from the work person employed thereon by him who may in the opinion
of the Engineer be incompetent or misconduct himself and such person
not be again employed on the work without the permission of the
Consultant.

22.

The work shall not be considered as completed until the consultant has
certified in writing that they have been virtually completed and defects
liability period shall commence from the date of such certificated.

23.

General technical specifications attached with tender. What ever


applicable to project form the book in considered as tender application.

24.

All necessary drawing of project will be given by consultant.

25.

All the petty items of this work shall be carried out in workman like
manner.

26.

No Claim of contractor for any extra item shall be ascertained unless


the extra item done is claiming of clearly distinguishable form the item
of agreement and is carried out as per instruction of the Engineer in
charge and consultant.

27.

The contractor shall engage an experienced and qualified supervisor as


his authoresses agent for this work. They shall be responsible for taking

INFINITE CIVIL SOLUTIONS PVT. LTD.

from time to time orders regarding work from the engineer in charge
and carrying them properly.
28.

The contractor shall maintain work order book on work site and design
and carryout property the orders given by the engineer. This work order
book shall be surrendered to the department on completion of work.

29.

The contractor shall have to clear the site of work before commencing
the work and after completion of work without any extra claim.

30.

The contactor shall provide at his own cost all labour and adequate
facilities for lining out. Setting and checking his work and tacking
measurement of the same.

31.

The contractor shall have to maintain a regular account of receipt and


use of controlled materials purchased by him.

32.

The contractor shall provide at his own cost necessary accommodation


water supply and sanitary arrangement for his staff and labour and
shall pay direct to the authority concerned royalties and other charges.
He shall also comply with the regulation of the health department
regarding materials measures etc.

33.

Water required for execution work shall have to be supplied by


contractor at his own cost.

34.

Dewatering of trenches, foundation etc. shall be done by contractor at


his own cost during execution or all item of his work completion in all
respect.

35.

The contractor shall have to cart at his own cost, pipes specials and
other materials to site of work.

36.

The contractor shall provide diversion to the existing road if required as


directed by the Engineer in charge.

INFINITE CIVIL SOLUTIONS PVT. LTD.

37.

In addition to requisite store he contractor shall have to provide at his


cost suitable temporary office with covered area of 20 sqmt. With
necessary furniture for use of inspection staff whole on work. The office
and furniture on completion of the work shall be removed by the
contractor at his cost.

38.

The contractor shall be responsible to pay complete compensation to


his staff and to his labours according to labour compensation rules on
account of accidents and loss of lives etc. due to the accident.

39.

Any item not covered in the schedule-B but required to be executed be


out by the contractor at the rate for such item available in divisional
schedule of rates in forces in time of giving order for extra item.

40.

The details specification for materials unless otherwise specified in the


description of item shall apply and binding to contactor as narrated in
his tender.

41.

In case any dispute regarding specification works the specification as


per R & B department of state and other concerned department if any
standard specification for relevant shall be final and binding to the
contractor.

42.

In case in excavation line any disturb of telephone line, Electric line,


Drainage line, water supply line or any other shall be managed for
remove and reinstating with necessary materials by the contractor at
his own cost.

43.

In case in excavation for line or chamber necessary of dewatering


contractor shall be provide arrangement at his own cost.

44.

The Contractor shall bind for quality of work and his 5% (Five Percent)
deposit shall released after One Years of completion if work is satisfied
that times & after getting NOC from consultant.

INFINITE CIVIL SOLUTIONS PVT. LTD.

45.

Condition of administrative order must bind the contractor.

46.

Payment should be released as per the availability of grants.

47.

All the terms condition and technical specification of G.W.S.S. B/ PWD


hand book in force must bind the contractor.

48.

In the case of work for which there is no such specification, such work
shall be carried out in accordance with the standard specification or as
directed by E.I.C. and Consultant.

49.

In the even of a discrepancy between description in words and figures


quoted by a tenderer in the rates column, the description in words shall
prevail.

50.

Definition :
a. The contract document consists of the Agreement, The General
condition of the contract, specification and Bills of Quantities
including all modification thereof incorporated in the document
before the execution and the contract drawings prepared by the
Architect form time to time. These form the contract.
b. The Employer

: The President/Chief officer


Anklav Nagarpalika, Anklav.
Dist Anand.

The Consulting Engineer/


Architect

: Infinite Civil Solution Pvt. Ltd.


Ahmedabad.

Are those mentioned as such in the agreement and shall include


their legal representatives, assignees or successors. They are
treated through our contract document as if each were of the
singular number and masculine gender.
c. The date of virtual completion of a project or specified area of a
project is the date when construction is sufficiently completed in
accordance with the contract document as modified by any change

INFINITE CIVIL SOLUTIONS PVT. LTD.

or variation orders agreed by the parties, so that the owner can


occupy the project for the use it was intended.
51.

Schedule of Quantities :
The Schedule of quantities given in the contract bill are provisional and
are meant to indicate the intent of the work and to provide a uniform
basis for tendering, The employer reserves the right to increase or
decrease any of the quantities or to totally omit any item of work and
the contract shall not claim any extra or demand on these a rounds.

52.

Contract Drawing :
a. In general the drawings shall indicate dimensions positions and type
of constructions: the specifications shall indicate the quantities and
the methods : the bill of quantities shall indicate the quantum and
the rate for each item of work. Any work indicated on the drawings
and not mentioned in the specifications or vice versa shall e
furnished as through fully set forth in both. Work not specifically
detailed, called for, marked of the specified shall be the same as
similar parts that are detailed, marked or specified.
b. The contractors work shall not deviate form the drawing and the
specifications. The consulting Engineer / Architects interpretation of
these document shall be final and without appeal.
c. Errors or inconsistencies shall be promptly brought to the attention
of the consulting Engineer / Architects interpretation or corrections.
Local conditions which may affect attention. If at any time, it is
discovered that work is done which is not in accordance with the
contract drawings and specifications. The contractor of defective
work shall not be a basis for any claim for extension of time.

53.

Scope and intent :


a. Scope :
The general charter and the scope of the work in illustrated and
defined by the specifications and the Bills of quantities herewith
attached and by the signed drawings. If the contractor shall find
any discrepancy and/or the contract bills be shall immediately

INFINITE CIVIL SOLUTIONS PVT. LTD.

give to the employer a written notice specifying the discrepancy or


divergence and the consulting Engineer shall issue instruction in
regard thereto.
54.

Samples :
a. After the award of the contract, the contractor shall furnish for the
approval of the Employer, Consulting Engineer, with such
promptness as to cause no delay in his work or in that of any other
sub-contractor, samples required by the specifications shall e
delivered as directed by the Employer, consulting Engineer.
b. The Employer Consulting Engineer / Architect Shall Check and
approve such samples, with reasonable promptness only for
conformity with the design concept of the project and for compliance
with the information in the contract Documents. The work shall be
in accordance with approved samples.

55.

Progress Chart :
The Contractor shall prepare progress chart and submit the same for
approval of the authorities and for his record within twenty-one days
of the Award of the Contract. The Charts shall indicate the expected
date of commencement and completion of each of the items of the
work and shall be in form approved by the scheduling of samples
and approvals.

56.

Architect, Consulting Engineer, Status and Decision :


a. Consulting Engineer: Consulting Engineer shall periodically visit the
site to familiarize himself generally with the progress and the quality
of the work and to determine in general if the work is proceeding in
accordance with the contract Document. He shall not be required to
make exhaustive or continuous on site inspection to check the
quality or quantity of the work and he shall note be responsible for
the contractors failure to carry the construction work in accordance
with the contract documents During such visits the contract
document, during such visits and on basis of his observations while

INFINITE CIVIL SOLUTIONS PVT. LTD.

at the site he shall keep the employer informed of the progress of the
work, shall endeavor to guard the employer against defects and
deficiencies in the work of the contractor and he shall condemn work
which fails to confirm to the contract document, He shall have
authority to act on behalf of the employer only to the extent
expressly provided in the contract document or otherwise in writing
have authority to stop the work whenever such stoppage may be
necessary in his reasonable opinion o ensure the proper execution of
the contract.
57.

Performance Bond :
Within ten days o the sinning of this contract the contractor shall
deposit with the Employer for due performance of this contract as
security deposit a sum that is referred to in the appendix to this
contract as security deposit.
The security Deposit shall be in the form approved by the employer and
shall remain so deposited with the Employer till the end of the Defects
liability period referred to in the appendix.

58.

Taxes :
The Contractor shall add to the amount of his tender the amount of
sales tax duty, any other tax for octroi legally payable and it shall be
assumed his rates cover for all taxes and duties and no claim on this
account will be entertained.

59.

Royalties and patent rights :


All royalties or there sums payable in respect of the supply and use in
carrying out the work as desired by or referred to in the contract Bills of
any patented articles, process to invention shall be deemed to have
been include in the contract sum, and the contractors shall indemnify
the employer from and against all claims, proceedings, damages, costs
and expenses which may be brought or made against the employer or to
which he may put by reasons of the contractors infringing or being help

INFINITE CIVIL SOLUTIONS PVT. LTD.

to have infringed any patent rights in relation to any such articles


processes and inventions.
60.

Claim for Extra :


When any instruction or decision at site involve an extract or where by
the contractor may plan to claim extra, it shall be the responsibility of
the contractor to inform the employer, consulting Engineer/Architect of
the extra amount and get written authorization from the said persons
before proceeding with the work involved. Any modification carried out
for expenditure of simplifying work at the request of the contractor or
his representatives shall not be taken as the basis for claiming an extra.

61.

Fluctuations :
The Contractor shall not claim any extra for fluctuations of prices and
the contract prices shall not be subject to any rise or fall of prices.

62.

Materials and Workmanship :


a. All materials and workmanship shall be as per the relevant code of
I.S.I. specifications and of approved type and the contractor shall
immediately remove form the works any material and / or
workmanship

which

in

the

opinion

of

the

consulting

Engineer/Architect are defective or unsuitable and shall substitute


proper material and/or workmanship at his own cost. The terms
approval used in connection with this contract shall mean the
approval of the consulting Engineer/Architect.
63.

Virtual Completion and defects Liability Period :


a. When in the opinion of the consulting Engineer the works are
practically completed, he shall forthwith issue a certificate to that
effect and Virtual completion of the works shall be deemed for all the
purpose of this contract to have taken place on the day named in
such certificates.
b. Any defects shrinkage or other faults which shall appear within the
Defects liability Period Stated in the appendix to these conditions

INFINITE CIVIL SOLUTIONS PVT. LTD.

and which are due to material and workmanship not in accordance


with this contract shall be specified not in by the employer in a
schedule of Defects which he shall deliver to the contract not later
than 14 days after the expiration of the said defects liabilities period
and within a reasonable time after receipt of such schedule the
defects shrinkages and other faults therein specified shall be made
good by the contractor and (unless the consulting Engineer shall
otherwise instruct in which case, the contract sum shall be adjusted
accordingly). Entirely at his own cost.
c. Not withstanding sub-clause (2) of this condition the consulting
Engineer may whenever he considers it necessary so to do, issue
instructions requiring any defect, shrinkages or other faults which
shall appear within the defects liability period named in the
appendix to these condition and which is due to materials and
workmanship not in accordance with this contract to be made good
and the contractor shall within a reasonable time after receipt of
such instructions comply with the same (and unless the consulting
Engineer shall otherwise instruct in which case the contract sum
shall be adjusted accordingly entirely at his own cost, provided that
no such instructions shall be issued after 14 days form the
expiration of the said Defects liability period.
d. When in the opinion the consulting Engineer any defects shrinkages
or other defaults which he may have required to be made good under
sub-clause (2) and (3) of this condition shall have been made good he
shall issue a certificate to that effect, and completion of making good
defects shall be deemed for all the purposes of this contract to have
taken place on the day named in such certificates.
e. In on case shall be contractor be required to make good at his own
cost any damage which may appear after virtual completion of the
work, unless the consulting Engineer shall certify that such damage
is due to injury which took place before virtual completion of the
works.
INFINITE CIVIL SOLUTIONS PVT. LTD.

64.

Payment employer may withhold or on account of a subsequently


discovered evidence nullify the whole or a part of any certificate to such
extent as may be necessary in his reasonable opinion to protect the
employer form loss on account of :
a.

Defective work not remedied.

b.

Failure of the contractor to make payments properly to subcontractor or for materials or labour.

c.

A reasonable doubt that the contract can be completed for the


balance then unpaid.

d.

Damage to another contractor or sub-contractor.

e.

Claims failed on reasonable evidence indication probable filling


of claims.

65.

Guarantee :
a. Besides

guaranties

required

elsewhere,

the

contractor

shall

guaranties the work in general for one year as noted under clause of
the conditions.
66.

Arbitrator :
All dispute and differences of any kind whatever arising out of or in
connection with the contract or the carrying out of the works (whether
during the progress of the works or after their completion and progress
of the works or after the determination, abandonment or breach of the
contract

shall

be

referred

to

and

settled

by

the

consulting

Engineer/Architect/The President who shall state his decision in


writing. Such decision may be in the form of a final certificate or
otherwise. The decision of the Consulting Engineer/Architect/The Chief
Manager with respect of any of the excepted matters shall be final and
without appeal.
67.

Decision:
The Consulting Engineer: The Consulting Engineer/Architect within a
reasonable time make decisions on all claims of the employer or the
contractor and all other matters relating to the execution and progress
of the work or the interpretation of the contract document. The

INFINITE CIVIL SOLUTIONS PVT. LTD.

consulting Engineer/Architect may in his absolute discretion and from


time

to

time

issue

further

drawings.

Details

and/or

written

instructions, written directions and written explanations in regard to:


1.

Variation or modification of the design.

2.

The quality or quantity of works or the additions or omission or


substitution of any work.

3.

Any discrepancy between the drawings and/or specifications.

4.

The removal and/or re-execution of any works executed by the


contractor.

5.

The dismissal from the works of any persons employed thereon.

6.

The opening up tor inspection of any work covered up.

7.

The amending and making good of any defects under defect liability
period.

8.

Assignment and sub letting.

9.

Delay and extension time.

10. The postponement of any work to be executed under the provision


of this Contract.
68.

Damages for non-completion:


If the contractor fails to complete the works by the time specified in
these conditions or with any extended time fixed by authority and the
employer certifies in writing that in his opinion the same ought
reasonably so to have been completed, the contractor shall pay or allow
to the Employer a sum calculated at the rate stated in the appendix as
agree liquidated damages for the period during which the said work
shall so remain or have remained form any movies otherwise payable to
the contractor under this contract.

69.

Nagar Palika G. TERMS & Condition/act will be consider.

Dated Sign of Contractor

INFINITE CIVIL SOLUTIONS PVT. LTD.

Potrebbero piacerti anche