Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
NO:
PTJ-E&I-QC-P001
00
PAGE
1/9
JOB NO:
APPROVED
(WORK CAN PROCEED)
REJECTED
(DOCUMENT
RELIEVE
THE
CONTRACTUAL
PROJECT:
CLIENT:
TECHINT / EMETHANEX
ISSUE STATUS
00
12-02-2009
FIRST ISSUE
REV
DATE
DESCRIPTION
HUKKERI
PREPARED
APPROVED
SIGNATURE
DOC. NO:
PTJ-E&I-QC-P001
00
PAGE
2/9
JOB NO:
TABLE OF CONTENT
1. SCOPE...........................................................................................
...............................3
2. REFERENCE
DOCUMENTS..................................................................................
......3
2.1 CONTRACTORS
DOCUMENTS............................................................................3
2.2 PETROJET
PROCEDURES...................................................................................
3
3.
ABBREVIATION.......................................................................................
....................3
4. DUTIES AND
RESPONSIBILITIES..........................................................................
....4
4.1 INSTRUMENT CONSTRUCTION
MANAGER.........................................................4
4.2 SITE QA/QC
MANAGER........................................................................................4
5. MATERIALS....................................................................................
.............................4
5.1 LADDER TYPE CABLE
TRAYS.............................................................................4
5.2 STANDARD
SIZES................................................................................................4
5.3
CONDUITS.............................................................................................................5
6. MATERIAL RECEIVING, HANDLING AND
STORAGE..............................................5
7. WORK
PROCEDURE...................................................................................
................5
7.1 PRELIMINARY
CHECKS........................................................................................5
7.2 CABLE TRAY
INSTALLATION...............................................................................5
7.3 CONDUIT
INSTALLATION.....................................................................................7
7.4 TOUCH UP
DOC. NO:
PTJ-E&I-QC-P001
00
PAGE
3/9
JOB NO:
PAINTING...........................................................................................7
8. INSPECTION...................................................................................
.............................7
9. SAFETY ACTION
PLAN.............................................................................................
.8
10.
DOCUMENTS..........................................................................
.....................................8
1.0
SCOPE
This procedure describes the general requirements and principals that shall
be performed during the handling and installation of instrument cable trays
and conduits for "Emethanex Damietta 1 Methanol project" located at
Damietta port free zone area.
The main objective of this document is to ensure that site activities is carried
out:
DOC. NO:
PTJ-E&I-QC-P001
00
PAGE
4/9
JOB NO:
2.0
REFERENCE DOCUMENTS
2.1
CONTRACTOR'S DOCUMENT
2386-0000-TO-E-03-0017
2386-0000-TO-E-03-0018
2386-0000-TO-E-02-0001
2386-0000-TO-E-02-0002
2.2
PETROJET PROCEDEURES
2386-0000-SO-X-05-P001
2386-0000-SO-X-05-P006
2386-0000-SO-X-05-P010
2386-0000-SO-X-05-P010
3.0
ABBREVIATION
QC:
ITP:
NCR:
4.0
buildin
g
5.0
MATERIALS
5.1 LADDER TYPE CABLE TRAYS
Hot Dip Galvanized
DOC. NO:
PTJ-E&I-QC-P001
00
PAGE
5/9
JOB NO:
5.3
CONDUITS:
Hot Dip Galvanized
6.0
7.0
WORK PROCEDURE
7.1
Preliminary Checks
According to the sequence and the schedule of construction
activities, the following preliminary checks shall be carried out
before the start of any activity to verify:
DOC. NO:
PTJ-E&I-QC-P001
00
PAGE
6/9
JOB NO:
DOC. NO:
PTJ-E&I-QC-P001
00
PAGE
7/9
JOB NO:
The clearance to any insulated line or hot process piping shall be min.300mm.
Where the cable trays are installed directly over the equipments, the vertical
clearance between the top of equipment and bottom of the cable tray shall not
be les than 600mm.
The minimum distance between the supports shall not exceed 2m.
The cable tray change in direction and level accessories such as elbow, tee, X,
V joints shall be of manufacturer standard make and shall be installed in line
and fastened.
Divider plates where required, shall be installed as per drawing as barrier to
separate different voltage level cables.
Cable tray shall be electrically continues and shall be bonded to earth every
three sections.
Top cable trays shall be protected after cable installation with cover to avoid
any damage form falling objects .
7.3 conduit installation
Install the conduits is limited between cable trays or under ground duct bank to
equipments or instruments or in buildings.
Material shall be rigid hot dip galvanized or flexible or PVC depending on the
location as per drawing and/or specification.
Conduit size shall not be less than 20 mm inside diameter.
Install the conduits at right angles to beam or wall and fasten to structure
Supports shall be made of galvanized steel profile or PVC.
DOC. NO:
PTJ-E&I-QC-P001
00
PAGE
8/9
JOB NO:
Conduits with vertical bottom entry to cable tray shall be sealed with
compound to prevent ingress of liquid.
Straight runs of conduit shall have pull boxes every 20m max.
Conduits shall be kept at least 300 mm away from parallel run to steam or hot
water pipes or surfaces.
Spare conduits shall be capped or plugged.
7.4 TOUCH UP PAINTING
Cut surfaces of cable trays shall be protected with cold zinc rich paint.
The paint shall be of approved make and type.
8.0
INSPECTION
Inspection and tests shall be carried out after completion of each phase
of work as per stages identified in the ITP and reports shall be prepared
following shall be covered as minimum:
Visual inspection for sharp edges and projections which could cause
damage to cable
DOC. NO:
PTJ-E&I-QC-P001
00
PAGE
9/9
JOB NO:
activity.
Petrojet safety supervisor shall carry out safety site inspections to ensure
that the safety requirements are strictly adhered during and after the civil
works as per HSE plan 2386-0000-SO-X-04-P003 and 2386-0000-SO-X-04P004 construction environmental plan.
10.0
DOCUMENTS
All the documents as mentioned in ITP shall be prepared and maintained. Review
of final documentation and traceability of quality records of system.