Sei sulla pagina 1di 10

SESSION 2012

http://www.cigre.org

B2 - 106

Area-wide dynamic line ratings based on weather measurements


R. PUFFER1), M. SCHMALE2), B. RUSEK3), C. NEUMANN3), M. SCHEUFEN1)
1)
RWTH Aachen University, Aachen, Germany, puffer@ifht.rwth-aachen.de
2)
TenneT TSO GmbH, Bayreuth, Germany,
3)
Amprion GmbH, Dortmund, Germany

SUMMARY
The load of overhead lines has increased due to raised transmission of electrical energy within Europe
as well as in the consequence of a growing feed-in from regenerative energy resources. The transmission capacities of overhead lines (OHL) are limited and already in many cases the bottlenecks which
restrict the power flows.
Dynamic rating is a measure to increase the ampacity of overhead lines depending on the actual
weather situation.
In the first section this paper focuses on the description and evaluation of different methods and tools
for OHL ampacity determination. The conductor temperature is measured directly with a sensor as
well as determined indirectly using a weather station close to the line and commercially available
weather data. Different scenarios where the measured wind speed is higher than the wind at the line
due to shadowing effects are taken into account. The results show that the conductor temperature determination from weather data may be done with a maximal adequacy of about 5 K in the conductor
temperature range up to 50C. This fact means that the dynamic line rating is applicable but some
safety margins have to be implemented. It is also shown that investigations on the thermal behaviour
at low wind speeds seem to be necessary.
In the second section the focus is on the implementation of a dynamic rating system into the 380 kV
transmission grid and the necessary measures to increase the ampacity up to 3,150 A. This dynamic
rating system uses the ambient temperature and the wind speed to determine the dynamic ampacity of
the line. Retrofitting in substations such as replacing circuit breakers and current transformers as well
as measures at overhead lines such as inspecting joints and raising towers had to be taken. Dynamic
aspects of the transmission system are discussed. The protection concept was revised in order to allow
a quick location of faults even in the case of a single technical component failure. The operational
experience using the dynamic rating system proves that it fits very well with the existing control centres technology. The distinct increase in dynamic current rating compared to static rating verifies the
technical and economical capability.

KEYWORDS
Ampacity, monitoring system, up rate, overhead line, thermal limit, meteorological data, real time
thermal rating, dynamic rating

puffer@ifht.rwth-aachen.de

1. Introduction
To enable the ongoing connection of regenerative energy sources in a timely manner, there is a need
for flexible measures to better utilise the existing transmission grid. One of those measures is dynamic
rating of overhead lines. Based on the thermal balance of the conductor it can be determined that the
meteorological conditions (wind speed, angle of oncoming flow of wind and ambient air temperature)
affect the temperature of the line conductors considerably. With certain combinations of these meteorological factors, the influence results in a cooling effect, thus much more heat caused by the current
flow can be generated without exceeding the maximum operating temperature. This means, that an
overhead line can be loaded more intensively (above nominal current). This effect can also be used for
a temporary increase of the line capacity (dynamic line rating). Thus it is possible to increase the ampacity of the line and at the same time to maintain the maximum allowable values for the conductor
temperature and the clearance to ground or objects.
This paper is divided into two main parts. The first section focuses on the methods for determination
of the conductor ampacity. For this purpose, the three methods (one direct and two indirect) will be
compared in terms of adequacy. The second section focuses on the measures necessary to enable a
retrofitting of existing 380 kV overhead lines in order to prepare them for dynamic rating. The most
significant among these measures were the introduction of dynamic rating, essential actions in the
overhead line sections like rising towers and inspection and replacement of primary technical equipment in the substations. Further the ampacity increases of OHL operated with dynamic rating are presented.

2. Comparison of methods for ampacity determination


2.1 Principal methods and tools
For dynamic line rating, the conductor temperature can be used. The interesting questions are how to
acquire the temperature, which adequacy is necessary and which monitoring system is the most suitable from the economical point of view. In order to answer these questions, a pilot installation of two
monitoring systems at Amprion GmbH (German TSO) was established (figure 1).
The first system measures directly the temperature of
the conductor by means of two passive surface
acoustic wave (SAW) sensors SAW 1 and SAW 2
located in two conductors of one circuit. The second
system (ls - local station) bases on an indirect method
using a thermal model for the calculation of conductor temperature under consideration of the meteorological conditions. In this case, a weather station is
placed in the vicinity of the conductor.
The cost of the pilot systems and the technical effort
was quite high. Taking into account the actual costs
of the measuring devices, the effort for the installa- Fig. 1 Pilot installation of monitoring systems
tion and the necessary line outages the installation of with SAW sensors and local weather station
such systems throughout the network is not economical. The application of weather stations similar to (ls) does not require de-energising of the line and the
installation cost expenditure is significantly lower. However, the necessity to equip all lines with
weather stations still remains. The simplest solution is to use already available weather stations, which
are located in the vicinity of the monitored line, and to project the measured meteorological conditions
on the line. Therefore, the pilot project was extended by an additional indirect method (rs - remote
station) which calculates the conductor temperature using the commercially available meteorological
data.
The aims of the project are to define the adequacy of conductor temperature determination from the
meteorological data, provided by the local and remote weather station and to find the most suitable
system from economical point of view.

puffer@ifht.rwth-aachen.de

2.2 The thermal model of the conductor


For the indirect method the CIGRE-thermal model of conductor
[2] is used. The principle of the model is well known; the thermal balance of the line, i. e. introduced heat and dissipated heat,
must be equal at any time (equation 1).

Pj (Tc ) + Pm + Pc + Ps = Pr (Tc ) + Pk (Tc ) + Pn

(1)

where : Pj- current losses, Pm magnetisation losses, Ps-solar radiation,


Pc- corona losses; Pk - convection, Pn rain, Pr radiation

Knowing the weather conditions and some constant conductor


parameters, the ampacity at which the conductor reaches its
maximum permissible temperature (in this case 80C) which also
Fig. 2 Principle of calculation of
corresponds to the maximum permissible conductor sag can be
ampacity @ maximal conductor
calculated according to equation 1 (see also figure 2).
temperature and conductor temThe calculation of conductor temperature based on the load curperature @ known load current
rent and the weather conditions is quite complex, because of
numerous dependencies on the conductor temperature itself. The direct derivation of conductor temperature (with a few simplifications) is possible [7]. This equation may also be solved by an iterative
approach (figure 2). The temperature of the conductor (Tc) will be varied until both sides of equation (1) are almost equal (error < 0.1C).

2.3 Statistical approach


The investigations cover almost 2 year of measurements almost 50,000 data sets with 15 min resolution. The most suitable approach for analysis of such amount of data is a statistical approach [8].
Hence in this work, the relative frequency of different parameters [11] will be applied.
From this statistical evaluation given in figure 3 it can be derived for both sensors SAW 1 and SAW 2
that the conductor temperatures were lower than 10C in 30% of time period considered and for 10%
of time period considered higher than 30C. This shows that the conductor temperatures are far below
the permissible limit of 80C and that there is a potential for increasing the ampacity which can be
utilised by overhead line monitoring.

2.4 Shadowing scenarios


The weather conditions which are measured by
local and remote weather stations give information about the condition in this particular
location [8][9]. Since the overhead lines may
be many kilometres long, the weather conditions along the line will not be the same and
particularly affected by different wind speeds
and directions. Additionally, a shadowing effect has to be taken into account, if the line
passes valleys or forest aisles [10].
Therefore, four scenarios with varying wind
speed and direction will be considered to simulate shadowing effects (table 1). The principle
of application of shadowing effect is shown in
figure 2.

scenario
S1

wind speed

wind
tion

v = 0.6 m/s

= 90

S2

v = vreal/2 &
min(v) = 0.6 m/s

= real &
min() = 30

S3

v = vreal/2 &
min(v) = 0.6 m/s
no restrictions

= 30

S4

direc-

= real &
min() = 30

Tab. 1: Different shadowing scenarios, where vreal is


the measured wind speed an v is the wind speed used
for ampacity calculation

2.5 Measured conductor temperatures and possible ampacities


In the considered period of time a variety of different weather and load conditions have been measured. The conductor temperatures varied between -10 and 50C and the load current between 0 and
100% of conductor nominal current (figure 3). That means that the complete current range was covered, but the maximum conductor temperature of 80C was not reached.

puffer@ifht.rwth-aachen.de

Fig. 3: Measured conductor temperature (A) and currents of the monitored overhead line (B)

2.6 Discussion of results


The two sensors of the conductor temperature measuring system (SAW 1 and SAW 2) are mounted on
two conductors of the same circuit, but at different heights. Due to the phase arrangement of the circuit
on the tower, sensor SAW 2 on conductor 2 is mounted about 3 meters higher than sensor SAW 1 on
conductor 1. The wind profile and herewith the cooling effect is depending on the height above
ground. Thus the cooling of the higher located conductor 2 should be more intensive than the cooling
of conductor 1. The resulting conductor temperatures should differ. This dependency on wind conditions can be seen in figure 4, curve (1). The positive deviations from Tc_saw1 show that for 90% of
considered period the temperature of the lower conductor is few degrees higher. Since the temperature
Tc_saw1 is higher than Tc_saw2, the conductor sag of conductor 1 will be larger than of conductor 2.
Therefore, the temperature of the conductor 1 (Tc_saw1) will be chosen as reference value.
The temperature of the conductor (Tc) is calculated using CIGRE-model and different shadowing scenarios. The weather conditions are measured by local weather station (ls) and remote weather station
(rs). The difference between calculated conductor temperatures (M2 and M3) and directly measured
conductor temperature (M1) is shown in figure 4. The cumulative frequency distribution of these deviations for exemplary study cases is also shown.

Fig. 4: Frequency of differences between measured and calculated conductor temperature for different
shadowing scenarios depending on the location of weather station (ls-local, rs-remote)

The curves in figure 4 can be analysed as follows:


Positive deviations mean that measured conductor temperature (Tc_saw1) is higher than the
calculated temperature. This condition implies a risk to exceed the maximum allowed conductor temperature.

puffer@ifht.rwth-aachen.de

Negative deviations are allowed, since the conductor temperature is in the permissible range.
In this case, the maximal ampacity will not be reached in any case.
Scenario S1 (only temperature, curve (8): This scenario gives the best adequacy because only
1% of deviations is higher than 5C. However, it does not utilise the maximum of conductor
ampacity, because 80% of deviations are negative. Interesting is, that the use of ambient temperature and standard normative weather conditions (v = 0.6 m/s, = 90) still produces positive deviations in 20% of data points. Hence, it can be concluded that either there are worse
weather conditions than those in standard or the models are not good enough at those small
wind speeds. This fact requires further investigations.
Scenario S2, (half wind speed, = real & min()=30, curves (6) & (7)): This scenario applies
the real wind direction in the model, in contrary to scenario S3 at which a constant angle of
wind direction is used. It is well to be seen in particular, if the curves for local station (5) and
(7) are compared. The positive deviations are almost equal to the use of temperature only
(scenario S1). The method provides a very good safety margin. Hence, the distribution curve
for a local station is very narrow and the scenario has a good safety margin, this location of
the weather station and this shadowing scenario give the best representation of the conductor
temperature.
Scenario S3 (half wind speed, = 30, curves (4) and (5)): For the local station there are about
50% of positive deviations and for the remote station slightly less than 40%. However, only
about 5% of deviations are higher than 5C. On the negative side of axis the calculations according to data from remote station exhibits much more inadequacy than for data coming from
local station.
Scenario S4 (wind speed with no restrictions, curves (2) and (3)): Almost 80% of deviations
are positive. However, only 10% of deviations are higher than 5C. Here, the calculated temperature is lower than the measured one. The direct use of wind speed with no restrictions for
calculation of conductor temperature is apparently not adequate enough. The local weather
station is located at a similar height above ground as the conductor; therefore it should provide
comparable results. The reason for this effect which mainly appears at low wind speeds (see
figure 5A) may occur due to inadequacy in weather measurements, the conductor models
and/or dynamic thermal behaviour of conductor. Moreover, the sensors measuring the temperature directly are calibrated for wind speeds in range of 4 m/s and may produce small deviations at low wind speeds.

According to discussion above, the scenario S2 is the most accurate for ampacity determination. But
the results also show that there is no method which can determine the conductor temperature very
exactly. In case of ls_S2 (local weather, half wind speed, and taking into account wind directions) a
deviation of 5 C may be reached. It has to be mentioned here, that this deviation refers only to the
conductor temperatures up to 50C. Above this value, no observations have been made.

puffer@ifht.rwth-aachen.de

Fig 5: Deviations of theoretically calculated conductor temperature to the measured conductor temperature
dependent of the wind speed (A), ambient temperature (B) and the season of the year (C)

The dependency of the deviations between measured conductor temperature and calculated temperature using the local and the remote weather conditions at scenario 2 is shown in figure 5.
At higher wind speeds the deviations become smaller (figure 5A). The dependency on the ambient
temperature (figure 5B) cannot be detected at the first look. The dependency on the season of the year
(figure 5C) is also difficult to recognise. Obviously the largest deviations occur within few days (peaks
in figure 5C) and at ambient temperatures of about 10C (peak in figure 5B). For clarification of these
details further investigations are needed.

3. Area-wide dynamic rating of 380 kV overhead lines


An important north to south connection in the
German grid of TenneT TSO GmbH is located
between the cities of Hamburg and Frankfurt (see
figure 6). To adjust the grid to the new boundary
conditions it is necessary to build new lines as
well as to improve the efficiency of the existing
infrastructure. The policy is to fully utilise the
existing infrastructure first and to have new lines
erected only for further demand.
An overview of the necessary measures to be
taken in order to increase the transmission capability of this part of the grid is given in figure 7.
In the 380 kV transmission grid it is essential to
keep up the stability of the system. By raising the
maximum allowable ampacities the development
of a new protection concept became necessary.
Also a concept to maintain system safety for
higher utilisation was required. As a result facilities providing reactive power had to be installed
and changes to the protection system were carried
out.

puffer@ifht.rwth-aachen.de

Denmark
Energienet.dk

Sweden
Svenska
Kraftnt

Hamburg
Netherlands
TenneT

50Hertz
Transmission

Amprion

Frankfurt
Czech Republic
CEPS

EnBW
Austria
TIWAG
APG

Fig. 6: Retrofitted connection between Hamburg and Frankfurt

check design temperature

OK?
yes

special inspection

OK?
yes

check joints

OK?
yes

check substation

OK?
yes

no

increase design temp.

no

replace

no

replace

no

replace
no

check protection and


dynamic aspects

OK?
yes

magnetic field threshold

OK?
yes

no

no

everything
done?

adapt, replace

yes
adapt max. ampacity
overhead line
dynamic rating
applicable

implementation of ampacity algorithm

weather station and location

documentation

Fig. 7: Workflow of necessary measures for dynamic rating implementation

3.1 Dynamic aspects of the transmission system


The transmission capacity is increased by raising the ampacity of the 380 kV bottleneck circuits to
3,150 A. With an increasing utilisation of the currently existing connections without adding new
transport capabilities from the north to the south, the risk of loosing the generator stability (phase angle stability) increases as well (see figure 8).
The stability limits mainly depend on the grid impedances (inductive and capacitive). Also the protection system is affected by high nominal currents, in regard to selectivity and reliability. It is more difficult to safely detect and isolate faults. High nominal currents make it hard to differentiate between
operational and fault currents without the chance of incorrect tripping.
P

P2 =

U1 U2
sin
X

increasing
transmission capacity

reduction of
transmission angle

with expansion of
transmission system

PDLR
P1

without expansion of
transmission system

static boundary

45

stable

instable

90
135
bertragungswinkel
transmission angle

180

Fig. 8: transmission angle as a function of the transmission capacity (DLR Dynamic Line Rating)
Where P1 is the feeding power and P2 is the load power, PDLR is the increased feeding power using dynamic line rating,
U1 and U2 are the voltages at the beginning and the end of the line, and is the angle between current and voltage

To improve the transport capacity of the grid the system boundaries which arise from system stability
and grid protection have to be taken into account during the grid planning process. Analysing the possibilities of enhancing the capacity of the main transmission corridors from north to south system
many studies were conducted. As a part of the EWIS study (European Wind Integration Study) the
results were verified in an European context, considering coordinated robust scenarios (European
market model for power plant operation) and measures (e. g. the grids at the borders to the Czech Republic, Poland, Austria, Benelux or Denmark).

puffer@ifht.rwth-aachen.de

3.2 Protection of the transmission system


The protection concept was revised in order to allow a quick location of faults even in the case of a
single technical component failure. The analysis of the calibration principles of the protection system
revealed that raising the boundary protection current and accordingly a less sensitive tripping setting
on its own was not sufficient to meet the increased requirements. In addition the influence of large
transmission angles on the measuring precision of the distance relays in the event of electric ark faults
and compensation currents in healthy lines at a single line fault are factors of consideration.

3.3 Realization of necessary measures


The ampacity of a high voltage circuit can be limited by the primary equipment in the substation bays
and by the overhead lines. The equipment used in the substation bays can generally be retrofitted to
match the ampacity that can be achieved using the dynamic rating of the line. In order to determine
presently available ampacity, the weather data has been evaluated. This evaluation shows that in about
80 % of the year a weather dependent ampacity of 3,150 A is possible (see figure 9).

weather dependent ampacity [A]

5,000

4,000 A

4,000

3,150 A

3,000
four bundle conductor ACSR 240/40: 2,580 A
2,500 A

2,000

2,000 A

1,000
0

10

20

30

40

50

60

70

80

90

100

time [%]

Fig. 9: Available ampacity with dynamic rating of the connection between Hamburg and Frankfurt

3.4 Measures in substations


In the substations the following primary equipment has been reviewed and replaced as needed:
circuit breaker
current transformer
isolating switch
voltage transformer
switch bay lines
For the circuit breaker, current transformer, isolating switch and for some voltage transformers (special types) the rated currents were checked. For equipment with thermal ratings below 3,150 A, the
device had to be replaced.
The switch bay lines and bus bars were checked in regard to their short circuit capability. Insufficiently dimensioned components have been replaced.
The above mentioned measures took a great amount of planning and coordination because of the limited operability of the grid during the intervention and the aim not to cause any impact on customers.

puffer@ifht.rwth-aachen.de

3.5 Measures at overhead lines


Since the usable ampacity of an overhead line depends among other things on the specific design temperature, generally the ampacity can be increased by raising the clearance. If the specific design temperature of lines is lower than the rated conductor temperature an ampacity increase can usually be
reached by the elevation of selected towers. However, the elevation of a 380 kV line tower yields a
couple of challenges. For example, in order to elevate a 10 ton tower, special cranes are needed which
have to approach the tower if necessary over provisional tracks (figure 10).

Fig. 10: Pictures of inserting additional body sections in a 380 kV tower near Stade

The joints in the line section were completely inspected on site. Only intact connection components
remained in the line whereas conspicuous components were replaced. The condition of joints was determined using infra-red thermography.
Raising the ampacity of an overhead line raises the maximum value of the magnetic field as well. Calculations of the magnetic field were carried out in order to assure the compliance with legal specifications.

3.6 Implementation of dynamic rating into the operating system


In order to improve the ampacity of 380 kV lines a dynamic rating system has been developed and
implemented into the existing operating system of TenneT TSO in Germany. This monitoring system
uses the ambient temperature and the wind speed to determine the dynamic current rating of the line. It
is directly linked to the control centre and delivers a dynamic current rating. There is no need for any
direct measurement of the conductor temperature to determine the dynamic current rating.
The operational experience using the dynamic rating system for the operation of 380 kV lines proves
that it interposes very well with the existing control centres technology. The distinct increase in dynamic current rating compared to static rating verifies the technical and economical capability.

puffer@ifht.rwth-aachen.de

4. Conclusion
Many overhead line monitoring systems (direct and indirect temperature determination methods) are
presently available on the market. The determination of conductor temperature using weather data is
riddled with many inadequacies.
Hence, the conductor temperature determination from weather data may be done with a maximal adequacy of about 5 K in the conductor temperature range up to 50C.
The findings of this paper show that the accuracy of indirect monitoring systems is comparable with
direct monitoring systems considering adequate safety margins. Moreover, investigations on the thermal behaviour at low wind speeds seem to be necessary as well as better understanding at what time
the largest deviations to the measured conductor temperature occur.
A dynamic rating system using weather measured in substations to calculate the ampacity was installed on 800 km of 380 kV overhead lines. Different retrofitting measures like checking the joints,
changing substation equipment, raising towers and verifying the stability criteria of the grid had to be
done.
The operational experience using the dynamic rating system delivers a distinct increase in dynamic
current rating which verifies the technical and economical capability of the system.

BIBLIOGRAPHY
[1]

Drger, H.-J.; Hussels, D.; Puffer, R.; Development and Implementation of a MonitoringSystem to Increase the Capacity of Overhead Lines, Paper B2-101, Cigr Session 2008
[2] Cigr, Technical Brochure 207; The Thermal Behaviour of Overhead conductors, August 2002
[3] H. Khn, F. Martin, M. Schmale, R. Puffer, W. Winter; Mehr Energie von Nord nach Sd, ew
3/2011 and 4/2011
[4] M. Schmale, R. Puffer; Freileitungen sicher betreiben und Reserven nutzen, netzpraxis, Jg. 49
(2010), Heft 11
[5] Blumenroth, F., Lbl, H., Gromann, S., Puffer, R. Hussels, D.: Ageing of high current joints in
power transmission ans distribution systems, Cired 2007, paper 537
[6] Schmale, M.; Puffer, R.; Drger, H.-J.; Experience with a Dynamic Rating System to Increase
the Ampacity of 380-kV Overhead Lines, Cigr Symposium Bologna 2011
[7] Teminova, R.; Hinrichsen, V.; Freese, J.; Hudasch, M.; Bebensee, R.; Neumann, C.:
Betriebserfahrungen mit passiven funkabfragbaren OFW-Sensoren zur Messung der Temperatur
von Freileitungsleiterseilen und Trennschalterkontakten, ETG Tagung, 2006
[8] Lange, M.; Focken, U.: Studie zur Abschtzung der Netzkapazitt in Mitteldeutschland in Wetterlagen mit hoher Windeinspeisung, Studie energy & meteo systems, Oldenburg, 2008; gefrdert vom BMU
[9] Roman, H. Dangrie, G.; Darendorf, S. Struck, T.: Freileitungsmonitoring im Hochspannungsnetz - Theoretisches Potenzial. ew Jg. 108 (2009), Heft 12, S. 62-66
[10] Roman, H. Dangrie, G.;Darendorf, S. Struck, T.: Freileitungsmonitoring im Hochspannungsnetz - Reales Potenzial. ew Jg. 108 (2009), Heft 13, S. 60-63
[11] Neumann, C.; Rusek, B.; Puffer, R.: Weather dependent loading of overhead lines based on
statistical consideration of weather data (in German). ETG Congress, Duesseldorf, 27. to 28.
October 2009, Report 3-7

puffer@ifht.rwth-aachen.de

10

Potrebbero piacerti anche