Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
2065/66
DETAIL ESTIMATE
S.N.
Descriptions
No.
Length (m)
Total
Length (m)
Breadth
(m)
Height/Dep
th (m)
Quantity
Unit
A- Civil Works :1
1.1
Earth Work
Clearing and grubbing the site for construction.
15.00
10.00
1
1
1
4
1
1
2
4.75
4.70
3.45
6.40
8.43
12.52
0.80
4.75
4.70
3.45
25.60
8.43
12.52
1.60
61.05
23.05
Total Quantity :-
1.05
230.50
230.50 sq.m.
1.10
70.51 cu.m.
Wall Foundation
Along Y-axis from North side
Depature Toilet
Partition wall
security check
Verandah pillar
Store partition wall
1.3 Filling in plinth with earth.
Administration room
Staircase case portion
VIP Room
Depature & VIP Toilet
Depature Lounge
Passage
1.4 Stone solling work.
In the wall
Administration room - Long wall
Short wall
Staircase case portion -Long wall
Short wall
VIP Room
- Long wall
Short wall
Toile tDepature and VIP
Short wall
Partition wall
Estimated by :-
3
2
2
1
2
1
10.30
2.40
2.40
1.80
1.05
1.50
30.90
4.80
4.80
1.80
2.10
1.50
1.05
1.10
1.05
1.10
0.55
1.10
1.05
1.10
1.05
1.10
0.55
1.10
Total Quantity :-
35.69
5.54
2.90
2.08
2.43
0.91
120.06 cu.m.
1
1
1
1
1
1
1
4.00
4.00
4.00
4.70
4.75
3.45
1.50
4.00
4.00
4.00
4.70
4.75
3.45
1.50
3.50
0.45
2.50
0.45
4.00
0.45
3.00
0.45
6.00
0.45
3.45
0.45
10.45
0.45
Total Quantity :-
6.30
4.50
7.20
6.35
12.83
5.36
7.05
49.58 cu.m.
2
2
1
1
1
2
2
2
2
4.45
3.95
4.45
2.95
4.45
4.45
4.70
3.45
3.45
8.90
7.90
4.45
2.95
4.45
8.90
9.40
6.90
6.90
Checked by :-
Approved by :-
Page 2 of 82
2065/66
DETAIL ESTIMATE
S.N.
Descriptions
Depature Hall
No.
- Long wall
Check in Hall
-Toile t-
Length (m)
2
2
2
2
3
4
0.80
8.2
3.00
3.45
2.25
1.95
Total :
2 Concrete Works
2.1 P.C.C. 1:3:6 under foundation
In the floor
Administration room
Staircase case portion
VIP Room
Depature & VIP Toilet
Depature Lounge
Passage
In the wall
Administration room - Long wall
Short wall
Staircase case portion -Long wall
Short wall
VIP Room
- Long wall
Short wall
Toile tDepature and VIP
Short wall
Partition wall
Depature Hall
Check in Hall
- Long wall
-Toile t-
Estimated by :-
1.60
16.40
6.00
6.90
6.75
7.80
106.20
1
1
1
1
1
1
1
4.00
4.00
4.00
4.70
4.75
3.45
1.50
4.00
4.00
4.00
4.70
4.75
3.45
1.50
2
2
1
1
1
2
2
2
2
2
2
2
2
3
4
4.45
3.95
4.45
2.95
4.45
4.45
4.70
3.45
3.45
0.80
8.2
3.00
3.45
2.25
1.95
8.90
7.90
4.45
2.95
4.45
8.90
9.40
6.90
6.90
1.60
16.40
6.00
6.90
6.75
7.80
106.20
Total :
2.2 Structural concrete P.C.C (1:2:4) work with
curing all complete works
Ground floor
Plinth beam
In the wall
Administration room - Long wall
Short wall
Staircase case portion -Long wall
Short wall
VIP Room
- Long wall
Short wall
Total
Length (m)
2
2
1
1
1
2
4.45
3.95
4.45
2.95
4.45
4.45
Checked by :-
Breadth
(m)
Height/Dep
th (m)
1.00
0.15
Total Quantity :-
3.50
2.50
4.00
3.00
6.00
3.45
10.45
0.075
0.075
0.075
0.075
0.075
0.075
0.075
1.00
0.075
Total Quantity :-
Quantity
Unit
15.93
15.93 cu.m.
1.05
0.75
1.20
1.06
2.14
0.89
1.18
7.97
16.23 cu.m.
8.90
7.90
4.45
2.95
4.45
8.90
Approved by :-
Page 3 of 82
2065/66
DETAIL ESTIMATE
S.N.
Descriptions
Toile t-
No.
Partition wall
Depature Hall
- Long wall
Check in Hall
-Toile t-
Length (m)
2
2
2
2
2
2
2
3
4
4.70
3.45
3.45
0.80
8.2
3.00
3.45
2.25
1.95
Total :
Tie Beam
In the wall
Administration room - Long wall
Short wall
Staircase case portion -Long wall
Short wall
VIP Room
- Long wall
Short wall
Toile tDepature and VIP
Short wall
Partition wall
Depature Hall
- Long wall
Check in Hall
-Toile t-
2
2
1
1
1
2
2
2
2
2
2
2
2
3
4
4.45
3.95
4.45
2.95
4.45
4.45
4.70
3.45
3.45
0.80
8.2
3.00
3.45
2.25
1.95
Total :
Slab
Administration room
Staircase case portion
VIP Room
Depature & VIP Toilet
Passage
First Floor :
Tie Beam
Airport Manager's room - Long wall
Short wall
Staircase case portion -Long wall
Short wall
Staff Room
- Long wall
Short wall
Toile tstaff Room
Short wall
Partition wall
Total
Length (m)
Breadth
(m)
Height/Dep
th (m)
Quantity
9.40
6.90
6.90
1.60
16.40
6.00
6.90
6.75
7.80
106.20
0.45
0.15
7.17
8.90
7.90
4.45
2.95
4.45
8.90
9.40
6.90
6.90
1.60
16.40
6.00
6.90
6.75
7.80
106.20
0.45
0.15
7.17
1
1
1
1
1
4.00
1.70
4.00
4.70
1.50
4.00
1.70
4.00
4.70
1.50
3.50
2.50
4.00
3.00
10.45
0.10
0.10
0.10
0.10
0.10
1.40
0.43
1.60
1.41
1.57
2
2
1
2
1
2
1
2
1
6.40
3.50
4.45
2.95
6.45
4.45
1.72
4.45
1.72
12.80
7.00
4.45
5.90
6.45
8.90
1.72
8.90
1.72
57.84
0.45
0.15
3.90
Total :
Unit
slab
Estimated by :-
Checked by :-
Approved by :-
Page 4 of 82
2065/66
DETAIL ESTIMATE
S.N.
Descriptions
No.
Top Floor
Slabs
Rcc inverted slab
Long side
short side
First Floor :
Tie Beam
Long side
short side
Staircase case
Step
Stair case Landing
2.3 Form work
Plinth beam
In the wall
Administration room - Long wall
Short wall
Staircase case portion -Long wall
Short wall
VIP Room
- Long wall
Short wall
Toile tDepature and VIP
Short wall
Partition wall
Depature Hall
Check in Hall
- Long wall
-Toile t-
Length (m)
Estimated by :-
Breadth
(m)
Height/Dep
th (m)
Quantity
1
1
6.85
8.62
6.85
8.62
7.35
4.90
0.10
0.10
5.03
4.22
2
2
7.40
6.40
14.80
12.80
0.60
0.60
0.10
0.10
0.89
0.77
2
3
7.40
6.40
4
32
3
3.16
1.00
1.85
14.80
19.20
34.00
12.64
32.00
5.55
4
4
2
2
2
4
4
4
4
4
4
4
4
6
8
4.45
3.95
4.45
2.95
4.45
4.45
4.70
3.45
3.45
0.80
8.2
3.00
3.45
2.25
1.95
Total :
Tie Beam
In the wall
Administration room - Long wall
Short wall
Staircase case portion -Long wall
Short wall
VIP Room
- Long wall
Short wall
Toile tDepature and VIP
Short wall
Partition wall
Total
Length (m)
4
4
2
2
2
4
4
4
4
4
4.45
3.95
4.45
2.95
4.45
4.45
4.70
3.45
3.45
0.80
Checked by :-
17.80
15.80
8.90
5.90
8.90
17.80
18.80
13.80
13.80
3.20
32.80
12.00
13.80
13.50
15.60
212.40
0.45
0.30
1.00
0.10
0.13
0.09
3.43
0.10
Total Quantity :-
0.15
Unit
4.59
1.26
0.36
1.90
43.68 cu.m.
31.86
17.80
15.80
8.90
5.90
8.90
17.80
18.80
13.80
13.80
3.20
Approved by :-
Page 5 of 82
2065/66
DETAIL ESTIMATE
S.N.
Descriptions
Depature Hall
No.
- Long wall
Check in Hall
-Toile t-
Length (m)
4
4
4
6
8
8.2
3.00
3.45
2.25
1.95
Total :
Slab
Administration room
Staircase case portion
VIP Room
Depature & VIP Toilet
Passage
First Floor :
Tie Beam
Airport Manager's room - Long wall
Short wall
Staircase case portion -Long wall
Short wall
Staff Room
- Long wall
Short wall
Toile tstaff Room
Short wall
Partition wall
Total
Length (m)
32.80
12.00
13.80
13.50
15.60
212.40
1
1
1
1
1
4.00
1.70
4.00
4.70
1.50
4.00
1.70
4.00
4.70
1.50
4
4
2
4
2
4
2
4
2
6.40
3.50
4.45
2.95
6.45
4.45
1.72
4.45
1.72
25.60
14.00
8.90
11.80
12.90
17.80
3.44
17.80
3.44
115.68
Total :
Breadth
(m)
Height/Dep
th (m)
0.15
3.50
2.50
4.00
3.00
10.45
Quantity
Unit
31.86
14.00
4.25
16.00
14.10
15.68
0.15
17.35
slab
1
1
6.85
8.62
6.85
8.62
7.35
4.90
50.35
42.24
Top Floor
Slabs
Rcc inverted slab
Long side
short side
Tie Beam
Long side
short side
4
4
7.40
6.40
29.60
25.60
0.60
0.60
17.76
15.36
1
1
7.40
6.40
Staircase case
Step
Stair case Landing
4
32
3
3.16
1.00
1.85
7.40
6.40
13.80
12.64
32.00
5.55
0.30
1.00
0.43
3.43
Total Quantity :-
4.14
39.94
13.76
35.22
274.94 sq.m.
2183.80 kg
2183.80 kg
3 Stone Works
3.1 R/R Masonary in mud mortar in foundation
Ist footing
Along X-axis from back side
Estimated by :-
Checked by :-
Approved by :-
Page 6 of 82
2065/66
DETAIL ESTIMATE
S.N.
Descriptions
Back wall Depature lounge
Back wall Depature Toilet
Back wall Depature lounge
wall, VIP, Staircase, Administration
Front wall Depature lounge
security check
Depature Toilet and VIP Toilet partition
No.
1
1
1
4
1
1
2
Length (m)
4.75
4.70
3.45
6.40
8.43
12.52
0.80
Total
Length (m)
Breadth
(m)
Height/Dep
th (m)
4.75
4.70
3.45
25.60
8.43
12.52
1.60
61.05
1.05
0.30
Quantity
Unit
19.23 cu.m.
Wall Foundation
Along Y-axis from North side
Depature Toilet
Partition wall
security check
Verandah pillar
Store partition wall
2nd footing
Along X-axis from back side
Back wall Depature lounge
Back wall Depature Toilet
Back wall Depature lounge
wall, VIP, Staircase, Administration
Front wall Depature lounge
security check
Depature Toilet and VIP Toilet partition
3
2
2
1
2
1
10.30
2.40
2.40
1.80
1.05
1.50
30.90
4.80
4.80
1.80
2.10
1.50
1.05
1.05
0.55
1.05
1.05
0.55
0.30
0.30
0.30
0.30
0.30
0.30
1
1
1
4
1
1
2
4.75
4.70
3.45
6.40
8.43
12.52
0.80
4.75
4.70
3.45
25.60
8.43
12.52
1.60
61.05
0.85
0.30
9.73
1.51
0.79
0.57
0.66
0.25
15.57 cu.m.
Wall Foundation
Along Y-axis from North side
Depature Toilet
Partition wall
security check
Verandah pillar
Store partition wall
3rd footing
Along X-axis from back side
Back wall Depature lounge
Back wall Depature Toilet
Back wall Depature lounge
wall, VIP, Staircase, Administration
Front wall Depature lounge
security check
Depature Toilet and VIP Toilet partition
3
2
2
1
2
1
10.30
2.40
2.40
1.80
1.05
1.50
30.90
4.80
4.80
1.80
2.10
1.50
0.85
0.85
0.35
0.85
0.85
0.35
0.30
0.30
0.30
0.30
0.30
0.30
1
1
1
4
1
1
2
4.75
4.70
3.45
6.40
8.43
12.52
0.80
4.75
4.70
3.45
25.60
8.43
12.52
1.60
61.05
0.65
0.30
30.90
0.65
0.30
7.88
1.22
0.50
0.46
0.54
0.16
11.90 cu.m.
Wall Foundation
Along Y-axis from North side
3
Estimated by :-
10.30
Checked by :-
6.03
Approved by :-
Page 7 of 82
2065/66
DETAIL ESTIMATE
S.N.
Descriptions
Depature Toilet
Partition wall
security check
Verandah pillar
Store partition wall
4th footing upto plinth
Along X-axis from back side
Back wall Depature lounge
Back wall Depature Toilet
Back wall Depature lounge
wall, VIP, Staircase, Administration
Front wall Depature lounge
security check
Depature Toilet and VIP Toilet partition
No.
Length (m)
Total
Length (m)
Breadth
(m)
Height/Dep
th (m)
Quantity
Unit
2
2
1
2
1
2.40
2.40
1.80
1.05
1.50
4.80
4.80
1.80
2.10
1.50
0.65
0.15
0.15
0.65
0.15
0.30
0.30
0.30
0.30
0.30
0.94
0.22
0.08
0.41
0.07
1
1
1
4
1
1
2
4.75
4.70
3.45
6.40
8.43
12.52
0.80
4.75
4.70
3.45
25.60
8.43
12.52
1.60
61.05
0.45
0.20
5.49 cu.m.
0.45
0.20
0.45
0.20
0.15
0.20
0.15
0.20
0.45
0.20
0.15
0.20
Total Quantity :-
2.78
0.43
0.14
0.05
0.19
0.05
87.85 cu.m.
0.45
2.72
72.76 cu.m.
0.45
2.72
0.45
2.72
0.15
2.72
0.45
2.72
Total Quantity :-
37.82
5.88
0.73
2.57
247.15 cu.m.
Wall Foundation
Along Y-axis from North side
Depature Toilet
Partition wall
security check
Verandah pillar
Store partition wall
3.2 Hammer dressed coursed stone masony in
mud mortar in superstructure.
Ground floor
Along X-axis from back side
Back wall Depature lounge
Back wall Depature Toilet
Back wall Depature lounge
wall, VIP, Staircase, Administration
Front wall Depature lounge
security check
3
2
2
1
2
1
10.30
2.40
2.40
1.80
1.05
1.50
30.90
4.80
4.80
1.80
2.10
1.50
1
1
1
4
1
1
4.75
4.70
3.45
6.40
8.43
12.52
4.75
4.70
3.45
25.60
8.43
12.52
59.45
Wall Foundation
Along Y-axis from North side
Depature Toilet
security check
Verandah pillar
3
2
1
2
10.30
2.40
1.80
1.05
30.90
4.80
1.80
2.10
3
1
1
1
2.30
1.50
1.00
1.50
6.90
1.50
1.00
1.50
Estimated by :-
Checked by :-
0.45
0.45
0.45
0.45
2.00
1.50
1.70
2.00
23.00
28.13
2.13
3.75
Approved by :-
Page 8 of 82
2065/66
DETAIL ESTIMATE
S.N.
Descriptions
Ventilation (v1)
Ventilation (v3)
Door / Window (Dw4)
Door 1
Door 2
Door 3
Door 4
Door 5
No.
Length (m)
5
1
1
2
2
4
3
1
0.80
1.00
2.20
1.50
1.00
0.90
0.75
0.90
2
2
1
0.80
2.40
1.50
Total
Length (m)
Breadth
(m)
Height/Dep
th (m)
4.00
1.00
2.20
3.00
2.00
3.60
2.25
0.90
0.45
0.60
0.45
0.50
0.45
2.40
0.45
2.40
0.45
2.40
0.45
2.40
0.45
2.00
0.45
2.00
Total Quantity :Net Quantity after Deduction :-
Quantity
Unit
3.00
0.63
5.28
40.50
5.40
4.86
6.75
4.05
127.47 cu.m.
119.68 cu.m.
1.60
4.80
1.50
0.15
0.15
0.15
2.72
2.72
2.72
0.65
1.96
0.61
3.22
Total
4.45
6.90
11.35
Total Length :1
1.85
16.79
12.80
8.90
6.90
11.35
56.74
1.85
0.45
0.15
2.72
2.72
69.45
0.75
2
1
6.40
3.20
12.80
3.20
0.45
0.45
0.45
0.45
Stone Pillar
2
8
7.40
0.45
14.80
3.60
0.45
0.45
0.45
2.27
2.59
0.65
3.00
3.68
80.12
3
1
3
1
1
2
1
along X-Axis
2
2
8.40
6.40
2
1
1
Total
2.30
1.00
1.00
1.20
2.43
1.00
0.75
Estimated by :-
6.90
1.00
3.00
1.20
2.43
2.00
0.75
0.45
1.60
0.45
1.70
0.45
1.60
0.45
1.60
0.45
2.20
0.45
2.40
0.45
2.00
Total Quantity :Net Quantity after Deduction :-
-4.97
-0.77
-2.16
-0.86
-2.41
-2.16
-0.68
-14.00 cu.m.
66.12
531.92
42.98
Checked by :-
Approved by :-
Page 9 of 82
2065/66
DETAIL ESTIMATE
S.N.
Descriptions
No.
Length (m)
Total
Length (m)
Breadth
(m)
Height/Dep
th (m)
Quantity
Unit
Total Quantity :-
293.87
868.77 sq m
0.075
0.125
Total Quantity :-
4.130 Cum
4.130 Cum
0.34
0.43
0.34
0.43
0.34
1.08
0.34
1.08
0.42
0.42
0.47
0.47
0.37
0.34
0.34
Total Quantity :-
1.43
1.83
2.14
2.75
0.88
2.63
0.44
0.88
3.27
3.86
1.57
0.48
0.32
0.25
0.27
23.00 Sqm
2
3
1
3
1
3
3
5
1
1
1
1
1
1
2
5
4
4
1
17.46
14.04
9.10
7.37
13.12
19.68
23.85
2.80
4.20
3.00
23.39
18.09
14.11
12.41
7.80
6.80
6.60
4.75
4.90
2*2
2*2
3*2
3*2
3*1
3*2
1*2
1*2
3*3
3*4
5*1
1*2
1*1
1
1
1.06
1.08
1.06
1.08
0.87
0.41
0.66
0.41
0.88
0.78
0.67
0.51
0.87
0.74
0.80
34.92
42.12
9.10
22.11
13.12
59.04
71.55
14.00
4.20
3.00
23.39
18.09
14.11
12.41
15.60
34.00
26.40
19.00
4.90
441.060
1.06
1.08
1.06
1.08
0.87
0.41
0.66
0.41
0.88
0.78
0.67
0.51
0.87
0.74
0.80
Estimated by :-
Checked by :-
Approved by :-
Page 10 of 82
2065/66
DETAIL ESTIMATE
S.N.
Descriptions
Door (DW1)
Door (DW2)
Door (DW3)
Door 1
Door 2
Door 3
Door 4
Door 5
5 Flooring Works
5.1 150 mm thick stone soling under floor
In the floor
Administration room
Staircase case portion
VIP Room
Depature & VIP Toilet
Depature Lounge
Passage
Administration room
Staircase case portion
VIP Room
Depature & VIP Toilet
Depature Lounge
Passage
Check in Hall
Airlines office
Baggage Store Room
Airlines office
Security Office
Passage
Verandah back
Verandah front
Estimated by :-
No.
Length (m)
Total
Length (m)
1
1
1
2
5
3
5
1
0.78
0.84
0.91
1.37
0.97
0.77
0.61
0.77
2*2
3*2
6
1
2
3*3
3*3
3*4
3*4
0.68
0.68
0.50
0.75
0.75
0.93
0.93
0.83
0.83
0.68
0.68
0.50
0.75
0.75
0.93
0.93
0.83
0.83
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
1
1
1
1
1
1
4.00
4.00
4.00
4.70
4.75
3.45
1.50
4.00
4.00
4.00
4.70
4.75
3.45
1.50
18.10
3.00
4.50
3.00
4.35
1.50
1.80
16.00
4.00
4.00
4.00
4.70
4.75
3.45
1.50
4.00
4.00
4.00
4.70
4.75
3.45
1.50
18.10
6.00
4.50
3.00
4.35
1.50
1.80
16.00
Checked by :-
Breadth
(m)
Height/Dep
th (m)
Quantity
Unit
2.27
2.27
2.15
1.83
1.94
1.94
1.94
1.94
Total Quantity :-
1.76
1.90
1.94
5.00
9.45
4.49
5.90
1.49
31.93 Sqm
1.13
1.13
0.50
1.13
0.43
1.23
0.47
1.24
0.47
Total Quantity :-
3.07
4.61
1.50
0.85
0.65
10.30
3.93
12.35
4.68
41.94 Sqm
3.50
2.50
4.00
3.00
6.00
3.45
10.45
3.50
2.50
4.00
3.00
6.00
3.45
10.45
8.25
3.00
3.00
4.30
3.50
3.00
4.45
1.50
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
2.10
1.50
2.40
2.12
4.28
1.79
2.35
2.10
1.50
2.40
2.12
4.28
1.79
2.35
22.40
2.70
2.03
1.94
2.28
0.68
1.20
3.60
Approved by :-
Page 11 of 82
2065/66
DETAIL ESTIMATE
S.N.
Descriptions
Estimated by :-
No.
Length (m)
Total
Length (m)
Breadth
(m)
Height/Dep
th (m)
Quantity
Unit
Total Quantity :-
69.87 cu.m.
1
1
1
1
1
1
1
1
2
1
1
1
1
1
1
4.00
4.00
4.00
4.70
4.75
3.45
1.50
18.10
3.00
4.50
3.00
4.35
1.50
1.80
16.00
4.00
4.00
4.00
4.70
4.75
3.45
1.50
18.10
6.00
4.50
3.00
4.35
1.50
1.80
16.00
3.50
0.05
2.50
0.05
4.00
0.05
3.00
0.05
6.00
0.05
3.45
0.05
10.45
0.05
8.25
0.05
3.00
0.05
3.00
0.05
4.30
0.05
3.50
0.05
3.00
0.05
4.45
0.05
1.50
0.05
Total Quantity :-
0.70
0.50
0.80
0.71
1.43
0.60
0.78
7.47
0.90
0.68
0.65
0.76
0.23
0.40
1.20
17.78 sq.m.
1
1
1
1
1
1
1
1
2
1
1
1
1
1
1
4.00
4.00
4.00
4.70
4.75
3.45
1.50
18.10
3.00
4.50
3.00
4.35
1.50
1.80
16.00
4.00
4.00
4.00
4.70
4.75
3.45
1.50
18.10
6.00
4.50
3.00
4.35
1.50
1.80
16.00
3.50
2.50
4.00
3.00
6.00
3.45
10.45
8.25
3.00
3.00
4.30
3.50
3.00
4.45
1.50
Total Quantity :-
14.00
10.00
16.00
14.10
28.50
11.90
15.68
149.33
18.00
13.50
12.90
15.23
4.50
8.01
24.00
355.64 sq.m.
1
1
1
1
1
5.43
6.00
5.95
1.70
7.40
1
1
5.95
6.85
Checked by :-
5.43
6.00
5.95
1.70
7.40
5.95
6.85
3.45
4.00
3.50
2.50
1.85
6.95
3.80
18.73
24.00
20.83
4.25
13.69
41.35
26.03
Approved by :-
Page 12 of 82
2065/66
DETAIL ESTIMATE
S.N.
Descriptions
No.
Length (m)
Total
Length (m)
1.75
1.75
1
1
1
3
1
1
1
15.00
16.00
20.45
24.00
12.00
15.70
54.30
15.00
16.00
20.45
72.00
12.00
15.70
54.30
1
1
18.90
20.00
18.90
20.00
244.35
1
1
1
4.70
1.50
1.25
Breadth
(m)
Height/Dep
th (m)
Depature
Gents
Ladies
Toilet Under the staircase
Toilet first floor
6 Roofing Works
6.1 MS tubular roof supporting structure
Main Truss -1
Bottom chord M50
Top chord
Vertical at centre
vertica at middle
vertical at end
bracing 1
bracing 2
Horizontal for support
Estimated by :-
8.58
157.46 sq.m.
Total Quantity :-
244.35
244.35 Rm
3.45
1.85
2.50
2
2
1.00
1.50
2.00
3.00
1.20
1.20
2
2
2
2
2
2
2
2
2
2
1.00
1.35
1.81
2.24
1.20
1.65
1.25
2.25
1.50
1.85
2.00
2.70
3.62
4.48
2.40
3.30
2.50
4.50
3.00
3.70
1.20
1.20
1.20
1.20
1.20
1.20
1.20
1.20
1.20
1.20
Total Quantity :-
4
4
4
4
4
4
4
2
5.95
8.83
2.93
2.13
1.27
2.86
2.31
7.85
23.80
35.32
11.72
8.52
5.08
11.44
9.24
15.70
Checked by :-
Unit
4.90
Total Quantity :-
Quantity
unit wt./m
5.10
5.10
5.10
3.61
3.61
3.61
3.61
5.10
16.22
2.78
3.13
22.12 sq.m.
2.40
3.60
2.40
3.24
4.34
5.38
2.88
3.96
3.00
5.40
3.60
4.44
44.64 sq.m.
121.38
180.13
59.77
30.76
18.34
41.30
33.36
80.07
Approved by :-
Page 13 of 82
2065/66
DETAIL ESTIMATE
S.N.
Descriptions
Verticl for support
Purlins
No.
2
2
2
2
2
2
2
2
2
Length (m)
2.94
8.05
9.05
5.87
6.87
4.04
5.04
2.02
3.20
Total
Length (m)
5.88
16.10
18.10
11.74
13.74
8.08
10.08
4.04
6.40
Breadth
(m)
Height/Dep
th (m)
5.10
3.61
3.61
3.61
3.61
3.61
3.61
3.61
3.61
Sub total =
6.6
2
1
1
4
2
4
2
2
2
2
2
1
1
2
1
1
1
1
19.30
9.05
19.3
8.83
19.30
5.50
8.05
9.05
19.30
8.05
9.05
11.71
18.10
3.00
4.50
3.00
4.35
1.50
38.60
9.05
5.50
8.05
Unit
29.99
58.12
65.34
42.38
49.60
29.17
36.39
14.58
23.10
913.78
45.69
959.47 kg.
Total Quantity :-
212.30
72.85
3.64
288.80 sq.m.
Total Quantity :-
54.62
54.62 rm
Total Quantity :-
94.8
94.80 sq.m.
Total Quantity :-
72.8
72.80 rm
13.90
8.25
3.00
3.00
4.30
3.50
3.00
Total Quantity :-
162.77
149.33
18.00
13.50
12.90
15.23
4.50
376.22 sq.m.
19.3
35.32
54.62
38.60
22.00
16.10
18.10
94.80
38.6
16.1
18.1
72.8
11.71
18.10
6.00
4.50
3.00
4.35
1.50
Quantity
7 Plaster/Finishes
7.1 Cement plaster
Estimated by :-
Checked by :-
Approved by :-
Page 14 of 82
2065/66
DETAIL ESTIMATE
S.N.
Descriptions
No.
Length (m)
Total
Length (m)
Breadth
(m)
Height/Dep
th (m)
ceilling
Administration room
Staircase case portion
VIP Room
Depature & VIP Toilet
Depature Lounge
Passage
staircase
Staircase case
Step
Stair case Landing
Quantity
Unit
242.76
42.98
20.00
1
1
1
1
1
1
1
1
4
32
3
4.00
4.00
4.00
4.70
4.75
3.45
1.50
12.64
3.16
1.00
1.85
4.00
4.00
4.00
4.70
4.75
3.45
1.50
12.64
12.64
32.00
5.55
3.50
2.50
4.00
3.00
6.00
3.45
10.45
1.00
1.00
0.43
3.43
Total Quantity :-
14.00
10.00
16.00
14.10
28.50
11.90
15.68
12.64
39.94
13.76
35.22
517.47 sq m
Total Quantity :-
517.47
868.77
-44.64
1341.60 sq.m.
Painting Works
8.1 Painting the plastered surface with waterproof
cement paint
20 mm plaster surface
Pointing area
Less tile area
8.2 Painting wooden surface with enamel paint
Window (w1)
Window (w2)
Window (w3)
Window (w4)
Window (w5)
Window (w6)
Window (w7)
Window (w8)
Window (w9)
Ventilation (v1)
Ventilation (v2)
Ventilation (v3)
Door / Window (Dw1)
Door / Window (Dw2)
Door / Window (Dw3)
Door / Window (Dw4)
Door 1
Door 2
Door 3
Door 4
Door 5
Estimated by :-
4*1.25
3*1.25
10*1.25
1*1.25
3*1.25
5*1.25
1*1.25
3*1.25
3*1.25
5*1.25
1*1.25
1*1.25
1
1
1
1
2*2.25
2*2.25
4*2.25
3*2.25
1*2.25
2.30
2.30
1.50
1.00
1.00
1.00
1.50
2.75
3.25
0.80
1.20
1.00
3.25
2.75
2.43
2.20
1.50
1.00
0.90
0.75
0.90
Checked by :-
2.00
1.60
1.50
1.70
1.60
2.00
2.00
2.17
2.17
0.60
1.60
0.50
2.77
2.77
2.20
2.40
2.40
2.40
2.40
2.00
2.00
23.00
13.80
28.13
2.13
6.00
12.50
3.75
22.38
26.45
3.00
2.40
0.63
9.00
7.62
5.35
5.28
40.50
10.80
19.44
10.13
4.05
Approved by :-
Page 15 of 82
2065/66
DETAIL ESTIMATE
S.N.
Descriptions
Tower
Check in Hall
No.
Length (m)
Total
Length (m)
Breadth
(m)
Height/Dep
th (m)
Quantity
Unit
1
1
11.71
18.10
11.71
18.10
13.90
8.25
Total Quantity :-
162.77
149.33
568.41 sq.m.
3.16
12.64
1.00
Total Quantity :-
12.64
12.64 sq.m.
Total Quantity :-
12.64
12.64 Rm
9 Miscellaneous Works
9.1 Staircase railing
4.00 Nos
4
4
4
4.00 Nos
4.00 Nos
4.00 Nos
50
50.00 Rm
3
4
5
9
10
11
12
13
14
15
Estimated by :-
1.00 Nos
100
100.00 Rm
2
5
50
2.00 Nos
5.00 Nos
50.00 Rm
50
50.00 Rm
100
1
1
1
Checked by :-
100.00
1.00
1.00
1.00
Rm
No
No
No
Approved by :-
Page 16 of 82
2065/66
DETAIL ESTIMATE
Height/Dep
th (m)
17
2.00 No
18
2.00 No
19
4.00 No
20
4.00 No
21
4.00 No
22
4.00 No
6.00 No
1
1
1.00 job
1.00 job
Length (m)
Breadth
(m)
Descriptions
23
No.
Total
Length (m)
S.N.
Quantity
Unit
4
5
1
2
3
1.00
No
1.00
No
1.00
No
2.00 No
1.00 No
2
1
15
Estimated by :-
15.00 month
Checked by :-
Approved by :-
Page 17 of 82
ABSTRACT OF COST.
Fiscal Year :-2065/66
S.No.
A
Description of work
Quantity
Unit
Rate ( Nrs)
Per
Amount ( Nrs)
230.50
sq m
13.23
One
3,048.36
120.06
cu m
885.00
One
106,249.98
49.58
cu m
135.13
One
6,699.48
15.93
cu m
6,448.32
One
102,721.66
CIVIL WORKS
1 EARTHWORK
1.1 Cleaning and grubbing of site for construction
including removal of grass, shrubs and levelling
undulated ground all compleate as per drawings and
instructions.
1.2 Earthwork in excavation in trenches, foundation etc.in
gravel mixed soil including dressing of sides, ramming
of bottom , lift up to 1.5 m stacking excavated
materials at least 3.00 m clear from the edge of
excavation and then filling stacked soil in 150 mm
layer by ramming and watering and then disposed of
all surplus excavated soil as directed within a lead of
30.00 m complete as per drawings and instructions.
16.23
cu m
8,637.88
One
140,178.22
43.68
cu.m
10,539.41
One
460,318.00
274.94
sq m
576.09
One
158,391.69
Estimated by :
Checked by :-
Approved by :-
Page 18 of 82
ABSTRACT OF COST.
Fiscal Year :-2065/66
S.No.
Description of work
2.4
3 STONE WORKS
3.1 Random rubble stone masonry in mud mortar in
foundation in required line and level in any size and
shape including scaffolding, timbering etc. all
complete as per drawings, Specifications and
instructions.
3.2 Coursed stone masonry with face dressed stone in mud
mortar in superstructure in any size and shape of wall
made to required line and level, scaffolding etc, all
complete as per drawings, specification and
instructions.
Quantity
Unit
2183.80
kg
Rate ( Nrs)
Per
132.80
One
Amount ( Nrs)
290,008.83
-
87.85
cu m
3,450.12
One
303,082.75
119.68
cu m
5,680.43
One
679,845.87
66.12
cu m
8,395.22
One
555,102.48
868.77
cu m
161.93
One
140,680.61
4.13
cu m
66,904.94
One
276,317.40
23.00
sq m
3,292.13
One
75,729.96
31.93
sq m
21,932.95
One
700,328.25
41.94
sq m
845.19
One
35,444.92
5 FLOORING
5.1 Stone boulder soling under floors including sand
blinding, watering, consolidating and dressing all
complete as per drawing, specification & instructions.
69.87
Estimated by :
Checked by :-
cu m
6,448.32
One
450,558.30
Approved by :-
Page 19 of 82
ABSTRACT OF COST.
Fiscal Year :-2065/66
S.No.
Description of work
Quantity
Unit
Rate ( Nrs)
Per
Amount ( Nrs)
17.78
cu m
8,637.88
One
153,597.70
355.64
sq.m
594.98
One
211,595.60
157.46
sq m
472.34
One
74,372.69
244.35
rm
414.23
One
101,217.66
22.12
sq.m
2,094.08
One
46,310.56
44.64
sq.m
2,094.08
One
93,479.69
6 ROOFING
6.1 Providing and fixing tubular roof trusses with rafters,
purlins, wind ties, brackets etc, made with required
grade mild steel tubes and mild steel sections of
required sizes, including hoisting, fixing in position
with MS bed plates, shoe angles, anchor bolts etc, and
concrete grouting, concreting nut bolts, fabrication,
fixing and treated with two coats of anticorrosive
paints all complete as per drawings, specifications and
instructions.
6.2 26 gauge corrugated galvanized iron color roof sheet
of approved make, required size, fixed to MS purlins
or wood purlins by nuts bolts, 8 mm J-hook, bitumen
and GI cup washer all complete as per drawings,
specifications and instructions.
Estimated by :
959.47
kg
288.80
sq.m
Checked by :-
179.64
One
172,360.91
1,352.53
One
390,604.94
Approved by :-
Page 20 of 82
ABSTRACT OF COST.
Fiscal Year :-2065/66
S.No.
Description of work
6.3 28 gauge, 600 mm wide GI ridge/valley with noncorrugated color sheet made to required shape
inclusive of fixing with 8 mm J-hooks all complete as
per drawings, specifications and instructions.
Quantity
Unit
54.62
rm
94.80
sq.m
Rate ( Nrs)
Per
Amount ( Nrs)
577.53
One
31,544.83
1,337.42
One
126,787.04
579.99
One
42,222.94
1,203.83
One
452,904.09
-
72.80
376.22
rm
7 FINISHING/FINISHING WORKS
7.1 Plastering with specified mortar in any level size and
shape of wall, column, ceiling, band, blocks etc as
required including racking, watering, cleaning of
base,plastering to plumb, line, level, smooth etc. and
curing complete as per drawing, specification and
instructions.
3/4" (20 mm) average thick cement plaster of mix 1:6
in plinth including neat cement finish.
8 PAINTING WORKS
8.1 Painting with two or more coats of cement paint of
approved manufacturers over plastered surface on
walls and ceilings at any height or shape including
wetting, surface preparation, curing all complete as per
drawings, specifications and instructions.
517.47
sq.m.
343.67
One
177,837.09
-
1341.60
sq.m
75.25
One
100,959.74
150.26
One
85,411.02
-
2,500.00
One
31,600.00
Estimated by :
Checked by :-
Rm
Approved by :-
Page 21 of 82
ABSTRACT OF COST.
Fiscal Year :-2065/66
S.No.
Description of work
Quantity
Unit
Rate ( Nrs)
Per
12.64
Amount ( Nrs)
Rm
2,000.00
One
25,280.00
6,802,793.27
4.00
Nos
6,515.90
One
26,063.60
4.00
4.00
4.00
Nos
Nos
Nos
4,950.75
748.07
763.02
One
One
One
19,803.00
2,992.28
3,052.08
50.00
Rm
264.94
One
13,247.00
1.00
Nos
370.17
One
370.17
100.00
Rm
443.78
One
44,378.00
2.00
5.00
50.00
50.00
100.00
1.00
1.00
1.00
Nos
Nos
Rm
Rm
Rm
No
No
No
10,781.25
480.12
592.25
428.95
377.20
880.90
598.57
430.67
One
One
One
One
One
One
One
One
21,562.50
2,400.60
29,612.50
21,447.50
37,720.00
880.90
598.57
430.67
2.00
No
993.02
One
1,986.04
2.00
No
1,052.82
One
2,105.64
B
1
Sub Total of Civil Works( A ) NRS :Water Supply & Sanitary Fitting works :
S/F of W/C Urisa pan of 58 x 44 cm size with 10 lit
capacity low level PVC cistern with angle valve and
other necessary fittings all complete work.
S/F of White glazed porcelin hand wash basin of size
46x30 cm (Hindware Vitreous) with angle valve
(Hindustha Jaguar), PVC conecting pipe , PVC bottle
trap and all necessary fittings all complete work.
3
4
5
9
10
11
12
13
14
15
17
18
Estimated by :
Checked by :-
Approved by :-
Page 22 of 82
ABSTRACT OF COST.
Fiscal Year :-2065/66
S.No.
Description of work
Quantity
19
20
21
22
23
Unit
Rate ( Nrs)
Per
Amount ( Nrs)
4.00
No
445.62
One
1,782.48
4.00
No
547.97
One
2,191.88
4.00
No
836.85
One
3,347.40
4.00
No
675.94
One
2,703.75
6.00
No
Ls :-1000
One
Total of Sanitary Fittings :-
6,000.00
244,676.56
PS
PS
50,000.00
300,000.00
C
1
2
3
1.00
No
Ps
One
100,000.00
1.00
No
Ps
One
50,000.00
200,000.00
700,000.00
no
Ls
One
20,000.00
no
Ls
One
5,000.00
Estimated by :
15 month
Ls
One
Total of General Items of works( D ) NRS :Sub Total of Civil Works( A ) NRS :water supply and sanitary fittings (B) NRS :Total of Provisional sums (C) NRS :Total of (A+B+C+D) NRS :2.5 % Contingency NRS :-
Checked by :-
75,000.00
100,000.00
6,802,793.27
244,676.56
700,000.00
7,847,469.83
196,186.75
Approved by :-
Page 23 of 82
ABSTRACT OF COST.
Fiscal Year :-2065/66
S.No.
Description of work
Quantity
Unit
Rate ( Nrs)
Per
VAT @ 13% NRS :Grand Total including 13 % VAT & Contingency NRS :-
Estimated by :
Checked by :-
Amount ( Nrs)
1,020,171.08
9,063,827.65
Approved by :-
Page 24 of 82
Rate Analysis
Project: Reconstruction of Terminal Building with Control Tower
Location: Salley,Rukum.
1
Norms No
2065/066
Analysed /sq m
Input
Unit
Rate (NRs)
Amount (NRs)
Man power
New Norms
1-5
Skilled Labour
Unskilled Labour
m-day
350.00
0.00
m-day
250.00
5.75
Total of -A: -
5.75
Total of -B: -
5.75
Total (A+B) :-
11.50
1.73
13.23
0.023
Materials
2
Norms No
DOR
9-2-b
Input
Unit
1.50
m-day
m-day
Rate (NRs)
Analysed /cu m
Amount (NRs)
350.00
250.00
Total of -A: -
0.00
375.00
375.00
Total of -B: Total (A+B) :3 % tools & plants :Total including Contractor's profit 15 % :Rate per Cu. m :-
375.00
750.00
22.50
112.50
885.00
Materials
3
Norms No
DOR
page -15
Input
Unit
0.25
m-day
m-day
1.10
cu m
Rate (NRs)
Analysed /cu m
Amount (NRs)
350.00
250.00
Total of -A: -
0.00
62.50
62.50
50.00
Total of -B: Total (A+B) :Total including Contractor's profit 15 % :Rate per Cu. m :-
55.00
55.00
117.50
17.63
135.13
Page 25 of 82
Rate Analysis
Project: Reconstruction of Terminal Building with Control Tower
Location: Salley,Rukum.
4
Norms No
11-16
page -107
5
Norms No
RAN-p -41
7-1-ka
Norms No
RAN-p -42
7-2-kha
Input
Unit
1.00
3.50
m-day
m-day
1.10
0.71
cu m
cu m
Input
Unit
0.30
4.00
m-day
m-day
0.220
0.940
0.470
mt
cu m
cu m
Input
Unit
1.00
4.00
m-day
m-day
0.320
0.890
0.445
mt
cu m
cu m
Rate (NRs)
350.00
875.00
1225.00
1853.85
3300.00
Total of -B: Total (A+B) :Total including Contractor's profit 15 % :Rate per Cu. m :-
2039.23
2343.00
4382.23
5607.23
841.08
6448.32
Rate (NRs)
Materials
cement
aggregates
sand
Analysed /cu m
Amount (NRs)
350.00
250.00
Total of -A: -
105.00
1000.00
1105.00
15660.00
1500.00
3300.00
Total of -B: Total (A+B) :Total including Contractor's profit 15 % :Rate per Cu. m :-
3445.20
1410.00
1551.00
6406.20
7511.20
1126.68
8637.88
Analysed /cu m
Amount (NRs)
350.00
250.00
Total of -A: -
Materials
cement
aggregates
sand
2065/066
Rate (NRs)
Analysed /cu m
Amount (NRs)
350.00
250.00
Total of -A: -
350.00
1000.00
1350.00
15660.00
1500.00
3300.00
Total of -B: Total (A+B) :Total including Contractor's profit 15 % :Rate per Cu. m :-
5011.20
1335.00
1468.50
7814.70
9164.70
1374.71
10539.41
Page 26 of 82
Rate Analysis
Project: Reconstruction of Terminal Building with Control Tower
Location: Salley,Rukum.
7
Norms No
RAN-p -55
8-2-ka
8
Norms No
RAN-p -47
7-5
Norms No
RAN-p -36
6-2-2
Rate (NRs)
Unit
1.72
2.57
m-day
m-day
350.00
250.00
Total of -A: -
602.00
642.50
1244.50
0.53
cu m
6662.70
3504.58
2.50
kg
104.16
Total of -B: Total (A+B) :Total including Contractor's profit 15 % :Rate per 10 Sq. m :Rate per Sq. m :-
260.40
3764.98
5009.48
751.42
5760.90
576.09
Input
Unit
12.00
12.00
m-day
m-day
1.05
10.00
mt
kg
Input
Unit
1.00
2.25
m-day
m-day
350.00
562.50
912.50
27.38
939.88
1.10
0.42
mt
cu m
2039.23
21.00
2060.23
3000.11
450.02
3450.12
Rate (NRs)
Materials
Rubble Stone
Mud
Analysed /kg
Amount (NRs)
350.00
250.00
Total of -A: -
4200.00
3000.00
7200.00
102000.00
117.86
Total of -B: Total (A+B) :Total including Contractor's profit 15 % :Rate per Mt :Rate Per kg Rs :-
107100.00
1178.60
108278.60
115478.60
17321.79
132800.39
132.80
Analysed /Sq m
Amount (NRs)
Input
Materials
MS rod
Binding wire
2065/066
Rate (NRs)
350.00
250.00
Total : 3% Tools & Plants of Total of Labour Cost :Total of -A: 1853.85
50.00
Total of -B: Total (A+B) :Total including Contractor's profit 15 % :Rate per Cu. m :-
Analysed /cu m
Amount (NRs)
Page 27 of 82
Rate Analysis
Project: Reconstruction of Terminal Building with Control Tower
Location: Salley,Rukum.
10
Norms No
RAN-p -36
6-2-2
Similar works
Materials
Dressed stone
Mud
11
Norms No
RAN-p -36
1-5-3
Rate (NRs)
Analysed /cu m
Amount (NRs)
Input
Unit
1.00
2.25
m-day
m-day
350.00
562.50
912.50
27.38
939.88
1.10
0.40
cu m
cu m
3979.63
20.00
3999.63
4939.51
740.93
5680.43
Input
Unit
2.00
5.40
m-day
m-day
0.11
0.47
1.10
mt
cu m
cu m
Input
Unit
10.00
14.00
m-day
m-day
3500.00
3500.00
7000.00
210.00
7210.00
0.306
0.63
mt
cu m
4791.96
2079.00
6870.96
14080.96
2112.14
16193.10
161.93
350.00
250.00
Total : 3% Tools & Plants of Total of Labour Cost :Total of -A: 3617.85
50.00
Total of -B: Total (A+B) :Total including Contractor's profit 15 % :Rate per Cu. m :-
12
2065/066
Rate (NRs)
350.00
250.00
Total of -A: -
700.00
1350.00
2050.00
15660.00
3300.00
1853.85
Total of -B: Total (A+B) :Total including Contractor's profit 15 % :Rate per Cu. m :-
1659.96
1551.00
2039.23
5250.19
7300.19
1095.03
8395.22
Norms No
Materials
Cement
Sand
Analysed /cu m
Amount (NRs)
Rate (NRs)
350.00
250.00
Total : 3% Tools & Plants of Total of Labour Cost :Total of -A: 15660.00
3300.00
Total of -B: Total (A+B) :Total including Contractor's profit 15 % :Total per 100 sq m :Rate per sq m :-
Analysed /sq m
Amount (NRs)
Page 28 of 82
Rate Analysis
Project: Reconstruction of Terminal Building with Control Tower
Location: Salley,Rukum.
13
Norms No
RAN-p -75
10-1-kha
14
Norms No
RAN-p -78
10-4
2065/066
Input
Unit
34.00
3.40
m-day
m-day
1.10
92.00
184.00
mt
No
No
Input
Unit
9.00
0.90
m-day
m-day
0.049
1.085
8.00
4.00
2.00
Ls
cu m
sq m
No
No
No
Rate (NRs)
Analysed /cu m
Amount (NRs)
350.00
250.00
Total of -A: -
11900.00
850.00
12750.00
39976.20
13.81
1.00
Total of -B: Total (A+B) :Total including Contractor's profit 15 % :Rate per cu m :-
43973.82
1270.39
184.00
45428.21
58178.21
8726.73
66904.94
Rate (NRs)
Analysed /sq m
Amount (NRs)
350.00
250.00
Total of -A: -
3150.00
225.00
3375.00
39976.20
616.60
25.67
20.67
46.00
1.04
Total of -B: Total (A+B) :Total including Contractor's profit 15 % :Rate per 2.23 sq m :Rate per Sq m :-
1958.83
669.01
205.33
82.66
92.00
1.04
3008.87
6383.87
957.58
7341.46
3292.13
Page 29 of 82
Rate Analysis
Project: Reconstruction of Terminal Building with Control Tower
Location: Salley,Rukum.
15
Norms No
RAN-p -76
10-2
16
Norms No
10-11 (b)
P-84
Norms No
RAN-p -96
11-1 -ga
Input
Unit
10.00
1.00
m-day
m-day
0.890
1.09
6.00
1.00
1.00
1.00
2.00
Ls
cu m
sq m
No
No
No
No
No
Input
Unit
0.006
0.06
m-day
m-day
Rate (NRs)
3500.00
250.00
3750.00
39976.20
616.60
25.67
20.67
50.80
46.00
100.00
100.00
Total of -B: Total (A+B) :Total including Contractor's profit 15 % :Rate per 2.114 sq m :Rate per Sq m :-
35578.82
669.01
154.00
20.67
Rate (NRs)
350.00
250.00
Total of -A:
616.60
1.00
Nos
4.05
Rm
25.00
Total of -B:
Total (A+B) :
Total including Contractor's profit @ 15 % :
Rate / sq m :
Analysed /sq m
Amount (NRs)
350.00
250.00
Total of -A: -
Materials
4 mm glass
Wooden listies
17
2065/066
Input
Unit
1.25
2.50
m-day
m-day
0.17
0.23
0.46
mt
cu m
cu m
Rate (NRs)
46.00
100.00
36568.49
40318.49
6047.77
46366.26
21932.95
Analysed /sq m
Amount (NRs)
350.00
250.00
Total of -A: -
437.50
625.00
1062.50
15660.00
3300.00
1500.00
Total of -B: Total (A+B) :Total including Contractor's profit 15 % :Rate per 10 sq m :Rate per sq m :-
2662.20
759.00
690.00
4111.20
5173.70
776.06
5949.76
594.98
Page 30 of 82
Rate Analysis
Project: Reconstruction of Terminal Building with Control Tower
Location: Salley,Rukum.
18
Norms No
RAN-p -96
11-1 -kha
19
Norms No
RAN-p -110
12-1 -ga
2065/066
Input
Unit
1.25
2.00
m-day
m-day
0.13
0.18
0.36
mt
cu m
cu m
Input
Unit
12.00
16.00
m-day
m-day
0.54
1.46
mt
cu m
1.00
1.00
m-day
m-day
53.20
kg
350.00
250.00
Total of -A: -
437.50
500.00
937.50
15660.00
3300.00
1500.00
Total of -B: Total (A+B) :Total including Contractor's profit 15 % :Rate per 10 sq m :Rate per sq m :-
2035.80
594.00
540.00
3169.80
4107.30
616.10
4723.40
472.34
Analysed /sq m
Amount (NRs)
Rate (NRs)
350.00
250.00
Total : 3 % Tools and Plants :Total of -A: -
4200.00
4000.00
8200.00
246.00
8446.00
15660.00
3300.00
Total of -B: Total (A+B) :Total including Contractor's profit 15 % :Rate per 100 sq m :Rate per sq m :-
8425.08
4818.00
13243.08
21689.08
3253.36
24942.44
249.42
S
Materials
cement
sand
Analysed /sq m
Amount (NRs)
Rate (NRs)
350.00
250.00
Total of -A: -
350.00
250.00
600.00
15.66
833.11
Total of -B: Total (A+B) :Total including Contractor's profit 15 % :Rate per 10 sq m :Rate per sq m :Rate of cement Skirting per square feet =581.18+496.72=Rs 1077.90
833.11
1433.11
214.97
1648.08
164.81
414.23
Materials
cement
Page 31 of 82
Rate Analysis
Project: Reconstruction of Terminal Building with Control Tower
Location: Salley,Rukum.
2065/066
20
Input
Unit
13.00
4.50
m-day
m-day
11.00
0.056
0.152
3.228
sq m
mt
cu m
kg
Rate (NRs)
Analysed /sq m
Amount (NRs)
350.00
250.00
Total of -A: -
4550.00
1125.00
5675.00
1004.88
15660.00
3300.00
31.66
Total of -B: Total (A+B) :Total including Contractor's profit 15 % :Rate per 10 sq m :Rate per sq m :-
11053.63
876.96
501.60
102.20
12534.38
18209.38
2731.41
20940.79
2094.08
21
22
Norms No
Input
Unit
13.00
4.50
m-day
m-day
11.00
0.056
0.152
3.228
sq m
mt
cu m
kg
Input
Unit
350.00
250.00
Total of -A: -
4550.00
1125.00
5675.00
1004.88
15660.00
3300.00
31.66
Total of -B: Total (A+B) :Total including Contractor's profit 15 % :Rate per 10 sq m :Rate per sq m :-
11053.63
876.96
501.60
102.20
12534.38
18209.38
2731.41
20940.79
2094.08
Analysed / 1 kg.
Man Power
Skilled Labour (Mason)
Unskilled Labour (Labour)
Materials
Tubler Truss
Plate,nuts & Blots etc
3% erection and fitting charge
Rate (NRs)
Analysed /sq m
Amount (NRs)
m-day
m-day
Rate (NRs)
Amount (NRs)
350.00
250.00
Total of -A:
141.66
10.00
0.00
0.00
0.00
141.66
10.00
4.55
Total of -B:
Total (A+B) :
Total including Contractor's profit @ 15 % :
Rate /kg:
156.21
156.21
179.64
179.64
1.00
Ls
kg
Page 32 of 82
Rate Analysis
Project: Reconstruction of Terminal Building with Control Tower
Location: Salley,Rukum.
23
Norms No
RAN-p -69
9-1
24
Norms No
RAN-p -69
9-2
Norms No
RAN-p -91
10-19
Input
Unit
1.10
1.25
m-day
m-day
Analysed for 10 Sq m
Amount (NRs)
Rate (NRs)
350.00
250.00
Total of -A:
482.23
12.00
m2
156.66
30.00
Nos
22.12
25.00
Nos
0.44
55.00
Nos
Total of -B:
Total (A+B) :
Total including Contractor's profit 15 % :
Rate per 10 Sq. m :
Rate per Sq.m.
385.00
312.50
697.50
5786.70
4699.80
552.95
24.20
11063.66
11761.16
13,525.33
13525.33
1352.53
25
2065/066
Input
Unit
2.00
3.00
m-day
m-day
7.20
Analysed for 10 Rm
Amount (NRs)
Rate (NRs)
350.00
250.00
Total of -A:
Sqm
482.23
LS
Total of -B:
Total (A+B) :
Total including Contractor's profit 15 % :
Rate per 10 Rm :
Rate per Rm :
Input
Unit
1.43
0.143
m-day
m-day
Rate (NRs)
350.00
250.00
Total of -A:
0.2750
m3
39976.20
100.00
LS
Total of -B:
Total (A+B) :
Total including Contractor's profit 15 % :
Rate per 10 Sq.m :
Rate per Sq.m :
700.00
750.00
1450.00
3472.02
100.00
3572.02
5022.02
5775.33
5775.33
577.53
Analysed for 10 Sq m
Amount (NRs)
500.50
35.75
536.25
10993.46
100.00
11093.46
11629.71
13374.16
13374.16
1337.42
Page 33 of 82
Rate Analysis
Project: Reconstruction of Terminal Building with Control Tower
Location: Salley,Rukum.
26
Norms No
Man power, Materials and Equipments
Referene
as
Man power
TIA(CMD)
Skilled Labour
Unskilled Labour
Materials
24 Gauge G.I. Plain Sheet
Brackets/ Nails/welding etc
27
Norms No
10-16 -ka
RAN-p -
Norms No
RAN-p -114
12-4-kha
Input
Unit
2.00
5.000
m-day
m-day
Rate (NRs)
350.00
250.00
Total of -A:
6.00
Rm
482.23
Ls
Total of -B:
Total (A+B) :
Total including Contractor's profit 15 % :
Rate per 10 Rm :
Rate per Rm :
Materials
Local wood
28
2065/066
Input
Unit
23.00
2.30
m-day
m-day
0.45
m3
37.50
Sq m
LS
LS
350.00
250.00
Total of -A:
39976.20
278.29
Total of -B:
Total (A+B) :
Total including Contractor's profit 15 % :
Rate per 35.68 Sq m
Rate per Sq m
Materials
Cement
Sand
Input
Unit
14.00
19.00
m-day
m-day
1950.00
2893.35
200.00
3093.35
5043.35
5799.85
5799.85
579.99
Rate (NRs)
700.00
1250.00
Rate (NRs)
350.00
250.00
Total : 3% Tools & Plants of Total of Labour Cost :Total of -A: 15660.00
0.810
Mt
3300.00
2.20
m3
Total of -B:
Total (A+B) :
Total including Contractor's profit @ 15 % :
Rate / 100 Sq m :
Rate / Sq m :
8050.00
575.00
8625.00
17989.29
10435.88
150.00
150.00
28725.17
37350.17
5602.52
42952.69
1203.83
Analysed / 100 Sq m
Amount (NRs)
4900.00
4750.00
9650.00
289.50
9939.50
12684.60
7260.00
19944.60
29884.10
4482.62
34366.72
343.67
Page 34 of 82
Rate Analysis
Project: Reconstruction of Terminal Building with Control Tower
Location: Salley,Rukum.
29
Norms No
RAN-p -116
13-4-kha
30
Norms No
2065/066
RAN-p -116
13-45- ka, kha,
Unskilled Labour
ga
Materials
Primer
Readymade Enamel
Analysed /1 sq m
Amount (NRs)
Input
Unit
Rate (NRs)
5.50
5.00
m-day
m-day
48.500
kg
Input
Unit
12.00
m-day
350.00
4200.00
8.00
m-day
250.00
2000.00
Total of -A: -
6200.00
234.46
310.46
Total of -B: Total (A+B) :Total including Contractor's profit 15 % :Rate per 100 sq m :Rate per Sq m :-
1899.12
4967.35
6866.47
13066.47
1959.97
15026.44
150.26
350.00
250.00
Total of -A: -
1925.00
1250.00
3175.00
69.46
Total of -B: Total (A+B) :Total including Contractor's profit 15 % :Rate per 100 sq m :Rate per Sq m :-
3368.77
3368.77
6543.77
981.57
7525.34
75.25
8.100
16.00
lit
lit
Analysed /100 sq m
Amount (NRs)
Rate (NRs)
Page 35 of 82
Rate Analysis
Project: Reconstruction of Terminal Building with Control Tower
Location: Salley,Rukum.
2065/066
1001
580 mm size Orissa pan with low level cistern complete set
Level
Qty
Unit
Rate/unit
sources
labour
materials
skilled
un skilled
a. 580 mm Porcelain clay white glaze Orissa Pan
(Hindustan, Parryware, Classica, cera or equi.)
b. P or S trap.
c.10.0 ltr.plastic low level flushing cistern complete
accessories (Internal PVC fittings)
d. 32mmx60mm size flushing CP pipe
e.1.5x45 cm(" x18") PVC pipe connector
f. screw, etc.
Transportation from nepalgunj to Salley by plane
cost
3
3
nos
nos
350.00
250.00
1050.00
750.00
nos
1400.00
1400.00
nos
0.00
0.00
1
1
nos
nos
1450.00
378.00
1450.00
378.00
1
LS
LS
nos
120.00
120.00
18.00
500.00
Actual rate
15% conctractor overhead
Total (Rs.)
`
1007
WASH BASIN COMPLETE SET 55x40cm
sources
labour
Level
Qty
2
Unit
nos
Rate/unit
350.00
cost
700.00
nos
250.00
500.00
nos
1260.00
1260.00
b.Bracket
c. 32 mm pvc bottle trap including 32mm CP waste
1
1
nos
nos
207.00
450.00
207.00
450.00
1
1
nos
nos
550.00
120.00
550.00
120.00
skilled
un skilled
a .55x40cm Porcelain clay white glaze Wash basin
materials
g. screw etc
Transportation from nepalgunj to Salley by plane
Ls
LS
18.00
500.00
Actual rate
15% conctractor overhead
Rate per set Rs. 4950.75
Prepared by :-
Total (Rs.)
Checked by :-
Approved by :-
Page 36 of 82
Rate Analysis
Project: Reconstruction of Terminal Building with Control Tower
Location: Salley,Rukum.
2065/066
1012
URINAL COMPLETE SET
sources
labour
materials
Level
Qty
2
Unit
nos
Rate/unit
350.00
cost
700.00
un skilled
nos
250.00
250.00
1
1
nos
nos
850.00
LS
850.00
150.00
1
Ls
nos
LS
skilled
120.00
18.00
LS
Actual rate
500.00
1020
500 Ltr. PVC WATER TANK
sources
labour
materials
materials
Level
Qty
Unit
skilled
nos
350.00
1050.00
un skilled
nos
250.00
1000.00
1
LS
nos
3625.00
3625.00
2500.00
a. 500 Ltr. PVC water tank with Inlet, outlet, over flow,
cleanout hole etc.
Base for tank stand
Rate/unit
cost
Ls
200.00
LS
1000.00
Actual rate
15% conctractor overhead
Rate per nos Rs. 10781.25
Total (Rs.)
1038
Looking Mirror 55x40cm (22"x 16")
sources
labour
Level
skilled(1/3)
Qty
Unit
0.33
nos
un skilled
materials
Rate/unit
350.00
cost
115.50
250.00
b . Screws
Transportation from nepalgunj to Salley by plane
nos
475.00
Ls
LS
475.00
10.00
50.00
Actual rate
15% conctractor overhead
Prepared by :-
Checked by :-
Approved by :-
Page 37 of 82
Rate Analysis
Project: Reconstruction of Terminal Building with Control Tower
Location: Salley,Rukum.
Rate per nos Rs. 748.07
2065/066
Total (Rs.)
1042
15mm CP Bib Cock Ordinary type
sources
labour
Level
skilled
Qty
Unit
0.11
nos
un skilled
materials
Rate/unit
350.00
cost
38.50
250.00
1
LS
nos
600.00
600.00
25.00
Actual rate
15% conctractor overhead
Rate per nos Rs. 763.02
Total (Rs.)
1046
G.M.15 mm Gate Valve
sources
labour
Level
skilled
Qty
Unit
0.11
nos
un skilled
materials
Rate/unit
350.00
cost
38.50
250.00
1
LS
nos
311.00
311.00
25.00
Actual rate
15% conctractor overhead
Rate per nos Rs. 430.67
Total (Rs.)
1047
G.M. 20 mm Gate Valve
sources
labour
Level
skilled
Qty
Unit
0.11
nos
un skilled
materials
Rate/unit
350.00
cost
38.50
250.00
nos
457.00
LS
457.00
25.00
Actual rate
15% conctractor overhead
Rate per nos Rs. 598.57
Prepared by :-
Total (Rs.)
Checked by :-
Approved by :-
Page 38 of 82
Rate Analysis
Project: Reconstruction of Terminal Building with Control Tower
Location: Salley,Rukum.
1048
G.M. 25mm Gate Valve
sources
labour
Level
skilled
2065/066
Qty
Unit
0.22
nos
un skilled
materials
Rate/unit
350.00
cost
77.00
250.00
nos
664.00
LS
664.00
25.00
Actual rate
15% conctractor overhead
Rate per nos Rs. 880.90
Total (Rs.)
1062
PVC FLOOR TRAP 11x7.5cm (4" X 2")
sources
labour
materials
Level
Qty
Unit
skilled
0.11
nos
un skilled
0.10
1
LS
nos
Rate/unit
cost
350.00
38.50
250.00
25.00
329.00
329.00
25.00
Actual rate
15% conctractor overhead
Rate per nos Rs. 480.12
Total (Rs.)
1069
15mm G. I . Pipe 'B ' class ( MEDIUM)
sources
labour
materials
Level
Qty
Unit
skilled
0.18
nos
350.00
63.00
un skilled
0.16
nos
250.00
40.00
Rm
155.00
155.00
Rate/unit
cost
Ls
10.00
c. Jointing materials
Transportation from nepalgunj to Salley by plane
Ls
5.00
55.00
LS
Actual rate
15% conctractor overhead
Prepared by :-
Total (Rs.)
Checked by :-
Approved by :-
Page 39 of 82
Rate Analysis
Project: Reconstruction of Terminal Building with Control Tower
Location: Salley,Rukum.
2065/066
1070
20 mm G. I . Pipe 'B ' class ( MEDIUM)
sources
labour
materials
Level
Qty
Unit
skilled
0.18
nos
350.00
63.00
un skilled
0.16
nos
250.00
40.00
Rm
200.00
200.00
a. 20 mm G. I . PipeB' class
Rate/unit
cost
Ls
10.00
c. Jointing materials
Transportation from nepalgunj to Salley by plane
Ls
5.00
55.00
LS
Actual rate
15% conctractor overhead
Total (Rs.)
1071
25 mm G. I . Pipe 'B ' class ( MEDIUM)
sources
labour
materials
Level
Qty
Unit
skilled
0.18
nos
350.00
63.00
un skilled
0.32
nos
250.00
80.00
Rm
302.00
302.00
Rate/unit
cost
Ls
15.00
c. Jointing materials
Ls
5.00
LS
50.00
Actual rate
15% conctractor overhead
Rate per Rm Rs. 592.25
Prepared by :-
Total (Rs.)
Checked by :-
Approved by :-
Page 40 of 82
Rate Analysis
Project: Reconstruction of Terminal Building with Control Tower
Location: Salley,Rukum.
2065/066
1081
75 mm dia PVC PIPE 4 KG/CM. SQ
sources
labour
materials
Level
Qty
Unit
skilled
0.11
nos
350.00
38.50
un skilled
0.11
nos
250.00
27.50
Rm
112.39
112.39
Rate/unit
Ls
cost
2.00
LS
50.00
Actual rate
15% conctractor overhead
Rate per Rm Rs. 264.94
Total (Rs.)
1082
90 mm dia PVC PIPE 4 KG/CM. SQ
sources
labour
materials
Level
Qty
Unit
skilled
0.17
nos
350.00
59.50
un skilled
0.20
nos
250.00
50.00
Rm
156.45
156.45
Rate/unit
Ls
cost
3.00
LS
50.00
Actual rate
15% conctractor overhead
Rate per nos Rs. 366.79
Total (Rs.)
1104
4 Kg/cm2, High Density Polethene Pipe 110mm
sources
labour
materials
Level
Qty
Unit
skilled
0.17
nos
350.00
59.50
un skilled
0.20
1
nos
RM
250.00
226.40
50.00
226.40
Rate/unit
LS
cost
50.00
Actual rate
15% conctractor overhead
Prepared by :-
Checked by :-
Approved by :-
Page 41 of 82
Rate Analysis
Project: Reconstruction of Terminal Building with Control Tower
Location: Salley,Rukum.
Rate per Rm Rs. 443.78
2065/066
Total (Rs.)
Level
Qty
Unit
skilled
0.17
nos
350.00
59.50
un skilled
0.2
1.0
1.0
LS
nos
Rm
sets
250.00
112.39
50.00
50.00
112.39
50.00
50.00
a.PVC pipe
b.PVC cowl
Transportation from nepalgunj to Salley by plane
Rate/unit
cost
Actual rate
15% conctractor overhead
Rate per set Rs. 370.17
Total (Rs.)
Level
Qty
Unit
skilled
0.17
nos
350.00
59.50
un skilled
0.2
1.0
LS
nos
nos
sets
250.00
1900.00
50.00
1900.00
50.00
Rate/unit
LS
cost
500.00
Actual rate
15% conctractor overhead
Rate per set Rs. 2943.42
Total (Rs.)
1011
KITCHEN SINK COMPLETE SET 60x45x25Cm ( 24"x18"x10") size LARGE
sources
labour
materials
Level
skilled
un skilled
a. 60x45x25Cm (24"x18"x10") steel sink with bracket.
b.Pvc bottle trap including 1" waste coupling with c p
chain
c. " Sink cock
d.screw etc.
Transportation from nepalgunj to Salley by plane
Qty
3
1
1
Unit
nos
nos
nos
Rate/unit
350.00
250.00
2000.00
cost
1050.00
250.00
2000.00
1
1
Ls
set
nos
450.00
900.00
450.00
900.00
18.00
LS
Actual rate
500.00
Checked by :-
Approved by :-
Page 42 of 82
Babarmahal, Kathmandu.
Rate Analysis
Project: Reconstruction of Terminal Building with Control Tower
Location: Salley,Rukum.
Rate per set Rs. 5943.2
Prepared by :-
Checked by :-
2065/066
Total (Rs.)
Approved by :-
Page 43 of 82
Rate Analysis
Project: Reconstruction of Terminal Building with Control Tower
Location: Salley,Rukum.
sources
labour
materials
Level
2065/066
skilled
un skilled
a. 15mm fancy type bib cock long neck
Transportation from nepalgunj to Salley by plane
Rate/unit
350.00
250.00
800.00
1
nos
LS
Actual rate
15% conctractor overhead
Total (Rs.)
cost
38.50
800.00
25.00
1061
CP Shower rose 7.5 cm (3") dia
Qty
Unit
Rate/unit
skilled
0.33
nos
350.00
1
nos
600.00
materials
a.7.5cm dia shower rose fancy type with 30cm CP rod
Transportation from nepalgunj to Salley by plane
Ls
Actual rate
15% contractor overhead
Rate per nos Rs. 1052.82
Total (Rs.)
sources
labour
Level
cost
115.50
600.00
200.00
1049
CP Soap Dish
sources
labour
materials
Level
skilled
a. Soap dish
b.Zink oxide screw etc.
Transportation from nepalgunj to Salley by plane
1048
CHROME PLATE TOILET PAPER HOLDER
CP TOILET PAPER HOLDER
sources
Level
labour
skilled
materials
a.Chrome plate toilet paper holder
b.Zink oxide screw etc.
Transportation from nepalgunj to Salley by plane
Qty
Unit
Rate/unit
0.11
nos
350.00
1
nos
189.00
Ls
Ls
Actual rate
15% contractor overhead
Total (Rs.)
cost
38.50
189.00
10.00
150.00
Qty
Unit
Rate/unit
0.11
nos
350.00
1
nos
278.00
Ls
Ls
Actual rate
15% contractor overhead
Total (Rs.)
cost
38.50
278.00
10.00
150.00
1055
CP Glass Shelf
sources
labour
materials
Prepared by :-
Level
skilled
a. C P Guard rail with glass
b. Screws etc.
Transportation from nepalgunj to Salley by plane
Checked by :-
Qty
Unit
Rate/unit
0.22
nos
350.00
1
nos
490.00
Ls
Ls
Actual rate
15% contractor overhead
cost
77.70
490.00
10.00
150.00
Approved by :-
Page 44 of 82
Babarmahal, Kathmandu.
Rate Analysis
Project: Reconstruction of Terminal Building with Control Tower
Location: Salley,Rukum.
Rate per nos Rs. 836.85
2065/066
Total (Rs.)
1052
C P towel rod 0.5"x 18"
sources
labour
materials
Level
skilled
a . C PTowel rod
b. Screws etc.
Transportation from nepalgunj to Salley by plane
Prepared by :-
Checked by :-
Qty
Unit
Rate/unit
0.22
nos
350.00
1
nos
350.00
Ls
Ls
Actual rate
15% contractor overhead
Total (Rs.)
cost
77.78
350.00
10.00
150.00
Approved by :-
Page 45 of 82
Babarmahal, Kathmandu.
Rate Analysis
3866.00
5,666.00
849.90
6,515.90
3105.00
4305.00
645.75
4950.75
Prepared by :-
Checked by :-
Approved by :-
Page 46 of 82
Babarmahal, Kathmandu.
Rate Analysis
1638.00
2588.00
388.2
2976.2
2050.00
7325.00
9375.00
1406.25
10781.25
115.50
535.00
650.50
97.57
Prepared by :-
Checked by :-
Approved by :-
Page 47 of 82
Babarmahal, Kathmandu.
Rate Analysis
748.07
38.50
625.00
663.50
99.52
763.02
38.50
336.00
374.50
56.17
430.67
38.50
482.00
520.50
78.07
598.57
Prepared by :-
Checked by :-
Approved by :-
Page 48 of 82
Babarmahal, Kathmandu.
Rate Analysis
G.M. 25mm Gate Valve
Total Cost
77.00
689.00
766.00
114.90
880.90
63.50
354.00
417.50
62.62
480.12
103.00
225.00
328.00
49.2
377.20
Prepared by :-
Checked by :-
Approved by :-
Page 49 of 82
Babarmahal, Kathmandu.
Rate Analysis
103.00
270.00
373.00
55.95
428.95
143.00
372.00
515.00
77.25
592.25
Prepared by :-
Checked by :-
Approved by :-
Page 50 of 82
Babarmahal, Kathmandu.
Rate Analysis
66.00
164.39
230.39
34.55
264.94
109.50
209.45
318.95
47.84
366.79
109.50
276.40
385.90
57.88
Prepared by :-
Checked by :-
Approved by :-
Page 51 of 82
Babarmahal, Kathmandu.
Rate Analysis
443.78
109.50
212.39
321.89
48.28
370.17
109.50
2450.00
2559.50
383.92
2943.42
3868.00
5168.00
775.2
Prepared by :-
Checked by :-
Approved by :-
Page 52 of 82
Babarmahal, Kathmandu.
Rate Analysis
5943.2
Prepared by :-
Checked by :-
Approved by :-
Page 53 of 82
Babarmahal, Kathmandu.
Rate Analysis
Total Cost
38.50
199.00
150.00
387.50
58.12
445.62
Total Cost
38.50
288.00
150.00
476.50
71.47
547.97
CP Glass Shelf
Total Cost
77.70
500.00
150.00
727.70
109.15
Prepared by :-
Checked by :-
Approved by :-
Page 54 of 82
Babarmahal, Kathmandu.
Rate Analysis
836.85
Total Cost
77.78
360.00
150.00
587.78
88.16
675.94
Prepared by :-
Checked by :-
Approved by :-
Page 55 of 82
Materials
Skilled Labor
Unskilled labor (jaymi)
Carpenter (sikarmi)
Bar-binder (nakarmi)
Painter (chitrakar)
Blacksmith (nakarmi)
Welder
Plumber
Sand
Cement (Indian 53 Grade) = 450per bag +
Transportation from Dang to Salley by truck with
load/ unload Rs 1.00 per kg
=
470/50*1000=9400.00
Earth from borrow (lose)
Block stone
Bond stone
Rubble stone
Dressed stone
Gravel
River cobbles and pebbles
5 mm to 10 mm size
11 mm to 20 mm size
21 mm to 40 mm size
Reinforcing bars (steel) (average size)
7 mm
8mm
10 mm
12mm
Binding wire
Nails
Salwood
Nut bolts
CGI Sheet (colour)
26 gauge ( Cost Per bundle as per Dang District
Rate
= 8170.00 & cost per sq m
=8170/17.84=457.96 & Transportation from Dang
to salley by Truck with load / unload Rs 6.66 per
kg & assumming one bundle =65 kg
Unit
Transportatio
Material Price
n Cost
source
(4.50/100)*14
8
Weight
(kg)
m-day
m-day
m-day
m-day
m-day
m-day
m-day
m-day
cum
Mt.
cum
cum
cum
cum
cum
cum
9000.00
50.00
1853.85
1853.85
1853.85
3617.85
6.66
1000.00
cum
cum
cum
15,660.00
50.00
1,853.85
1,853.85
1,853.85
3,617.85
1,500.00
1,500.00
1,500.00
1,500.00
kg
kg
kg
kg
kg
kg
cum
kg
103.25
93.70
92.20
92.20
111.20
97.50
33516.00
150.00
6.66
6.66
6.66
6.66
6.66
6.66
6.66
6.66
1.00
1.00
1.00
1.00
1.00
1.00
970.00
1.00
109.91
100.36
98.86
98.86
117.86
104.16
39,976.20
156.66
-
sqm
457.96
6.66
3.64
sqm
457.96
6.66
3.64
482.23
482.23
no
no
no
21.17
0.34
1.04
6.66
0.10
0.14
GI Plain sheet
26 gauge colour Plain sheet
J-hook & U-hook :- ( Rate per kg = Rs 127.00 in
Dang and assuming Per No = 0.14 kg & In 1 kg =
6 No of J-hooks.
Bitumen washer
Screws (25, 40, 50, 65 mm)
Rate of
Labour &
Materials at
Site
350.00
250.00
350.00
350.00
350.00
350.00
350.00
300.00
3,300.00
22.12
0.44
1.04
Page 56 of 82
Transportatio
Material Price
n Cost
source
(4.50/100)*14
8
Weight
(kg)
Materials
Unit
no
12.86
6.66
0.14
no
no
no
25.00
30.00
50.00
6.66
6.66
6.66
0.10
0.12
0.25
no
no
no
no
20.00
50.00
65.00
95.00
6.66
6.66
6.66
6.66
0.10
0.12
0.20
0.25
no
no
no
no
no
no
250.00
190.00
45.00
600.00
180.00
450.00
6.66
6.66
6.66
6.66
6.66
6.66
0.35
0.25
0.15
0.45
1.00
1.00
sqm
sqm
550.00
600.00
6.66
6.66
10.00
12.50
sqm
sqm
Rm
bag
Sqm
Sqm
Sqm
ltr
kg
ltr
ltr
sheet
Rm
sqm
kg
kg
ltr
%
170.00
235.00
6.66
6.66
4.50
6.50
1250.00
880.00
880.00
880.00
227.00
62.00
385.00
303.00
5.00
135.00
1398.00
135.00
10.00
147.00
15.00
6.66
6.66
6.66
6.66
6.66
6.66
6.66
6.66
50.00
18.75
18.75
19.75
1.12
1.12
1.12
1.12
6.66
6.66
6.66
6.66
6.66
1.00
10.76
1.00
1.00
1.12
75 mm
100 mm
150 mm
Tower bolts ( Aluminium)
75 mm
100 mm
150 mm
300 mm
Aldrops
12" long
10" long
Handle 150 mm
Mortise lock( CP Steel Lock)
Ordinary door spring
Hydraulic door spring
Glass
4 mm thick
5 mm thick
Commercial plywood
4 mm thick
6 mm thick
Wooden beads
White cement
Porcelain glazed tile (4"x8")
Porcelain non-glazed tile (6"x6")
Porcelain non-skid tile (6"x6")
Primer
Waterproof cement paint
Aluminum paint
Readymade Enamel
Sand paper
Black Pipe
3 x 20 mm MS grille
Tubular truss (complete)
Welding rod
Anticorrosive paint
Contractor's Overhead & Profit
Rates are based on market prevailing market value and district rate.
All the rates listed above are excluding VAT but inclusive of transportation.
Rates which are not available are taken as per market survey.
Source for other materials than locally available is taken Dang as source market.
Rate of
Labour &
Materials at
Site
13.81
25.67
30.80
51.67
20.67
50.80
66.33
96.67
252.33
191.67
46.00
603.00
186.66
456.66
616.60
683.25
199.97
278.29
25.00
1,583.00
1,004.88
1,004.88
1,011.54
234.46
69.46
392.46
310.46
5.00
141.66
1,469.66
141.66
16.66
154.46
15.00
Page 57 of 82
Transportatio
Material Price
n Cost
Weight
Materials
Unit
source
(4.50/100)*14
(kg)
8
Transportation from Dang to Salley by Truck on Gravel road and rate is taken 148 km *Rs 4.50 per quintel.
Materials weight is calculated as per Engineering standard weight
Material rate out side from Dang is takes as for Nepalgunj
Transportation cost from Dang to Salley =148 km *Rs 4.50 Per quintel by truck.
Rate of sanitary fitting are taken from Nepalgunj District Rate and Transportation is taken as Lump sump
Rate of
Labour &
Materials at
Site
Page 58 of 82
2065/66
Qty
Unit
Rate
Amount
Total Amount
No
440.00
880.00
No
350.00
1050.00
1.25
No
300.00
375.00
Labour
Skilled
Semi skilled
Un-skilled
2,305.00
Materials
1.b
1.00
No
2,100.00
2,100.00
1.00
No
800.00
800.00
1.00
No
550.00
550.00
9.00
No
500.00
4,500.00
10.00
No
220.00
2,200.00
10,150.00
Transportation 30%
3,045.00
13,195.00
Total :
15,500.00
2,325.00
Total :
17,825.00
Say :
17,825.00
Qty
Unit
Rate
Amount
Total Amount
No
440.00
880.00
No
350.00
1050.00
1.25
No
300.00
375.00
2,100.00
Labour
Skilled
Semi skilled
Un-skilled
2,305.00
Materials
Enclosure (1P 8way)
1.00
No
2,100.00
0.00
No
800.00
1.00
No
550.00
550.00
7.00
No
500.00
3,500.00
7.00
No
Estimated by :-
220.00
1,540.00
7,690.00
Transportation 30%
2,307.00
9,997.00
Total :
12,302.00
1,845.30
Total :
14,147.30
Checked by :-
Approved by :-
Page 59 of 82
2065/66
Say :
Estimated by :-
Checked by :-
14,147.00
Approved by :-
Page 60 of 82
2065/66
Qty
Unit
Rate
Amount
Total Amount
nos
440.00
440.00
1.5
nos
350.00
525.00
nos
300.00
900.00
2*7/20 wire
110
Rm
37.78
4,155.56
1*3/20 wire
110
Rm
16.11
1,772.22
110
Rm
110.00
12,100.00
25 mm Conduit Pipe
101
Rm
28.00
2,828.00
20,955.78
Transportation 30%
6,286.73
27,242.51
Total :
29,107.51
4,366.13
Total :
33,473.64
334.74
Labour
Skilled
Semi skilled
Un-skilled
1,865.00
Materials
Screws/Nais etc.
2.2
Ls
100.00
2*3/20+1*1/18 PVC copper Wire Nepal, Prakash with 25 mm HDP Pipe etc.
Particulars
Qty
Unit
Rate
Amount
nos
440.00
440.00
1.5
nos
350.00
525.00
nos
300.00
900.00
2*3/20 wire
110
Rm
16.11
1,772.22
1*1/18 wire
110
Rm
8.33
916.67
110
Rm
110.00
12,100.00
25 mm Conduit Pipe
101
Rm
28.00
2,828.00
Total Amount
Labour
Skilled
Semi skilled
Un-skilled
1,865.00
Materials
Screws/Nais etc.
Estimated by :-
Ls
100.00
Total of Material Cost :
17,716.89
Transportation 30%
5,315.07
23,031.96
Total :
24,896.96
3,734.54
Total :
28,631.50
286.31
Checked by :-
Approved by :-
Page 61 of 82
3.1
2065/66
Qty
Unit
Rate
Amount
Total Amount
Labour
Skilled
0.10
No
440.00
44.00
Semi skilled
0.20
No
350.00
70.00
Un-skilled
0.25
No
300.00
75.00
10.00
10.00
100.00
1.00
Pc
115.00
115.00
1.00
Pc
90.00
Total of Material Cost :
Transportation 30%
189.00
Materials
Copper Wire 3/22
200.00
415.00
124.50
Total :
Conctractor Overhead 15% :
Total :
539.50
728.50
109.28
837.78
837.78
Estimated by :-
Qty
0.20
0.25
0.25
Unit
Rate
440.00
350.00
300.00
No
No
No
Amount
Total Amount
88.00
87.50
75.00
250.50
116.67
50.00
166.67
50.00
Total :
Conctractor Overhead 15% :
Total :
Rate Per Unit :
216.67
467.17
70.08
537.24
537.00
5.00
M
23.33
5.00
M
10.00
Total of Material Cost :
Transportation 30%
Checked by :-
Approved by :-
Page 62 of 82
4.2
Qty
Unit
1
2
0
nos
nos
nos
10
10
2065/66
Rate
440.00
350.00
300.00
Amount
Total Amount
440.00
700.00
-
1,140.00
1,900.00
400.00
65.00
2,365.00
709.50
Total :
Conctractor Overhead 15% :
Total :
Rate Per Unit :
3,074.50
4,214.50
632.18
4,846.68
484.67
nos
190.00
nos
40.00
LS
Total of Material Cost :
Transportation 30%
Estimated by :-
Qty
Unit
1
2
0
nos
nos
nos
10
10
Rate
440.00
350.00
300.00
Amount
Total Amount
440.00
700.00
-
1,140.00
4,000.00
400.00
100.00
4,500.00
1,350.00
Total :
Conctractor Overhead 15% :
Total :
Rate Per Unit :
5,850.00
6,990.00
1,048.50
8,038.50
803.85
nos
400.00
nos
40.00
LS
Total of Material Cost :
Transportation 30%
Checked by :-
Approved by :-
Page 63 of 82
6
6.1
Qty
Unit
0.50
0.50
10
20
10
20
Rate
440.00
350.00
300.00
No
No
No
2065/66
Amount
Total Amount
220.00
175.00
-
395.00
14,500.00
1,900.00
150.00
300.00
50.00
16,900.00
5,070.00
Total :
Conctractor Overhead 15% :
Total :
Rate Per Unit :
21,970.00
21,970.00
3,295.50
25,265.50
2,526.55
nos
1450.00
nos
95.00
Rm
15.00
nos
15.00
LS
Total of Material Cost :
Transportation 30%
Estimated by :-
Qty
Unit
0.5
nos
440.00
220.00
0.5
0
nos
nos
350.00
300.00
175.00
10
Rate
nos
300.00
ls
Total of Material Cost :
Transportation 30%
Amount
Total Amount
3,000.00
50.00
3,050.00
915.00
Total :
Conctractor Overhead 15% :
Total :
Rate Per Unit :
Checked by :-
395.00
3,965.00
4,360.00
654.00
5,014.00
501.40
Approved by :-
Page 64 of 82
Qty
Unit
0.5
0.5
0
nos
nos
nos
10
2065/66
Rate
440.00
350.00
300.00
Amount
Total Amount
220.00
175.00
-
395.00
5,000.00
50.00
5,050.00
1,515.00
Total :
Conctractor Overhead 15% :
Total :
Rate Per Unit :
6,565.00
6,960.00
1,044.00
8,004.00
800.40
nos
500.00
ls
Total of Material Cost :
Transportation 30%
Estimated by :-
Qty
Unit
0.5
0.75
1.5
nos
nos
nos
Rate
440.00
350.00
300.00
Amount
Total Amount
220.00
262.50
450.00
932.50
5,000.00
5,712.50
1,713.75
Total :
Conctractor Overhead 15% :
Total :
Rate Per Unit :
7,426.25
8,358.75
1,253.81
9,612.56
9,612.56
job
5000.00
Total of Material Cost :
Transportation 30%
Checked by :-
Approved by :-
Page 65 of 82
Unit
0.25
0.5
1
nos
nos
nos
1
4
Rate
250.00
220.00
175.00
Amount
Total Amount
62.50
110.00
175.00
347.50
9,500.00
7,000.00
16,500.00
4,950.00
Total :
Conctractor Overhead 15% :
Total :
Rate Per Unit :
21,450.00
21,797.50
3,269.63
25,067.13
25,067.13
Set
9500.00
nos
1750.00
Total of Material Cost :
Transportation 30%
10
Qty
2065/66
Qty
Unit
0.5
0.5
0
nos
nos
nos
Rate
440.00
350.00
300.00
Amount
Total Amount
220.00
175.00
-
395.00
2,300.00
60.00
450.00
10.00
2,820.00
846.00
Total :
Conctractor Overhead 15% :
Total :
Rate Per Unit :
3,666.00
4,061.00
609.15
4,670.15
4,670.15
nos
2300.00
LS
1
nos
450.00
LS
Total of Material Cost :
Transportation 30%
Estimated by :-
Qty
Unit
1
1
nos
nos
nos
Rate
440.00
350.00
300.00
Amount
Total Amount
440.00
350.00
-
790.00
1,900.00
500.00
50.00
2,450.00
735.00
Total :
Conctractor Overhead 15% :
3,185.00
3,975.00
596.25
nos
1900.00
LS
LS
Total of Material Cost :
Transportation 30%
Checked by :-
Approved by :-
Page 66 of 82
Estimated by :-
Checked by :-
2065/66
4,571.25
4,571.25
Approved by :-
Page 67 of 82
Material Cost.
Project :- Dolpa ( Juphal ) Airport Project
Place :- Dolpa.
2
2065/066
Norms No
B
22-4-ga
Prepared by :-
Input
Unit
12.31
m-day
Rate (NRs)
Amount (NRs)
Checked by:-
250.00
3076.92
3076.92
3076.92
Approved by :-
Page 68 of 82
Material Cost.
Project :- Dolpa ( Juphal ) Airport Project
Place :- Dolpa.
3
Cost of Rubble Stone :-
2065/066
Input
4.62
Unit
Rate (NRs)
Amount (NRs)
cu m
700.00
700.00
m-day
250.00
1153.85
1853.85
1853.85
Norms No
A
3-8
Prepared by :-
Input
Unit
5.88
m-day
Rate (NRs)
Amount (NRs)
300.00
1853.85
1764.00
3617.85
3617.85
Checked by:-
Approved by :-
Page 69 of 82
Material Cost.
Project :- Dolpa ( Juphal ) Airport Project
Place :- Dolpa.
5
Cost of Earth :Collection, Transportation and providing
of Earth to site per cu m with an average
lead of 50.00 m
Norms No
A
Norms No
A
Rate (NRs)
m-day
0.70
m-day
0.00
210.00
Total of -A: -
210.00
300.00
120.00
120.00
330.00
330.00
from 50 m
0.40
Input
Unit
0.00
m-day
m-day
Rate (NRs)
Amount (NRs)
Man power
Materials
440.00
300.00
Total of -A: -
Prepared by :-
Amount (NRs)
300.00
Materials
Skilled Labour
Unskilled Labour
Unit
Man power
Excavation
Analysed /cu m
Input
2065/066
from
0.00
0.00
0.00
8280.00
kosh
6.00
Checked by:-
600.00
1.45
5220.00
8280.00
13500.00
13500.00
Approved by :-
Page 70 of Pages
S.No.
A
Description of work
Quantity
Unit
In Figure
Rate (NRs)
In Words
Per
CIVIL WORKS
1 EARTHWORK
1.1 Cleaning and grubbing of site for construction including removal
of grass, shrubs and levelling undulated ground all compleate as
per drawings and instructions.
1.2
sq m
cu m
1.3 Filling in plinth and floor with earth in 150 mm layers under floor
including watering consolidating by using mechanical vibrator and
dressing all complete as per drawings, specifications and
instructions
cu m
cu m
2 CONCRETE WORK
2.1 Plain cement concrete of mix 1:3:6 in foundation base with 1
cement, 3 course sand and 6 aggrigates of 19 mm and down grade
including mixing , laying, compacting , finishing, curing , laid to
exact line, level and dimensions inclusive of side shuttering
complete as per drawings, specifications and instructions.
cu m
2.2 Structural concrete of specified grade in any form, size, shape and
level of all Reinforced cement concrete work (except in flooring
work) including setting out, mixing, laying, compacting, curing,
testing and finishing all complete as per drawings, specifications
and instructions.
P.C.C for R.C.C in 1:2:4
cu.m
one
Amount(NRs)
Page 71 of Pages
BILL OF QUANTITIES.
FY: 2065-66
Site:Dolpa (Juphal) Airport
S.No.
2.3
Description of work
Form work, shuttering, centering with approved materials such as
shuttering plywood, plain steel sheets etc. for all RCC works of
any shape, size, and at any level with necessary propping ( MS
pipe /timber) staging , supporting, wedging, inclusive of providing
the final surface in concrete line,level, cleaaring surface and
applying form oil all complete as per drawings, specifications and
instructions.
Quantity
Unit
In Figure
Rate (NRs)
In Words
Per
sq m
2.4 Tor Steel /torkari Reinforcement (Fe 415) bar tested grade 1 steel
conforming to I.S. 1786-1966 or IS 1139-1966 in RCC work
including bending, binding with GI wire, Placing in position and
the cost of G.I. wire all complete works as per drawings,
specifications and instructions.
kg
3 STONE WORKS
3.1 Random rubble stone masonry in mud mortar in foundation in
required line and level in any size and shape including scaffolding,
timbering etc. all complete as per drawings, Specifications and
instructions.
cu m
3.2 Coursed stone masonry with face dressed stone in mud mortar in
superstructure in any size and shape of wall made to required line
and level, scaffolding etc, all complete as per drawings,
specification and instructions.
cu m
3.3 Coursed stone masonry with face dressed stone in cement mortar
1:6 (1cement: 6sand) in superstructure in any size and shape of
wall made to required line and level, scaffolding etc, all complete
as per drawings,specification and instructions.
cu m
cu m
Sqm
one
Amount(NRs)
Page 72 of Pages
BILL OF QUANTITIES.
FY: 2065-66
Site:Dolpa (Juphal) Airport
S.No.
Description of work
Quantity
Unit
In Figure
Rate (NRs)
In Words
Per
Sqm
Cum
Sqm
one
one
Sqm
one
one
4.6 38mm thick local hard wood framed flush door shutter.
Sqm
one
5 FLOORING
5.1 Stone boulder soling under floors including sand blinding,
watering, consolidating and dressing all complete as per drawing,
specification & instructions.
cu m
5.3 Providing and laying two layer of 500 gauge polythene sheet
under floor with 30 % overlap all complete as per drawings,
specifications and instructions.
sq.m
5.3 Plain cement concrete of mix 1:3:6 in floor base with 1 cement, 3
coarse sand and 6 aggregate of 19 mm and down grade including
mixing, laying, compacting, finishing, curing, laid to exact line,
level and dimensions inclusive of side shuttering complete as per
drawing, specification and instructions.
cu m
5.4 50 mm thick IPS floor finish with cement concrete of mix 1:2:4
laid in panels of 1m x 1m, finished in required pattern & slope as
per drawing, specification and instructions.
sq.m
5.5 40 mm thick IPS floor finish with cement concrete of mix 1:2:4
laid in panels of 1m x 1m, finished in required pattern & slope as
per drawing, specification and instructions.
sq m
rm
Amount(NRs)
Page 73 of Pages
BILL OF QUANTITIES.
FY: 2065-66
Site:Dolpa (Juphal) Airport
S.No.
Description of work
Quantity
Unit
5.7 Providing and laying approved brand non glazed vitrified ceramic
tile on the floor and filling making tile joints water tight including
cement screed of required thickness to receive the tile floor
complete as per drawing, specification and instructions.
sq.m
5.8 Providing and laying approved brand glazed ceramic tile in wall
with 18 mm thick cement mortar of mix 1 : 3 backing and filling
joints with approved materials all complete as per drawing,
specification and complete as per drawing, specification and
instructions.
sq.m
6 ROOFING
6.1
Providing and fixing tubular roof trusses with rafters, purlins,
wind ties, brackets etc, made with required grade mild steel tubes
and mild steel sections of required sizes, including hoisting, fixing
in position with MS bed plates, shoe angles, anchor bolts etc, and
concrete grouting, concreting nut bolts, fabrication, fixing and
treated with two coats of anticorrosive paints all complete as per
drawings, specifications and instructions.
kg
sq.m
rm
6.4 Providing and fixing in position (25 mm) thick timber fascia board
in position with required fittings inclusive of waterproof painting
all complete as per drawings, specifications and instructions.
sq.m
rm
sq.m.
7 FINISHING/FINISHING WORKS
In Figure
Rate (NRs)
In Words
Per
Amount(NRs)
Page 74 of Pages
BILL OF QUANTITIES.
FY: 2065-66
Site:Dolpa (Juphal) Airport
S.No.
Description of work
Quantity
Unit
7.1 Plastering with specified mortar in any level size and shape of
wall, column, ceiling, band, blocks etc as required including
racking, watering, cleaning of base,plastering to plumb, line,
level, smooth etc. and curing complete as per drawing,
specification and instructions.
a)
b)
3/4" (20 mm) average thick cement plaster of mix 1:6 in plinth
including neat cement finish.
sq.m
1/2 (12.5 mm) average thick cement plaster of mix 1:4 in RCC
surface ceiling.
sq.m
8 PAINTING WORKS
8.1 Painting with two or more coats of cement paint of approved
manufacturers over plastered surface on walls and ceilings at any
height or shape including wetting, surface preparation, curing all
complete as per drawings, specifications and instructions.
8.2
sq.m
sq.m
sq.m
sq.m
sq.m
Rm
In Figure
Rate (NRs)
In Words
Per
Amount(NRs)
Page 75 of Pages
BILL OF QUANTITIES.
FY: 2065-66
Site:Dolpa (Juphal) Airport
S.No.
9.4
Description of work
Providing and fixing in position 100 x 75 mm size local hard
wood staircase handrail over 20 x 20 mm size square MS
balustrade fixed with mild steel strip of size 50 x 6 mm size or any
other designed balustrade with necessary welding, screwing,
including two or more coats of enamel paint over MS surface and
wood staining over wooden surface all complete as per drawings,
specifications and instructions.
Quantity
Unit
Providing and laying in position and in slope various dia. Pipes for
soil and waste line including earthwork excavation, joining of
pipes with color and back filling all complete works as per
instruction of site incharge..
a 110 mm diameter UPVC pipe
b 2 nos of each 110 mm diameter UPVC pipe.
Per
Rm
sq m
9.6 Staircase
9.6.1
Providing and fixing in position steel framed stair with timber
tread with all necessary fittings, paintings etc all complete with
following details.
a) MS sections including cutting, welding, anchoring in position,
painting all complete.
b) Providing and fixing in position 40 mm thick timber tread
inclusive of all fittings and painting.
9.6.2 Staircase made with MS sections with Timber tread from first
floor to Tower
a) Structural steel work
b) 40 mm thick Timber tread
In Figure
Rate (NRs)
In Words
One
Rm
Rm
Amount(NRs)
Page 76 of Pages
BILL OF QUANTITIES.
FY: 2065-66
Site:Dolpa (Juphal) Airport
Description of work
set
One
set
One
set
One
a
b
Quantity
Unit
Rate (NRs)
In Words
S.No.
In Figure
Per
Amount(NRs)
Page 77 of Pages
BILL OF QUANTITIES.
FY: 2065-66
Site:Dolpa (Juphal) Airport
S.No.
Description of work
Unit
In Figure
Rate (NRs)
In Words
Per
Providing and fixing in position C.P. soap tray with C.P. screws
etc. all complete works with testing and ready for operation.
Providing and fixing in position of heavy type C.P. bib cocks all
complete works with testing and ready for operation.
Quantity
set
One
Providing, joining and fixing in position PVC soil and waste pipes
and fittings for the vertical and horizontal lines with necessay
claims, cutting, holes in the floor or walls and repair in the same to
its original finished all complete works with testing and ready for
operation.
a 75 mm dia UPVC pipes
b 110 mm diameter UPVC pipe
Sub Total of Soil, Waste, and Vent Pipes and Fitting
Works( D ) Nrs :E. Water Supply Installation.
One
no
One
Amount(NRs)
Page 78 of Pages
BILL OF QUANTITIES.
FY: 2065-66
Site:Dolpa (Juphal) Airport
S.No.
2
Description of work
Quantity
Unit
In Figure
Rate (NRs)
In Words
Per
Providing, and fixing heavy type full flow GM gate valve all
complete works with testing and ready for operation.
a 1" dia . G..M. gate valve.
b 3/4" dia . G..M. gate valve.
Providing, and installation of plastic overhead water tank of 1000
liters capacity fixed over thebuilt in elevated plate form including
required connections for supply and distribuation, overflow and
washout all complete works with testing and ready for operation.
set
One
no
One
no
One
Sub-Total of Water Supply Installation Works (E) Nrs :F. Electrical Works.
1
no
rm
rm
Amount(NRs)
Page 79 of Pages
BILL OF QUANTITIES.
FY: 2065-66
Site:Dolpa (Juphal) Airport
S.No.
Description of work
Quantity
Unit
In Figure
Rate (NRs)
In Words
Per
2.2
3.1
One way light point :- Light/ Fan points with 2x3/22 PVC
insulated copper cable in 16/20 mm dia. HDP pipe including the
cost of requird gang switch plate but excluding light fixtures.
3.2
rm
One
rm
One
rm
One
no
One
3.3
4.1
4.2
Amount(NRs)
Page 80 of Pages
BILL OF QUANTITIES.
FY: 2065-66
Site:Dolpa (Juphal) Airport
S.No.
5
Description of work
Fluorescent Tube Light Fixtures :- Supplying, installation and
Putting in to operation of following types of fluorescent light
fixture having open type copper chowk, powder coated fininshing,
PF capacitor, complete in all respect and putting in to operation
including all required fixing and connectioning materials as
requird complete as per drawings, specifications and instructions
( Approved make- Lumex).
5.1
6
6.1
Quantity
Unit
no
In Figure
Rate (NRs)
In Words
Per
One
Amount(NRs)
Page 81 of Pages
BILL OF QUANTITIES.
FY: 2065-66
Site:Dolpa (Juphal) Airport
S.No.
Description of work
6.2
a
b
c
E
1
2
Quantity
Unit
In Figure
Rate (NRs)
In Words
Per
Amount(NRs)
no
LS
PS
Total of General Items
Sub Total of Civil Works( A ) Nrs :Sub Total of drainage Works( B ) Nrs :Sub Total of Sanitary Works( C )Nrs :Sub Total of Soil, Waste, and Vent Pipes and Fitting Works( D ) Nrs :Sub-Total of Water Supply Installation Works (E) Nrs :Total Electrical Works (F) Nrs :Total of A,B,C,D,E, & F NRs :13 % VAT NRs :Grand Total Including 13% VAT NRs :-
50,000.00
50,000.00
Page 82 of Pages
BILL OF QUANTITIES.
FY: 2065-66
Site:Dolpa (Juphal) Airport
S.No.
Description of work
Quantity
Unit
In Figure
Rate (NRs)
In Words
Firms Seal:
Per
Amount(NRs)