WELL : TT-28
LOCATION : TTM-SA1
DRILLING 2009
DAFTAR ISI
WELL : TT-28
LOCATION : TTM-SA1
1. CLOSED OUT
2. WELL DATA, EXECUTIVE SUMMARY &
WELL PROFILE
3. WELL OPERATION SUMMARY & WCR
4. DRILLING TIME SUMMARY
5. WEEKLY DRILLING REPORT
6. DAILY DRILLING REPORT
7. BIT RECORD
8. CASING TALLY
9. TUBING TALLY
10. MATERIAL REPORT
11. BERITA ACARA & MOM
12. MUD ENGINEERING REPORT
13. MUD LOGGING UNIT REPORT
14. CEMENTING REPORT
15. DIRECTIONAL DRILLING &
MEASUREMENT
16. EWLPP REPORT
17. WELL PROGRAM
DRILLING - 2009
CLOSED OUT
WELL : TT-28
LOCATION : TTM-SA1
DRILLING - 2009
BPMIGAS
PERTAMINA PETROLEUM CONTRACT
AUTHORIZATION FOR EXPENDITURES - DRILLING AND WORKOVER
BPMIGAS : Approved by :
Position :
Date :
Asumsi 1 USD = Rp. 9.400,-
BPMIGAS SCHEDULE NO.20
PERTAMINA PETROLEUM CONTRACT
AUTHORIZATION FOR EXPENDITURE - DRILLING AND WORKOVER MATERIAL LIST ATTACHMENT TO SCHEDULE 19
A TANGIBLE COSTS
CASING
20" OD Casing, K-55, 54.5 ppf, R3, BTC Mtr 30 170,4 5.112 30 5.112 28 170 4.771 (2) (341)
13 3/8" OD Casing, K-55, 54.5 ppf, R3, BTC Mtr 200 118,5 23.700 200 23.700 196 119 23.226 (4) (474)
9 5/8" OD Casing, K-55, 36 ppf, R3,BTC Mtr 700 81,0 56.700 700 56.700 1.188 81 96.228 488 39.528
7" OD Casing, K-55, 23 ppf, R3, BTC. Mtr 1.421 52,0 73.892 1.421 73.892 1.439 52 74.828 18 936
Sub Total 159.404 159.404 199.053 39.649
CASING ACCESSORIES
13 3/8 Casing Accessories
Float Collar 13 3/8" pce 1 1.287 1.287 1 1.287 1 1.287,00 1.287 0 0
Float Shoe 13 3/8" pce 1 1.111 1.111 1 1.111 1 1.111 1.111 0 0
Top Plug 13 3/8" pce 1 720 720 1 720 1 720 720 0 0
Bottom Plug 13 3/8" pce 1 640 640 1 640 1 640 640 0 0
Centralizer 13 3/8" pce 7 121 847 7 847 4 121 484 (3) (363)
Stop Ring 13 3/8" pce 7 51 357 7 357 4 51 204 (3) (153)
Sub Total 13 3/8" Csg Accecories 4.962 4.962 4.446
Page 1 Of 4
BPMIGAS SCHEDULE NO.20
PERTAMINA PETROLEUM CONTRACT
AUTHORIZATION FOR EXPENDITURE - DRILLING AND WORKOVER MATERIAL LIST ATTACHMENT TO SCHEDULE 19
7 1/16" x 3" - 3000 psi Tubing Adaptor Flange pce 1 1.026,00 1.026 1 1.026 (1) (1.026)
3 1/2" EU x 10" Long J-55 pce 1 49 49 1 49 (1) (49)
Rod BOP 2 7/8" x 3000 pce 1 1.643,00 1.643 1 1.643 (1) (1.643)
3 1/2" EU x 3 1/2" EUE x 3" LP x 1" LP Flow Tee ( ID = 3" ) pce 1 136,00 136 1 136 (1) (136)
3" LP x 16" Nipple pce 1 175,00 175 1 175 (1) (175)
3 " LP x 8" Nipple pce 1 87,00 87 1 87 (1) (87)
1" x 3000 Ball Valve pce 1 203,00 203 1 203 (1) (203)
1" LP x 8" Nipple. pce 1 22,00 22 1 22 (1) (22)
1/2" x 6000 Psi Needle Valve pce 1 49,00 49 1 49 (1) (49)
3" x 1500 Ball Valve Series F. pce 1 1.680,00 1.680 1 1.680 (1) (1.680)
Pressure Switch Range pce 0 783,12 0 0 0 0 0
Wellhead Accecories PKT 1 6 189
6.189 6 189
6.189 1 6 189
6.189
Sub Total Well Head & Accecories 25.570 25.570 35.189 3.430
Pump Jack c/w 100 HP electromotor. ( C1280-365-192) pce 1 237.448 237.448 1 237.448
Polish Rod 1 1/2" x 30' pce 1 636 637 1 637 1 1.028 1.028 0 391
Stuffing Box pce 1 368 368 1 368
Stuffing Box Packing pce 1 19 19 1 19
Pump Jack Mutten pce 1 15.000 15.000 1 15.000
Sub Total 279.042 279.042 36.216 3.821
WELL EQUIPMENT SUBSURFACE
1" S. Rod. jts 69 85,70 5.914 69 5.914
Rod Guide 1" x 3" ea 138 10 1.396 138 1.396
7/8" S-Rod jts 67 80,1 5.366 67 5.366
Rod Guide 7/8" x 3" ea 134 10 1.355 134 1.355
3/4" S-Rod jts 19 68,3 1.299 19 1.299
Rod Guide 3/4" x 3" ea 38 10 385 38 385
3 1/2" Perforated Pup Joint jts 1 100 100 1 100
Tubing Pump Assy. ( 30-275-THEM-18) ea 1 3.750 3.750 1 3.750 1 2.320 2.320 0 (1.430)
Sub Total 19.565 19.565 2.320 (1.430)
TOTAL TANGIBLE COSTS 504.579 504.579 282.440 45.817
2 INTANGIBLE COSTS
DRILLING OPERATIONS
Mud Chemical
Barite, SG min = 4.2 As per API Spec. 13A - Sec. 2 100 lbs/sack sack 1.063,7 10,99 11.690 1.064 11.690 1.320 11 14.507 256 2.817
Bentonite, Wyoming Grade As per API Spec. 13A 100 lbs/sack sack 697,6 14,04 9.795 698 9.795 556 14 7.806 (142) (1.989)
Caustic Soda 25 kg/sack sack 27,2 26,26 714 27 714 15 26 394 (12) (320)
KOH 25 kg/sack sack 94,4 53,74 5.072 94 5.072 43 54 2.311 (51) (2.761)
KCl (KCl , K2O content : >96% & >60%) 50 kg/sack sack 956,6 65,00 62.180 957 62.180 1.019 65 66.235 62 4.055
Pac-R 25 kg/sack sack 144,2 96,53 13.923 144 13.923 161 97 15.541 17 1.619
Pac- L 25 kg/sack sack 276,3 88,29 24.396 276 24.396 152 88 13.420 (124) (10.976)
Page 2 Of 4
BPMIGAS SCHEDULE NO.20
PERTAMINA PETROLEUM CONTRACT
AUTHORIZATION FOR EXPENDITURE - DRILLING AND WORKOVER MATERIAL LIST ATTACHMENT TO SCHEDULE 19
Page 3 Of 4
BPMIGAS SCHEDULE NO.20
PERTAMINA PETROLEUM CONTRACT
AUTHORIZATION FOR EXPENDITURE - DRILLING AND WORKOVER MATERIAL LIST ATTACHMENT TO SCHEDULE 19
PDC Bit 12 1/4" ( Soft-Medium) pce 1 26.775,0 26.775 1 26.775 1 26.775 26.775 0 0
PDC Bit 8 1/2" ( Soft-Medium) pce 1 22.575,0 22.575 1 22.575 1 22.575 22.575 0 0
Sub Total Rock Bits 100.142 100.142
Cement and Additives sack 2.262 8,90 20.141 2.262 20.141 4.540 9 40.406 2.278 20.265
Diesel Fuel liter 127.500 1,28 162.766 127.500 162.766 (127.500) (162.766)
PT PERTAMINA EP : BPMIGAS :
Approved by : Bagus Sudaryanto Tri Siwindono Approved by
Position : Direktur Operasi PEP Presiden Direktur PEP Position
Date : Date
Signature : Signature
Page 4 Of 4
Evaluasi Teknis Closed Out AFE
AFE No : 09-3930
Sumur / Tipe : TT-28
PT PERTAMINA EP
DRILLING DEPARTMENT
Anggaran US $
Line No. Deskripsi Penjelasan Teknis Tindak Lanjut
Disetujui Realisasi Over/Under %
1 TANGIBLE COSTS
2 - Casing 153.479 199.053 29,7 Perubahan casing design 9-5/8" dari 700 m ke 1186 m.
Pemakaian stop ring dan centralizer csg 13-3/8", 9-5/8" dan 7" lebih sedikit dari
3 - Casing Accessories 24.746 19.595 (20,8)
program.
4 - Tubing 21.478 25.256 17,6 Unit Price tubing lebih tinggi dari rencana
►
5 - Well Equipment - Surface 279.042 36.216 (87,0) Belum dibebankan pumping unit
6 - Well Equipment - Subsurface 19.565 2.320 (88,1) ►Belum dibebankan rod pumping
7 - Other Tangible Costs - -
8
9 TOTAL TANGIBLE COSTS 498.310 282.440 (43,3)
10 INTANGIBLE COSTS
11 PREPARATION AND TERMINATION
12 - Survey - -
13 - Location Staking / Positioning - -
14 - Well Site & Access Road Preparation 100.975 100.975 0,0 ►Belum dimasukkan Harus kofirmasi dgn teknik
15 - Service Lines & Communication - 22.369 ►Diperlukan karena tidak ada signal di lokasi.
16 - Water System 979 - (100,0) ► Harus kofirmasi dgn teknik
►Biaya mobilisasi di share ke 23 sumur (US$ 36,956 / sumur) dan moving hanya 7
17 - Rigging Up / Rigging Down 232.478 159.317 (31,5)
hari (lumpsum)
18
19 SUBTOTAL 334.432 282.661
20 DRILLING/WORKOVER OPERATIONS
►Waktu operasi drilling lebih lama 11.54 hari dari rencana dan waktu komplesi
21 - Contract Rig 611.500 838.809 37,2
lebih lama 13 hari dari rencana .
22 - Drilling Rig Crew / Contract Rig Crew - -
►Karena waktu operasi lebih lama dari rencana sehingga material lumpur untuk
23 - Mud, Chemical & Engineering Services 198.643 205.200 3,3
treatment lebih banyak.
24 - Water 7.120 -
25 - Bits Reamers & Core Heads 100.142 80.305 (19,8) ►Tidak menggunakan pahat tricone 8,5", karena hanya digunakan PDC 8.5"
26 - Equipment Rentals 5.721 - ►Menggunakan mud cleaner dari Rig
27 - Directional Drilling and Surveys - -
28 - Diving Services - -
29 - Casing Installation Materials - -
►Dilakukan 3 kali pekerjaan semen karbonat plug untuk combating loss dan
30 - Cement, Cementing and Pumping Fees 70.623 207.078 193,2
excess semen untuk casing 7" sampai 350% (pembesaran lubang)
31
32 SUBTOTAL 993.749 1.331.393 34,0
33 FORMATION EVALUATION
34 - Coring - -
Evaluasi Teknis Closed Out AFE
AFE No : 09-3930
Sumur / Tipe : TT-28
PT PERTAMINA EP
DRILLING DEPARTMENT
Anggaran US $
Line No. Deskripsi Penjelasan Teknis Tindak Lanjut
Disetujui Realisasi Over/Under %
35 - Mud Logging Service 11.915 14.252 19,6 ►Waktu operasi lebih lama dari rencana
36 - Drill Stem Test (DST) - -
37 - Open Hole Electrical Wireline Logging Services 63.285 77.021 21,7 ►Realisasi harga lebih tinggi dari rencana
38 - OTHER
39 SUBTOTAL 75.200 91.273 21,4
40 COMPLETION
41 - Casing, Liner and Tubing Installation - -
42 - Cement, Cementing and Pumping Fees - -
►Menggunakan logging CET karena digunakan semen low density (SG 1.4
15.412 68,9
43 - Cased Hole Electric Logging Services 26.025 litecrete system)
44 - Perforation and Wireline Services 71.690 47.816 (33,3) ►Realisasi harga lebih kecil dari rencana
45 - Stimulation Treatment & Others - - 100,0 ►
46 - Production Test - -
47
48 SUBTOTAL 87.102 73.841 (15,2) ►
49 GENERAL
►
(28,4) Realisasi harga lebih kecil dari rencana
50 - Supervision 6.472 4.637
►Kedalaman TD lebih dalam dari rencana dan nilai ansuransi lebih tinggi dari
739,9
51 - Insurance 3.360 28.220 rencana
52 - Permits and Fees - -
53 - Marine Rental and Charters - -
54 - Helicopter & Aviation Charges - -
►
(100,0)
55 - Land Transportation 1.791 -
56 - Other Transportation - -
57 - Fuel and Lubricants 162.766 131.209 (19,4) ►Realisasi harga lebih kecil dari rencana
58 - Camp Facilities - -
►
125,7 Waktu operasi lebih lama dari rencana
59 - Allocated Overhead : Field Office 3.327 7.510
►
44,8 Waktu operasi lebih lama dari rencana
60 - : Jakarta Office 11.331 16.411
61 - : Overseas Office - -
62 - Technical Services from Abroad - -
63
64 SUB TOTAL 189.047 187.987
TOTAL INTANGIBLE COSTS 1.679.530 1.967.154
WELL DATA
EXECUTIVE SUMMARY
WELL PROFILE
WELL : TT-28
LOCATION : TTM-SA1
DRILLING - 2009
WELL DATA
Doc No. : EP1012/Form/DSpv/01
Form Rev : 02 DRILLING DEPARTMENT
Sumur Eksploitasi TT-28 (TTM-SA1) dibor secara vertikal dengan program hari kerja 30 hari dan actual
hari kerja kerja 41 hari 13 jam (lebih lambat 11 hari 13 jam dari yang direncanakan) di luar waktu Rig
move dan Rig Up, dengan kedalaman akhir 1440 m. Ringkasan operasional pemboran dapat dilihat pada
Well Operation Summary, sedangkan kegiatan operasi pemboran Sumur Ekploitasi TT-28 (TTM-SA1)
dapat diringkas sebagai berikut :
1. Bor Stove pipe dengan TCB 26” spi 28 mku (casing point 20”). Masuk dan semen casing 20” K55 94
ppf BTC R3 spi 28 mku. Install Over flow dan running test semua peralatan rig.
2. Bor Formasi dengan pahat 17-1/2" TCB + BHA dari 28 m sampai sampai 197 m. Cabut rangk pht 17-
1/2" Tricone spi permukaan.Totco survey: 0.5 deg. Msk Csg 13-3/8", K-55,54.5 ppf, BTC R-3 spi 196
m (shoe). Penyemenan Csg 13-3/8". Semen tidak sampai permukaan. Lakukan penyemenan Top
Job.
3. Jajak puncak semen dengan pahat PDC 12 ¼” + BHA Rotary di 181 mku. Lanjut bor vertikal semen
dan formasi spi 200 mku, sirkulasi, lakukan MOT dengan SG eq 1.7, bor formasi spi 1188 mku
(casing point 9.5/8”) dengan inklinasi 1.5 deg. Run logging (Run# 1 : DLL-BHC-MSFL-GR, Run#2 :
LDL-CNL-GR). Masuk pahat PDC 12-1/4" + BHA Trip. Masuk casing 9-5/8” spi shoe di 1186 mku.
Penyemenan casing 9-5/8” satu tahap. Potong kelebihan casing 9.5/8". Gantung BOP group 13.5/8" x
5000 psi. N/U CHS 13-5/8” x 11” x 3000 psi. Pasang dan test BOP Group 13-5/8” x 5000 psi.
4. Masuk rangkaian PDC 8-1/2" + BHA spi jajak puncak semen di 1125 m. Bor semen spi kedalaman
1180 m. Tes tekanan selubung 1000 psi/10 mnt, baik. Lanjut bor semen, shoe, dan formasi spi
kedalaman 1192 m. Sirkulasi kondisikan lumpur Sgin/out = 1.08. MOT SG eq 1.50. Lanjut bor formasi
spi 1268 m, loss total. Combat loss dengan LCM, tidak berhasil. Blind drilling dari 1268 m spi 1309 m.
Combat loss dengan semen karbonate -1, observasi loss stat 0 bpm. Lanjut bor formasi dari 1309 m
spi 1329 m, loss total. Blind drilling dari 1329 m spi 1372 m. Combat loss dengan LCM, tidak berhasil.
Combat loss dengan semen karbonat -2, observasi loss stat 0 bpm. Lanjut bor formasi dari 1372 m
spi 1411 m, loss total. Blind drilling dari 1411 m spi 1430 m. Combat loss dengan LCM, tidak berhasil.
Lanjut blind drilling dari 1430 m spi 1440 m. Combat loss dengan LCM, tidak berhasil. Combat loss
dengan semen karbonat -3, observasi loss stat 0 bpm. Run logging DLL-BHC-MSFL-GR-SP-CALS int
1168-1440 m. Run logging LDL-CNL-GR-CALS int 1168-1440 m.
5. Penyelesaian sumur :
- Run casing 7" K-55 23 ppf BTC R3 dari permukaan spi FS di 1439.0 m, FC di 1414.9 m, dan DSCC di
1131.5 m.
- Penyemenan casing 7” dengan 2 stage, open hole excess 350%. Stage I int (1440-1131) m
menggunakan lead litecrete cement SG 1.40 dan tail litecrete cement SG 1.60. Stage II int (1131-700)
m menggunakan cement slurry Sg 1.65.
C1 - Zone Polish rod (new) : 1 1/2" x 36' c/w stfg box, 1.87 m stick up
1325.0 - 1327.0 m
Note : - 20.000 # Tbg string weight on EPI-35 weight indicator
- 8.500 # Rod string weight on EPI-35 weight indicator
- 3 1/2" Cavins desander sub (type : D 3416)
- Std valve welded to PSN
Top cement @ 1431.25 mKB - 2 7/8" Dump valve (D.V : 2875)
Feb 04, 2010
7", K- 55, 23 ppf, R3, BTC
F Shoe @ 1439.0 mKB
TD = 1440.0 mKB
Supervisor :
SURATNO / H. DJADI UNTUNG
WELL OPERATION SUMMARY
WELL COMPLETION REPORT
WELL : TT-28
LOCATION : TTM-SA1
DRILLING - 2009
WELL OPERATION SUMMARY
Doc No. : EP1012/Form/DSpv/04
DR IL LIN G DEP ARTM E N T
Form Rev : 02
BIT CASING
SIZE CODE QTY *) INTERVAL SIZE FROM TO QTY
TYPE / SERIAL No. Type, ppf, Conn, R2/R3
(inch) IADC (pcs) (m) (inch) (mMD) (mMD) (pcs)
26 TCB VARELL 1 28 20 0 28 K-55, 94.0 ppf, BTC R-3 3
17-1/2 TCB Type 535J, S/N 150142 1 196 13-3/8 0 196 K-55, 54.5 ppf, BTC R-3 17
12-1/4 PDC VMR-173, S/N 4292 1 1186 9-5/8 0 1186 K-55, 36.0 ppf, BTC R-3 102
8-1/2 PDC CHUANKE, S/N 1613737 1 1440 7 0 1439 K-55, 23.0 ppf, BTC R-3 123
(*) Jumlah pahat yang digunakan berturut-turut dengan ukuran jenis yang sama.
MUD PROPERTIES
FROM TO VISC FL Solid Sand Cl- Water
TYPE MUD SG PH REMARK
(mMD) (mMD) (dtk) (cc/30') (%) (%) (ppm) (%)
Gel Water 0 28 1,01 39 0 0 0 0 0 0 0
KCL POLYMER 0 196 1.03-1.06 48-52 6 9 3 0.1 22000 97 0
KCL POLYMER 0 1186 1.03-1.18 40-60 6 9 6 0.2 45000 95 0
KCL POLYMER 0 1188 1.10-1.23 40-60 5 9 6 0.2 45000 96 0
KCL POLYMER 0 1440 1.01-1.08 35-55 - - - - 26000 - 0
LOGGING
NO JENIS LOG SCALE RANGE REMARK
1 DLL-BHC-MSFL-GR 1:200/1:1000 700 - 1188 Logging OH 12-1/4"
2 LDL-CNL-GR 1:200/1:1000 700 - 1188 Logging OH 12-1/4"
3 DLL-BHC-MSFL-GR 1:200/1:1000 1186 - 1440 Logging OH 8-1/2"
4 LDL-CNL-GR 1:200/1:1000 1186 - 1440 Logging OH 8-1/2"
5 CBL-CET-VDL-GR 1:200/1:1000 700 - 1434 Logging Casing 7"
ANALYSIS LOG :
- Bor Stove pipe dengan TCB 26” spi 28 mku (casing point 20”). Masuk dan semen casing 20” K55 94 ppf BTC R3 spi 28 mku. Install
Over flow dan running test semua peralatan rig.
- Bor Formasi dengan pahat 17-1/2" TCB + BHA dari 28 m sampai sampai 197 m. Cabut rangk pht 17-1/2" Tricone spi
permukaan.Totco survey: 0.5 deg. Msk Csg 13-3/8", K-55,54.5 ppf, BTC R-3 spi 196 m (shoe). Penyemenan Csg 13-3/8". Semen
tidak sampai permukaan. Lakukan penyemenan Top Job I dan II.
Jajak puncak semen dengan pahat PDC 12 ¼” + BHA Rotary di 181 mku. Lanjut bor vertikal semen dan formasi spi 200 mku,
sirkulasi, lakukan MOT dengan SG eq 1.7, bor formasi spi 1188 mku (casing point 9.5/8”) dengan inklinasi 1.5 deg. Run logging (Run#
1 : DLL-BHC-MSFL-GR, Run#2 : LDL-CNL-GR). Masuk pahat PDC 12-1/4" + BHA Trip. Masuk casing 9-5/8” spi shoe di 1186 mku.
Penyemenan casing 9-5/8” satu tahap. Potong kelebihan casing 9.5/8". Gantung BOP group 13.5/8" x 5000 psi. N/U CHS 13-5/8” x
11” x 3000 psi. Pasang dan test BOP Group 13-5/8” x 5000 psi.
- Masuk rangkaian PDC 8-1/2" + BHA spi jajak puncak semen di 1125 m. Bor semen spi kedalaman 1180 m. Tes tekanan selubung
1000 psi/10 mnt, baik. Lanjut bor semen, shoe, dan formasi spi kedalaman 1192 m. Sirkulasi kondisikan lumpur Sgin/out = 1.08. MOT
SG eq 1.50. Lanjut bor formasi spi 1268 m, loss total. Combat loss dengan LCM, tidak berhasil. Blind drilling dari 1268 m spi 1309 m.
Combat loss dengan semen karbonate -1, observasi loss stat 0 bpm. Lanjut bor formasi dari 1309 m spi 1329 m, loss total. Blind
drilling dari 1329 m spi 1372 m. Combat loss dengan LCM, tidak berhasil. Combat loss dengan semen karbonat -2, observasi loss stat
0 bpm. Lanjut bor formasi dari 1372 m spi 1411 m, loss total. Blind drilling dari 1411 m spi 1430 m. Combat loss dengan LCM, tidak
berhasil. Lanjut blind drilling dari 1430 m spi 1440 m. Combat loss dengan LCM, tidak berhasil. Combat loss dengan semen karbonat -
3, observasi loss stat 0 bpm. Run logging DLL-BHC-MSFL-GR-SP-CALS int 1168-1440 m. Run logging LDL-CNL-GR-CALS int 1168-
1440 m.
- Penyelesaian sumur :
- Run casing 7" K-55 23 ppf BTC R3 dari permukaan spi FS di 1439.0 m, FC di 1414.9 m, dan DSCC di 1131.5 m.
- Penyemenan casing 7” dengan 2 stage, open hole excess 350%. Stage I int (1440-1131) m menggunakan lead litecrete
cement SG 1.40 dan tail litecrete cement SG 1.60. Stage II int (1131-700) m menggunakan cement slurry Sg 1.65.
- Komplesi pertama dimulai dengan menggunakan Rig Service EPI#35 terhitung mulai tanggal 3 Februari 2010 sampai
tanggal 16 Februari 2010. Dilakukan perforasi selang :
PERF "C1" ZONE INTV : 1325.0 - 1327.0 m, FIRED @ 10:37 HRS
PERF "Cb" ZONE INTV : 1316.0 - 1320.0 m, FIRED @ 11:49 HRS
PERF "Cb" ZONE INTV : 1309.0 - 1314.0 m, FIRED @ 12:58 HRS
PERF "Ca" ZONE INTV : 1284.0 - 1290.0 m, FIRED @ 14:12 HRS
- Lakukan pekerjaan uji produksi dengan swab job. Masuk rangkaian pipa produksi tubing 2-7/8” PSN @ 1328.64 mKB,
TAIL END @ 1348.70 mKB . Sumur diproduksikan dengan menggunakan pump jack.
- Komplesi dilanjutkan dengan menggunakan Rig EPI#35 sejak tanggal 18 Februari 2010 sampai tanggal 21 Februari 2010.
Dilakukan pekerjaan rod job, karena pompa pump off. Masuk rangkaian tubing 2-7/8” sampai kedalaman PSN @ 1273.36
mKB, TAIL END @ 1293.80 mKB. Produksikan sumur dengan menggunakan pump jack
EVALUATION
L ACTUAL PERCENTAGE
WORK PROGRAM AND ESTIMATED ACTUAL EXPENDITURES
I REVISED BUDGET FINAL BUDGET OVER/(UNDER) OVER/(UNDER)
DESCRIPTION BUDGET
N PRIOR YEARS CURRENT YEARS TOTAL BUDGET BUDGET
E 1 2 3 4 5 6 7 8
9 TOTAL TANGIBLE COST 498.310 498.310 282.440 282.440 (215.870) -43%
65 TOTAL INTANGIBLE COST 1.679.530 1.679.530 1.967.154 1.967.154 287.624 17%
66 TOTAL COSTS 2.177.840 2.177.840 2.249.595 2.249.595 71.754 3%
Lokasi TJG-SA1 ditajak sebagai sumur TT-28 pada tanggal 11 Desember 2009 dan drilling days diselesaikan sampai tanggal 21 Januari 2010 (41.54 hari), lebih lama 11.54 hari dari rencana. Hal ini
disebabkan karena terjadi hambatan selama operasi yaitu NPT combating loss = 174,5 jam, NPT perbaikan Rig =90 jam, Reaming=15 jam,NPT top drive =10,5 jam dan NPT cementing=7 jam. Rig
released tanggal 21 Januari 2010 dan dilanjutkan dengan rig Service selama 18 hari untuk komplesi lanjutan. Komplesi diselesaikan tgl dengan tanggal 21 Februari 2010 dengan hasil produksi minyak 59
BOPD.
PUT THE PICTURE PUT THE PICTURE
HERE HERE
5 LOST CIRCULATION 21,23 Combating loss menghabskan waktu sebanyak 174,5 jam
6 WELL CONTROL
Berita Acara COMAN no. EP1012/Form/DSpv/15
7 RIG REPAIR 21 Perbaikan rig menghabiskan waktu total 90 jam. Perbaikan ini adalah perbaikan Mud Pump
tanggal 1 Jan 2010
8 DOWNHOLE EQP FAIL
9 DRILL STRING FAIL
10 CEMENT JOB FAIL 30 Adanya pekerjaan Top Job pada casing 13-3/8"
15 MOVING IN RIGGING UP CEMENTING UNIT 21 Tunggu Cementing Unit PT. Dowell Anadrill
16
17
18
19
20
21
22
1 9 5/8" Casing point 2 Untuk menghindari permasalahan shale saat menghadapi loss circulation zone di trayek 8.5"
BPMIGAS RECOMMENDATION
WELL : TT-28
LOCATION : TTM-SA1
DRILLING - 2009
DRILLING TIME SUMMARY
Doc No. : EP1012/Form/DSpv/05
DRILLING DEPARTMENT
Form Rev : 02
WELL : TT-28
LOCATION : TTM-SA1
IADC Sub
Description Sub Description Code NPT Hours Details
Code code
1 Rig Up and Tear Down a Rig Up 1a 15,00
b Tear Down 1b 11,00
2 Drilling Actual a Drill actual 2a 291,50 Bor formasi, Bor semen, Bor collar
b SPR 2b -
c MOT or LOT 2c 0,50 start from pressure testing line until job done
3 Reaming 3 NPT 15,00 at depth bit start taking weight until actial drilling depth
4 Coring a Persiapan 4a - M/U tools
b Coring Job 4b - RIH coring tools, circulate, Coring Job, POOH, Job completed
5 Circulation a Circulate Hole Clean 5a 14,50 condition mud before cementing, increase SG
b Condition Mud 5b 7,00 circulate before POOH
6 Trips a Drilling BHA 6a 104,00 for RIH and POOH BHA drilling only
b Others BHA 6b - for others BHA example : scrapper, Open end, etc
c Prepare BHA 6c -
d Stand Up or L/D 6d 24,00
7 Lubricate Rig 7 -
8 Repair Rig 8 NPT 90,00 Rig repair (include Pull out BHA to shoe waiting for repair)
9 Cut off Drilling Line 9 -
10 Deviation Survey 10 - RIH totco or GYRO and POOH survey by sand line
11 Wireline Logs a Persiapan 11a 5,50 M/U logging tools, wheels, PCE and pressure test
b Logs 11b 24 50
24,50 RIH logging tools
tools, Log Up and POOH
12 Run Casing a Persiapan 12a 4,00 M/U casing running gears
b Run casing job 12b 27,00 RIH Casing to bottom
13 Cement a Persiapan 13a 13,00 M/U cementing line, R/U cementing head, mixing additives, pressure test
b Cementing jobs 13b 24,00 start pumping spacer until bumping and bleed off.
14 Wait on Cement 14 59,50 No other job done in this phase
15 N/U BOP & N/D BOP a N/U BOP & N/D BOP 15a 20,50
b BOP TEST 15b 3,00
16 N/U Well Head N/U Wellhead 16 22,00 Cut off casing, welding, test etc
17 DRIL STEM TEST a Persiapan 17a - M/U DST tools
b DST Job 17b - RIH DST tools, set packer, DST Job, POOH, Job completed
18 Cement Plug Back 18 - start pumping spacer until before POOH.
19 Squeeze Cement 19 - start pumping spacer until before POOH.
20 Down hole Problem a combating loss 20a NPT 174,50 start pumping LCM pills, wait on reaction, etc. (if Using OE start from POOH bit and RIH OE)
b Gumbo problems 20b NPT - circulate gumbo out
c pipe sticking 20c NPT - start pumping pipe freeing agent, wait on reaction, until pipe free
d Fishing job 20d NPT - start running fishing tools until POOH (not incuded in trips because NPT)
e well control situation 20e NPT - start closing BOP, killing process unttil open BOP
21 Surface Problem a Mud company 21a NPT - wait on material, tools, etc
b Cementing company 21b NPT 7,00
c Logging Company 21c NPT - wait on material, tools, rig up tools too long, pressure test not success
d Directional company 21d NPT - wait on material, tools, rig up tools too long, shallow test not success
e Top Drive 21e NPT 10,50 wait on material, tools, rig up tools too long, running test not success
f Operator Material/tools 21f NPT - wait on Pertamina's material, tools, employee or labour
g weather 21g NPT - wait due to bad weather
h location repair 21h NPT - wait due to bad location
i Government regulation 21i NPT - wait eksplosive (Election day, independence day, idul fitri day)
22 Drills 22 - Fire drill, H2S drill, safety drill, BOP drill
23 Others 23 29,50
24 Production test 24 -
TOTAL RUN HOURS 997,00
NPT starts whenever normal operation cease and there is no drilling progress
REALISASI BIAYA
KEDALAMAN (MKU)
600 60%
700
50%
800
900 40%
Perbaikan Mud Pump #1, #2 dan #3,
1000 NPT Rig 59.5 jam
30%
1100 Perbaikan Top Drive, NPT 4.5 jam
Combat loss total di 1268 m
9-5/8" 9-5/8" 1200 20%
1187 1186 m E F Combat loss total di 1329 m
1300 Cabut PDC 8-1/2" + BHA, tekanan naik Combat loss total di 10%
1411 m
dari 1500 mjd 2500 psi, NPT 18 jam
1400
1500 G H I 0%
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42
7" 1424 m 7" 1439 m
TD 1426 m TD 1440 m
Form Rev : 02
WELL : TT
TT-28
28
LOCATION : TTM-SA1
N/U Wellhead
NPT-Cementing Comp
10,53%
5,26% Drilling Actual
28,57%
BOP TEST
0,75%
WOC
14,29%
, Circ-Hole Clean
2 63%
2,63%
Form Rev : 02
WELL : TT 28
TT-28
LOCATION : TTM-SA1
Wireline Job
1,80%
Others
Wireline-Prep 6,64%
0,56%
MOT/LOT
Circ-Cond Mud
0,11%
1,01%
Repair Rig
20,27% Reaming
0,45%
Trips-Drilling
Trips Drilling BHA
13,29%
Circ-Hole Clean
Stand Up or L/D
1,80%
1,13%
WELL : TT-28
TT 28
LOCATION : TTM-SA1
NPT-Top Drive
1,88%
Drilling Actual
Combat loss
18,01%
65,48%
Reaming
4,88%
Circ-Hole Clean
0,56%
Trips-Drilling BHA
4,13%
Wireline Job
Wireline-Prep
4,32%
0,75%
WELL : TT-28
TT 28
LOCATION : TTM-SA1
COMPLETION ACTIVITY
SECTION
Circ-Cond Mud
Run Csg job
1,88%
8,27%
Wireline-Prep
0,75% Stand Up or L/D Trips-Drilling BHA
Run Csg-Prep Wireline Job 9,02% 15,41%
0,75% 3,76%
WELL : TT-28
LOCATION : TTM
TTM-SA1
SA1
Form Rev : 02
WELL : TT-28
LOCATION : TTM-SA1
NPT-Top Drive
NPT-Cementing Comp 3,5%
2,4% Reaming
5,1%
Repair Rig
30,3%
Combat loss
58,8%
Well : TT-28
Location : TTM-SA1
Preparation 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
Bor lubang 26" Bor Stove Pipe pilot hole dgn pht 12-1/4" spi 28 m, L/D pht 12-1/4" 0,0 0,00 0,00 0,00 28,00 0 11/12/2009 12:00 : Jumat 48,0 02:00:00
A 48,00 48,00 2,00 2,00 30,00
48,00 0,00 2,00 30,00 Perbesar lubang dgn pht 26" spi 28 m 2a 0,0 0,00 0,00 0,00 28,00 0 11/12/2009 12:00 : Jumat 48,0
Masuk & semen Stove Pipe, psg Diverter, Bell Nipple, Over Masuk & semen Stove Pipe 20" @ 28 m, psg Diverter, Bell Nipple, 0,0 0,00 0,00 0,00 28,00 0 11/12/2009 12:00 : Jumat 96,0 04:00:00
B Flow. M/U BHA Bit 17 1/2", Persp bor dgn Pht 17 1/2" 48,00 96,00 2,00 4,00 30,00 Over Flow. M/U BHA Bit 17 1/2", Running Test all equiptment, baik.
Persiapan Tajak Lokasi TTM-SA1
Trayek Stove Pipe 20" @ 30 meter 96,00 96,00 4,00 4,00 30,00 0,00 0,00 0,00 0,00 0,00 0
Bor dengan pahat 17-1/2" spi Csg Point Depth @ 200 m. Rig Up 100%. Tajak lokasi TTM-SA1 sebagai Sumur TT-28 jam 00.00 0 12/12/2009 04:00 : Sabtu 128,0 05:08:00
WITA, 11 Desember 2009. Bor Formasi dengan pahat 17-1/2" TCB
C 2a 48,00 144,00 2,00 6,00 200,00 2a 16,0 16,00 0,67 0,67 100,00
(RR type 535J, S/N 150142, Nozzle 3x20) + BHA dari 28 m sampai
100 m
144,00 0,00 6,00 200,00 Ljt Bor formasi dari 100 m spi 146 m 2a 8,0 24,00 0,33 1,00 146,00 0 12/12/2009 12:00 : Sabtu 120,0 05:00:00
144,00 0,00 6,00 200,00 Ljt Bor formasi dari 146 m spi 197 m (Csg point 13-/8") 2a 12,5 36,50 0,52 1,52 197,00 0 13/12/2009 00:30 : Minggu 107,5 04:11:30
Trip, masuk & semen Csg 13 3/8". Psg BF 13 3/8 - 3000, Sirk bersih, swept-out Hi-vis 30 bbls. 0 13/12/2009 01:00 : Minggu 179,0 07:11:00
DSAF, 13 3/8 x 3000 - 5000 PSI, BOP 13 3/8 - 5000 Psi, bell
D nipple, over flow dan surface line. Test BOP, M/U 12 1/4" Bit + 6a 72,00 216,00 3,00 9,00 200,00 5a 0,5 37,00 0,02 1,54 197,00
BHA, bor plug, semen dan formasi spi 153 m, Formation
Integrity Test.
Cabut rangk TCB 17-1/2" spi permukaan,Ada OP 10 klbs @ 81 m. L/D 0 13/12/2009 03:30 : Minggu 176,5 07:08:30
216,00 0,00 9,00 200,00 6a 2,5 39,50 0,10 1,65 197,00
Stab 12-1/4".
216,00 0,00 9,00 200,00 Msk kembali rangk pht 17-1/2" Tricone spi 36 m 6a 0,5 40,00 0,02 1,67 197,00 0 13/12/2009 04:00 : Minggu 176,0 07:08:00
216,00 0,00 9,00 200,00 Ljt msk dr 36 m spi dasar 197 m 6a 2,0 42,00 0,08 1,75 197,00 0 13/12/2009 06:00 : Minggu 174,0 07:06:00
Sirk bersih sbl naikkan SG ke ECD 1.06 SG, swept hi-vis 30 bbls, spot 0 13/12/2009 08:00 : Minggu 172,0 07:04:00
216,00 0,00 9,00 200,00 5a 2,0 44,00 0,08 1,83 197,00
hi-vis 30 bbls. Drop totco
Cabut rangk pht 17-1/2" Tricone spi permukaan.Totco survey: 0.5 deg. 0 13/12/2009 11:00 : Minggu 169,0 07:01:00
216,00 0,00 9,00 200,00 6a 3,0 47,00 0,13 1,96 197,00
Per. msk Csg 13-3/8" ( K-55, 54,5 ppf, BTC R-3)-Check FS & FC 0 13/12/2009 12:00 : Minggu 168,0 07:00:00
,
216,00 0,00
, 9,00
, 200,00
, 12a 1,0
, 48,00
, 0,04
, 2,00
, 197,00
,
dipermukaan baik
Msk Csg 13-3/8", K-55,54.5 ppf, BTC R-3 spi162 m 0 13/12/2009 16:00 : Minggu 164,0 06:20:00
216,00 0,00 9,00 200,00 12b 4,0 52,00 0,17 2,17 197,00
Ljt msk Csg 13-3/8" dr 162 m spi 196 m (shoe) 0 13/12/2009 17:00 : Minggu 163,0 06:19:00
216,00 0,00 9,00 200,00 12b 1,0 53,00 0,04 2,21 197,00
Sirk sbl tunggu Dowell Cementing Set up unit (7 jam NPT Dowell) NPT 14/12/2009 00:00 : Senin 156,0 06:12:00
216,00 0,00 9,00 200,00 21b 7,0 60,00 0,29 2,50 197,00
Mixing fluid & Spacer 0 14/12/2009 02:00 : Senin 154,0 06:10:00
216,00 0,00 9,00 200,00 13a 2,0 62,00 0,08 2,58 197,00
216,00 0,00 9,00 200,00 Pers Penyemenan Csg 13-3/8" 13a 0,5 62,50 0,02 2,60 197,00 0 14/12/2009 02:30 : Senin 153,5 06:09:30
Penyemenan Csg 13-3/8" dgn excess 100%: 0 14/12/2009 04:30 : Senin 151,5 06:07:30
- PJSM.
- Flush cmt line dgn 2 bbl air. Press. test cmt line 2000 psi/10 min,
baik. Pompakan 30 bbl Mud Push (Spacer). Jatuhkan bottom plug.
- Aduk dan pompakan 168 bbl tail slurry 1.90 SG (819 sxs semen
216,00 0,00 9,00 200,00 13b 2,0 64,50 0,08 2,69 197,00
kelas G + 8 gal D047 + 115 lbs D153 + 409 gal D193 + 123 D145A +
77 bbls S001), Jatuhkan top plug. Dorong cmt slurry dgn 93 bbl
lumpur SG 1.06 spi tekanan bentur 700 psi/5 min. Semen tdk spi
permukaan, saat dorong dr 20-70 bbl tdk ada aliran balik. Ablas
tekanan, aliran balik 1 bbl, float baik.
216,00 0,00 9,00 200,00 TSK 14 6,0 70,50 0,25 2,94 197,00 0 14/12/2009 10:30 : Senin 145,5 06:01:30
216,00 0,00 9,00 200,00 Msk Macaroni 1" u/ jajak semen, puncak semen di 22 m. 13a 1,5 72,00 0,06 3,00 197,00 0 14/12/2009 12:00 : Senin 144,0 06:00:00
Pers& Penyemenan Top Job 13-3/8". 0 14/12/2009 16:00 : Senin 140,0 05:20:00
-Potong semen klas "G" 60 sak. PJSM.Flush cmt line dgn 2 bbl air.-
Press. test cmt line 2000 psi/10 min, baik.- Aduk dan pompakan 12
bbl cement slurry SG:1.9 (60 sxs semen klas "G"+ 0.6 gal D047),
216,00 0,00 9,00 200,00 13b 4,0 76,00 0,17 3,17 197,00
dgn rate 1 bpm/100 psi,pompa 1-2 bbls pertama ada aliran balik &
kontaminasi semen, dr pemompaan 3-12 bbls tdk ada aliran
balik,teruskan pompa semen spi 25 bbls, tdk ada aliran balik.Stop
pemompaan, cabut macaroni.
216,00 0,00 9,00 200,00 TSK sbl potong kelebihan csg 20" 14 4,0 80,00 0,17 3,33 197,00 0 14/12/2009 20:00 : Senin 136,0 05:16:00
216,00 0,00 9,00 200,00 Msk macaroni 1" jajak puncak semen di 20 m 13a 1,0 81,00 0,04 3,38 197,00 0 14/12/2009 21:00 : Senin 135,0 05:15:00
216,00 0,00 9,00 200,00 Pers utk Top Job II 13-3/8". Potong semen 160 sak 13a 3,0 84,00 0,13 3,50 197,00 0 15/12/2009 00:00 : Selasa 132,0 05:12:00
Penyemenan Top Job II Csg 13-3/8" 13b 3,0 0 15/12/2009 03:00 : Selasa 129,0 05:09:00
- PJSM. Flush cmt line dgn 2 bbl air. Press. test cmt line 2000 psi/10
min, baik. Aduk dan pompakan 30 bbl cement slurry SG:1.9 (160 sxs
216,00 0,00 9,00 200,00 87,00 0,13 3,63 197,00
semen klas "G"+ 1 gal D047), dgn rate 1 bpm/100 psi, Semen
keluar sampai permukaan SG:1.85.
216,00 0,00 9,00 200,00 TSK 14 4,0 91,00 0,17 3,79 197,00 0 15/12/2009 07:00 : Selasa 125,0 05:05:00
216,00 0,00 9,00 200,00 Bersihkan semen dalam cellar (semen keras) 14 5,0 96,00 0,21 4,00 197,00 0 15/12/2009 12:00 : Selasa 120,0 05:00:00
Potong csg 20" (20 cm lebih rendah) dan bersihkan semen utk 16 1,5 0 15/12/2009 13:30 : Selasa 118,5 04:22:30
216,00 0,00 9,00 200,00 97,50 0,06 4,06 197,00
memudahkan pengelasan BF 13-3/8" x 3000 psi
216,00 0,00 9,00 200,00 Potong & ratakan permukaan csg 13-3/8". Install Ring plate 16 1,5 99,00 0,06 4,13 197,00 0 15/12/2009 15:00 : Selasa 117,0 04:21:00
216,00 0,00 9,00 200,00 N/U BF 13-5/8" x 3k psi. 16 0,5 99,50 0,02 4,15 197,00 0 15/12/2009 15:30 : Selasa 116,5 04:20:30
216,00 0,00 9,00 200,00 Las bagian luar & dalam BF 13-5/8" x 3000 psi 16 3,0 102,50 0,13 4,27 197,00 0 15/12/2009 18:30 : Selasa 113,5 04:17:30
Cooling (pendingininan), test hasil pengelesan, bocor bagian dalam. 16 2,0 0 15/12/2009 20:30 : Selasa 111,5 04:15:30
216,00 0,00 9,00 200,00 104,50 0,08 4,35 197,00
216,00 0,00 9,00 200,00 Las kembali bag dalam BF 13-5/8" 3000 psi 16 2,5 107,00 0,10 4,46 197,00 0 15/12/2009 23:00 : Selasa 109,0 04:13:00
Cooling (pendingininan),test hasil pengelasan dgn 1500 psi (hand 16 3,0 0 16/12/2009 02:00 : Rabu 106,0 04:10:00
216,00 0,00 9,00 200,00 110,00 0,13 4,58 197,00
pump by welder), baik
N/U BOP 13-5/8" x 5000 psi + DSAF 13-5/8" 3000 x 5000 psi.Pasang 15a 7,0 0 16/12/2009 09:00 : Rabu 99,0 04:03:00
216,00 0,00 9,00 200,00 117,00 0,29 4,88 197,00
saluran permukaan.
PLAN ACTUAL GAIN / LOSS
TIME REALIZATION &
NO OPERATION IADC CUMM. IADC
HOURS DAYS CUMM. DEPTH JOB DESCRIPTION HOURS CUMM. DAYS CUMM. DEPTH NPT PREDICTION HOUR DD:HH:MM
CODE HOURS CODE
Function test Annular,Pipe ram, HCR OK. Press Test dgn tester cup 15b 1,0 0 16/12/2009 10:00 : Rabu 98,0 04:02:00
Annular low/high 500/1500 psi 10 mnt,baik. Pipe ram 500/1500 psi 10
216,00 0,00 9,00 200,00 118,00 0,04 4,92 197,00
mnt,baik, Press test blind ram 500/1500 10 mnt, baik. Test aliran ke
flare,baik,install flow line
216,00 0,00 9,00 200,00 N/D Kelly & Swivel 1a 2,0 120,00 0,08 5,00 197,00 0 16/12/2009 12:00 : Rabu 96,0 04:00:00
Ljt R/u Top drive (100%), function test ( 1a 13,0 17/12/2009 01:00 : Kamis 83,0 03:11:00
216,00 0,00 9,00 200,00 133,00 0,54 5,54 197,00
robotic,Low/Hig RPM, Test dgn 2000 psi), OK
216,00 0,00 9,00 200,00 Stand up DP 5" 34 stands. 6d 3,0 136,00 0,13 5,67 197,00 17/12/2009 04:00 : Kamis 80,0 03:08:00
216,00 0,00 9,00 200,00 Ljt stand up DP 5" 16 stands (kum 50 stds). 6d 4,0 140,00 0,17 5,83 197,00 17/12/2009 08:00 : Kamis 76,0 03:04:00
216,00 0,00 9,00 200,00 M/U & RIH 12-1/4" PDC, Tag TOC @ 181 m. 6a 4,0 144,00 0,17 6,00 197,00 17/12/2009 12:00 : Kamis 72,0 03:00:00
216,00 0,00 9,00 200,00 Ljt bor plug, semen spi kedalaman 192 m. 6a 1,5 145,50 0,06 6,06 197,00 17/12/2009 13:30 : Kamis 70,5 02:22:30
216,00 0,00 9,00 200,00 Sirkulasi bersih & Uji tekanselubung 1000 psi / 5 mnt, baik. 5a 0,5 146,00 0,02 6,08 197,00 17/12/2009 14:00 : Kamis 70,0 02:22:00
216,00 0,00 9,00 200,00 Ljt bor semen & formasi spi kedalaman 200 m. 2a 1,5 147,50 0,06 6,15 200,00 17/12/2009 15:30 : Kamis 68,5 02:20:30
Sirkulasi bersih & kondisikan lumpur Sgin/out = 1.06, MOT SG eq = 5a 0,5 17/12/2009 16:00 : Kamis 68,0 02:20:00
216,00 0,00 9,00 200,00 148,00 0,02 6,17 200,00
1.70, baik.
Trayek Casing 13-3/8" @ 200 meter 120,00 216,00 5,00 9,00 200,00 148,00 148,00 6,17 6,17 200,00
E Bor formasi dengan Pht 12 -1/4" spi TD @ 1189 mKB. 2a 240,00 456,00 10,00 19,00 1189,00 Ljt bor formasi spi kedalaman 259 m 2a 12,0 160,00 0,50 6,67 259,00 18/12/2009 04:00 : Jumat 296,0 12:08:00
456,00 0,00 19,00 1189,00 Ljt bor formasi spi kedalaman 290 m 2a 8,0 168,00 0,33 7,00 290,00 18/12/2009 12:00 : Jumat 288,0 12:00:00
456,00 0,00 19,00 1189,00 Ljt bor formasi spi kedalaman 313 m 2a 4,0 172,00 0,17 7,17 313,00 18/12/2009 16:00 : Jumat 284,0 11:20:00
456,00 0,00 19,00 1189,00 Ljt bor formasi spi kedalaman 353 m. 2a 6,0 178,00 0,25 7,42 353,00 18/12/2009 22:00 : Jumat 278,0 11:14:00
456,00 0,00 19,00 Perbaikan pompa : ganti seating valve MP#2 (NPT Rig = 0.5 jam) 8 0,5 178,50 0,02 7,44 353,00 NPT 18/12/2009 22:30 : Jumat 277,5 11:13:30
1189,00
456,00 0,00 19,00 1189,00 Ljt bor formasi spi kedalaman 380 m. 2a 5,5 184,00 0,23 7,67 380,00 19/12/2009 04:00 : Sabtu 272,0 11:08:00
456,00 0,00 19,00 Lakukan drill off test dgn perubahan WOB dan RPM, kemajuan hanya 2a 1,0 185,00 0,04 7,71 380,50 19/12/2009 05:00 : Sabtu 271,0 11:07:00
1189,00 380.5 m (last lith @380m : 10%SST, 10% Shale, 80% CLST).
456,00 0,00 19,00 1189,00 Sirkulasi Bersih & Swept out hi vis 30 bbls. 5a 1,0 186,00 0,04 7,75 380,50 19/12/2009 06:00 : Sabtu 270,0 11:06:00
456,00 0,00 19,00 POOH 12-1/4" PDC + BHA Rotary to surface, L/D Stabilizer 2 unit, 2 6a 5,0 191,00 0,21 7,96 380,50 19/12/2009 11:00 : Sabtu 265,0 11:01:00
1189,00
jts DC 8".
456,00 0,00 19,00 1189,00 M/U & RIH 12-1/4" PDC + BHA Rotary spi kedalaman 96 m. 6a 1,0 192,00 0,04 8,00 380,50 19/12/2009 12:00 : Sabtu 264,0 11:00:00
456,00 0,00 19,00 1189,00 Ljt RIH 12-1/4" PDC + BHA Rotary spi kedalaman 180 m. 6a 0,5 192,50 0,02 8,02 380,50 19/12/2009 12:30 : Sabtu 263,5 10:23:30
456,00 0,00 19,00 Perbaikan Pompa : 3 pcs dies plug PTO patah MP#1, ganti 8 3,5 196,00 0,15 8,17 380,50 NPT 19/12/2009 16:00 : Sabtu 260,0 10:20:00
1189,00
seating valve MP#2 & MP#3. (NPT Rig = 3.5 jam, kum 4.0 jam).
456,00 0,00 19,00 Ljt perbaikan pompa : Ganti 3 pcs dies plug PTO MP#1 (NPT Rig 8 11,0 207,00 0,46 8,63 380,50 NPT 20/12/2009 03:00 : Minggu 249,0 10:09:00
1189,00
= 11 jam, kum 15 jam).
456,00 0,00 19,00 Running Test MP#1, MP#2, MP#3 : SPM#1 90, SPM#2 90, SPM#3 8 0,5 207,50 0,02 8,65 380,50 NPT 20/12/2009 03:30 : Minggu 248,5 10:08:30
1189,00 100, GPM 700, Tekanan 900 psi (NPT Rig = 0.5 jam, kum 15.5
jam).
456,00 0,00 19,00 1189,00 Ljt RIH 12-1/4" PDC + BHA Rotary spi kedalaman 293 m. 6a 0,5 208,00 0,02 8,67 380,50 20/12/2009 04:00 : Minggu 248,0 10:08:00
456,00 0,00 19,00 1189,00 Ljt RIH 12-1/4" PDC + BHA Rotary spi kedalaman 380 m. 6a 0,5 208,50 0,02 8,69 380,50 20/12/2009 04:30 : Minggu 247,5 10:07:30
456,00 0,00 19,00 1189,00 Sirkulasi bersih di dasar. 6a 0,5 209,00 0,02 8,71 380,50 20/12/2009 05:00 : Minggu 247,0 10:07:00
456,00 0,00 19,00 Ljt bor formasi 380.5 - 423 m (ROP 5 mnt/m, lith 80% coal, 10% 2a 7,0 216,00 0,29 9,00 423,00 20/12/2009 12:00 : Minggu 240,0 10:00:00
1189,00
CLST, 10%SST).
456,00 0,00 19,00 Ljt bor formasi spi kedalaman 447 m (ROP 4 mnt/m, Lith 40% SST, 2a 4,0 220,00 0,17 9,17 447,00 20/12/2009 16:00 : Minggu 236,0 09:20:00
1189,00
40% CLST, 20% Coal).
456,00 0,00 19,00 Ljt bor formasi spi kedalaman 525 m (ROP 9 mnt/m, lith: 20% SST, 2a 12,0 232,00 0,50 9,67 525,00 21/12/2009 04:00 : Senin 224,0 09:08:00
1189,00
20% CLST, 60% Coal).
456,00 0,00 19,00 Ljt bor formasi spi kedalaman 545 m (ROP 10 mnt/m, lith: 20% SST, 2a 3,5 235,50 0,15 9,81 545,00 21/12/2009 07:30 : Senin 220,5 09:04:30
1189,00
50% CLST, 30% Coal).
456,00 0,00 19,00 Perbaikan Pompa : SPM#1 & SPM#2 turun, set ulang disk clutch 8 0,5 236,00 0,02 9,83 545,00 NPT 21/12/2009 08:00 : Senin 220,0 09:04:00
1189,00
MP#1 & MP#2, (NPT Rig = 0.5 jam, kum 16 jam).
456,00 0,00 19,00 Sirkulasi kondisikan lumpur, naikan viscositas (SPM#1 90; 8 0,5 236,50 0,02 9,85 545,00 NPT 21/12/2009 08:30 : Senin 219,5 09:03:30
1189,00 SPM#3 90; GPM 450), sambil ljt perbaikan MP#2, set disk clutch
(NPT Rig = 0.5 jam, kum 16.5 jam).
456,00 0,00 19,00 POOH 12-1/4" PDC + BHA Rotary spi shoe @ 197 m, sambil ljt 8 2,5 239,00 0,10 9,96 545,00 NPT 21/12/2009 11:00 : Senin 217,0 09:01:00
perbaikan MP#2 (disk clutch) & reposisi engine MP#3
1189,00
dikarenakan stock 2 pcs V-belt berukuran pendek (NPT Rig = 2.5
jam, kum 19.5 jam)
456,00 0,00 19,00 Ljt perbaikan MP#2 & MP#3, sambil running test MP#1, 110 SPM, 8 1,0 240,00 0,04 10,00 545,00 NPT 21/12/2009 12:00 : Senin 216,0 09:00:00
1189,00 275 GPM (NPT Rig = 1 jam, kum 20 jam).
456,00 0,00 19,00 Ljt perbaikan MP#2 & MP#3, (NPT Rig = 4 jam, kum 24 jam). 8 4,0 244,00 0,17 10,17 545,00 NPT 21/12/2009 16:00 : Senin 212,0 08:20:00
1189,00
456,00 0,00 19,00 1189,00 Ljt perbaikan MP#2 & MP#3, (NPT Rig = 1.5 jam, kum 25.5 jam). 8 1,5 245,50 0,06 10,23 545,00 NPT 21/12/2009 17:30 : Senin 210,5 08:18:30
456,00 0,00 19,00 Ljt perbaikan MP#2 (disk clutch), sambil running test MP#1 & 8 2,0 247,50 0,08 10,31 545,00 NPT 21/12/2009 19:30 : Senin 208,5 08:16:30
1189,00 MP#3, Debit Max 600 gal/mnt, dgn kombinasi SPM#1 130 &
SPM#3 110. (NPT Rig = 2 jam, kum 27.5 jam).
456,00 0,00 19,00 RIH 12-1/4" PDC + BHA Rotary, rangkaian duduk 10 klbs @ 405 8 0,5 248,00 0,02 10,33 545,00 NPT 21/12/2009 20:00 : Senin 208,0 08:16:00
1189,00
m, 412 m (NPT Rig = 0.5 jam, kum 28 jam).
456,00 0,00 19,00 Reaming down & Sirkulasi sambil WOP spi kedalaman 545 m, 23 5,5 253,50 0,23 10,56 545,00 0 22/12/2009 01:30 : Selasa 202,5 08:10:30
1189,00
terdapat rontokan (caving) batubara.
456,00 0,00 19,00 Ljt bor formasi kedalaman 545 - 554 m (ROP 10 mnt/m, lith @ 551m; 2a 2,5 256,00 0,10 10,67 554,00 22/12/2009 04:00 : Selasa 200,0 08:08:00
1189,00
20% STT, 80% CLST).
456,00 0,00 19,00 Ljt bor formasi spi kedalaman 602 m (ROP 4 mnt/m, lith 80% Coal, 2a 8,0 264,00 0,33 11,00 602,00 22/12/2009 12:00 : Selasa 192,0 08:00:00
1189,00
10%CLST, 10% SST).
456,00 0,00 19,00 Ljt bor formasi spi kedalaman 622 m (ROP 8 mnt/m, lith 70% CLST, 2a 4,0 268,00 0,17 11,17 622,00 22/12/2009 16:00 : Selasa 188,0 07:20:00
1189,00
30% Coal).
456,00 0,00 19,00 Ljt bor formasi spi kedalaman 679 m (ROP 10 mnt/m, Lith 60% SST, 2a 10,5 278,50 0,44 11,60 679,00 23/12/2009 02:30 : Rabu 177,5 07:09:30
1189,00
40% CLST)
456,00 0,00 19,00 Perbaikan Pompa : Flexible Joint 4" Suction line Charging 8 1,5 280,00 0,06 11,67 679,00 NPT 23/12/2009 04:00 : Rabu 176,0 07:08:00
Pump#1 bocor, ganti bongkar pasang dari Charging Pump#2,
1189,00
sambil sirkulasi dgn MP#3 300 GPM (NPT Rig = 1.5 jam, kum 29.5
jam).
456,00 0,00 19,00 Ljt bor formasi spi kedalaman 719 m (ROP 7 mnt/m, lith: 50% Coal, 2a 8,0 288,00 0,33 12,00 719,00 23/12/2009 12:00 : Rabu 168,0 07:00:00
1189,00
30% CLST, 20% SST).
456,00 0,00 19,00 Ljt bor formasi spi kedalaman 738 m (ROP 11 mnt/m, lith: 70% CLST, 2a 4,0 292,00 0,17 12,17 738,00 23/12/2009 16:00 : Rabu 164,0 06:20:00
1189,00
30% Coal).
456,00 0,00 19,00 Ljt bor formasi spi kedalaman 779 m (ROP 16 mnt/m, lith: 50% CLST, 2a 12,0 304,00 0,50 12,67 779,00 24/12/2009 04:00 : Kamis 152,0 06:08:00
1189,00
40% SST, 10% Coal).
456,00 0,00 19,00 Ljt bor formasi spi kedalaman 796 m (ROP 11 mnt/m, lith: 20% SST, 2a 2,5 306,50 0,10 12,77 796,00 24/12/2009 06:30 : Kamis 149,5 06:05:30
1189,00
30% CLST, 50% Coal).
456,00 0,00 19,00 Sirkulasi sambil ganti rubber piston & seating valve MP#3. 8 2,0 308,50 0,08 12,85 796,00 NPT 24/12/2009 08:30 : Kamis 147,5 06:03:30
Running pompa msh belum normal, diputuskan utk POOH 12-
1/4" PDC + BHA Rotary spi shoe dan lakukan perbaikan pompa :
1189,00 MP#2 (dies plug PTO & bearing) dan ganti ukuran liner 6" MP#1,
2, 3 (NPT Rig =2 jam, kum 31.5 jam).
PLAN ACTUAL GAIN / LOSS
TIME REALIZATION &
NO OPERATION IADC CUMM. IADC
HOURS DAYS CUMM. DEPTH JOB DESCRIPTION HOURS CUMM. DAYS CUMM. DEPTH NPT PREDICTION HOUR DD:HH:MM
CODE HOURS CODE
456,00 0,00 19,00 POOH 12-1/4" PDC + BHA Rotary spi kedalaman 467 m (NPT Rig = 8 3,5 312,00 0,15 13,00 796,00 NPT 24/12/2009 12:00 : Kamis 144,0 06:00:00
1189,00
3.5 jam, kum 35 jam).
456,00 0,00 19,00 Ljt POOH 12-1/4" PDC + BHA Rotary spi shoe @ 197m (NPT Rig = 8 3,0 315,00 0,13 13,13 796,00 NPT 24/12/2009 15:00 : Kamis 141,0 05:21:00
1189,00
3 jam, kum 38 jam).
456,00 0,00 19,00 Ljt perbaikan pompa : ganti ukuran liner 6" MP#1, 2, 3 & dies 8 1,0 316,00 0,04 13,17 796,00 NPT 24/12/2009 16:00 : Kamis 140,0 05:20:00
1189,00 plug PTO MP#2 patah (NPT Rig = 1 jam, kum 39 jam).
456,00 0,00 19,00 Ljt perbaikan pompa : (1) Ganti ukuran liner 6" MP#1, 2, 3, OK. (2) 8 11,5 327,50 0,48 13,65 796,00 NPT 25/12/2009 03:30 : Jumat 128,5 05:08:30
Setting ulang disk clutch PTO MP#1, OK. (3) Ganti dies plug PTO
1189,00
MP#2, disk plate patah, sdg dibubut (NPT Rig = 11.5 jam, kum
50.5 jam).
456,00 0,00 19,00 Running test MP#1 & 3, SPM#1 120, SPM#3 120, P 1100 psi, GPM 8 1,0 328,50 0,04 13,69 796,00 NPT 25/12/2009 04:30 : Jumat 127,5 05:07:30
1189,00 700, selama 1 jam. Sambil tunggu bearing pillow & disk plate
bubutan (NPT Rig = 1 jam, kum 51.5 jam).
456,00 0,00 19,00 Ljt perbaikan pompa: disk clutch & disk plate MP#2, sambil 8 7,5 336,00 0,31 14,00 796,00 NPT 25/12/2009 12:00 : Jumat 120,0 05:00:00
1189,00 tunggu pillow bearing MP#2 (NPT Rig = 7.5 jam, kum 59 jam).
456,00 0,00 19,00 Ljt perbaikan pompa; disk clutch & disk plate MP#2, sambil 8 4,0 340,00 0,17 14,17 796,00 NPT 25/12/2009 16:00 : Jumat 116,0 04:20:00
1189,00 tunggu pillow bearing MP#2 (NPT Rig = 4 jam, kum 63 jam).
456,00 0,00 19,00 RIH 12-1/4" PDC + BHA Rotary, rangkaian duduk 10 klbs @ 313 m 8 12,0 352,00 0,50 14,67 796,00 NPT 26/12/2009 04:00 : Sabtu 104,0 04:08:00
dan setiap kemajuan 1 jt. Reaming down spi kedalaman 600 m,
1189,00 cutting yg keluar berupa rontokan coal. Sambil ljt perbaikan
MP#2 (pillow bearing) & MP#3 (V-belt kendur & hose airflex
bocor). (NPT Rig = 12 jam, kum 75 jam).
456,00 0,00 19,00 Ljt reaming down spi kedalaman 630 m, sambil running test 8 1,0 353,00 0,04 14,71 796,00 NPT 26/12/2009 05:00 : Sabtu 103,0 04:07:00
1189,00
MP#2, OK. (NPT Rig = 1 jam, kum 76 jam).
456,00 0,00 19,00 Ljt reaming down spi kedalaman 726 m (NPT Rig = 7 jam, kum 83 8 7,0 360,00 0,29 15,00 796,00 NPT 26/12/2009 12:00 : Sabtu 96,0 04:00:00
1189,00
jam).
456,00 0,00 19,00 Ljt reaming down spi kedalaman 776 m (NPT Rig = 4 jam, kum 87 8 4,0 364,00 0,17 15,17 796,00 NPT 26/12/2009 16:00 : Sabtu 92,0 03:20:00
1189,00
jam).
456,00 0,00 19,00 Ljt reaming down spi kedalaman 796 m (NPT Rig = 1 jam, kum 88 8 1,0 365,00 0,04 15,21 796,00 NPT 26/12/2009 17:00 : Sabtu 91,0 03:19:00
1189,00
jam).
456,00 0,00 19,00 Sirkulasi Bersih & Swept out hi vis 30 bbls (NPT Rig = 1 jam, kum 8 1,0 366,00 0,04 15,25 796,00 NPT 26/12/2009 18:00 : Sabtu 90,0 03:18:00
1189,00
89 jam).
456,00 0,00 19,00 Ljt bor formasi spi kedalaman 834 m (ROP 13 mnt/m, Lith 80% SST, 2a 10,0 376,00 0,42 15,67 834,00 27/12/2009 04:00 : Minggu 80,0 03:08:00
1189,00
20% CLST).
456,00 0,00 19,00 Ljt bor formasi spi kedalaman 856 m (ROP 28 mnt/m, lith 20% Shale, 2a 8,0 384,00 0,33 16,00 856,00 27/12/2009 12:00 : Minggu 72,0 03:00:00
1189,00
20% Coal, 60% SST).
456,00 0,00 19,00 Ljt bor formasi spi kedalaman 864 m (ROP 18 mnt/m, lith 70% SST, 2a 4,0 388,00 0,17 16,17 864,00 27/12/2009 16:00 : Minggu 68,0 02:20:00
1189,00
30% Shale).
456,00 0,00 19,00 1189,00 Ljt bor formasi spi kedalaman 902 m. 2a 5,5 393,50 0,23 16,40 902,00 27/12/2009 21:30 : Minggu 62,5 02:14:30
456,00 0,00 19,00 Sirkulasi sambil perbaikan Pompa : MP#2 (SPM naik turun, ganti 8 1,0 394,50 0,04 16,44 902,00 NPT 27/12/2009 22:30 : Minggu 61,5 02:13:30
fuel pump), MP#3 (SPM turun). Running SPM#1 110 & SPM#3
1189,00 110, max debit 650 GPM. (NPT Rig = 1 jam, kum 90 jam).
456 00
456,00 0 00
0,00 19 00
19,00 Ljt bor formasi spi kedalaman 911 m, m (DP screen putus & est 2a 15
1,5 396 00
396,00 0 06
0,06 16 50
16,50 911 00
911,00 28/12/2009 00:00 : Senin 60 0
60,0 02:12:00
1189,00
tertinggal di HWDP).
456,00 0,00 19,00 1189,00 Sirkulasi, tekanan 1500 psi / 700 GPM, normal. 5a 0,5 396,50 0,02 16,52 911,00 28/12/2009 00:30 : Senin 59,5 02:11:30
456,00 0,00 19,00 Ljt bor formasi spi kedalaman 930 m (ROP 11 mnt/m, lith @ 921m: 2a 3,5 400,00 0,15 16,67 930,00 28/12/2009 04:00 : Senin 56,0 02:08:00
1189,00
70% SST, 30% Shale).
456,00 0,00 19,00 Ljt bor formasi spi kedalaman 983 m (ROP 11 mnt/m, Lith 60% Shale, 2a 8,0 408,00 0,33 17,00 983,00 28/12/2009 12:00 : Senin 48,0 02:00:00
1189,00
40% SST).
456,00 0,00 19,00 Ljt bor formasi spi kedalaman 1008 m (ROP 9 mnt/m, lith 50% SST, 2a 4,0 412,00 0,17 17,17 1008,00 28/12/2009 16:00 : Senin 44,0 01:20:00
1189,00
10% Shale, 40% Coal).
456,00 0,00 19,00 Ljt bor formasi spi kedalaman 1068 m (ROP 16 mnt/m, lith 70% SST, 2a 7,5 419,50 0,31 17,48 1068,00 28/12/2009 23:30 : Senin 36,5 01:12:30
1189,00
30% Shale).
456,00 0,00 19,00 Perbaikan Top Drive : ganti lower kelly cock (washout). Cabut 21e 4,5 424,00 0,19 17,67 1068,00 NPT 29/12/2009 04:00 : Selasa 32,0 01:08:00
rangkaian spi kedalaman 1047 m, pasang topi sirkulasi, swept
out hi vis 30 bbls & lanjut sirkulasi sambil perbaikan. Running
1189,00 RPM 170 high, OK. Pressure test tidak bisa dilakukan, actuator
valve tdk bisa menutup (NPT Rig = 4.5 jam. Kum 94.5 jam).
456,00 0,00 19,00 Ljt bor formasi spi kedalaman 1124 m (ROP 5.73 mnt/m. lith 10% 2a 8,0 432,00 0,33 18,00 1124,00 29/12/2009 12:00 : Selasa 24,0 01:00:00
1189,00
Coal, 20% Shale, 70% SST).
456,00 0,00 19,00 Ljt bor formasi spi kedalaman 1141 m (ROP 6 mnt/m, lith 30% SST, 2a 4,0 436,00 0,17 18,17 1141,00 29/12/2009 16:00 : Selasa 20,0 00:20:00
1189,00
70% Shale).
456,00 0,00 19,00 Ljt bor formasi spi kedalaman 1162 m (ROP 12 mnt/m, lith 40% 2a 2,0 438,00 0,08 18,25 1162,00 29/12/2009 18:00 : Selasa 18,0 00:18:00
1189,00 Shale, 60 SST). Indikasi tekanan naik 2500 psi, normal 1500 psi,
string buntu.
456,00 0,00 19,00 POOH 12-1/4" PDC + BHA Rotary spi kedalaman 123 m. OP 10-15 23 10,0 448,00 0,42 18,67 1162,00 30/12/2009 04:00 : Rabu 8,0 00:08:00
1189,00
klbs @ 1116, 989, 960, 738 m.
456,00 0,00 19,00 Ljt POOH 12-1/4" PDC + BHA Rotary spi permukaan, terdapat 23 1,0 449,00 0,04 18,71 1162,00 30/12/2009 05:00 : Rabu 7,0 00:07:00
1189,00 potongan DP Screen plate lingkaran ukuran 2 inch di atas Totco Ring.
456,00 0,00 19,00 RIH 12-1/4" PDC + BHA Rotary spi kedalaman 583 m, rangkaian 23 7,0 456,00 0,29 19,00 1162,00 30/12/2009 12:00 : Rabu 0,0 00:00:00
1189,00 duduk 10klbs @ 432m, 465m, 525m. Reaming down interval 432 -
448m, 465 - 486m, 525 - 544m.
456,00 0,00 19,00 RIH 12-1/4" PDC + BHA Rotary spi kedalaman 1114m, duduk 15 klbs. 23 2,5 458,50 0,10 19,10 1162,00 30/12/2009 14:30 : Rabu -2,5 00:02:30
1189,00
456,00 0,00 19,00 1189,00 Washdown & work on pipe interval 1114 - 1140 m, OK. 23 0,5 459,00 0,02 19,13 1162,00 30/12/2009 15:00 : Rabu -3,0 00:03:00
456,00 0,00 19,00 Reaming down interval 1140 - 1162 m, rangkaian duduk 10 klbs. 3 1,0 460,00 0,04 19,17 1162,00 NPT 30/12/2009 16:00 : Rabu -4,0 00:04:00
1189,00
456,00 0,00 19,00 Ljt bor formasi spi kedalaman 1188 m (Csg Point 9-5/8"). (ROP 14 2a 5,0 465,00 0,21 19,38 1188,00 30/12/2009 21:00 : Rabu -9,0 00:09:00
1189,00 mnt/m, Lith 80% Shale, 10% Coal, 10% SST)
456,00 0,00 19,00 1189,00 Sirkulasi kondisikan lumpur, naikan berat sebesar ECD 1.18 SG 5b 2,0 467,00 0,08 19,46 1188,00 30/12/2009 23:00 : Rabu -11,0 00:11:00
456,00 0,00 19,00 1189,00 Swept out hi vis 30 bbls & sirkulasi bersih. 5a 1,0 468,00 0,04 19,50 1188,00 31/12/2009 00:00 : Kamis -12,0 00:12:00
456,00 0,00 19,00 Short trip, POOH 12-1/4" PDC + BHA Rotary spi kedalaman 564 m. 6a 4,0 472,00 0,17 19,67 1188,00 31/12/2009 04:00 : Kamis -16,0 00:16:00
1189,00
OP 15 klbs @ 1013, 774, 754 m.
456,00 0,00 19,00 Ljt short trip, POOH 12-1/4" PDC + BHA Rotary spi shoe @ 197 m. 6a 2,0 474,00 0,08 19,75 1188,00 31/12/2009 06:00 : Kamis -18,0 00:18:00
1189,00
456,00 0,00 19,00 1189,00 Sirkulasi bersih 5a 0,5 474,50 0,02 19,77 1188,00 31/12/2009 06:30 : Kamis -18,5 00:18:30
456,00 0,00 19,00 RIH 12-1/4" PDC + BHA Rotary spi kedalaman 548 m, duduk 10 klbs. 6a 1,5 476,00 0,06 19,83 1188,00 31/12/2009 08:00 : Kamis -20,0 00:20:00
1189,00
456,00 0,00 19,00 1189,00 Washdown interval 548 - 564 m. 6a 0,5 476,50 0,02 19,85 1188,00 31/12/2009 08:30 : Kamis -20,5 00:20:30
456,00 0,00 19,00 Ljt RIH 12-1/4" PDC + BHA Rotary spi kedalaman 1174 m, duduk 15 6a 3,0 479,50 0,13 19,98 1188,00 31/12/2009 11:30 : Kamis -23,5 00:23:30
1189,00
klbs.
456,00 0,00 19,00 1189,00 Reaming down interval 1174 - 1182 m. 3 0,5 480,00 0,02 20,00 1188,00 31/12/2009 12:00 : Kamis -24,0 00:01:00
PLAN ACTUAL GAIN / LOSS
TIME REALIZATION &
NO OPERATION IADC CUMM. IADC
HOURS DAYS CUMM. DEPTH JOB DESCRIPTION HOURS CUMM. DAYS CUMM. DEPTH NPT PREDICTION HOUR DD:HH:MM
CODE HOURS CODE
456,00 0,00 19,00 Lanjut reaming down interval 1182 - 1188 m, sambil sirkulasi naikan 6a 1,0 481,00 0,04 20,04 1188,00 31/12/2009 13:00 : Kamis -25,0 01:02:00
1189,00
SG 1.21 (ECD).
456,00 0,00 19,00 1189,00 Swept out hi vis 30 bbls & spot hi vis 30 bbls di dasar 5a 0,5 481,50 0,02 20,06 1188,00 31/12/2009 13:30 : Kamis -25,5 01:01:30
456,00 0,00 19,00 1189,00 Jatuhkan Totco Survey 23 0,5 482,00 0,02 20,08 1188,00 31/12/2009 14:00 : Kamis -26,0 01:03:00
456,00 0,00 19,00 1189,00 POOH 12-1/4" PDC + BHA Rotary spi kedalaman 815 m. 6a 2,0 484,00 0,08 20,17 1188,00 31/12/2009 16:00 : Kamis -28,0 01:05:00
456,00 0,00 19,00 Ljt POOH 12-1/4" PDC + BHA Rotary spi permukaan, Totco Survey 6a 5,5 489,50 0,23 20,40 1188,00 31/12/2009 21:30 : Kamis -33,5 01:09:30
1189,00 1.5 deg (Dull Grading 12-1/4" PDC : 0/ 6/ CT/ G/ X/ X/ NO/ TD).
456,00 0,00 19,00 M/U & RIH 12-1/4" PDC (Open Nozzle) + BHA Rotary spi kedalaman 6a 6,5 496,00 0,27 20,67 1188,00 01/01/2010 04:00 : Jumat -40,0 01:17:00
1189,00
1170 m, duduk 10klbs.
456,00 0,00 19,00 1189,00 Reaming down spi kedalaman 1188 m. 3 0,5 496,50 0,02 20,69 1188,00 01/01/2010 04:30 : Jumat -40,5 01:16:30
456,00 0,00 19,00 Sirkulasi bersih, swept out hi vis 30 bbls & Spot 30 bbls hi vis di 5a 2,0 498,50 0,08 20,77 1188,00 01/01/2010 06:30 : Jumat -42,5 01:18:30
1189,00
dasar.
456,00 0,00 19,00 POOH 12-1/4" PDC (Open Nozzle) + BHA Rotary spi kedalaman 133 6a 5,5 504,00 0,23 21,00 1188,00 01/01/2010 12:00 : Jumat -48,0 01:01:00
1189,00
m, OP 15 klbs @ 1139 m.
456,00 0,00 19,00 Ljt POOH 12-1/4" PDC (Open Nozzle) + BHA Rotary spi permukaan. 6a 2,0 506,00 0,08 21,08 1188,00 01/01/2010 14:00 : Jumat -50,0 02:03:00
1189,00
456,00 0,00 19,00 1189,00 Persiapan & RIH logging #1 (DLL-BHC-MSFL-GR) 11a 1,0 507,00 0,04 21,13 1188,00 01/01/2010 15:00 : Jumat -51,0 02:04:00
456,00 0,00 19,00 1189,00 Run Logging #1 (DLL-BHC-MSFL-GR) 11b 1,0 508,00 0,04 21,17 1188,00 01/01/2010 16:00 : Jumat -52,0 02:05:00
456,00 0,00 19,00 Ljt run logging#1 (DLL-BHC-MSFL-GR). Interval log 700 - 1183.1 m. 11b 4,0 512,00 0,17 21,33 1188,00 01/01/2010 20:00 : Jumat -56,0 02:09:00
1189,00
456,00 0,00 19,00 1189,00 Persiapan & RIH logging #2 (LDL-CNL-GR) 11a 1,0 513,00 0,04 21,38 1188,00 01/01/2010 21:00 : Jumat -57,0 02:10:00
456,00 0,00 19,00 1189,00 Run Logging #2 (LDL-CNL-GR), Interval log 700 - 1185.5 m. 11b 3,0 516,00 0,13 21,50 1188,00 02/01/2010 00:00 : Sabtu -60,0 02:13:00
456,00 0,00 19,00 1189,00 R/D Wireline Elnusa 11a 0,5 516,50 0,02 21,52 1188,00 02/01/2010 00:30 : Sabtu -60,5 02:12:30
F Trip, masuk & semen Csg 9 5/8". Psg CHS 13 3/8 X 9 5/8 - 3000 528,00 3,00 22,00 Round Trip, M/U & RIH 12-1/4" PDC (open Nozzle) + BHA Rotary spi 6a 3,5 520,00 0,15 21,67 1188,00 02/01/2010 04:00 : Sabtu 8,0 00:08:00
psi, DSAF, 9 5/8 - 3000 x 13 3/8 - 5000 PSI, BOP group 13 3/8 - kedalaman 718 m.
5000 Psi, bell nipple, over flow dan surface line. Test BOP, M/U 12 6a 72,00 1189,00
1/4" Bit + BHA, bor plug, semen dan formasi spi 1192 m, Formation
528,00 0,00 22,00 Ljt round Trip, M/U & RIH 12-1/4" PDC (open Nozzle) + BHA Rotary 6a 1,5 521,50 0,06 21,73 1188,00 02/01/2010 05:30 : Sabtu 6,5 00:06:30
1189,00
spi kedalaman 1173 m, duduk 15 klbs.
528,00 0,00 22,00 1189,00 Washdown spi kedalaman 1180 m. 5a 0,5 522,00 0,02 21,75 1188,00 02/01/2010 06:00 : Sabtu 6,0 00:06:00
528,00 0,00 22,00 1189,00 Sirkulasi kondisikan lumpur SG 1.23 (ECD) 5b 1,0 523,00 0,04 21,79 1188,00 02/01/2010 07:00 : Sabtu 5,0 00:05:00
528,00 0,00 22,00 1189,00 Swept out hi vis 30 bbls & spot hi vis 30 bbls di dasar 5a 1,0 524,00 0,04 21,83 1188,00 02/01/2010 08:00 : Sabtu 4,0 00:04:00
528,00 0,00 22,00 POOH 12-1/4" PDC (Open Nozzle) + BHA Rotary spi kedalaman 352 6a 4,0 528,00 0,17 22,00 1188,00 02/01/2010 12:00 : Sabtu 0,0 00:00:00
1189,00
m.
528,00 0,00 22,00 Ljt POOH 12-1/4" PDC (Open Nozzle) + BHA Rotary spi permukaan 6a 4,0 532,00 0,17 22,17 1188,00 02/01/2010 16:00 : Sabtu -4,0 00:05:00
1189,00
& L/D 4 jts DC 8".
528,00 0,00 22,00 1189,00 Persiapan masuk casing & handling tools. 12a 2,0 534,00 0,08 22,25 1188,00 02/01/2010 18:00 : Sabtu -6,0 00:07:00
528,00 0,00 22,00 RIH Casing 9-5/8" K55 36# R3 spi kedalaman 1176 m, duduk 15 klbs. 12b 10,0 544,00 0,42 22,67 1188,00 03/01/2010 04:00 : Minggu -16,0 00:17:00
1189,00
528,00 0,00 22,00 Usaha masuk lebih dalam dengan sirkulasi (650 GPM / P 1000 psi), 12b 1,0 545,00 0,04 22,71 1188,00 03/01/2010 05:00 : Minggu -17,0 00:17:00
1189,00 turunkan secara bertahap spi 40 klbs, tekanan normal 1000 psi, shoe
@1186 m; Collar @1162.95 m.
528,00 0,00 22,00 1189,00 Sirkulasi bersih di dasar. 5a 1,0 546,00 0,04 22,75 1188,00 03/01/2010 06:00 : Minggu -18,0 00:18:00
528,00 0,00 22,00 1189,00 M/U Cementing Head & Cementing Line 13a 1,5 547,50 0,06 22,81 1188,00 03/01/2010 07:30 : Minggu -19,5 00:19:30
528 00
528,00 0 00
0,00 22 00
22,00 1189 00
1189,00 Sirkulasi kondisikan lumpur
lumpur, turunkan YP
YP. 5b 10
1,0 548 50
548,50 0 04
0,04 22 85
22,85 1188 00
1188,00 03/01/2010 08:30 : Minggu -20,5
20 5 00:20:30
528,00 0,00 22,00 PJSM, Flush line 5 bbls, Pressure Test 2000 psi/5mnt. Pompakan 50 13b 3,5 552,00 0,15 23,00 1188,00 03/01/2010 12:00 : Minggu -24,0 01:00:00
bbls Spacer 1.4 SG (Mud Push 2100 gal; D020 275 lbs, D047 14 gal),
jatuhkan bottom plug. Pompakan 134.5 bbls Lead 1.65 SG (560 sxs
1189,00 semen, D124 5292 lbs; D047 6 gal; D153 155 lbs; D145A 138 gal;
D193 221 gal; S001 934 lbs) & 277.13 bbls Tail 1.9 SG (1600 sxs
semen, D047 14 gal; D153 203 lbs; D145A 215.4 gal; D193 934 gal,
S001 405 lbs). Jatuhkan top plug.
528,00 0,00 22,00 Ljt Cementing Jobs Csg 9-5/8" : dorong semen dengan 295 bbls 13b 2,0 554,00 0,08 23,08 1188,00 03/01/2010 14:00 : Minggu -26,0 01:02:00
1189,00 lumpur, pemompaan ke 240 bbls, tidak ada aliran balik. Ljt pompa spi
295 bbls, tdk tercapai tekanan bentur.
528,00 0,00 22,00 1189,00 Flushing line dari kontaminasi semen. 23 1,0 555,00 0,04 23,13 1188,00 03/01/2010 15:00 : Minggu -27,0 01:03:00
528,00 0,00 22,00 1189,00 TSK (Tunggu Semen Keras) 14 1,0 556,00 0,04 23,17 1188,00 03/01/2010 16:00 : Minggu -28,0 01:04:00
528,00 0,00 22,00 1189,00 Lanjut TSK. 14 3,5 559,50 0,15 23,31 1188,00 03/01/2010 19:30 : Minggu -31,5 01:07:30
528,00 0,00 22,00 1189,00 Jajak puncak semen di annulus casing 13-3/8" - 9-5/8", TOC 9 m. 23 0,5 560,00 0,02 23,33 1188,00 03/01/2010 20:00 : Minggu -32,0 01:08:00
528,00 0,00 22,00 1189,00 N/D Cementing Head. 13a 1,5 561,50 0,06 23,40 1188,00 03/01/2010 21:30 : Minggu -33,5 01:09:30
528,00 0,00 22,00 Gantung BOP Group 13-5/8 x 5K, & Lakukan Sack Jobs dengan 2 sxs 13b 1,5 563,00 0,06 23,46 1188,00 03/01/2010 23:00 : Minggu -35,0 01:11:00
1189,00
semen.
528,00 0,00 22,00 1189,00 Pasang Slip Hanger & Potong Casing 9-5/8". 16 4,0 567,00 0,17 23,63 1188,00 04/01/2010 03:00 : Senin -39,0 01:15:00
528,00 0,00 22,00 1189,00 N/U Wellhead Sec B (13-5/8" x 11" x 3 K) 16 2,0 569,00 0,08 23,71 1188,00 04/01/2010 05:00 : Senin -41,0 01:17:00
528,00 0,00 22,00 N/U DSAF 11" x 3K, Riser Spool 11" x 13-5/8" x 3 K, Drilling Spool 13- 15a 4,5 573,50 0,19 23,90 1188,00 04/01/2010 09:30 : Senin -45,5 01:21:30
5/8" x 3K x 5K, BOP Group 13-5/8" x 5K, & Bell Nipple. Function test
1189,00
Annular, Pipe ram, HCR OK. (NPT Rig = 0.5 Jam, kum 96 jam).
528,00 0,00 22,00 Perbaikan Top Drive : Ganti Actuator Valve, OK. (NPT Rig = 1 21e 1,0 574,50 0,04 23,94 1188,00 NPT 04/01/2010 10:30 : Senin -46,5 01:22:30
1189,00
Jam, kum 97 jam).
528,00 0,00 22,00 Press Test dgn tester cup Annular 500/1000 psi 10 mnt, baik. Pipe 15b 1,0 575,50 0,04 23,98 1188,00 04/01/2010 11:30 : Senin -47,5 01:23:30
1189,00 ram 500/1000 psi 10 mnt,baik. (NPT Rig = 1 jam, kum 97.5 jam).
528,00 0,00 22,00 1189,00 Stand up DP 5" tambahan, sebanyak 2 jts. 6d 0,5 576,00 0,02 24,00 1188,00 04/01/2010 12:00 : Senin -48,0 02:00:00
528,00 0,00 22,00 1189,00 Ljt stand up DP 5" tambahan sebanyak 28 jts kum 30 jts. 6d 4,0 580,00 0,17 24,17 1188,00 04/01/2010 16:00 : Senin -52,0 02:04:00
528,00 0,00 22,00 1189,00 Ljt stand up DP 5", tambahan sebanyak 10 jts kum 40 jts 6d 0,5 580,50 0,02 24,19 1188,00 04/01/2010 16:30 : Senin -52,5 02:04:30
528,00 0,00 22,00 1189,00 M/U & RIH 8-1/2" PDC (Open Nozzle) + BHA Rotary, tag TOC @ 1125 6a 4,5 585,00 0,19 24,38 1188,00 04/01/2010 21:00 : Senin -57,0 02:09:00
528,00 0,00 22,00 1189,00 Tes tekanan selubung 1000 psi/10 mnt, baik. 23 0,5 585,50 0,02 24,40 1188,00 04/01/2010 21:30 : Senin -57,5 02:09:30
528,00 0,00 22,00 1189,00 Ljt bor plug, semen shoe track spi kedalaman 1170 m. 2a 6,5 592,00 0,27 24,67 1188,00 05/01/2010 04:00 : Selasa -64,0 02:17:00
528,00 0,00 22,00 1189,00 Ljt bor plug, semen shoe track spi kedalaman 1180 m. 2a 1,5 593,50 0,06 24,73 1188,00 05/01/2010 05:30 : Selasa -65,5 02:17:30
528,00 0,00 22,00 1189,00 Tes tekanan selubung 1000 psi/10 mnt, baik. 23 0,5 594,00 0,02 24,75 1188,00 05/01/2010 06:00 : Selasa -66,0 02:19:00
528,00 0,00 22,00 1189,00 Ljt bor semen, float shoe, formasi spi kedalaman 1192 m. 2a 2,5 596,50 0,10 24,85 1188,00 05/01/2010 08:30 : Selasa -68,5 02:20:30
528,00 0,00 22,00 1189,00 Sirkulasi kondisikan lumpur Sgin/out = 1.08. 5b 0,5 597,00 0,02 24,88 1188,00 05/01/2010 09:00 : Selasa -69,0 02:22:00
528,00 0,00 22,00 POOH 8-1/2" PDC (Open Nozzle)spi shoe @ 1186 m. MOT SG eq 2c 0,5 597,50 0,02 24,90 1188,00 05/01/2010 09:30 : Selasa -69,5 02:21:30
1189,00
1.50.
Trayek Casing 9 5/8" @ 1878 meter 312,00 528,00 3,00 22,00 1189,00 449,50 597,50 18,73 24,90 1188,00
G Bor formasi dengan Pahat 8 1/2" spi TD di 1426 m 2a 72,00 600,00 3,00 25,00 Ljt bor formasi spi kedalaman 1206 m (ROP 6 mnt/m, lith 70% Shale, 2a 2,5 600,00 0,10 25,00 1206,00 05/01/2010 12:00 : Selasa 0,0 00:00:00
1426,00
30% SST)
600,00 0,00 25,00 Ljt bor formasi spi kedalaman 1225 m (ROP 5 mnt/m, lith 60% Shale, 2a 4,0 604,00 0,17 25,17 1225,00 05/01/2010 16:00 : Selasa -4,0 00:05:00
1426,00
40% SST).
600,00 0,00 25,00 1426,00 Ljt bor formasi spi kedalaman 1267 m 2a 8,0 612,00 0,33 25,50 1267,00 06/01/2010 00:00 : Rabu -12,0 00:13:00
600,00 0,00 25,00 Perbaikan Top Drive : Seal Reversed Torque bocor (NPT Rig = 1 21e 1,0 613,00 0,04 25,54 1267,00 NPT 06/01/2010 01:00 : Rabu -13,0 00:14:00
1426,00
Jam, kum 98 jam).
600,00 0,00 25,00 Ljt bor formasi spi kedalaman 1268 m (ROP 10 mnt/m, Lith: 80% 2a 0,5 613,50 0,02 25,56 1268,00 06/01/2010 01:30 : Rabu -13,5 00:13:30
1426,00
SST, 20% Shale), Loss Total.
PLAN ACTUAL GAIN / LOSS
TIME REALIZATION &
NO OPERATION IADC CUMM. IADC
HOURS DAYS CUMM. DEPTH JOB DESCRIPTION HOURS CUMM. DAYS CUMM. DEPTH NPT PREDICTION HOUR DD:HH:MM
CODE HOURS CODE
600,00 0,00 25,00 Combat loss#1 : spot 60 ppb LCM (Kwikseal M-C) 50 bbls, aliran 20a 0,5 614,00 0,02 25,58 1268,00 NPT 06/01/2010 02:00 : Rabu -14,0 00:15:00
1426,00
balik normal.
600,00 0,00 25,00 Ljt bor formasi spi kedalaman 1269 m (ROP 6 mnt/m, lith: 80% SST, 2a 0,5 614,50 0,02 25,60 1269,00 06/01/2010 02:30 : Rabu -14,5 00:14:30
1426,00
20% Shale).
600,00 0,00 25,00 1426,00 Ljt blind drilling spi kedalaman 1276 m (tidak ada aliran balik). 2a 1,0 615,50 0,04 25,65 1276,00 06/01/2010 03:30 : Rabu -15,5 00:15:30
600,00 0,00 25,00 Combat loss#2 : spot 60 ppb LCM (Kwikseal M-C) 100 bbls, tdk 20a 0,5 616,00 0,02 25,67 1276,00 NPT 06/01/2010 04:00 : Rabu -16,0 00:17:00
1426,00
ada aliran balik.
600,00 0,00 25,00 1426,00 POOH 8-1/2" PDC (Open Nozzle)spi shoe @ 1186 m. 20a 0,5 616,50 0,02 25,69 1276,00 NPT 06/01/2010 04:30 : Rabu -16,5 00:16:30
600,00 0,00 25,00 20a 2,5 619,00 0,10 25,79 1276,00 NPT 06/01/2010 07:00 : Rabu -19,0 00:20:00
1426,00 Tunggu Air , sambil Mixing LCM (NPT Tunggu Air = 2.5 jam)
600,00 0,00 25,00 RIH 8-1/2" PDC (Open Nozzle) + BHA Rotary spi kedalaman 1276 20a 0,5 619,50 0,02 25,81 1276,00 NPT 06/01/2010 07:30 : Rabu -19,5 00:19:30
1426,00
m.
600,00 0,00 25,00 Combat loss#3 : Campuran 40 ppb LCM (CaCO3 M-C) 280 bbls 2a 2,5 622,00 0,10 25,92 1295,00 0 06/01/2010 10:00 : Rabu -22,0 00:23:00
1426,00 kedalaman sistem, sambil ljt blind drilling spi kedalaman 1295 m,
tidak ada aliran balik.
600,00 0,00 25,00 20a 0,5 622,50 0,02 25,94 1295,00 NPT 06/01/2010 10:30 : Rabu -22,5 00:22:30
1426,00 Combat loss#4 : spot 60 ppb LCM (Kwikseal M-C), 100 bbls.
600,00 0,00 25,00 1426,00 POOH 8-1/2" PDC (Open Nozzle)spi shoe @ 1186 m. 20a 0,5 623,00 0,02 25,96 1295,00 NPT 06/01/2010 11:00 : Rabu -23,0 00:00:00
600,00 0,00 25,00 Tunggu Air , sambil Mixing LCM (NPT Tunggu Air = 1 jam, kum 20a 1,0 624,00 0,04 26,00 1295,00 NPT 06/01/2010 12:00 : Rabu -24,0 00:01:00
1426,00
3.5 jam)
600,00 0,00 25,00 Ljt Tunggu Air , sambil Mixing LCM (NPT Tunggu Air = 3.5 jam, 20a 3,5 627,50 0,15 26,15 1295,00 NPT 06/01/2010 15:30 : Rabu -27,5 01:03:30
1426,00
kum 7 jam)
600,00 0,00 25,00 RIH 8-1/2" PDC (Open Nozzle) + BHA Rotary spi kedalaman 1295 20a 0,5 628,00 0,02 26,17 1295,00 NPT 06/01/2010 16:00 : Rabu -28,0 01:05:00
1426,00
m.
600,00 0,00 25,00 Combat loss#5 : Campuran 40 ppb LCM (CaCO3 M-C) 300 bbls 2a 3,0 631,00 0,13 26,29 1309,00 0 06/01/2010 19:00 : Rabu -31,0 01:08:00
1426,00 kedalam sistem, sambil ljt blind drilling spi kedalaman 1309 m, tidak
ada aliran balik.
600,00 0,00 25,00 Combat loss#6 : spot 50 ppb LCM (Kwikseal M-C) 100 bbls, tidak 20a 0,5 631,50 0,02 26,31 1309,00 NPT 06/01/2010 19:30 : Rabu -31,5 01:07:30
1426,00
ada aliran balik.
600,00 0,00 25,00 1426,00 POOH 8-1/2" PDC (Open Nozzle) spi permukaan. 20a 5,5 637,00 0,23 26,54 1309,00 NPT 07/01/2010 01:00 : Kamis -37,0 01:14:00
600,00 0,00 25,00 RIH ROE spi kedalaman 859 m, sambil persiapan penyemenan 20a 3,0 640,00 0,13 26,67 1309,00 NPT 07/01/2010 04:00 : Kamis -40,0 01:17:00
1426,00
karbonat.
600,00 0,00 25,00 1426,00 Ljt RIH ROE spi kedalaman 1186 m. 20a 1,0 641,00 0,04 26,71 1309,00 NPT 07/01/2010 05:00 : Kamis -41,0 01:18:00
600,00 0,00 25,00 1426,00 Ljt mixing semen karbonat. 20a 2,0 643,00 0,08 26,79 1309,00 NPT 07/01/2010 07:00 : Kamis -43,0 01:20:00
600,00 0,00 25,00 1426,00 Ljt RIH ROE spi kedalaman 1308 m. 20a 0,5 643,50 0,02 26,81 1309,00 NPT 07/01/2010 07:30 : Kamis -43,5 01:19:30
600,00 0,00 25,00 1426,00 M/U Circulating head & treating line . 20a 0,5 644,00 0,02 26,83 1309,00 NPT 07/01/2010 08:00 : Kamis -44,0 01:21:00
600,00 0,00 25,00 PJSM, flush line, pressure test 2500 psi/10', OK. Pompakan 20 20a 1,5 645,50 0,06 26,90 1309,00 NPT 07/01/2010 09:30 : Kamis -45,5 01:21:30
bbls water ahead, 50 bbls cement carbonat SG 1.60 (125 sxs
1426,00
semen, D047 1 gal, D020 451 lbs, D145A 10 gal, D081 gal). Dorong
dengan 60 bbls air.
600,00 0,00 25,00 1426,00 POOH ROE spi kedalaman 1000 m. 20a 1,0 646,50 0,04 26,94 1309,00 NPT 07/01/2010 10:30 : Kamis -46,5 01:22:30
600,00 0,00 25,00 Pompakan 50 bbls cement carbonat SG 1.60 (125 sxs semen, 20a 0,5 647,00 0,02 26,96 1309,00 NPT 07/01/2010 11:00 : Kamis -47,0 01:00:00
D047 1 gal, D020 451 lbs, D145A 10 gal, D081 4.8 gal). Dorong
1426,00
dengan 10 bbls air pertama, ada aliran balik. Ljt dorong dengan
air spi 50 bbls (aliran balik normal).
600,00
600 00 0 00
0,00 25 00
25,00 1426 00
1426,00 POOH ROE spii kedalaman
k d l 800 m. 20a
20 0,5
0 5 647 50
647,50 0 02
0,02 26 98
26,98 1309 00
1309,00 NPT 07/01/2010 11
11:30
30 : K
Kamis
i -47,5
47 5 01 23 30
01:23:30
600,00 0,00 25,00 1426,00 Sirkulasi keluar kontaminasi semen. 20a 0,5 648,00 0,02 27,00 1309,00 NPT 07/01/2010 12:00 : Kamis -48,0 01:01:00
600,00 0,00 25,00 1426,00 POOH ROE spi permukaan. 20a 3,0 651,00 0,13 27,13 1309,00 NPT 07/01/2010 15:00 : Kamis -51,0 02:04:00
600,00 0,00 25,00 20a 3,0 654,00 0,13 27,25 1309,00 NPT 07/01/2010 18:00 : Kamis -54,0 02:07:00
1426,00 M/U & RIH 8-1/2" PDC (Open Nozzle) + BHA spi kedalaman 505 m.
600,00 0,00 25,00 1426,00 Lanjut TSK. 20a 4,0 658,00 0,17 27,42 1309,00 NPT 07/01/2010 22:00 : Kamis -58,0 02:11:00
600,00 0,00 25,00 Lanjut RIH 8-1/2" PDC + BHA dari 505 m spi 824 m, jajak puncak 20a 1,0 659,00 0,04 27,46 1309,00 NPT 07/01/2010 23:00 : Kamis -59,0 02:12:00
1426,00
semen.
600,00 0,00 25,00 Bor semen dari 824 m spi 1055 m dengan GPM/SPP = 550/700 psi, 20a 13,0 672,00 0,54 28,00 1309,00 NPT 08/01/2010 12:00 : Jumat -72,0 02:01:00
1426,00
ROPavg = 1.80. Observasi, tidak ada loss.
600,00 0,00 25,00 Bor semen dari 1055 m spi 1309 m dengan GPM/SPP = 450- 20a 12,5 684,50 0,52 28,52 1309,00 NPT 09/01/2010 00:30 : Sabtu -84,5 03:12:30
1426,00
550/600-700 psi, ROPavg = 1.85.
600,00 0,00 25,00 Sirkulasi bersikan lubang, swept out 30 bbl hi-vis. Observasi, 20a 0,5 685,00 0,02 28,54 1309,00 NPT 09/01/2010 01:00 : Sabtu -85,0 03:14:00
1426,00
tidak ada loss.
600,00 0,00 25,00 Lanjut bor formasi dari 1309 m spi 1329 m dengan GPM/SPP = 2a 2,0 687,00 0,08 28,63 1329,00 0 09/01/2010 03:00 : Sabtu -87,0 03:16:00
1426,00 500/600 psi, ROPavg 2.5 mpm, Lithologi 100% Sand. Terjadi loss
total di 1329 m.
600,00 0,00 25,00 1426,00 Blind drilling formasi dari 1329 m spi 1372 m, tidak ada aliran. 2a 8,5 695,50 0,35 28,98 1372,00 0 09/01/2010 11:30 : Sabtu -95,5 03:23:30
600,00 0,00 25,00 1426,00 Spot 60 bbl LCM-7 (Kwikseal + CaCO3) 60 pbb, tidak ada aliran. 20a 0,5 696,00 0,02 29,00 1372,00 NPT 09/01/2010 12:00 : Sabtu -96,0 03:01:00
600,00 0,00 25,00 1426,00 Cabut rangkaian PDC 8-1/2" + BHA dari 1372 m spi permukaan. 20a 5,0 701,00 0,21 29,21 1372,00 NPT 09/01/2010 17:00 : Sabtu -101,0 04:05:00
600,00 0,00 25,00 1426,00 Masuk rangkaian open end dari permukaan spi 1370 m. 20a 4,0 705,00 0,17 29,38 1372,00 NPT 09/01/2010 21:00 : Sabtu -105,0 04:09:00
600,00 0,00 25,00 1426,00 Sirkulasi kondisikan lumpur, tidak ada aliran. 20a 0,5 705,50 0,02 29,40 1372,00 NPT 09/01/2010 21:30 : Sabtu -105,5 04:09:30
600,00 0,00 25,00 Penyemenan karbonat plug balance #2 untuk combat loss int 20a 1,5 707,00 0,06 29,46 1372,00 NPT 09/01/2010 23:00 : Sabtu -107,0 04:11:00
(1372-1309) m dengan prosedur : PJSM. Mixing 60 bbl cement
slurry SG 1.60. M/U cementing head, test cementing line 2000
1426,00 psi/5 mnt baik. Pompakan 20 bbl water ahead. Pompakan 60 bbl
cement slurry SG 1.60 (125 sx semen + add). Displace cement
slurry dengan 62.5 bbl air, setelah displace 48 bbl diperoleh
aliran.
600,00 0,00 25,00 20a 0,5 707,50 0,02 29,48 1372,00 NPT 09/01/2010 23:30 : Sabtu -107,5 04:11:30
Cabut rangkaian open end, rangkaian stuck. Cabut rangkaian
dengan WOP 0 - 115 ton, tidak berhasil. Putar rangkaian, tidak
1426,00 bisa. Cabut rangkaian dengan WOP 0 - 115 ton sambil pompakan
air dengan GPM/SPP 125/550 psi, rangkaian berhasil dicabut
(berat rangkaian open end 55 ton, over pull 60 ton).
600,00 0,00 25,00 20a 1,0 708,50 0,04 29,52 1372,00 NPT 10/01/2010 00:30 : Minggu -108,5 04:12:30
Cabut rangkaian open end dari 1370 m spi 985 m. Sirkulasi lurus,
1426,00
diperoleh kontaminasi semen. Observasi loss stat 0 bpm.
600,00 0,00 25,00 Lanjut cabut rangkaian dari 985 m spi permukaan, rangkaian 20a 3,5 712,00 0,15 29,67 1372,00 NPT 10/01/2010 04:00 : Minggu -112,0 04:16:00
1426,00
terangkat semua.
600,00 0,00 25,00 Masuk rangkaian PDC 8-1/2" + BHA spi 1141 m, gantung 20a 4,0 716,00 0,17 29,83 1372,00 NPT 10/01/2010 08:00 : Minggu -116,0 04:20:00
1426,00
rangkaian.
600,00 0,00 25,00 1426,00 TSK. 20a 4,0 720,00 0,17 30,00 1372,00 NPT 10/01/2010 12:00 : Minggu -120,0 05:00:00
600,00 0,00 25,00 1426,00 Lanjut TSK, sampel semen belum keras. 20a 3,0 723,00 0,13 30,13 1372,00 NPT 10/01/2010 15:00 : Minggu -123,0 05:03:00
600,00 0,00 25,00 Lanjut masuk rangkaian PDC 8-1/2" + BHA dari 1141 m spi 1270 20a 1,0 724,00 0,04 30,17 1372,00 NPT 10/01/2010 16:00 : Minggu -124,0 05:04:00
1426,00
m, jajak puncak semen.
600,00 0,00 25,00 Bor semen dari 1270 m spi 1372 m dengan GPM/SPP : 500/600 20a 11,0 735,00 0,46 30,63 1372,00 NPT 11/01/2010 03:00 : Senin -135,0 05:15:00
1426,00
psi.
600,00 0,00 25,00 Sirkulasi bersikan lubang, swept out 30 bbl hi-vis. Observasi, 20a 1,0 736,00 0,04 30,67 1372,00 NPT 11/01/2010 04:00 : Senin -136,0 05:16:00
1426,00
loss stat : 0 bpm
PLAN ACTUAL GAIN / LOSS
TIME REALIZATION &
NO OPERATION IADC CUMM. IADC
HOURS DAYS CUMM. DEPTH JOB DESCRIPTION HOURS CUMM. DAYS CUMM. DEPTH NPT PREDICTION HOUR DD:HH:MM
CODE HOURS CODE
600,00 0,00 25,00 Bor formasi dari 1372 m spi 1411 m dengan GPM/SPP: 500/600 psi, 2a 8,0 744,00 0,33 31,00 1411,00 0 11/01/2010 12:00 : Senin -144,0 06:00:00
1426,00
ROPavg: 9.0 mpm, litologi shale 100%. Terjadi loss total di 1411 m.
600,00 0,00 25,00 1426,00 Blind drilling dari 1411 m spi 1430 m, tidak ada aliran. 2a 4,0 748,00 0,17 31,17 1430,00 0 11/01/2010 16:00 : Senin -148,0 06:04:00
600,00 0,00 25,00 Spot 50 bbl LCM-8 (kwikseal+CaCO3) 60 ppb. Cabut rangkaian 20a 2,0 750,00 0,08 31,25 1430,00 NPT 11/01/2010 18:00 : Senin -150,0 06:06:00
1426,00 spi 1305 m. Sirkulasi, aliran intermittent. Masuk rangkaian spi
1430 m.
600,00 0,00 25,00 1426,00 Lanjut blind drilling dari 1430 m spi 1440 m (TD), tidak ada aliran. 2a 3,5 753,50 0,15 31,40 1440,00 0 11/01/2010 21:30 : Senin -153,5 06:09:30
600,00 0,00 25,00 20a 2,5 756,00 0,10 31,50 1440,00 NPT 12/01/2010 00:00 : Selasa -156,0 06:12:00
Spot 60 bbl LCM-9 (kwikseal+CaCO3) 60 ppb. Cabut rangkaian
1426,00
spi 1305 m. Sirkulasi, aliran normal. Masuk rangkaian spi 1430 m.
600,00 0,00 25,00 20a 1,5 757,50 0,06 31,56 1440,00 NPT 12/01/2010 01:30 : Selasa -157,5 06:13:30
Sirkulasi di dasar, swept out 30 bbl hi-vis. Observasi, loss stat
1426,00
0.1 bpm. Selama sirkulasi keluar cutting shale dan batubara.
600,00 0,00 25,00 Spot 40 bbl LCM-10 (diaseal-m+air) 50 ppb. Observasi, loss stat 20a 0,5 758,00 0,02 31,58 1440,00 NPT 12/01/2010 02:00 : Selasa -158,0 06:14:00
1426,00
0.5 bpm.
600,00 0,00 25,00 20a 5,5 763,50 0,23 31,81 1440,00 NPT 12/01/2010 07:30 : Selasa -163,5 06:19:30
1426,00 Cabut rangkaian PDC 8-1/2" + BHA dari 1440 m spi permukaan.
600,00 0,00 25,00 1426,00 Masuk rangkaian open end dari permukaan spi 1178 m. 20a 4,5 768,00 0,19 32,00 1440,00 NPT 12/01/2010 12:00 : Selasa -168,0 07:00:00
600,00 0,00 25,00 Ganti elevator link, lanjut masuk rangkaian open end dari 1178 m 20a 1,5 769,50 0,06 32,06 1440,00 NPT 12/01/2010 13:30 : Selasa -169,5 07:01:30
1426,00
spi 1438.5 m.
600,00 0,00 25,00 1426,00 Sirkulasi kondisikan lumpur, aliran keluar. 20a 0,5 770,00 0,02 32,08 1440,00 NPT 12/01/2010 14:00 : Selasa -170,0 07:02:00
600,00 0,00 25,00 20a 4,0 774,00 0,17 32,25 1440,00 NPT 12/01/2010 18:00 : Selasa -174,0 07:06:00
Penyemenan karbonat plug balance #3 untuk combat loss int
(1372-1309) m dengan prosedur : PJSM. Mixing 60 bbl cement
slurry SG 1.60. M/U cementing head, test 2000 psi/5 mnt baik.
Pompakan 15 bbl water ahead. Pompakan 60 bbl cement slurry
1426,00
SG 1.60 (125 sx semen + add). Displace cement slurry dengan
67.5 bbl air. Cabut rangkaian open end spi 1091 m. Sirkulasi,
keluar kontaminasi semen. Squeeze hesitasi, max press 202
psi/3.6 bbl. Vakum sumur.
600,00 0,00 25,00 1426,00 TSK sambil vakum sumur. 20a 3,0 777,00 0,13 32,38 1440,00 NPT 12/01/2010 21:00 : Selasa -177,0 07:09:00
600,00 0,00 25,00 1426,00 Cabut rangkaian open end dari 1091 m spi permukaan. 20a 3,0 780,00 0,13 32,50 1440,00 NPT 13/01/2010 00:00 : Rabu -180,0 07:12:00
600,00 0,00 25,00 1426,00 Ganti elevator link. 20a 1,0 781,00 0,04 32,54 1440,00 NPT 13/01/2010 01:00 : Rabu -181,0 07:13:00
600,00 0,00 25,00 Masuk rangkaian PDC 8-1/2" + BHA spi 1160 m, sirkulasi. 20a 5,0 786,00 0,21 32,75 1440,00 NPT 13/01/2010 06:00 : Rabu -186,0 07:18:00
1426,00
Gantung rangkaian, sampel semen belum keras.
600,00 0,00 25,00 1426,00 Lanjut TSK. 20a 6,0 792,00 0,25 33,00 1440,00 NPT 13/01/2010 12:00 : Rabu -192,0 08:00:00
600,00 0,00 25,00 1426,00 Lanjut TSK. 20a 3,0 795,00 0,13 33,13 1440,00 NPT 13/01/2010 15:00 : Rabu -195,0 08:03:00
600,00 0,00 25,00 Lanjut masuk rangkaian PDC 8-1/2" + BHA dari 1160 m spi 1252 20a 1,0 796,00 0,04 33,17 1440,00 NPT 13/01/2010 16:00 : Rabu -196,0 08:04:00
1426,00
m, jajak puncak semen.
600,00 0,00 25,00 Bor semen dari 1252 m spi 1295 m dgn GPM/SPP: 500/600 psi, 20a 3,0 799,00 0,13 33,29 1440,00 NPT 13/01/2010 19:00 : Rabu -199,0 08:07:00
1426,00 Top drive tidk dapat berputar. Sirkulasi, observasi loss stat 0
bpm.
600,00 0,00 25,00 21e 4,0 803,00 0,17 33,46 1440,00 NPT 13/01/2010 23:00 : Rabu -203,0 08:11:00
Cabut rangkaian PDC 8 8-1/2"
1/2 + BHA dari 1295 m spi 1180 m. m
1426,00 Perbaikan DC power pin drill panel Top drive, baik. Masuk
rangkaian PDC 8-1/2" + BHA spi 1295 m. NPT Top Drive 4 jam.
600,00 0,00 25,00 Lanjut bor semen dari 1295 m spi 1353 m dgn GPM/SPP : 500/600 20a 5,0 808,00 0,21 33,67 1440,00 NPT 14/01/2010 04:00 : Kamis -208,0 08:16:00
1426,00
psi. Observasi loss stat 0.3 bpm.
600,00 0,00 25,00 Lanjut bor formasi dari 1353 m spi 1440 m dgn GPM/SPP : 20a 6,0 814,00 0,25 33,92 1440,00 NPT 14/01/2010 10:00 : Kamis -214,0 08:22:00
1426,00
500/600 psi. Observasi loss stat 0.07 bpm.
600,00 0,00 25,00 1426,00 Sirkulasi, swept out 30 bbl hi-vis. 20a 1,0 815,00 0,04 33,96 1440,00 NPT 14/01/2010 11:00 : Kamis -215,0 08:23:00
600,00 0,00 25,00 Cabut rangkaian PDC 8-1/2" + BHA dari 1440 m spi 1350 m. Spot 20a 1,0 816,00 0,04 34,00 1440,00 NPT 14/01/2010 12:00 : Kamis -216,0 08:01:00
1426,00
40 bbl LCM-11 (Diaseal-M + Air) 50 ppb.
600,00 0,00 25,00 Lanjut cabut rangkaian PDC 8-1/2" + BHA dari 1350 m spi 1180 m. 20a 1,0 817,00 0,04 34,04 1440,00 NPT 14/01/2010 13:00 : Kamis -217,0 09:02:00
1426,00
Sirkulasi tunggu reaksi LCM.
600,00 0,00 25,00 20a 1,5 818,50 0,06 34,10 1440,00 NPT 14/01/2010 14:30 : Kamis -218,5 09:02:30
1426,00 Masuk rangkaian PDC 8-1/2" + BHA dari 1180 m spi 1440 m.
600,00 0,00 25,00 Sirkulasi, swept out 30 bbl hi-vis. Observasi loss stat 0.05 bpm. 20a 1,5 820,00 0,06 34,17 1440,00 NPT 14/01/2010 16:00 : Kamis -220,0 09:05:00
1426,00
Ganti isi lubang dgn salinity 25000 ppm.
600,00 0,00 25,00 20a 5,0 825,00 0,21 34,38 1440,00 NPT 14/01/2010 21:00 : Kamis -225,0 09:10:00
1426,00 Cabut rangkaian PDC 8-1/2" + BHA dari 1440 m spi permukaan.
H Trip, Logging, trip 6a 24,00 624,00 1,00 26,00 1426,00 R/U wireline logging unit Elnusa 11a 1,0 826,00 0,04 34,42 1440,00 0 14/01/2010 22:00 : Kamis -202,0 08:11:00
624,00 0,00 26,00 Run logging DLL-BHC-MSFL-GR-SP-CALS spi 1274 m,rangkaian 11b 4,0 830,00 0,17 34,58 1440,00 0 15/01/2010 02:00 : Jumat -206,0 08:15:00
1426,00 duduk dari 1270-1274 m. Indikasi lubang wash out, ketika bor formasi
loss total di 1268 m. Cabut logging tool spi permukaan.
624,00 0,00 26,00 Masuk rangkaian PDC 8-1/2" + BHA spi 1440 m, reaming down 3 7,0 837,00 0,29 34,88 1440,00 NPT 15/01/2010 09:00 : Jumat -213,0 08:22:00
1426,00
dan reaming up dari 1235 m spi 1440 m.
624,00 0,00 26,00 1426,00 Sirkulasi bersikan lubang, swept out 30 bbl hi-vis. 3 1,5 838,50 0,06 34,94 1440,00 NPT 15/01/2010 10:30 : Jumat -214,5 08:22:30
624,00 0,00 26,00 1426,00 Cabut rangkaian PDC 8-1/2" + BHA dari 1440 m spi 1132 m. 3 1,5 840,00 0,06 35,00 1440,00 NPT 15/01/2010 12:00 : Jumat -216,0 08:01:00
624,00 0,00 26,00 Lanjut cabut rangkaian PDC 8-1/2" + BHA dari 1132 m spi 3 3,0 843,00 0,13 35,13 1440,00 NPT 15/01/2010 15:00 : Jumat -219,0 09:04:00
1426,00
permukaan.
624,00 0,00 26,00 1426,00 R/U wireline logging unit Elnusa. 11a 1,0 844,00 0,04 35,17 1440,00 0 15/01/2010 16:00 : Jumat -220,0 09:05:00
624,00 0,00 26,00 Run logging DLL-BHC-MSFL-GR-SP-CALS int 1168-1440 m, skala 11b 4,0 848,00 0,17 35,33 1440,00 0 15/01/2010 20:00 : Jumat -224,0 09:09:00
1426,00
1:200 dan 1:1000.
624,00 0,00 26,00 1426,00 Run logging LDL-CNL-GR-CALS int 1168-1440 m, skala 1:200 dan 11b 3,5 851,50 0,15 35,48 1440,00 0 15/01/2010 23:30 : Jumat -227,5 09:11:30
624,00 0,00 26,00 1426,00 1 1000 rangkaian PDC 8-1/2" + BHA spi 1440 m.
Masuk 6a 5,5 857,00 0,23 35,71 1440,00 0 16/01/2010 05:00 : Sabtu -233,0 09:18:00
624,00 0,00 26,00 Sirkulasi bersikan lubang, swept out dan spot 60 bbl hi-vis. Observasi 5a 1,5 858,50 0,06 35,77 1440,00 16/01/2010 06:30 : Sabtu -234,5 09:18:30
1426,00
loss stat 0 bpm, drop totco.
624,00 0,00 26,00 Cabut rangkaian PDC 8-1/2" + BHA dari 1440 m spi permukaan. L/D 6a 5,5 864,00 0,23 36,00 1440,00 16/01/2010 12:00 : Sabtu -240,0 09:01:00
1426,00 12 jts 6-1/4" DC. Totco survey 2 deg. Bit dull grading : 0-
1/WT/OT/X/1/16/NO/TD, total bit hours 30.5 jam.
Trayek Casing 7" @ 2028 meter 96,00 624,00 4,00 26,00 1426,00 266,50 864,00 11,10 36,00 1440,00
I Masuk & semen Csg 7", N/D 13 5/8" x 5000 BOP group, N/U THS 9 12a 1,0 865,00 0,04 36,04 1440,00 0 16/01/2010 13:00 : Sabtu -145,0 06:02:00
5/8 x 7 1/16" - 2000, 7 1/16 x 3000 BOP group, RIH 6 1/8" Bit to drill
Plug, RIH 7" Csg Scrapper, replace Mud w/ Completion Fluid. Log 12a 96,00 720,00 4,00 30,00 1426,00 Persiapan masuk casing 7".
CBL-VDL-GR. N/U production facilities, Rig Release.
720,00 30,00 1426,00 Run casing 7" K-55 23 ppf BTC R3 dari permukaan spi FS di 1439.0 12b 11,0 876,00 0,46 36,50 1440,00 17/01/2010 00:00 : Minggu -156,0 06:13:00
0,00 m, FC di 1414.9 m, dan DSCC di 1131.5 m. Masuk sambil sirkulasi
dari 1431 spi 1439 m.
720,00 30,00 1426,00 M/U cmtng head & cmtng line. Sirkulasi kondisikan lumpur sambil 13a 2,0 878,00 0,08 36,58 1440,00 17/01/2010 02:00 : Minggu -158,0 06:15:00
0,00
mixing cement additives
PLAN ACTUAL GAIN / LOSS
TIME REALIZATION &
NO OPERATION IADC CUMM. IADC
HOURS DAYS CUMM. DEPTH JOB DESCRIPTION HOURS CUMM. DAYS CUMM. DEPTH NPT PREDICTION HOUR DD:HH:MM
CODE HOURS CODE
720,00 30,00 1426,00 Penyemenan casing 7" dgn 2 stage, open hole excess 350%. Stage I 13b 6,0 884,00 0,25 36,83 1440,00 17/01/2010 08:00 : Minggu -164,0 06:21:00
int (1440-1131.5) m menggunakan litecrete cement dgn prosedur :
PJSM. Test cemtng line 2500 psi/5 mnt,baik. Batcth mix 40 bbl lead
litecrete cement Sg 1.40. Pompakan 50 bbl spacer Sg 1.20.
Pompakan 40 bbl lead litecrete cement Sg 1.40 (155 sxs cement + 6.5
gal D-047 + 26 gal D-154A + 129.8 gal D-193 + 2.6 gal D-081 + 194.7
gal D-155 + 36.6 lbs D-153 + 146.4 lbs S-001). Aduk dan pompakan
0,00 80 bbl tail litecrete cement Sg 1.60 (260 sxs cement + 2.8 gal D-047 +
69.8 gal D-154A + 223.5 gal D-193 + 279.4 gal D-155 + 95.4 lbs D-
153 + 214.7 lbs S-001 + Cemcade). Drop flexible plug. Displace
cement dgn 184 bbl lumpur Sg 1.02, tidak di peroleh bumping dgn
max pressure 525 psi. Blead off pressure, diperoleh aliran balik 0.6
bbl. Check valve, baik. Drop opening bomb. Naikkan tekanan spi 605
psi untuk buka DSCC, baik. Sirkulasi, diperoleh 10 bbl cement
contamination Sg 1.21.
720,00 0,00 30,00 1426,00 TSK sambil L/D 14 jts HWDP 5" dan 25 jts DP 5". 14 4,0 888,00 0,17 37,00 1440,00 17/01/2010 12:00 : Minggu -168,0 06:01:00
720,00 0,00 30,00 1426,00 Lanjut TSK sambil L/D 13 jts DP 5", kumm 38 jts. 14 2,0 890,00 0,08 37,08 1440,00 17/01/2010 14:00 : Minggu -170,0 07:03:00
720,00 30,00 1426,00 Penyemenenan stage II int (1131.5-700)m menggunakan cement 13b 2,0 892,00 0,08 37,17 1440,00 17/01/2010 16:00 : Minggu -172,0 07:05:00
slurry dgn prosedur: Pompakan 30 bbl spacer Sg 1.20. Pompakan 45
bbl cement slurry Sg 1.65 (165 sxs cement + 1.6 gal D-047 + 57.1 D-
145A + 57.1 D-193 + 276.2 lbs S-001 + 46 lbs D-153).Drop clossing
0,00
plug. Displace cement dgn 147 bbl lumpur Sg 1.02, bumping dgn
pressure 500 psi. Naikkan tekanan spi 1300 psi dan tahan selama 5
mnt untuk tutup DSCC,baik. Blead off pressure, aliran balik 0.6 bbl
indikasi DSCC berhasil di tutup.
720,00 0,00 30,00 1426,00 Lanjut TSK sambil L/D 100 jts DP 5", kumm 138 jts. 14 10,0 902,00 0,42 37,58 1440,00 18/01/2010 02:00 : Senin -182,0 07:15:00
720,00 30,00 1426,00 Lanjut TSK sambil M/U stand up 56 stand up DP 3-1/2" (112 jts), 14 10,0 912,00 0,42 38,00 1440,00 18/01/2010 12:00 : Senin -192,0 07:01:00
0,00
sampel semen lead litecrete Sg 1.40 belum keras.
720,00 30,00 1426,00 Lanjut TSK sambil M/U 10 stand up DP 3-1/2" (kumm 132 jts), 5 stand 14 4,0 916,00 0,17 38,17 1440,00 18/01/2010 16:00 : Senin -196,0 08:05:00
0,00
up HWDP 3-1/2" (10 jts), dan 4 stand up DC 4-3/4" (8 jts).
720,00 0,00 30,00 1426,00 Lanjut TSK, Sampel semen lead litecrete Sg 1.40 belum keras (kumm 14 6,0 922,00 0,25 38,42 1440,00 18/01/2010 22:00 : Senin -202,0 08:11:00
TSK 32 jam).
720,00 0,00 30,00 1426,00 Gantung BOP 13-5/8" x 5k psi. 15a 2,0 924,00 0,08 38,50 1440,00 19/01/2010 00:00 : Selasa -204,0 08:13:00
720,00 0,00 30,00 1426,00 N/U casing slip 7", potong dan ratakan kelebihan casing 7". N/U THS 16 2,0 926,00 0,08 38,58 1440,00 19/01/2010 02:00 : Selasa -206,0 08:15:00
11" x 7-1/16 x 3k psi.
720,00 0,00 30,00 1426,00 Dudukan BOP 13-5/8" 5k psi dan kencangkan sambungan, tidak bisa 15a 3,0 929,00 0,13 38,71 1440,00 19/01/2010 05:00 : Selasa -209,0 08:18:00
karena Rig menggunakan DSAF 13-5/8" x 3k x 7-1/16 x 2k psi. Ganti
DSAF dgn 13-5/8" x 3k x 7-1/16" x 3k psi dan dudukan kembali BOP
13-5/8" x 5k psi.
720,00 0,00 30,00 1426,00 Test BOP 13-5/8" x 5k psi dgn tekanan 1000 psi, bocor pada 15b 1,0 930,00 0,04 38,75 1440,00 19/01/2010 06:00 : Selasa -210,0 08:19:00
sambungan DSAF & THS. Kencangkan sambungan. Test kembali
BOP dgn tekanan 1000 psi/5 mnt, baik.
720,00 0,00 30,00 1426,00 RIH rangkaian TCB 6-1/8" + BHA spi 1130.6 m, jajak DSCC. 6a 4,5 934,50 0,19 38,94 1440,00 19/01/2010 10:30 : Selasa -214,5 08:22:30
720,00 0,00 30,00 1426,00 2a 1,5 936,00 0,06 39,00 1440,00 19/01/2010 12:00 : Selasa -216,0 08:01:00
Bor DSCC dari 1130.6 m spi 1131.5 m dgn GPM/SPP 250/700 psi.
720,00 0,00 30,00 1426,00 Lanjut masuk rangkaian TCB 6-1/8" + BHA dari 1131.5 m spi 1381 m, 2a 1,5 937,50 0,06 39,06 1440,00 19/01/2010 13:30 : Selasa -217,5 09:01:30
jjajak
j p puncak semen.
720,00 0,00 30,00 1426,00 Bor semen dari 1381 spi 1434 m dgn GPM/SPP 250/700 psi. 2a 6,5 944,00 0,27 39,33 1440,00 19/01/2010 20:00 : Selasa -224,0 09:09:00
720,00 0,00 30,00 1426,00 Sirkulasi bersikan lubang. Tes casing 7" dengan tekanan 1000 psi/5 5a 1,5 945,50 0,06 39,40 1440,00 19/01/2010 21:30 : Selasa -225,5 09:09:30
mnt, baik.
720,00 0,00 30,00 1426,00 Cabut rangkaian TCB 6-1/8" + BHA dari 1434 m spi permukaan. 6a 5,5 951,00 0,23 39,63 1440,00 20/01/2010 03:00 : Rabu -231,0 09:16:00
720,00 0,00 30,00 1426,00 Masuk rangkaian Scrapper 7" spi 1434 m. 6a 5,5 956,50 0,23 39,85 1440,00 20/01/2010 08:30 : Rabu -236,5 09:20:30
720,00 0,00 30,00 1426,00 Sirkulasi bersikan lubang, ganti isi lubang dengan CF Sg 1.01. 5b 2,5 959,00 0,10 39,96 1440,00 20/01/2010 11:00 : Rabu -239,0 09:00:00
720,00 0,00 30,00 1426,00 Cabut rangkaian Scrapper 7" dari 1434 m spi 1175 m. 6a 1,0 960,00 0,04 40,00 1440,00 20/01/2010 12:00 : Rabu -240,0 09:01:00
720,00 0,00 30,00 1426,00 Lanjut cabut rangkaian Scrapper 7" dari 1175 m spi permukaan. 6a 4,0 964,00 0,17 40,17 1440,00 20/01/2010 16:00 : Rabu -244,0 10:05:00
720,00 0,00 30,00 1426,00 R/D Top drive. 1b 11,0 975,00 0,46 40,63 1440,00 21/01/2010 03:00 : Kamis -255,0 10:16:00
720,00 0,00 30,00 1426,00 R/U Wireline unit case hole logging Elnusa. 11a 1,0 976,00 0,04 40,67 1440,00 21/01/2010 04:00 : Kamis -256,0 10:17:00
720,00 0,00 30,00 1426,00 Run logging : CBL-CET-VDL-GR int (700-1434) m. Hasil logging 700- 11b 5,0 981,00 0,21 40,88 1440,00 21/01/2010 09:00 : Kamis -261,0 10:22:00
900 m : 25-60 mv, 900-1131 m : 5-25 mv, 1131-1175 m : 5-50 mv,
1175-1190 m : 1-20 mv, 1190-1263 m: 5-40 mv, 1263-1273 m : 5 mv,
1273-1275 m : 5-40 mv, 1275-1358 m : 1-10 mv, 1358-1365 m : 5-22
mv, 1365-1434 m : 1-10 mv.
720,00 0,00 30,00 1426,00 L/D 8 jts DC 4-3/4", 10 jts HWDP 3-1/2", 25 jts DP 3-1/2". 6d 3,0 984,00 0,13 41,00 1440,00 21/01/2010 12:00 : Kamis -264,0 10:01:00
720,00 0,00 30,00 1426,00 Lanjut L/D 107 jts DP 3-1/2", kumm 132 jts. 6d 9,0 993,00 0,38 41,38 1440,00 21/01/2010 21:00 : Kamis -273,0 11:10:00
720,00 0,00 30,00 1426,00 N/D BOP Group 13-5/8" x 5000 psi. N/U Production well head. 15a 4,0 997,00 0,17 41,54 1440,00 22/01/2010 01:00 : Jumat -277,0 11:14:00
Completion 96,00 720,00 4,00 30,00 1426,00 133,00 997,00 5,54 41,54 1440,00
WEEKLY DRILLING REPORT
WELL : TT-28
LOCATION : TTM-SA1
DRILLING - 2009
Doc. No : EP1012/Form/DSpv/06
WEEKLY DRILLING REPORT
Form Rev : 02
DRILL ING DEPARTM ENT
Week 1 Page : 1
Date : 11 Des 2009 s/d 13 Des 2009
DATA CASING, LINER / SCREEN DAN PERFORASI
Ukuran inchi 20 13-3/8
Jenis K-55 K-55
B e r a t ( Lbs/ft ) 94 54,5
Disemen di ( mku ) 28 196
Perforasi
.
11 Desember 2009 28 mku / KCL-Polymer Rig Up 100%. Tajak lokasi TTM-SA1 sebagai Sumur TT-28 jam 00.00 WITA, 11
Jumat 28 mkt 1,05 / 48 / 6 th Desember 2009. Bor Formasi dengan pahat 17-1/2" TCB (RR Type 535J, S/N
Hari = 0 / 5 20000 / 24000 / 0 150142, Nozzle 3x20) + BHA dari 28 m sampai 32. Ljt Bor Formasi dari 32 m
10 / 18 / 5-7 sampai 146 m
0 / 3 / 0,1
12 Desember 2009 197 mku / KCL-Polymer Ljt bor formasi lubang 17-1/2"dr 146 m spi 165 m (GPM/SPP/RPM/WOB/AVG-
Sabtu 197 mkt 1,06 / 52 / 6 Last ROP: 800/500 psi/120/5-10 klbs/5-8). Ljt bor form dr 165 - 197 m (Csg point
Hari = 1 / 6 18000 / 22000 / 0 13-3/8")Sirk bersih, swept-out Hi-vis 30 bblCabut rangk TCB 17-1/2" spi
10 / 23 / 9-15 permukaan,Ada OP 10 klbs @ 81 m. L/D Stab 12-1/4". Msk kembali rangk pht 17-
97 / 3 / 0,1 1/2" Tricone spi dasar 197 m. Sirk bersih sbl naikkan SG ke ECD 1.06 SG, swept
hi-vis 30 bbls, spot hi-vis 30 bbls. Drop totcoCabut rangk pht 17-1/2" Tricone spi
permukaan.Totco survey: 0.5 deg. Per. msk Csg 13-3/8" ( K-55, 54,5 ppf, BTC R-
3)-Check FS & FC dipermukaan baik.
13 Desember 2009 197 mku / KCL-Polymer Msk Csg 13-3/8", K-55,54.5 ppf, BTC R-3 spi162 m. Ljt msk Csg 13-3/8" dr 162 m
Minggu 197 mkt 1,06 / 52 / 6 spi 196 m (shoe). Mixing fluid & Spacer. Pers Penyemenan Csg 13-
Hari = 2 / 7 18000 / 22000 / 0 3/8"Penyemenan Csg 13-3/8" dgn excess 100%:- PJSM.- Flush cmt line dgn 2
10 / 23 / 9-15 bbl air.- Press. test cmt line 2000 psi/10 min, baik.- Pompakan 30 bbl Mud Push
97 / 3 / 0,1 (Spacer)- Jatuhkan bottom plug.- Aduk dan pompakan 168 bbl tail slurry 1.90 SG
(819 sxs semen kelas G + 8 gal D047 + 115 lbs D153 + 409 gal D193 + 123
D145A + 77 bbls S001), Jatuhkan top plug. Dorong cmt slurry dgn 93 bbl lumpur
SG 1.06 spi p tekanan bentur 700 p psi/5 min. Semen tdk spip ppermukaan,, saat
dorong dr 20-70 bbl tdk ada aliran balik. Ablas tekanan, aliran balik 1 bbl, float
baik.TSK. Msk Macaroni 1" u/ jajak semen, puncak semen di 22 m.
14 Desember 2009 197 mku / KCL-Polymer Pers& Penyemenan Top Job 13-3/8",Potong semen klas "G" 60 sak, PJSM, Flush
Senin 197 mkt 1,06 / 52 / 6 cmt line dgn 2 bbl air, Press. test cmt line 2000 psi/10 min, baik, Aduk dan
Hari = 3 / 8 18000 / 22000 / 0 pompakan 12 bbl cement slurry SG 1.9 (60 sxs semen klas "G"+ 0.6 gal D047),
10 / 23 / 9-15 dgn rate 1 bpm/100 psi, pompa 1-2 bbls pertama ada aliran balik & kontaminasi
97 / 3 / 0,1 semen, dr pemompaan 3-12 bbls tdk ada aliran balik,teruskan pompa semen spi
25 bbls, tdk ada aliran balik, Stop pemompaan, cabut macaroni. TSK sbl potong
kelebihan csg 20". Msk macaroni 1" jajak puncak semen di 20 m. Pers utk Top
Job II 13-3/8". Potong semen 160 sak.
Penyemenan Top Job II Csg 13-3/8" : PJSM, Flush cmt line dgn 2 bbl air, Press.
test cmt line 2000 psi/10 min, baik. Aduk dan pompakan 30 bbl cement slurry
SG:1.9 (160 sxs semen klas "G"+ 1 gal D047), dgn rate 1 bpm/100 psi, Semen
keluar sampai permukaan SG:1.85. TSK. Bersihkan semen dalam cellar (semen
keras).
Mitra Kerja :
DD Engineering : -
Mud Logging Unit : Edy S / RP Suranto
Top Drive : Budi
Mud Engineer : Arie M
Cementing Unit : Ady
Mengetahui,
MAN. OPS. DRILLING KTI
Sukardono Utomo
Week 2 Page : 1
Date : 15 Des 2009 s/d 21 Des 2009
.
15 Desember 2009 197 mku / KCL Poly Potong csg 20" (20 cm lebih rendah) dan bersihkan semen utk memudahkan
Selasa 197 mkt 1,06 / 52 / 6 pengelasan BF 13-3/8" x 3000 psi. Potong & ratakan permukaan csg 13-3/8".
Hari = 4 / 9 18000 / 22000 / 0 Install Ring plate. N/U BF 13-5/8" x 3k psi. Las bagian luar & dalam BF 13-5/8" x
10 / 23 / 9-15 3000 psi. Cooling (pendingininan), test hasil pengelesan, bocor bagian dalam. Las
97 / 3 / 0,1 kembali bag dalam BF 13-5/8" 3000 psi. Cooling (pendinginan),test hasil
pengelasan dgn 1500 psi (hand pump by welder), baik. N/U BOP 13-5/8" x 5000
psi + DSAF 13-5/8" 3000 x 5000 psi.Pasang saluran permukaan. Function test
Annular,Pipe ram, HCR OK. Press Test dgn tester cup Annular low/high 500/1500
psi 10 mnt,baik. Pipe ram 500/1500 psi 10 mnt,baik, Press test blind ram 500/1500
10 mnt, baik. Test aliran ke flare,baik,install flow line. N/D Kelly & Swivel.
16 Desember 2009 197 mku / KCL Poly Ljt R/u Top drive (100%), function test (robotic,Low/Hig RPM, Test dgn 2000 psi),
Rabu 197 mkt 1,06 / 52 / 6 OK. Stand up DP 5" 34 stands. Ljt stand up DP 5" 16 stands (kum 50 stds). M/U &
Hari = 5 / 10 24000 / 0 / 120 RIH 12-1/4" PDC, Tag TOC @ 181 m.
10 / 23 / 9-15
0 / 3 / 0,1
17 Desember 2009 290 mku / KCL Poly Ljt bor plug, semen spi kedalaman 192 m. Sirkulasi bersih & Uji tekanselubung
Kamis 290 mkt 1,06 / 52 / 6 1000 psi / 5 mnt, baik. Ljt bor semen & formasi spi kedalaman 200 m. Sirkulasi
Hari = 6 / 11 24000 / 0 / 120 bersih & kondisikan lumpur Sgin/out = 1.06, MOT SG eq = 1.70, baik. Ljt bor
10 / 23 / 9-15 formasi spi kedalaman 259 m. Ljt bor formasi spi kedalaman 290 m.
0 / 3 / 0,1
18 Desember 2009 380.5 mku / KCL Poly Ljt bor formasi spi kedalaman 313 m. Ljt bor formasi spi kedalaman 353 m. Stop
Jumat 380.5 mkt 1,07 / 53 / 5,8 bor, ganti seating valve MP#2 (NPT Rig = 0.5 jam). Ljt bor formasi spi kedalaman
Hari = 7 / 12 30000 / 0 / 200 380 m. Lakukan drill off test dgn perubahan WOB dan RPM, kemajuan hanya
11 / 21 / 5-9 380.5 m (last lith @380m : 10%SST, 10% Shale, 80% CLST). Sirkulasi Bersih &
0 / 4 / 0,2 Swept out hi vis 30 bbls. POOH 12-1/4" PDC + BHA Rotary to surface, L/D
Stabilizer 2 unit, 2 jts DC 8". M/U & RIH 12-1/4" PDC + BHA Rotary spi
kedalaman 96 m.
(Lanjutan)
Minggu : 2 Halaman : 2 SUMUR : TT-28
Tanggal : 15 Des 2009 s/d 21 Des 2009
19 Desember 2009 423 mku / KCL Poly Ljt RIH 12-1/4" PDC + BHA Rotary spi kedalaman 180 m. Perbaikan Pompa : 3
Sabtu 423 mkt 1,09 / 54 / 5,3 pcs dies plug patah MP#1, ganti seating valve MP#2 & MP#3. (NPT Rig = 3.5 jam,
Hari = 8 / 13 29000 / 41000 / 180 kum 4.0 jam). Ljt perbaikan pompa : Ganti 3 pcs dies plug PTO MP#1 (NPT Rig =
18 / 27 / 5-7 11 jam, kum 15 jam). Running Test MP#1, MP#2, MP#3 : SPM#1 90, SPM#2 90,
5 / 5 / 0,7 SPM#3 100, GPM 700, Tekanan 900 psi (NPT Rig = 0.5 jam, kum 15.5 jam). Ljt
RIH 12-1/4" PDC + BHA Rotary spi kedalaman 293 m. Ljt RIH 12-1/4" PDC + BHA
Rotary spi kedalaman 380 m. Sirkulasi bersih di dasar. Ljt bor formasi 380.5 - 423
m (ROP 5 mnt/m, lith 80% coal, 10% CLST, 10%SST).
20 Desember 2009 545 mku / KCL Poly Ljt bor formasi spi kedalaman 447 m (ROP 4 mnt/m, Lith 40% SST, 40% CLST,
Minggu 545 mkt 1,11 / 62 / 5 20% Coal). Ljt bor formasi spi kedalaman 525 m (ROP 9 mnt/m, lith: 20% SST,
Hari = 9 / 14 31000 / 46000 / 180 20% CLST, 60% Coal). Ljt bor formasi spi kedalaman 545 m (ROP 10 mnt/m, lith:
23 / 36 / 8-11 20% SST, 50% CLST, 30% Coal). Perbaikan Pompa : SPM#1 & SPM#2 turun, set
0 / 6 / 0,8 ulang disk clutch MP#1 & MP#2, (NPT Rig = 0.5 jam, kum 16 jam). Sirkulasi
kondisikan lumpur, naikan viscositas (SPM#1 90; SPM#3 90; GPM 450), sambil ljt
perbaikan MP#2, set disk clutch (NPT Rig = 0.5 jam, kum 16.5 jam). POOH 12-
1/4" PDC + BHA Rotary spi shoe @ 197 m, sambil ljt perbaikan MP#2 (disk clutch)
& reposisi engine MP#3 dikarenakan stock 2 pcs V-belt berukuran pendek (NPT
Rig = 2.5 jam, kum 19.5 jam). Ljt perbaikan MP#2 & MP#3, sambil running test
MP#1, 110 SPM, 275 GPM (NPT Rig = 1 jam, kum 20 jam).
21 Desember 2009 602 mku / KCL Poly Ljt perbaikan MP#2 & MP#3, (NPT Rig = 4 jam, kum 24 jam). Ljt perbaikan MP#2
Senin 602 mkt 1,11 / 58 / 5 & MP#3, (NPT Rig = 1.5 jam, kum 25.5 jam). Ljt perbaikan MP#2 (disk clutch),
Hari = 10 / 15 29000 / 41000 / 180 sambil running test MP#1 & MP#3, Debit Max 600 gal/mnt, dgn kombinasi SPM#1
19 / 31 / 6-10 130 & SPM#3 110. (NPT Rig = 2 jam, kum 27.5 jam). RIH 12-1/4" PDC + BHA
0 / 6 / 0,8 Rotary, rangkaian duduk 10 klbs @ 405 m, 412 m (NPT Rig = 0.5 jam, kum 28
jam). Reaming down & Sirkulasi sambil WOP spi kedalaman 545 m, terdapat
rontokan (caving) batubara. Ljt bor formasi kedalaman 545 - 554 m (ROP 10
mnt/m, lith @ 551m; 20% STT, 80% CLST). Ljt bor formasi spi kedalaman 602 m
(ROP 4 mnt/m, lith 80% Coal, 10%CLST, 10% SST).
Mitra Kerja :
DD Engineering : -
Mud Logging Unit : Edy S / RP Suranto
Top Drive : Budi
Mud Engineer : Arie M
Cementing Unit : Ady
Mengetahui,
MAN. OPS. DRILLING KTI
SUKARDONO UTOMO
Week 3 Page : 1
Date : 22 Des 2009 s/d 28 Des 2009
.
22 Desember 2009 719 mku / KCL Poly Ljt bor formasi spi kedalaman 622 m (ROP 8 mnt/m, lith 70% CLST, 30% Coal). Ljt
Selasa 719 mkt 1,11 / 54 / 5 bor formasi spi kedalaman 679 m (ROP 10 mnt/m, Lith 60% SST, 40% CLST).
Hari = 11 / 16 31000 / 42000 / 180 Perbaikan Pompa : Flexible Joint 4" Suction line Charging Pump#1 bocor, ganti
19 / 28 / 6-9 bongkar pasang dari Charging Pump#2, sambil sirkulasi dgn MP#3 300 GPM (NPT
0 / 5 / 0,8 Rig = 1.5 jam, kum 29.5 jam). Ljt bor formasi spi kedalaman 719 m (ROP 7 mnt/m,
lith: 50% Coal, 30% CLST, 20% SST).
23 Desember 2009 796 mku / KCL Poly Ljt bor formasi spi kedalaman 738 m (ROP 11 mnt/m, lith: 70% CLST, 30% Coal).
Rabu 796 mkt 1,11 / 56 / 5 Ljt bor formasi spi kedalaman 779 m (ROP 16 mnt/m, lith: 50% CLST, 40% SST,
Hari = 12 / 17 31000 / 41000 / 180 10% Coal). Ljt bor formasi spi kedalaman 796 m (ROP 11 mnt/m, lith: 20% SST,
18 / 29 / 7-9 30% CLST, 50% Coal). Sirkulasi sambil ganti rubber piston & seating valve MP#3.
0 / 5 / 0,7 Running pompa msh belum normal, diputuskan utk POOH 12-1/4" PDC + BHA
Rotary spi shoe dan lakukan perbaikan pompa : MP#2 (dies plug PTO & bearing)
dan ganti ukuran liner 6" MP#1, 2, 3 (NPT Rig =2 jam, kum 31.5 jam). POOH 12-
1/4" PDC + BHA Rotary spi kedalaman 467 m (NPT Rig = 3.5 jam, kum 35 jam).
24 Desember 2009 796 mku / KCL Poly Ljt POOH 12-1/4" PDC + BHA Rotary spi shoe @ 197m (NPT Rig = 3 jam, kum 38
Kamis 796 mkt 1,11 / 56 / 5 jam). Ljt perbaikan pompa : ganti ukuran liner 6" MP#1, 2, 3 & dies plug PTO
Hari = 13 / 18 31000 / 41000 / 180 MP#2 patah (NPT Rig = 1 jam, kum 39 jam). Ljt perbaikan pompa : (1) Ganti
17 / 30 / 7-9 ukuran liner 6" MP#1, 2, 3, OK. (2) Setting ulang disk clutch PTO MP#1, OK. (3)
0 / 5 / 0,6 Ganti dies plug PTO MP#2, disk plate patah, sdg dibubut (NPT Rig = 11.5 jam,
kum 50.5 jam). Running test MP#1 & 3, SPM#1 120, SPM#3 120, P 1100 psi,
GPM 700, selama 1 jam. Sambil tunggu bearing pillow & disk plate bubutan (NPT
Rig = 1 jam, kum 51.5 jam). Ljt perbaikan pompa: disk clutch & disk plate MP#2,
sambil tunggu pillow bearing MP#2 (NPT Rig = 7.5 jam, kum 59 jam).
25 Desember 2009 796 mku / KCL Poly Ljt perbaikan pompa; disk clutch & disk plate MP#2, sambil tunggu pillow bearing
Jumat 796 mkt 1,14 / 58 / 4,8 MP#2 (NPT Rig = 4 jam, kum 63 jam). RIH 12-1/4" PDC + BHA Rotary, rangkaian
Hari = 14 / 19 30000 / 40000 / 180 duduk 10 klbs @ 313 m dan setiap kemajuan 1 jt. Reaming down spi kedalaman
16 / 32 / 7-10 600 m, cutting yg keluar berupa rontokan coal. Sambil ljt perbaikan MP#2 (pillow
0 / 6 / 0,4 bearing) & MP#3 (V-belt kendur & hose airflex bocor). (NPT Rig = 12 jam, kum 75
jam). Ljt reaming down spi kedalaman 630 m, sambil running test MP#2, OK. (NPT
Rig = 1 jam, kum 76 jam). Ljt reaming down spi kedalaman 726 m (NPT Rig = 7
jam, kum 83 jam).
(Lanjutan)
Minggu : 3 Halaman : 2 SUMUR : TT-28
Tanggal : 22 Des 2009 s/d 28 Des 2009
26 Desember 2009 856 mku / KCL Poly Ljt reaming down spi kedalaman 776 m (NPT Rig = 4 jam, kum 87 jam). Ljt
Sabtu 856 mkt 1,14 / 58 / 4,8 reaming down spi kedalaman 796 m (NPT Rig = 1 jam, kum 88 jam). Sirkulasi
Hari = 15 / 20 30000 / 40000 / 180 Bersih & Swept out hi vis 30 bbls (NPT Rig = 1 jam, kum 89 jam). Ljt bor formasi
16 / 32 / 7-10 spi kedalaman 834 m (ROP 13 mnt/m, Lith 80% SST, 20% CLST). Ljt bor formasi
0 / 6 / 0,4 spi kedalaman 856 m (ROP 28 mnt/m, lith 20% Shale, 20% Coal, 60% SST).
27 Desember 2009 983 mku / KCL Poly Ljt bor formasi spi kedalaman 864 m (ROP 18 mnt/m, lith 70% SST, 30% Shale).
Minggu 983 mkt 1,14 / 58 / 5 Ljt bor formasi spi kedalaman 902 m. Sirkulasi sambil perbaikan Pompa : MP#2
Hari = 16 / 21 30000 / 39000 / 140 (SPM naik turun, ganti fuel pump), MP#3 (SPM turun). Running SPM#1 110 &
18 / 34 / 9-12 SPM#3 110, max debit 650 GPM. (NPT Rig = 1 jam, kum 90 jam). Ljt bor formasi
0 / 6 / 0,3 spi kedalaman 911 m, (DP screen putus & est tertinggal di HWDP). Sirkulasi,
tekanan 1500 psi / 700 GPM, normal. Ljt bor formasi spi kedalaman 930 m (ROP
11 mnt/m, lith @ 921m: 70% SST, 30% Shale). Ljt bor formasi spi kedalaman 983
m (ROP 11 mnt/m, Lith 60% Shale, 40% SST).
28 Desember 2009 1124 mku / KCL Poly Ljt bor formasi spi kedalaman 1008 m (ROP 9 mnt/m, lith 50% SST, 10% Shale,
Senin 1124 mkt 1,15 / 57 / 5 40% Coal). Ljt bor formasi spi kedalaman 1068 m (ROP 16 mnt/m, lith 70% SST,
Hari = 17 / 22 31000 / 41000 / 140 30% Shale). Perbaikan Top Drive : ganti lower kelly cock (washout). Cabut
17 / 34 / 11-15 rangkaian spi kedalaman 1047 m, pasang topi sirkulasi, swept out hi vis 30 bbls &
0 / 7 / 0,3 lanjut sirkulasi sambil perbaikan. Running RPM 170 high, OK. Pressure test tidak
bisa dilakukan, actuator valve tdk bisa menutup (NPT Rig = 4.5 jam. Kum 94.5
jam). Ljt bor formasi spi kedalaman 1124 m (ROP 5.73 mnt/m. lith 10% Coal, 20%
Shale, 70% SST).
Mitra Kerja :
DD Engineering : -
Mud Logging Unit : Edy S / RP Suranto
Top Drive : Budi
Mud Engineer : Arie M
Cementing Unit : Ady
Mengetahui,
MAN. OPS. DRILLING KTI
SUKARDONO UTOMO
Week 4 Page : 1
Date : 29 Des 2009 s/d 04 Jan 2010
.
29 Desember 2009 1162 mku / KCL Poly Ljt bor formasi spi kedalaman 1141 m (ROP 6 mnt/m, lith 30% SST, 70% Shale).
Selasa 1162 mkt 1,14 / 57 / 5 Ljt bor formasi spi kedalaman 1162 m (ROP 12 mnt/m, lith 40% Shale, 60 SST).
Hari = 18 / 23 30000 / 41000 / 140 Indikasi tekanan naik 2500 psi, normal 1500 psi, string buntu. POOH 12-1/4" PDC
18 / 33 / 11-16 + BHA Rotary spi kedalaman 123 m. OP 10-15 klbs @ 1116, 989, 960, 738 m. Ljt
0 / 6 / 0,3
03 POOH 12-1/4" PDC + BHA Rotary spi permukaan, terdapat potongan DP Screen
plate lingkaran ukuran 2 inch di atas Totco Ring. RIH 12-1/4" PDC + BHA Rotary
spi kedalaman 583 m, rangkaian duduk 10klbs @ 432m, 465m, 525m. Reaming
down interval 432 - 448m, 465 - 486m, 525 - 544m.
30 Desember 2009 1188 mku / KCL Poly RIH 12-1/4" PDC + BHA Rotary spi kedalaman 1114m, duduk 15 klbs. Washdown
Rabu 1188 mkt 1,21 / 63 / 5 & work on pipe interval 1114 - 1140 m, OK. Reaming down interval 1140 - 1162 m,
Hari = 19 / 24 29000 / 35000 / 140 rangkaian duduk 10 klbs. Ljt bor formasi spi kedalaman 1188 m (Csg Point 9-5/8").
18 / 36 / 14-19 (ROP 14 mnt/m, Lith 80% Shale, 10% Coal, 10% SST). Sirkulasi kondisikan
0 / 8 / 0,2 lumpur, naikan berat sebesar ECD 1.18 SG. Swept out hi vis 30 bbls & sirkulasi
bersih. Short trip, POOH 12-1/4" PDC + BHA Rotary spi kedalaman 564 m. OP 15
klbs @ 1013, 774, 754 m. Ljt short trip, POOH 12-1/4" PDC + BHA Rotary spi shoe
@ 197 m. Sirkulasi bersih. RIH 12-1/4" PDC + BHA Rotary spi kedalaman 548 m,
duduk 10 klbs. Washdown interval 548 - 564 m. Ljt RIH 12-1/4" PDC + BHA Rotary
spi kedalaman 1174 m, duduk 15 klbs. Reaming down interval 1174 - 1182 m.
31 Desember 2009 1188 mku / KCL Poly Lanjut reaming down interval 1182 - 1188 m, sambil sirkulasi naikan SG 1.21
Kamis 1188 mkt 1,21 / 63 / 5 (ECD). Swept out hi vis 30 bbls & spot hi vis 30 bbls di dasar. Jatuhkan Totco
Hari = 20 / 25 29000 / 35000 / 140 Survey. POOH 12-1/4" PDC + BHA Rotary spi kedalaman 815 m. Ljt POOH 12-
18 / 36 / 14-19 1/4" PDC + BHA Rotary spi permukaan, Totco Survey 1.5 deg (Dull Grading 12-
0 / 8 / 0,2 1/4" PDC : 0/ 6/ CT/ G/ X/ X/ NO/ TD). M/U & RIH 12-1/4" PDC (Open Nozzle) +
BHA Rotary spi kedalaman 1170 m, duduk 10klbs. Reaming down spi kedalaman
1188 m. Sirkulasi bersih, swept out hi vis 30 bbls & Spot 30 bbls hi vis di dasar.
POOH 12-1/4" PDC (Open Nozzle) + BHA Rotary spi kedalaman 133 m, OP 15
klbs @ 1139 m.
01 Januari 2010 1188 mku / KCL Poly Ljt POOH 12-1/4" PDC (Open Nozzle) + BHA Rotary spi permukaan. Persiapan &
Jumat 1188 mkt 1,23 / 58 / 5 RIH logging #1 (DLL-BHC-MSFL-GR). Run Logging #1 (DLL-BHC-MSFL-GR). Ljt
Hari = 21 / 26 29000 / 35000 / 140 run logging#1 (DLL-BHC-MSFL-GR). Interval log 700 - 1183.1 m. Persiapan & RIH
18 / 35 / 13-18 logging #2 (LDL-CNL-GR). Run Logging #2 (LDL-CNL-GR), Interval log 700 -
0 / 9 / 0,2 1185.5 m. R/D Wireline Elnusa. Round Trip, M/U & RIH 12-1/4" PDC (open
Nozzle) + BHA Rotary spi kedalaman 718 m. Ljt round Trip, M/U & RIH 12-1/4"
PDC (open Nozzle) + BHA Rotary spi kedalaman 1173 m, duduk 15 klbs.
Washdown spi kedalaman 1180 m. Sirkulasi kondisikan lumpur SG 1.23 (ECD).
Swept out hi vis 30 bbls & spot hi vis 30 bbls di dasar. POOH 12-1/4" PDC (Open
Nozzle) + BHA Rotary spi kedalaman 352 m.
(Lanjutan)
Minggu : 4 Halaman : 2 SUMUR : TT-28
Tanggal : 29 Des 2009 s/d 04 Jan 2010
02 Januari 2010 1188 mku / KCL Poly Ljt POOH 12-1/4" PDC (Open Nozzle) + BHA Rotary spi permukaan & L/D 4 jts
Sabtu 1188 mkt 1,23 / 60 / 5,8 DC 8". Persiapan masuk casing & handling tools. RIH Casing 9-5/8" K55 36# R3
Hari = 22 / 27 29000 / 35000 / 140 spi kedalaman 1176 m, duduk 15 klbs. Usaha masuk lebih dalam dengan sirkulasi
19 / 36 / 14-19 (650 GPM / P 1000 psi), turunkan secara bertahap spi 40 klbs, tekanan normal
0 / 9 / 0,2 1000 psi, shoe @1186 m; Collar @1162.95 m. Sirkulasi bersih di dasar. M/U
Cementing Head & Cementing Line. Sirkulasi kondisikan lumpur, turunkan YP.
PJSM, Flush line 5 bbls, Pressure Test 2000 psi/5mnt. Pompakan 50 bbls Spacer
1.4 SG (Mud Push 2100 gal; D020 275 lbs), jatuhkan bottom plug. Pompakan
134.5 bbls Lead 1.65 SG (560 sxs semen, D124 5292 lbs; D047 5.5 mT; D153 155
lbs; D145A 138 gal; D193 221 gal; S001 934 lbs) & 277.13 bbls Tail 1.9 SG (1600
sxs semen, D047 14.362 mT; D153 203 lbs; D145A 215.4 gal; D193 934 gal, S001
405 lbs). Jatuhkan top plug.
03 Januari 2010 1188 mku / KCL Poly Ljt Cementing Jobs Csg 9-5/8" : dorong semen dengan 295 bbls lumpur,
Minggu 1188 mkt 1,19 / 49 / 5,4 pemompaan ke 240 bbls, tidak ada aliran balik. Ljt pompa spi 295 bbls, tdk
Hari = 23 / 28 19000 / 29000 / 140 tercapai tekanan bentur. Flushing line dari kontaminasi semen. TSK (Tunggu
13 / 26 / 11-14 Semen Keras). Lanjut TSK. Jajak puncak semen di annulus casing 13-3/8" - 9-
0 / 7 / 0,1 5/8", TOC 9 m. N/D Cementing Head & Treating Line. Gantung BOP Group 13-5/8
x 5K, & Lakukan Sack Jobs dengan 2 sxs semen. Pasang Slip Hanger & Potong
Casing 9-5/8". N/U Wellhead Sec B (13-5/8" x 11" x 3 K). N/U DSAF 11" x 3K,
Riser Spool 11" x 13-5/8" x 3 K, Drilling Spool 13-5/8" x 3K x 5K, BOP Group 13-
5/8" x 5K, & Bell Nipple. Function test Annular, Pipe ram, HCR OK. (NPT Rig = 0.5
Jam, kum 96 jam). Perbaikan Top Drive : Ganti Actuator Valve, OK. (NPT Rig = 1
Jam, kum 97 jam). Press Test dgn tester cup Annular 500/1000 psi 10 mnt, baik.
Pipe ram 500/1000 psi 10 mnt,baik. (NPT Rig = 1 jam, kum 97.5 jam). Stand up
DP 5" tambahan, sebanyak 2 jts.
04 Januari 2010 1026 mku / KCL Poly Ljt stand up DP 5" tambahan sebanyak 28 jts kum 30 jts. Ljt stand up DP 5",
Senin 1026 mkt 1,08 / 42 / 6,8 tambahan sebanyak 10 jts kum 40 jts. M/U & RIH 8-1/2" PDC (Open Nozzle) +
Hari = 24 / 29 12000 / 22000 / 200 BHA Rotary, tag TOC @ 1125 m. Tes tekanan selubung 1000 psi/10 mnt, baik. Ljt
8 / 21 / 7-9 bor plug, semen shoe track spi kedalaman 1170 m. Ljt bor plug, semen shoe track
0 / 4 / 0,1 spi kedalaman 1180 m. Tes tekanan selubung 1000 psi/10 mnt, baik. Ljt bor
semen, float shoe, formasi spi kedalaman 1192 m. Sirkulasi kondisikan lumpur
Sgin/out = 1.08. POOH 8-1/2" PDC (Open Nozzle)spi shoe @ 1186 m. MOT SG
eq 1.50. Ljt bor formasi spi kedalaman 1206 m (ROP 6 mnt/m, lith 70% Shale,
30% SST)
Mitra Kerja :
DD Engineering : -
Mud Logging Unit : Edy S / RP Suranto
Top Drive : Alex Iskandar
Mud Engineer : Arie M
Cementing Unit : Ady/ Ricky Ferdinand
Mengetahui,
MAN. OPS. DRILLING KTI
SUKARDONO UTOMO
Week 5 Page : 1
Date : 05 Jan 2010 s/d 11 Jan 2010
DATA CASING, LINER / SCREEN DAN PERFORASI
Ukuran inchi 20 13-3/8 9-5/8
Jenis K-55 K-55 K-55
B e r a t ( Lbs/ft ) 94 54,5 36
Disemen di ( mku ) 28 196 1186
Perforasi
.
05 Januari 2010 1309 mku / Water Ljt bor formasi spi kedalaman 1225 m (ROP 5 mnt/m, lith 60% Shale, 40% SST).
Selasa 1309 mkt 1,01 / 0 / 0 Ljt bor formasi spi kedalaman 1267 m. Perbaikan Top Drive : Seal Reversed
Hari = 25 / 30 0/0/0 Torque bocor (NPT Rig = 1 Jam, kum 98 jam). Ljt bor formasi spi kedalaman 1268
0 / 0 / 0-0 m (ROP 10 mnt/m, Lith: 80% SST, 20% Shale), Loss Total. Combat loss#1 : spot
0/0/0 60 ppb LCM (Kwikseal M-C) 50 bbls, aliran balik normal. Ljt bor formasi spi
kedalaman 1269 m ((ROP 6 mnt/m,, lith: 80% SST,, 20% Shale). ) Ljt
j blind drilling
g spi
p
kedalaman 1276 m (tidak ada aliran balik). Combat loss#2 : spot 60 ppb LCM
(Kwikseal M-C) 100 bbls, tdk ada aliran balik. POOH 8-1/2" PDC (Open Nozzle)spi
shoe @ 1186 m. Tunggu Air , sambil Mixing LCM (NPT Tunggu Air = 2.5 jam). RIH
8-1/2" PDC (Open Nozzle) + BHA Rotary spi kedalaman 1276 m. Combat loss#3 :
Campuran 40 ppb LCM (CaCO3 M-C) 280 bbls kedalaman sistem, sambil ljt blind
drilling spi kedalaman 1295 m, tidak ada aliran balik. Combat loss#4 : spot 60 ppb
LCM (Kwikseal M-C), 100 bbls. POOH 8-1/2" PDC (Open Nozzle)spi shoe @ 1186
m. Tunggu Air , sambil Mixing LCM (NPT Tunggu Air = 1 jam, kum 3.5 jam).
06 Januari 2010 1309 mku / Water Ljt Tunggu Air , sambil Mixing LCM. RIH 8-1/2" PDC (Open Nozzle) + BHA Rotary
Rabu 1309 mkt 1,01 / 0 / 0 spi kedalaman 1295 m. Combat loss#5 : Campuran 40 ppb LCM (CaCO3 M-C)
Hari = 26 / 31 0/0/0 300 bbls kedalam sistem, sambil ljt blind drilling spi kedalaman 1309 m, tidak ada
0 / 0 / 0-0 aliran balik. Combat loss#6 : spot 50 ppb LCM (Kwikseal M-C) 100 bbls, tidak ada
0/0/0 aliran balik. POOH 8-1/2" PDC spi permukaan. RIH ROE spi kedalaman 859 m. Ljt
RIH ROE spi kedalaman 1186 m. Ljt mixing semen karbonat. Ljt RIH ROE spi
kedalaman 1308 m. M/U Circulating head & treating line. PJSM, flush line,
pressure test 2500 psi/10', OK. Pompakan 20 bbls water ahead, 50 bbls cement
carbonat SG 1.60 (125 sxs semen + add). Dorong dengan 60 bbls air. POOH ROE
spi kedalaman 1000 m. Pompakan 50 bbls cement carbonat SG 1.60 (125 sxs
semen + add). Dorong dengan 10 bbls air pertama, ada aliran balik. Ljt dorong
dengan air spi 50 bbls (aliran balik normal). POOH ROE spi kedalaman 800 m.
Sirkulasi keluar kontaminasi semen.
07 Januari 2010 1309 mku / Water POOH ROE spi permukaan. M/U & RIH 8-1/2" PDC + BHA spi kedalaman 505 m.
Kamis 1309 mkt 1,01 / 0 / 0 Lanjut TSK. Lanjut RIH 8-1/2" PDC + BHA dari 505 m spi 824 m, jajak puncak
Hari = 27 / 32 0/0/0 semen. Bor semen dari 824 m spi 1055 m dengan GPM/SPP = 550/700 psi,
0/0/- ROPavg = 1.80. Observasi, tidak ada loss.
0/0/0
08 Januari 2010 1372 mku / Water Bor semen dari 1055 m spi 1309 m dengan GPM/SPP = 450-550/600-700 psi,
Jumat 1372 mkt 1,01 / 0 / 0 ROPavg = 1.85. Sirkulasi bersikan lubang, swept out 30 bbl hi-vis. Observasi,
Hari = 28 / 33 0/0/0 tidak ada loss. Lanjut bor formasi dari 1309 m spi 1329 m dengan GPM/SPP =
0/0/- 500/600 psi, ROPavg 2.5 mpm, Lithologi 100% Sand. Terjadi loss total di 1329 m.
0/0/0 Blind drilling formasi dari 1329 m spi 1372 m, tidak ada aliran. Spot 60 bbl LCM-7
(Kwikseal + CaCO3) 60 pbb, tidak ada aliran.
(Lanjutan)
Minggu : 5 Halaman : 2 SUMUR : TT-28
Tanggal : 05 Jan 2010 s/d 11 Jan 2010
09 Januari 2010 1372 mku / KCL Poly Cabut rangkaian PDC 8-1/2" + BHA dari 1372 m spi permukaan. Masuk rangkaian
Sabtu 1372 mkt 1,01 / 0 / 0 open end spi 1370 m. Sirkulasi kondisikan lumpur, tidak ada aliran. Penyemenan
Hari = 29 / 34 0/0/0 karbonat plug balance #2 untuk combat loss int (1372-1309) m dengan prosedur :
0/0/- PJSM. Mixing 60 bbl cement slurry SG 1.60. M/U cementing head, test cementing
0/0/0 line 2000 psi/5 mnt baik. Pompakan 20 bbl water ahead. Pompakan 60 bbl cement
slurry SG 1.60 (125 sx semen + add). Displace cement slurry dengan 62.5 bbl air,
setelah displace 48 bbl diperoleh aliran. Cabut rangkaian open end, rangkaian
stuck. Cabut rangkaian dengan WOP 0 - 115 ton, tidak berhasil. Putar rangkaian,
tidak bisa. Cabut rangkaian dengan WOP 0 - 115 ton sambil pompakan air dengan
GPM/SPP 125/550 psi, rangkaian berhasil dicabut (berat rangkaian open end 55
ton, over pull 60 ton). Cabut rangkaian open end spi 985 m. Sirkulasi lurus,
diperoleh kontaminasi semen. Lanjut cabut rangkaian spi permukaan. Masuk
rangkaian PDC 8-1/2" + BHA spi 1141 m, gantung rangkaian. TSK.
10 Januari 2010 1411 mku / KCL Poly Lanjut TSK, sampel semen belum keras. Lanjut masuk rangkaian PDC 8-1/2" +
Minggu 1411 mkt 1,01 / 0 / 0 BHA dari 1141 m spi 1270 m, jajak puncak semen. Bor semen dari 1270 m spi
Hari = 30 / 35 0/0/0 1372 m dengan GPM/SPP : 500/600 psi. Sirkulasi bersikan lubang, swept out 30
0/0/- bbl hi-vis. Observasi, loss stat : 0 bpm. Bor formasi dari 1372 m spi 1411 m
0/0/0 dengan GPM/SPP: 500/600 psi, ROPavg: 9.0 mpm, litologi shale 100%. Terjadi
loss total di 1411 m.
11 Januari 2010 1440 mku / KCL Poly Blind drilling dari 1411 m spi TD di 1430 m, tidak ada aliran. Spot 50 bbl LCM-8
Senin 1440 mkt 1,01 / 0 / 0 (kwikseal+CaCO3) 60 ppb. Cabut rangkaian spi 1305 m. Sirkulasi, aliran
Hari = 31 / 36 0/0/0 intermittent. Masuk rangkaian spi 1430 m. Lanjut blind drilling dari 1430 m spi 1440
0/0/- m (TD), tidak ada aliran. Spot 60 bbl LCM-9 (kwikseal+CaCO3) 60 ppb. Cabut
0/0/0 rangkaian spi 1305 m. Sirkulasi, aliran normal. Masuk rangkaian spi 1430 m.
Sirkulasi di dasar, swept out 30 bbl hi-vis. Observasi, loss stat 0.1 bpm. Selama
sirkulasi keluar cutting shale dan batubara. Spot 40 bbl LCM-10 (diaseal-m+air) 50
ppb. Observasi, loss stat 0.5 bpm. Cabut rangkaian PDC 8-1/2" + BHA dari 1440
m spi permukaan. Masuk rangkaian open end dari permukaan spi 1178 m.
Mitra Kerja :
DD Engineering : -
Mud Logging Unit : Edy S / RP Suranto
Top Drive : Alex Iskandar
Mud Engineer : Arie M
Cementing Unit : Ady/ Ricky Ferdinand/ Arie Wibowo
Mengetahui,
MAN. OPS. DRILLING KTI
SUKARDONO UTOMO
Week 6 Page : 1
Date : 12 Jan 2010 s/d 18 Jan 2010
.
12 Januari 2010 1440 mku / Water Ganti elevator link,, lanjut
j masuk rangkaian
g open
p end dari 1178 m spi
p 1438.5 m.
Selasa 1440 mkt 1,01 / 0 / 0 Sirkulasi kondisikan lumpur, aliran keluar. Penyemenan karbonat plug balance #3
Hari = 32 / 37 0/0/0 untuk combat loss int (1372-1309) m. TSK sambil vakum sumur. Cabut rangkaian
0 / 0 / 0-0 open end dari 1091 m spi permukaan. Ganti elevator link. Masuk rangkaian PDC 8-
0/0/0 1/2" + BHA spi 1160 m, sirkulasi. Gantung rangkaian. Lanjut TSK, sampel semen
belum keras.
13 Januari 2010 1440 mku / Water Lanjut TSK. Lanjut masuk rangkaian PDC 8-1/2" + BHA dari 1160 m spi 1252 m,
Rabu 1440 mkt 1,01 / 0 / 0 jajak puncak semen. Bor semen dari 1252 m spi 1295 m dgn GPM/SPP: 500/600
Hari = 33 / 38 0/0/0 psi, Top drive tidk dapat berputar. Sirkulasi, observasi loss stat 0 bpm. Perbaikan
0 / 0 / 0-0 DC power pin drill panel Top drive, baik. Lanjut bor semen dari 1295 m spi 1353 m
0/0/0 dgn GPM/SPP : 500/600 psi. Observasi loss stat 0.3 bpm. Lanjut bor formasi dari
1353 m spi 1440 m dgn GPM/SPP : 500/600 psi. Observasi loss stat 0.07 bpm.
Sirkulasi, swept out 30 bbl hi-vis. Cabut rangkaian PDC 8-1/2" + BHA dari 1440 m
spi 1350 m. Spot 40 bbl LCM-11 (Diaseal-M + Air) 50 ppb.
14 Januari 2010 1440 mku / Water Lanjut cabut rangkaian PDC 8-1/2" + BHA dari 1350 m spi 1180 m. Sirkulasi
Kamis 1440 mkt 1,01 / 0 / 0 tunggu reaksi LCM. Masuk rangkaian PDC 8-1/2" + BHA dari 1180 m spi 1440 m.
Hari = 34 / 39 0/0/0 Sirkulasi, swept out 30 bbl hi-vis. Observasi loss stat 0.05 bpm. Ganti isi lubang
0/0/- dgn salinity 25000 ppm. Cabut rangkaian PDC 8-1/2" + BHA dari 1440 m spi
0/0/0 permukaan. Run logging DLL-BHC-MSFL-GR-SP-CALS spi 1274 m,rangkaian
duduk dari 1270-1274 m. Indikasi lubang wash out, ketika bor formasi loss total di
1268 m. Cabut logging tool spi permukaan. Masuk rangkaian PDC 8-1/2" + BHA
spi 1440 m, reaming down dan reaming up dari 1235 m spi 1440 m. Sirkulasi
bersikan lubang, swept out 30 bbl hi-vis. Cabut rangkaian PDC 8-1/2" + BHA dari
1440 m spi 1132 m
15 Januari 2010 1440 mku / KCl Polymer Lanjut cabut rangkaian PDC 8-1/2" + BHA dari 1132 m spi permukaan. R/U
Jumat 1440 mkt 1,02 / 0 / 0 wireline logging unit Elnusa. Run logging DLL-BHC-MSFL-GR-SP-CALS int 1168-
Hari = 35 / 40 0/0/0 1440 m, skala 1:200 dan 1:1000. Run logging LDL-CNL-GR-CALS int 1168-1440
0/0/- m, skala 1:200 dan 1:1000. Masuk rangkaian PDC 8-1/2" + BHA spi 1440 m.
0/0/0 Sirkulasi bersikan lubang, swept out dan spot 60 bbl hi-vis. Observasi loss stat 0
bpm, drop totco. Cabut rangkaian PDC 8-1/2" + BHA dari 1440 m spi permukaan.
L/D 12 jts 6-1/4" DC. Totco survey 2 deg. Bit dull grading : 0-
1/WT/OT/X/1/16/NO/TD, total bit hours 30.5 jam.
(Lanjutan)
Minggu : 6 Halaman : 2 SUMUR : TT-28
Tanggal : 12 Jan 2010 s/d 18 Jan 2010
16 Januari 2010 1440 mku / KCl Polymer Persiapan masuk casing 7". Run casing 7" K-55 23 ppf BTC R3 dari permukaan
Sabtu 1440 mkt 1,02 / 0 / 0 spi FS di 1439.0 m, FC di 1414.9 m, dan DSCC di 1131.5 m. Penyemenan casing
Hari = 36 / 41 0/0/0 7" dgn 2 stage, open hole excess 350%. Stage I int (1440-1131.5)m
0/0/- menggunakan litecrete cement dgn prosedur : PJSM. Test cemtng line 2500 psi/5
0/0/0 mnt,baik. Batcth mix 40 bbl lead litecrete cement Sg 1.40. Pompakan 50 bbl
spacer Sg 1.20. Pompakan 40 bbl lead litecrete cement Sg 1.40 (155 sxs cement
+ add). Aduk dan pompakan 80 bbl tail litecrete cement Sg 1.60 (260 sxs cement +
add). Drop flexible plug. Displace cement dgn 184 bbl lumpur Sg 1.02, tidak di
peroleh bumping dgn max pressure 525 psi. Blead off pressure, diperoleh aliran
balik 0.6 bbl. Check valve, baik. Drop opening bomb. Naikkan tekanan spi 605 psi
untuk buka DSCC, baik. Sirkulasi, diperoleh 10 bbl cement contamination Sg 1.21.
TSK sambil L/D 14 jts HWDP 5" dan 25 jts DP 5".
17 Januari 2010 1440 mku / KCl Polymer Lanjut TSK sambil L/D 13 jts DP 5", kumm 38 jts. Penyemenenan stage II int
Minggu 1440 mkt 1,02 / 0 / 0 (1131.5-700)m menggunakan cement slurry dgn prosedur: Pompakan 30 bbl
Hari = 37 / 42 0/0/0 spacer Sg 1.20. Pompakan 45 bbl cement slurry Sg 1.65 (165 sxs cement + 1.6
0/0/- gal D-047 + 57.1 D-145A + 57.1 D-193 + 276.2 lbs S-001 + 46 lbs D-153).Drop
0/0/0 clossing plug. Displace cement dgn 147 bbl lumpur Sg 1.02, bumping dgn
pressure 500 psi. Naikkan tekanan spi 1300 psi dan tahan selama 5 mnt untuk
tutup DSCC,baik. Blead off pressure, aliran balik 0.6 bbl indikasi DSCC berhasil di
t t
tutup. L j t TSK sambil
Lanjut bil L/D 100 jts
jt DP 5",
5" kumm
k 138 jts.
jt Lanjut
L j t TSK sambil
bil M/U
stand up 56 stand up DP 3-1/2" (112 jts), sampel semen lead litecrete Sg 1.40
belum keras.
18 Januari 2010 1440 mku / KCl Polymer Lanjut TSK sambil M/U 10 stand up DP 3-1/2" (kumm 132 jts), 5 stand up HWDP 3-
Senin 1440 mkt 1,02 / 0 / 0 1/2" (10 jts), dan 4 stand up DC 4-3/4" (8 jts). Lanjut TSK, Sampel semen lead
Hari = 38 / 43 0/0/0 litecrete Sg 1.40 belum keras (kumm TSK 32 jam). Gantung BOP 13-5/8" x 5k psi.
0/0/- N/U casing slip 7". Potong dan ratakan kelebihan casing 7". N/U THS 11" x 7-1/16
0/0/0 x 3k psi. N/U BOP 13-5/8" x 5k psi. Test 1000 psi/5 mnt, baik. RIH rangkaian TCB
6-1/8" + BHA spi 1130.6 m, jajak DSCC. Bor DSCC dari 1130.6 m spi 1131.5 m
dgn GPM/SPP 250/700 psi.
Mitra Kerja :
DD Engineering : -
Mud Logging Unit : Edy S / RP Suranto
Top Drive : Alex Iskandar
Mud Engineer : Arie M
Cementing Unit : Ady/ Ricky Ferdinand/ Arie Wibowo
Mengetahui,
MAN. OPS. DRILLING KTI
SUKARDONO UTOMO
Week 7 Page : 1
Date : 19 Jan 2010 s/d 21 Jan 2010
.
19 Januari 2010 1440 mku / Completion Fluide Lanjut masuk rangkaian TCB 6-1/8" + BHA dari 1131.5 m spi 1381 m, jajak
Selasa 1440 mkt 1,01 / 0 / 0 puncak semen. Bor semen dari 1381 spi 1434 m dgn GPM/SPP 250/700 psi.
Hari = 39 / 44 0/0/0 Sirkulasi bersikan lubang. Tes casing 7" dengan tekanan 1000 psi/5 mnt, baik.
0 / 0 / 0-0 Cabut rangkaian TCB 6-1/8" + BHA dari 1434 m spi permukaan. Masuk rangkaian
0/0/0 Scrapper 7" spi 1434 m. Sirkulasi bersikan lubang, ganti isi lubang dengan CF Sg
1.01. Cabut rangkaian Scrapper 7" dari 1434 m spi 1175 m.
20 Januari 2010 1440 mku / Completion Fluide Lanjut cabut rangkaian Scrapper 7" dari 1175 m spi permukaan. R/D Top drive.
Rabu 1440 mkt 1,01 / 0 / 0 R/U Wireline unit case hole logging Elnusa. Run logging : CBL-CET-VDL-GR int
Hari = 40 / 45 0/0/0 (700-1434)
(700 1434) m. Hasil logging 700
700-900
900 m : 25
25-60
60 mv, 900
900-1131
1131 m : 5
5-25
25 mv, 1131
1131-
0 / 0 / 0-0 1175 m : 5-50 mv, 1175-1190 m : 1-20 mv, 1190-1263 m: 5-40 mv, 1263-1273 m :
0/0/0 5 mv, 1273-1275 m : 5-40 mv, 1275-1358 m : 1-10 mv, 1358-1365 m : 5-22 mv,
1365-1434 m : 1-10 mv. L/D 8 jts DC 4-3/4", 10 jts HWDP 3-1/2", 25 jts DP 3-1/2".
21 Januari 2010 1440 mku / Completion Fluide Lanjut L/D 107 jts DP 3-1/2", kumm 132 jts. N/D BOP Group 13-5/8" x 5000 psi.
Kamis 1440 mkt 1,01 / 0 / 0 N/U Production well head. Rig RG-750/ JML-3 release TMT 21 Januari 2010,
Hari = 41 / 46 0/0/0 pukul 13.00 WITA. Kegitatan operasi completion sumur TT-28 akan
0/0/- dilanjutkan menggunakan Rig Produksi UBEP Tanjung.
0/0/0
Mitra Kerja :
DD Engineering : -
Mud Logging Unit : Edy S / RP Suranto
Top Drive : Alex Iskandar
Mud Engineer : Arie M
Cementing Unit : Ady/ Ricky Ferdinand/ Arie Wibowo
Mengetahui,
MAN. OPS. DRILLING KTI
SUKARDONO UTOMO
WELL : TT-28
LOCATION : TTM-SA1
DRILLING - 2009
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 1
Well Name TT-28 Type Exploratory Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig ZJ-30/ JML-03 Avg WOB klbs 5-10 AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs 16,41 AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM 100 Daily Cost US 35.888,06
Current MD ft 196,86 Torque lb.ft Cum. Cost US 188.599,03
Progress MD ft 196,86 Stand Pipe Press Psi 500 Daily Mud Cost US 14.596,56
PTMD ft 6.588,25 Flow Rate gpm 800 Cum. Mud Cost US 22.956,69
Spud Date 11-Des-2009 String Weight lbs Day Supervisor ANDY HARAHAP
Release Date Rotating Weight lbs Night Supervisor
Planned Days 30 Total Drilling Time hrs Engineer DIAN PERMANA
Days from Spud Circulating Press psi Geologist
Rig Up 100%. Tajak lokasi TTM-SA1 sebagai Sumur TT-28 jam 00.00 WITA, 11 th Desember 2009. Bor Formasi dengan pahat 17-1/2" TCB (RR Type 535J, S/N 150142,
24 Hours Summary Nozzle 3x20) + BHA dari 28 m sampai 32. Ljt Bor Formasi dari 32 m sampai 146 m
STATUS PAGI: Lanjut Bor formasi dari 146 spi 165 m
Ljt bor formasi lubang 17-1/2" sampai 197 m (set csg 13-3/8" @ 196 m). Sirk bersih. Trip. Sirk brsih, swept out Hi-vis, Spot Hi-vis. Cabut TCB 17-1/2" + BHA sampai
24 Hours Forecast
permukaan. Pers masuk casing 13-3/8"
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
Rig Up 100%. Tajak lokasi TTM-SA1 sebagai Sumur TT-28 jam 00.00 WITA, 11 th
00:00 04:00 4:00 0 104,992 104,992 Drilling Y P 2. Drill Actual Desember 2009. Bor Formasi dengan pahat 17-1/2" TCB (RR Type 535J, S/N 150142,
Nozzle 3x20) + BHA dari 28 m sampai 32
04:00 00:00 20:00 104,992 479,026 374,034 Drilling Y P 2. Drill Actual Ljt Bor Formasi dari 32 m sampai 146 m
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name
PT. PERTAMINA EP 2 SECURITY Time hh:mm
PT. DOWELL SCHLUMBER ANADRILL Slow Speed? y/n
PT. SCHOMI 2 PT TOP DRIVE MARITIM Circulate
PT. ESLOG HOT HED 0 Strokes SPM
PT. JML 13 FMC 0 Pressure psi
PT. USAYANA GS Liner Size in
PT. PATRAKOM 1 Efficiency %
PARAMEDIC 1
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
13-Des-2009 DRIL LING DEPARTME NT
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 2
Well Name TT-28 Type Exploratory Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig ZJ-30/ JML-03 Avg WOB klbs 5-10 AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs 16,41 AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM 100 Daily Cost US 49.091,42
Current MD ft 646,36 Torque lb.ft Cum. Cost US 242.643,64
Progress MD ft 167,33 Stand Pipe Press Psi 500 Daily Mud Cost US 11.148,26
PTMD ft 4.678,71 Flow Rate gpm 800 Cum. Mud Cost US 34.104,95
Spud Date 11-Des-2009 String Weight lbs Day Supervisor ANDY HARAHAP
Release Date Rotating Weight lbs Night Supervisor
Planned Days 30 Total Drilling Time hrs Engineer DIAN PERMANA
Days from Spud Circulating Press psi Geologist
Ljt bor formasi lubang 17-1/2"dr 146 m spi 165 m (GPM/SPP/RPM/WOB/AVG-Last ROP: 800/500 psi/120/5-10 klbs/5-8). Ljt bor form dr 165 - 197 m (Csg point 13-3/8")Sirk
bersih, swept-out Hi-vis 30 bblCabut rangk TCB 17-1/2" spi permukaan,Ada OP 10 klbs @ 81 m. L/D Stab 12-1/4". Msk kembali rangk pht 17-1/2" Tricone spi dasar 197 m. Sirk
24 Hours Summary
bersih sbl naikkan SG ke ECD 1.06 SG, swept hi-vis 30 bbls, spot hi-vis 30 bbls. Drop totcoCabut rangk pht 17-1/2" Tricone spi permukaan.Totco survey: 0.5 deg. Per. msk Csg 13-
3/8" ( K-55, 54,5 ppf, BTC R-3)-Check FS & FC dipermukaan baik. STATUS PAGI: Msk Csg 13-3/8" spi 162 m
24 Hours Forecast Ljt msk Csg 13-3/8" spi dasar (shoe @ 196 m), Sirk, Penyemenan Csg 13-3/8" (excess 100%)
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
2. Drill Actual
Ljt bor formasi lubang 17-1/2"dr 146 m spi 165 m
00:00 04:00 4:00 479,026 541,365 62,339 Drilling Y P
GPM/SPP/RPM/WOB/AVG-Last ROP: 800/500 psi/120/5-10 klbs/5-8
2. Drill Actual
04:00 12:30 8:30 541,365 646,357 104,992 Drilling Y P Ljt bor form dr 165 - 197 m (Csg point 13-3/8")
5. Condition Mud &
12:30 13:00 0:30 646,357 646,357 0 Drilling Y P Sirk bersih, swept-out Hi-vis 30 bbl
6. Trips
13:00 15:30 2:30 646,357 646,357 0 Drilling Y P Cabut rangk TCB 17-1/2" spi permukaan,Ada OP 10 klbs @ 81 m. L/D Stab 12-1/4".
6. Trips
15:30 16:00 0:30 646,357 646,357 0 Drilling Y P Msk kembali rangk pht 17-1/2" Tricone spi 36 m
6. Trips
16:00 18:00 2:00 646,357 646,357 0 Drilling Y P Ljt msk dr 36 m spi dasar 197 m
5. Condition Mud &
Sirk bersih sbl naikkan SG ke ECD 1.06 SG, swept hi-vis 30 bbls, spot hi-vis 30 bbls. Drop
18:00 20:00 2:00 646,357 646,357 0 Drilling Y P
totco
6. Trips
20:00 23:00 3:00 646,357 646,357 0 Drilling Y P Cabut rangk pht 17-1/2" Tricone spi permukaan.Totco survey: 0.5 deg.
12. Run Casing & C
23:00 00:00 1:00 646,357 646,357 0 Drilling Y P Per. msk Csg 13-3/8" ( K-55, 54,5 ppf, BTC R-3)-Check FS & FC dipermukaan baik
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name
PT. PERTAMINA EP 2 SECURITY Time hh:mm
PT. DOWELL SCHLUMBERG ANADRILL Slow Speed? y/n
PT. SCHOMI 2 PT TOP DRIVE MARITIM Circulate
PT. ESLOG HOT HED Strokes SPM
PT. JML 13 FMC Pressure psi
PT. USAYANA GS Liner Size in
PT. PATRAKOM 1 Efficiency %
PARAMEDIC 1
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 3
Well Name TT-28 Type Exploratory Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig ZJ-30/ JML-03 Avg WOB klbs AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM Daily Cost US 33.334,20
Current MD ft 646,36 Torque lb.ft Cum. Cost US 275.977,84
Progress MD ft Stand Pipe Press Psi Daily Mud Cost US 1.229,20
PTMD ft 4.678,71 Flow Rate gpm Cum. Mud Cost US 35.334,15
Spud Date 11-Des-2009 String Weight lbs Day Supervisor ANDY HARAHAP
Release Date Rotating Weight lbs Night Supervisor
Planned Days 30 Total Drilling Time hrs Engineer DIAN PERMANA
Days from Spud Circulating Press psi Geologist
Msk Csg 13-3/8", K-55,54.5 ppf, BTC R-3 spi162 m. Ljt msk Csg 13-3/8" dr 162 m spi 196 m (shoe). Mixing fluid & Spacer. Pers Penyemenan Csg 13-3/8"Penyemenan Csg 13-
3/8" dgn excess 100%:- PJSM.- Flush cmt line dgn 2 bbl air.- Press. test cmt line 2000 psi/10 min, baik.- Pompakan 30 bbl Mud Push (Spacer)- Jatuhkan bottom plug.- Aduk dan
pompakan 168 bbl tail slurry 1.90 SG (819 sxs semen kelas G + 8 gal D047 + 115 lbs D153 + 409 gal D193 + 123 D145A + 77 bbls S001), - Jatuhkan top plug.
- Dorong cmt slurry dgn 93 bbl lumpur SG 1.06 spi tekanan bentur 700 psi/5 min. Semen tdk spi permukaan, saat dorong dr 20-70 bbl tdk ada aliran balik. Ablas tekanan, aliran
24 Hours Summary
balik 1 bbl, float baik.TSK. Msk Macaroni 1" u/ jajak semen, puncak semen di 22 m. STATUS PAGI: Pers& Penyemenan Top Job 13-3/8".
-Potong semen klas "G" 60 sak. PJSM.Flush cmt line dgn 2 bbl air. Press. test cmt line 2000 psi/10 min, baik. Aduk dan pompakan 12 bbl cement slurry SG:1.9 (60 sxs semen
klas "G"+ 0.6 gal D047), dgn rate 1 bpm/100psi,pompa 1-2 bbls pertama ada aliran balik & kontaminasisemen, dr pemompaan 3-12 bbls tdk ada aliran balik,teruskan pompa semen
spi 25 bbls, tdk ada aliran balik.Stop pemompaan, cabut macaroni. TSK (4 jam)
24 Hours Forecast Jajak puncak semen. Top Job II. Potong kelebihan Csg 20". N/U BF 13-5/8" x 3k psi. N/U BOP 13-5/8" x 5k ps
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
12. Run Casing &
00:00 04:00 4:00 646,357 646,357 0 Drilling Y P Msk Csg 13-3/8", K-55,54.5 ppf, BTC R-3 spi 162 m
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name
PT. PERTAMINA EP 2 SECURITY Time hh:mm
PT. DOWELL SCHLUMBER ANADRILL Slow Speed? y/n
PT. SCHOMI 2 PT TOP DRIVE MARITIM Circulate
PT. ESLOG HOT HED Strokes SPM
PT. JML 13 FMC Pressure psi
PT. USAYANA GS Liner Size in
PT. PATRAKOM 1 Efficiency %
PARAMEDIC 1
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report
DRILLING DEPARTM ENT
15-Des-2009
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 4
Well Name TT-28 Type Exploratory Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig ZJ-30/ JML-03 Avg WOB klbs AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM Daily Cost US 81.651,64
Current MD ft 646,36 Torque lb.ft Cum. Cost US 357.629,48
Progress MD ft Stand Pipe Press Psi Daily Mud Cost US 350,00
PTMD ft 4.678,71 Flow Rate gpm Cum. Mud Cost US 35.684,15
Spud Date 11-Des-2009 String Weight lbs Day Supervisor ANDY HARAHAP
Release Date Rotating Weight lbs Night Supervisor
Planned Days 30 Total Drilling Time hrs Engineer DIAN PERMANA
Days from Spud Circulating Press psi Geologist
Pers & Penyemenan Top Job 13-3/8".
-Potong semen klas "G" 60 sak. PJSM.Flush cmt line dgn 2 bbl air.- Press. test cmt line 2000 psi/10 min, baik.- Aduk dan pompakan 12 bbl cement slurry SG:1.9 (60 sxs semen
klas "G"+ 0.6 gal D047), dgn rate1 bpm/100 psi,pompa 1-2 bbls pertama ada aliran balik & kontaminasi semen, dr pemompaan 3-12 bbls tdk ada aliran balik,teruskan pompa
semen spi 25 bbls, tdk ada aliran balik.Stop pemompaan, cabut macaroni. TSK sbl potong kelebihan csg 20" Msk macaroni 1" jajak puncak semen di 20 m. Pers utk Top Job II 13-
24 Hours Summary 3/8". Potong semen 160 sak.Penyemenan Top Job II Csg 13-3/8". PJSM. Flush cmt line dgn 2 bbl air. Press. test cmt line 2000 psi/10 min, baik. Aduk dan pompakan 30 bbl
cement slurry SG:1.9 (160 sxs semen klas "G"+ 1 gal D047), dgn rate 1 bpm/100 psi, Semen keluar sampai permukaan SG:1.85. Bersihkan semen dalam cellar (semen keras).
STATUS PAGI: Potong csg 20" (20 cm lebih rendah) dan bersihkan semen utk memudahkan pengelasan BF 13-3/8" x 3000 psi. Potong & ratakan permukaan csg 13-3/8". Install
Ring plate.N/U BF 13-5/8" x 3k psi.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
Pers& Penyemenan Top Job 13-3/8".
-Potong semen klas "G" 60 sak. PJSM.Flush cmt line dgn 2 bbl air.- Press. test cmt line
2000 psi/10 min, baik.- Aduk dan pompakan 12 bbl cement slurry SG:1.9 (60 sxs
00:00 04:00 4:00 646,357 646,357 0 Drilling Y P 12. Run Casing & semen klas "G"+ 0.6 gal D047), dgn rate 1 bpm/100 psi,pompa 1-2 bbls pertama ada
aliran balik & kontaminasi semen, dr pemompaan 3-12 bbls tdk ada aliran
balik,teruskan pompa semen spi 25 bbls, tdk ada aliran balik.Stop pemompaan, cabut
macaroni.
04:00 08:00 4:00 646,357 646,357 0 Drilling Y P 13. Wait On Ceme TSK sbl potong kelebihan csg 20"
08:00 09:00 1:00 646,357 646,357 0 Drilling N NP 23. Other Msk macaroni 1" jajak puncak semen di 20 m
09:00 12:00 3:00 646,357 646,357 0 Drilling N NP 23. Other Pers utk Top Job II 13-3/8". Potong semen 160 sak
19:00 00:00 5:00 646,357 646,357 0 Drilling N NP 23. Other Bersihkan semen dalam cellar (semen keras)
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name
PT. PERTAMINA EP 2 SECURITY Time hh:mm
PT. DOWELL SCHLUMBER ANADRILL Slow Speed? y/n
PT. SCHOMI 2 PT TOP DRIVE MARITIM Circulate
PT. ESLOG 4 HOT HED Strokes SPM
PT. JML 13 FMC Pressure psi
PT. USAYANA GS Liner Size in
PT. PATRAKOM 1 Efficiency %
PARAMEDIC 1
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report
DRILL IN G DEP ART MEN T
16-Des-2009
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 5
Well Name TT-28 Type Exploratory Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig ZJ-30/ JML-03 Avg WOB klbs AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM Daily Cost US 18.822,38
Current MD ft 646,36 Torque lb.ft Cum. Cost US 376.451,86
Progress MD ft Stand Pipe Press Psi Daily Mud Cost US 350,00
PTMD ft 4.678,71 Flow Rate gpm Cum. Mud Cost US 36.034,15
Spud Date 11-Des-2009 String Weight lbs Day Supervisor ANDY HARAHAP
Release Date Rotating Weight lbs Night Supervisor
Planned Days 30 Total Drilling Time hrs Engineer DIAN PERMANA
Days from Spud Circulating Press psi Geologist
Potong csg 20" (20 cm lebih rendah) dan bersihkan semen utk memudahkan pengelasan BF 13-3/8" x 3000 psi. Potong & ratakan permukaan csg 13-3/8". Install Ring plate.
N/U BF 13-5/8" x 3k psi. Las bagian luar & dalam BF 13-5/8" x 3000 psi.Cooling (pendingininan), test hasil pengelesan, bocor bagian dalam. Las kembali bag dalam BF 13-5/8"
3000 psi. Cooling (pendingininan),test hasil pengelasan dgn 1500 psi (hand pump by welder), baik. N/U BOP 13-5/8" x 5000 psi + DSAF 13-5/8" 3000 x 5000 psi.Pasang saluran
permukaan. Function test Annular,Pipe ram, HCR OK. Press Test dgn tester cup Annular low/high 500/1500 psi 10 mnt,baik. Pipe ram 500/1500 psi 10 mnt,baik, Press test blind
24 Hours Summary
ram 500/1500 10 mnt, baik. Test aliran ke flare,baik,install flow line. N/D Kelly & Swivel.
Potong csg 20" (20 cm lebih rendah) dan bersihkan semen utk memudahkan
00:00 01:30 1:30 646,357 646,357 0 Drilling Y P 23. Other
pengelasan BF 13-3/8" x 3000 psi
01:30 03:00 1:30 646,357 646,357 0 Drilling Y P 23. Other Potong & ratakan permukaan csg 13-3/8". Install Ring plate
03:00 03:30 0:30 646,357 646,357 0 Drilling Y P 23. Other N/U BF 13-5/8" x 3k psi.
03:30 06:30 3:00 646,357 646,357 0 Drilling Y P 23. Other Las bagian luar & dalam BF 13-5/8" x 3000 psi
06:30 08:30 2:00 646,357 646,357 0 Drilling Y P 23. Other Cooling (pendingininan), test hasil pengelesan, bocor bagian dalam.
08:30 11:00 2:30 646,357 646,357 0 Drilling Y P 23. Other Las kembali bag dalam BF 13-5/8" 3000 psi
Cooling (pendingininan),test hasil pengelasan dgn 1500 psi (hand pump by welder),
11:00 14:00 3:00 646,357 646,357 0 Drilling Y P 23. Other
baik
N/U BOP 13-5/8" x 5000 psi + DSAF 13-5/8" 3000 x 5000 psi.Pasang saluran
14:00 21:00 7:00 646,357 646,357 0 Drilling Y P 14. Nipple Up B.O.
permukaan.
Function test Annular,Pipe ram, HCR OK. Press Test dgn tester cup Annular low/high
21:00 22:00 1:00 646,357 646,357 0 Drilling Y P 15. Test B.O.P 500/1500 psi 10 mnt,baik. Pipe ram 500/1500 psi 10 mnt,baik, Press test blind ram
500/1500 10 mnt, baik. Test aliran ke flare,baik,install flow line
22:00 00:00 2:00 646,357 646,357 0 Drilling Y P 23. Other N/D Kelly & Swivel
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name
PT. PERTAMINA EP 2 SECURITY Time hh:mm
PT. DOWELL SCHLUMBER ANADRILL Slow Speed? y/n
PT. SCHOMI 2 PT TOP DRIVE MARITIM Circulate
PT. ESLOG 4 HOT HED Strokes SPM
PT. JML 13 FMC Pressure psi
PT. USAYANA GS Liner Size in
PT. PATRAKOM 1 Efficiency %
PARAMEDIC 1
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 6
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig ZJ-03 / JML-03 Avg WOB klbs AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM Daily Cost US 47.593,02
Current MD ft 646,36 Torque lb.ft Cum. Cost US 424.044,88
Progress MD ft Stand Pipe Press Psi Daily Mud Cost US 5.474,56
PTMD ft Flow Rate gpm 650 Cum. Mud Cost US 41.508,71
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Rizkiansyah
Release Date Rotating Weight lbs Night Supervisor Rizkiansyah
Planned Days 30 Total Drilling Time hrs Engineer Dian Permana
Days from Spud 5 Circulating Press psi Geologist -
24 Hours Summary R/U Top Drive 100%, Stand up 50 stands DP 5", M/U & RIH 12-1/4" PDC, Tag TOC @ 181 m.
24 Hours Forecast Ljt bor formasi spi kedalaman 1187 m
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
00:00 13:00 13:00 646,357 646,357 0 Drilling Y P 23. Other Ljt R/u Top drive (100%), function test (robotic,Low/Hig RPM, Test dgn 2000 psi), OK
13:00 16:00 3:00 646,357 646,357 0 Drilling Y P 23. Other Stand up DP 5" 34 stands.
16:00 20:00 4:00 646,357 646,357 0 Drilling Y P 23. Other Ljt stand up DP 5" 16 stands (kum 50 stds).
20:00 00:00 4:00 646,357 646,357 0 Drilling Y P 2. Drill Actual M/U & RIH 12-1/4" PDC, Tag TOC @ 181 m.
17-Des-2009
00:00 01:30 1:30 646,357 646,357 0 Drilling Y P 2. Drill Actual Ljt bor plug, semen spi kedalaman 192 m.
5. Condition Mud
01:30 02:00 0:30 646,357 646,357 0 Drilling Y P Sirkulasi bersih & Uji tekanselubung 1000 psi / 5 mnt, baik.
& Circulate
02:00 03:30 1:30 646,357 656,2 9,843 Drilling Y P 2. Drill Actual Ljt bor semen & formasi spi kedalaman 200 m.
5. Condition Mud
03:30 04:00 0:30 656,2 656,2 0 Drilling Y P & Circulate Sirkulasi bersih & kondisikan lumpur Sgin/out = 1.06, MOT SG eq = 1.70, baik.
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm
PT. DOWELL SCHLUMBER Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in
PT. PATRAKOM 1 Efficiency %
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 7
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig ZJ-03 / JML-03 Avg WOB klbs AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM Daily Cost US 59.598,22
Current MD ft 646,36 Torque lb.ft Cum. Cost US 483.643,10
Progress MD ft Stand Pipe Press Psi 1200 Daily Mud Cost US 3.321,58
PTMD ft Flow Rate gpm 650 Cum. Mud Cost US 44.830,29
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Rizkiansyah
Release Date Rotating Weight lbs Night Supervisor Rizkiansyah
Planned Days 30 Total Drilling Time hrs Engineer Dian Permana
Days from Spud 6 Circulating Press psi Geologist -
24 Hours Summary Ljt bor plug, semen, dan formasi spi kedalaman 290 m.
24 Hours Forecast Ljt bor formasi spi kedalaman 700 m. Short trip. Ljt bor formasi spi kedalaman 1189 m.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
00:00 01:30 1:30 646,357 646,357 0 Drilling Y P 2. Drill Actual Ljt bor plug, semen spi kedalaman 192 m.
5. Condition Mud
01:30 02:00 0:30 646,357 646,357 0 Drilling Y P Sirkulasi bersih & Uji tekanselubung 1000 psi / 5 mnt, baik.
& Circulate
02:00 03:30 1:30 646,357 656,2 9,843 Drilling Y P 2. Drill Actual Ljt bor semen & formasi spi kedalaman 200 m.
5. Condition Mud
03:30 04:00 0:30 656,2 656,2 0 Drilling Y P Sirkulasi bersih & kondisikan lumpur Sgin/out = 1.06, MOT SG eq = 1.70, baik.
& Circulate
04:00 16:00 12:00 656,2 849,779 193,579 Drilling Y P 2. Drill Actual Ljt bor formasi spi kedalaman 259 m
16:00 00:00 8:00 849,779 951,49 101,711 Drilling Y P 2. Drill Actual Ljt bor formasi spi kedalaman 290 m
Morning Status, 18-Des-2009
00:00 04:00 4:00 951,49 977,738 26,248 Drilling Y P 2. Drill Actual Ljt bor formasi spi kedalaman 313 m
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBER Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 100 100
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 8
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig ZJ-03 / JML-03 Avg WOB klbs AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM Daily Cost US 47.503,38
Current MD ft 1.246,78 Torque lb.ft Cum. Cost US 531.146,49
Progress MD ft Stand Pipe Press Psi 1200 Daily Mud Cost US 18.142,17
PTMD ft Flow Rate gpm 650 Cum. Mud Cost US 62.972,46
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Rizkiansyah
Release Date Rotating Weight lbs Night Supervisor Rizkiansyah
Planned Days 30 Total Drilling Time hrs 24,00 Engineer Dian Permana
Days from Spud 7 Circulating Press psi Geologist -
24 Hours Summary Ljt bor formasi spi kedalaman 380 m. POOH 12-1/4" PDC + BHA Rotary spi permukaan, L/D Stabilizer & DC 8". M/U & RIH 12-1/4" PDC + BHA Rotary spi kedalaman 96 m.
24 Hours Forecast Ljt RIH 12-1/4" PDC + BHA Rotary spi kedalaman 380 m. Lanjut bor formasi spi kedalaman 1189 m.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
00:00 04:00 4:00 951,49 1026,953 75,463 Drilling Y P 2. Drill Actual Ljt bor formasi spi kedalaman 313 m
04:00 10:00 6:00 1026,953 1158,193 131,24 Drilling Y P 2. Drill Actual Ljt bor formasi spi kedalaman 353 m.
10:00 10:30 0:30 1158,193 1158,193 0 Drilling N NP 23. Other Perbaikan pompa : ganti seating valve MP#2 (NPT Rig = 0.5 jam)
10:30 16:00 5:30 1158,193 1246,78 88,587 Drilling Y P 2. Drill Actual Ljt bor formasi spi kedalaman 380 m.
2. Drill Actual Lakukan drill off test dgn perubahan WOB dan RPM, kemajuan hanya 380.5 m (last lith
16:00 17:00 1:00 1246,78 1246,78 0 Drilling Y P
@380m : 10%SST, 10% Shale, 80% CLST).
5. Condition Mud
17:00 18:00 1:00 1246,78 1246,78 0 Drilling Y P Sirkulasi Bersih & Swept out hi vis 30 bbls.
& Circulate
18:00 23:00 5:00 1246,78 1246,78 0 Drilling Y P 6. Trips POOH 12-1/4" PDC + BHA Rotary to surface, L/D Stabilizer 2 unit, 2 jts DC 8".
23:00 00:00 1:00 1246,78 1246,78 0 Drilling Y P 6. Trips M/U & RIH 12-1/4" PDC + BHA Rotary spi kedalaman 96 m.
Morning Status, 19-Des-2009
00:00 00:30 0:30 1246,78 1246,78 0 Drilling Y P 6. Trips Ljt RIH 12-1/4" PDC + BHA Rotary spi kedalaman 180 m.
Perbaikan Pompa : 3 pcs dies plug PTO patah MP#1, ganti seating valve MP#2 &
00:30 04:00 3:30 1246,78 1246,78 0 Drilling N NP 23. Other
MP#3. (NPT Rig = 3.5 jam, kum 4.0 jam).
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBER Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 100 100
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 9
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig RG-750 / JML-03 Avg WOB klbs AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM Daily Cost US 31.113,84
Current MD ft 1.466,61 Torque lb.ft Cum. Cost US 562.260,33
Progress MD ft 219,83 Stand Pipe Press Psi 1500 Daily Mud Cost US 5.926,43
PTMD ft Flow Rate gpm 650 Cum. Mud Cost US 68.898,89
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Rizkiansyah
Release Date Rotating Weight lbs Night Supervisor Rizkiansyah
Planned Days 30 Total Drilling Time hrs 24,00 Engineer Dian Permana
Days from Spud 8 Circulating Press psi Geologist -
Ljt RIH 12-1/4" PDC + BHA Rotary spi 180 m. Perbaikan pompa. Running Test. Ljt RIH 12-1/4" PDC + BHA Rotary spi 380 m. Sirkulasi bersih. Ljt bor formasi spi kedalaman
24 Hours Summary
423 m.
24 Hours Forecast Ljt bor formasi spi kedalaman 800 m. Short trip. Ljt bor formasi spi kedalaman 1189 m.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
00:00 00:30 0:30 1246,78 1246,78 0 Drilling Y P 6. Trips Ljt RIH 12-1/4" PDC + BHA Rotary spi kedalaman 180 m.
Perbaikan Pompa : 3 pcs dies plug PTO patah MP#1, ganti seating valve MP#2 &
00:30 04:00 3:30 1246,78 1246,78 0 Drilling N NP 23. Other
MP#3. (NPT Rig = 3.5 jam, kum 4.0 jam).
Ljt perbaikan pompa : Ganti 3 pcs dies plug PTO MP#1 (NPT Rig = 11 jam, kum 15
04:00 15:00 11:00 1246,78 1246,78 0 Drilling N NP 23. Other
jam).
Running Test MP#1, MP#2, MP#3 : SPM#1 90, SPM#2 90, SPM#3 100, GPM 700,
15:00 15:30 0:30 1246,78 1246,78 0 Drilling N NP 23. Other
Tekanan 900 psi (NPT Rig = 0.5 jam, kum 15.5 jam).
15:30 16:00 0:30 1246,78 1246,78 0 Drilling Y P 6. Trips Ljt RIH 12-1/4" PDC + BHA Rotary spi kedalaman 293 m.
16:00 16:30 0:30 1246,78 1246,78 0 Drilling Y P 6. Trips Ljt RIH 12-1/4" PDC + BHA Rotary spi kedalaman 380 m.
5. Condition Mud
16:30 17:00 0:30 1246,78 1246,78 0 Drilling Y P Sirkulasi bersih di dasar.
& Circulate
17:00 00:00 7:00 1246,78 1246,78 0 Drilling Y P 2. Drill Actual Ljt bor formasi 380.5 - 423 m (ROP 5 mnt/m, lith 80% coal, 10% CLST, 10%SST).
Morning Status, 20-Des-2009
6. Trips Ljt bor formasi spi kedalaman 447 m (ROP 4 mnt/m, Lith 40% SST, 40% CLST, 20%
00:00 04:00 4:00 1246,78 1246,78 0 Drilling Y P
Coal).
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBER Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 130 130
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
20-Des-2009 D RIL LING D EP A RT M E NT
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 10
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig RG-750 / JML-03 Avg WOB klbs 5 AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM 110 Daily Cost US 32.490,85
Current MD ft 1.788,15 Torque lb.ft 1.500,00 Cum. Cost US 594.751,17
Progress MD ft 400,28 Stand Pipe Press Psi 1500 Daily Mud Cost US 3.693,69
PTMD ft Flow Rate gpm 650 Cum. Mud Cost US 72.592,58
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Rizkiansyah
Release Date Rotating Weight lbs Night Supervisor Rizkiansyah
Planned Days 30 Total Drilling Time hrs 24,00 Engineer Dian Permana
Days from Spud 9 Circulating Press psi Geologist -
24 Hours Summary Ljt bor formasi spi kedalaman 545 m. Perbaikan pompa MP#2 & MP#3. POOH 12-1/4" PDC + BHA Rotary spi shoe @ 197 m.
24 Hours Forecast Ljt perbaikan pompa. RIH 12-1/4" PDC + BHA Rotary spi 545 m. Ljt bor formasi spi kedalaman 900 m. Short trip. Ljt bor formasi spi kedalaman 1189 m.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
2. Drill Actual
00:00 04:00 4:00 1246,78 1466,607 219,827 Drilling Y P Ljt bor formasi spi kedalaman 447 m (ROP 4 mnt/m, Lith 40% SST, 40% CLST, 20% Coal).
2. Drill Actual
04:00 16:00 12:00 1466,607 1722,525 255,918 Drilling Y P Ljt bor formasi spi kedalaman 525 m (ROP 9 mnt/m, lith: 20% SST, 20% CLST, 60% Coal).
2. Drill Actual
16:00 19:30 3:30 1722,525 1788,145 65,62 Drilling Y P Ljt bor formasi spi kedalaman 545 m (ROP 10 mnt/m, lith: 20% SST, 50% CLST, 30% Coal).
Perbaikan Pompa : SPM#1 & SPM#2 turun, set ulang disk clutch MP#1 & MP#2, (NPT Rig =
19:30 20:00 0:30 1788,145 1788,145 0 Drilling N NP 23. Other
0.5 jam, kum 16 jam).
Sirkulasi kondisikan lumpur, naikan viscositas (SPM#1 90; SPM#3 90; GPM 450), sambil ljt
20:00 20:30 0:30 1788,145 1788,145 0 Drilling N NP 23. Other
perbaikan MP#2, set disk clutch (NPT Rig = 0.5 jam, kum 16.5 jam).
POOH 12-1/4" PDC + BHA Rotary spi shoe @ 197 m, sambil ljt perbaikanMP#2 (disk clutch)
20:30 23:00 2:30 1788,145 1788,145 0 Drilling N NP 23. Other & reposisi engine MP#3 dikarenakan stock 2 pcs V-belt berukuran pendek (NPT Rig = 2.5
jam, kum 19.5 jam)
Ljt perbaikan MP#2 & MP#3, sambil running test MP#1, 110 SPM, 275 GPM (NPT Rig = 1
23:00 00:00 1:00 1788,145 1788,145 0 Drilling N NP 23. Other
jam, kum 20 jam).
00:00 04:00 4:00 1788,145 1788,145 0 Drilling N NP 23. Other Ljt perbaikan MP#2 & MP#3, (NPT Rig = 4 jam, kum 24 jam).
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBERG Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 130 130
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
21-Des-2009 D RIL LING D EP A RT M E NT
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 11
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig RG-750 / JML-03 Avg WOB klbs 5 AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM 110 Daily Cost US 33.849,23
Current MD ft 2.040,78 Torque lb.ft 1.500,00 Cum. Cost US 628.600,40
Progress MD ft 252,64 Stand Pipe Press Psi 1500 Daily Mud Cost US 6.480,85
PTMD ft Flow Rate gpm 650 Cum. Mud Cost US 79.073,43
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Rizkiansyah
Release Date Rotating Weight lbs Night Supervisor Rizkiansyah
Planned Days 30 Total Drilling Time hrs 24,00 Engineer Dian Permana
Days from Spud 10 Circulating Press psi Geologist -
Ljt perbaikan MP#2 & MP#3. RIH 12-1/4" PDC + BHA Rotary spi kedalaman 405 m. Reaming down & Sirkulasi sambil WOP spi kedalaman 545 m, terdapat rontokan (caving)
24 Hours Summary
batubara. Ljt bor spi kedalaman 602 m.
24 Hours Forecast Ljt bor formasi spi kedalaman 900 m. wiper trip. Ljt bor formasi spi kedalaman 1189 m.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
00:00 04:00 4:00 1788,145 1788,145 0 Drilling N NP 23. Other Ljt perbaikan MP#2 & MP#3, (NPT Rig = 4 jam, kum 24 jam).
04:00 16:00 12:00 1788,145 1788,145 0 Drilling N NP 23. Other Ljt perbaikan MP#2 & MP#3, (NPT Rig = 1.5 jam, kum 25.5 jam).
Ljt perbaikan MP#2 (disk clutch), sambil running test MP#1 & MP#3, Debit Max 600 gal/mnt,
16:00 19:30 3:30 1788,145 1788,145 0 Drilling N NP 23. Other
dgn kombinasi SPM#1 130 & SPM#3 110. (NPT Rig = 2 jam, kum 27.5 jam).
RIH 12-1/4" PDC + BHA Rotary, rangkaian duduk 10 klbs @ 405 m, 412 m (NPT Rig = 0.5
19:30 20:00 0:30 1788,145 1788,145 0 Drilling N NP 23. Other
jam, kum 28 jam).
6. Trips Reaming down & Sirkulasi sambil WOP spi kedalaman 545 m, terdapat rontokan (caving)
20:00 20:30 0:30 1788,145 1788,145 0 Drilling N NP
batubara.
2. Drill Actual
20:30 23:00 2:30 1788,145 1817,674 29,529 Drilling Y P Ljt bor formasi kedalaman 545 - 554 m (ROP 10 mnt/m, lith @ 551m; 20% STT, 80% CLST).
2. Drill Actual
23:00 00:00 1:00 1817,674 1975,162 157,488 Drilling Y P Ljt bor formasi spi kedalaman 602 m (ROP 4 mnt/m, lith 80% Coal, 10%CLST, 10% SST).
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBERG Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 130 130
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 12
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig RG-750 / JML-03 Avg WOB klbs 5 AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM 110 Daily Cost US 35.136,47
Current MD ft 2.359,04 Torque lb.ft 1.500,00 Cum. Cost US 663.736,87
Progress MD ft 383,88 Stand Pipe Press Psi 1000 Daily Mud Cost US 5.793,06
PTMD ft Flow Rate gpm 600 Cum. Mud Cost US 84.866,49
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Rizkiansyah
Release Date Rotating Weight lbs Night Supervisor Rizkiansyah
Planned Days 30 Total Drilling Time hrs 24,00 Engineer Dian Permana
Days from Spud 11 Circulating Press psi Geologist -
24 Hours Summary Ljt bor formasi spi kedalaman 679 m. Perbaikan pompa, sambil sirkulasi. Ljt bor formasi spi kedalaman 719 m.
24 Hours Forecast Ljt bor formasi spi kedalaman 900 m. Short trip. Lanjut bor formasi spi kedalaman 1189 m.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
00:00 04:00 4:00 1975,162 2040,782 65,62 Drilling Y P 2. Drill Actual Ljt bor formasi spi kedalaman 622 m (ROP 8 mnt/m, lith 70% CLST, 30% Coal).
04:00 14:30 10:30 2040,782 2227,799 187,017 Drilling Y P 2. Drill Actual Ljt bor formasi spi kedalaman 679 m (ROP 10 mnt/m, Lith 60% SST, 40% CLST)
Perbaikan Pompa : Flexible Joint 4" Suction line Charging Pump#1 bocor, ganti
14:30 16:00 1:30 2227,799 2227,799 0 Drilling N NP 23. Other bongkar pasang dari Charging Pump#2, sambil sirkulasi dgn MP#3 300 GPM (NPT Rig
= 1.5 jam, kum 29.5 jam).
2. Drill Actual Ljt bor formasi spi kedalaman 719 m (ROP 7 mnt/m, lith: 50% Coal, 30% CLST, 20%
16:00 00:00 8:00 2227,799 2359,039 131,24 Drilling Y P
SST).
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBER Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 130 130
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 14
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig RG-750 / JML-03 Avg WOB klbs 5 AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM 110 Daily Cost US 23.000,31
Current MD ft 2.611,68 Torque lb.ft 1.500,00 Cum. Cost US 722.839,86
Progress MD ft Stand Pipe Press Psi 1100 Daily Mud Cost US 511,22
PTMD ft Flow Rate gpm 700 Cum. Mud Cost US 92.093,65
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Rizkiansyah
Release Date Rotating Weight lbs Night Supervisor Rizkiansyah
Planned Days 30 Total Drilling Time hrs 24,00 Engineer Dian Permana
Days from Spud 13 Circulating Press psi Geologist -
24 Hours Summary Ljt POOH 12-1/4" PDC + BHA Rotary spi shoe @ 197 m. Ljt perbaikan pompa: MP#1, 2, 3.
24 Hours Forecast Ljt bor formasi spi kedalaman 1189 m.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
Ljt POOH 12-1/4" PDC + BHA Rotary spi shoe @ 197m (NPT Rig = 3 jam, kum 38
00:00 03:00 3:00 2611,676 2611,676 0 Drilling N NP 23. Other
jam).
Ljt perbaikan pompa : ganti ukuran liner 6" MP#1, 2, 3 & dies plug PTO MP#2 patah
03:00 04:00 1:00 2611,676 2611,676 0 Drilling N NP 23. Other
(NPT Rig = 1 jam, kum 39 jam).
Ljt perbaikan pompa : (1) Ganti ukuran liner 6" MP#1, 2, 3, OK. (2) Setting ulang disk
04:00 15:30 11:30 2611,676 2611,676 0 Drilling N NP 23. Other clutch PTO MP#1, OK. (3) Ganti dies plug PTO MP#2, disk plate patah, sdg dibubut
(NPT Rig = 11.5 jam, kum 50.5 jam).
Running test MP#1 & 3, SPM#1 120, SPM#3 120, P 1100 psi, GPM 700, selama 1 jam.
15:30 16:30 1:00 2611,676 2611,676 0 Drilling N NP 23. Other
Sambil tunggu bearing pillow & disk plate bubutan (NPT Rig = 1 jam, kum 51.5 jam).
Ljt perbaikan pompa: disk clutch & disk plate MP#2, sambil tunggu pillow bearing
16:30 00:00 7:30 2611,676 2611,676 0 Drilling N NP 23. Other
MP#2 (NPT Rig = 7.5 jam, kum 59 jam).
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBER Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 130 130
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 15
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig RG-750 / JML-03 Avg WOB klbs 5 AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM 110 Daily Cost US 30.624,07
Current MD ft 2.611,68 Torque lb.ft 1.500,00 Cum. Cost US 753.463,93
Progress MD ft Stand Pipe Press Psi 1100 Daily Mud Cost US 3.550,76
PTMD ft Flow Rate gpm 700 Cum. Mud Cost US 95.644,41
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Rizkiansyah
Release Date Rotating Weight lbs Night Supervisor Rizkiansyah
Planned Days 30 Total Drilling Time hrs 24,00 Engineer Dian Permana
Days from Spud 14 Circulating Press psi Geologist -
24 Hours Summary Ljt perbaikan pompa. RIH 12-1/4" PDC + BHA Rotary, duduk @ 313 m, reaming down spi kedalaman 726 m.
24 Hours Forecast Ljt bor formasi spi kedalaman 1189 m.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
Ljt perbaikan pompa; disk clutch & disk plate MP#2, sambil tunggu pillow bearing
00:00 04:00 4:00 2611,676 2611,676 0 Drilling N NP 23. Other
MP#2 (NPT Rig = 4 jam, kum 63 jam).
RIH 12-1/4" PDC + BHA Rotary, rangkaian duduk 10 klbs @ 313 m dan setiap
kemajuan 1 jt. Reaming down spi kedalaman 600 m, cutting yg keluar berupa rontokan
04:00 16:00 12:00 2611,676 2611,676 0 Drilling N NP 23. Other
coal. Sambil ljt perbaikan MP#2 (pillow bearing) & MP#3 (V-belt kendur & hose airflex
bocor). (NPT Rig = 12 jam, kum 75 jam).
Ljt reaming down spi kedalaman 630 m, sambil running test MP#2, OK. (NPT Rig = 1
16:00 17:00 1:00 2611,676 2611,676 0 Drilling N NP 23. Other
jam, kum 76 jam).
17:00 00:00 7:00 2611,676 2611,676 0 Drilling N NP 23. Other Ljt reaming down spi kedalaman 726 m (NPT Rig = 7 jam, kum 83 jam).
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBER Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 130 130
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 16
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig RG-750 / JML-03 Avg WOB klbs 5 AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM 110 Daily Cost US 32.151,77
Current MD ft 2.808,54 Torque lb.ft 1.500,00 Cum. Cost US 785.615,70
Progress MD ft 196,86 Stand Pipe Press Psi 1100 Daily Mud Cost US 4.178,80
PTMD ft Flow Rate gpm 700 Cum. Mud Cost US 99.823,21
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Rizkiansyah
Release Date Rotating Weight lbs Night Supervisor Rizkiansyah
Planned Days 30 Total Drilling Time hrs 24,00 Engineer Dian Permana
Days from Spud 15 Circulating Press psi Geologist -
24 Hours Summary Ljt reaming down spi kedalaman 796 m. Sirkulasi bersih. Ljt bor formasi spi kedalaman 856 m.
24 Hours Forecast Ljt bor formasi spi kedalaman 1189 m.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
00:00 04:00 4:00 2611,676 2611,676 0 Drilling N NP 23. Other Ljt reaming down spi kedalaman 776 m (NPT Rig = 4 jam, kum 87 jam).
04:00 05:00 1:00 2611,676 2611,676 0 Drilling N NP 23. Other Ljt reaming down spi kedalaman 796 m (NPT Rig = 1 jam, kum 88 jam).
05:00 06:00 1:00 2611,676 2611,676 0 Drilling N NP 23. Other Sirkulasi Bersih & Swept out hi vis 30 bbls (NPT Rig = 1 jam, kum 89 jam).
06:00 16:00 10:00 2611,676 2736,354 124,678 Drilling Y P 2. Drill Actual Ljt bor formasi spi kedalaman 834 m (ROP 13 mnt/m, Lith 80% SST, 20% CLST).
2. Drill Actual Ljt bor formasi spi kedalaman 856 m (ROP 28 mnt/m, lith 20% Shale, 20% Coal, 60%
16:00 00:00 8:00 2736,354 2808,536 72,182 Drilling Y P
SST).
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBER Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 130 130
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 17
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig RG-750 / JML-03 Avg WOB klbs 5 AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM 130 Daily Cost US 35.084,35
Current MD ft 3.225,22 Torque lb.ft 3.000,00 Cum. Cost US 820.700,05
Progress MD ft 488,87 Stand Pipe Press Psi 1500 Daily Mud Cost US 6.022,24
PTMD ft Flow Rate gpm 750 Cum. Mud Cost US 105.845,45
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Rizkiansyah
Release Date Rotating Weight lbs Night Supervisor Rizkiansyah
Planned Days 30 Total Drilling Time hrs 24,00 Engineer Dian Permana
Days from Spud 16 Circulating Press psi Geologist -
24 Hours Summary Ljt bor formasi spi kedalaman 902 m. Perbaikan MP#2 & MP#3. Ljt bor formasi spi kedalaman 983 m.
24 Hours Forecast Ljt bor formasi spi kedalaman 1189 m.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
00:00 04:00 4:00 2736,354 2834,784 98,43 Drilling Y P 2. Drill Actual Ljt bor formasi spi kedalaman 864 m (ROP 18 mnt/m, lith 70% SST, 30% Shale).
04:00 09:30 5:30 2834,784 2959,462 124,678 Drilling Y P 2. Drill Actual Ljt bor formasi spi kedalaman 902 m.
Sirkulasi sambil perbaikan Pompa : MP#2 (SPM naik turun, ganti fuel pump), MP#3
09:30 10:30 1:00 2959,462 2959,462 0 Drilling N NP 23. Other (SPM turun). Running SPM#1 110 & SPM#3 110, max debit 650 GPM. (NPT Rig = 1
jam, kum 90 jam).
2. Drill Actual
10:30 12:00 1:30 2959,462 2988,991 29,529 Drilling Y P Ljt bor formasi spi kedalaman 911 m, (DP screen putus & est tertinggal di HWDP).
5. Condition Mud
12:00 12:30 0:30 2988,991 2988,991 0 Drilling Y P Sirkulasi, tekanan 1500 psi / 700 GPM, normal.
& Circulate
2. Drill Actual Ljt bor formasi spi kedalaman 930 m (ROP 11 mnt/m, lith @ 921m: 70% SST, 30%
12:30 16:00 3:30 2988,991 3051,33 62,339 Drilling Y P
Shale).
16:00 00:00 8:00 3051,33 3225,223 173,893 Drilling Y P 2. Drill Actual Ljt bor formasi spi kedalaman 983 m (ROP 11 mnt/m, Lith 60% Shale, 40% SST).
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBER Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 130 130
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 18
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig RG-750 / JML-03 Avg WOB klbs 5 AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM 130 Daily Cost US 39.582,03
Current MD ft 3.687,84 Torque lb.ft 3.000,00 Cum. Cost US 860.282,08
Progress MD ft 462,62 Stand Pipe Press Psi 1500 Daily Mud Cost US 4.767,85
PTMD ft Flow Rate gpm 750 Cum. Mud Cost US 110.613,30
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Rizkiansyah
Release Date Rotating Weight lbs Night Supervisor Rizkiansyah
Planned Days 30 Total Drilling Time hrs 24,00 Engineer Dian Permana
Days from Spud 17 Circulating Press psi Geologist -
24 Hours Summary Lanjut bor formasi spi kedalaman 1068 m. Perbaikan Top Drive : ganti lower kelly cock (washout). Ljt bor formasi spi kedalaman 1124 m.
24 Hours Forecast Ljt bor formasi spi kedalaman 1189 m.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
2. Drill Actual Ljt bor formasi spi kedalaman 1008 m (ROP 9 mnt/m, lith 50% SST, 10% Shale, 40%
00:00 04:00 4:00 3225,223 3307,248 82,025 Drilling Y P
Coal).
04:00 11:30 7:30 3307,248 3504,108 196,86 Drilling Y P 2. Drill Actual Ljt bor formasi spi kedalaman 1068 m (ROP 16 mnt/m, lith 70% SST, 30% Shale).
Perbaikan Top Drive : ganti lower kelly cock (washout). Cabut rangkaian spi kedalaman
1047 m, pasang topi sirkulasi, swept out hi vis 30 bbls & lanjut sirkulasi sambil
11:30 16:00 4:30 3504,108 3504,108 0 Drilling N NP 23. Other
perbaikan. Running RPM 170 high, OK. Pressure test tidak bisa dilakukan, actuator
valve tdk bisa menutup (NPT Rig = 4.5 jam. Kum 94.5 jam).
2. Drill Actual Ljt bor formasi spi kedalaman 1124 m (ROP 5.73 mnt/m. lith 10% Coal, 20% Shale,
16:00 00:00 8:00 3504,108 3687,844 183,736 Drilling Y P
70% SST).
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBER Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 130 130
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 19
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig RG-750 / JML-03 Avg WOB klbs 5 AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM 130 Daily Cost US 25.130,38
Current MD ft 3.812,52 Torque lb.ft 3.000,00 Cum. Cost US 885.412,45
Progress MD ft 124,68 Stand Pipe Press Psi 1500 Daily Mud Cost US 1.426,61
PTMD ft Flow Rate gpm 750 Cum. Mud Cost US 112.039,91
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Rizkiansyah
Release Date Rotating Weight lbs Night Supervisor Rizkiansyah
Planned Days 30 Total Drilling Time hrs 24,00 Engineer Dian Permana
Days from Spud 18 Circulating Press psi Geologist -
24 Hours Summary Ljt bor formasi spi kedalaman 1162 m, string buntu. POOH 12-1/4" PDC + BHA Rotary spi permukaan. RIH 12-1/4" PDC + BHA Rotary spi kedalaman 583 m.
24 Hours Forecast Ljt bor formasi spi kedalaman 1189 m.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
2. Drill Actual
00:00 04:00 4:00 3687,844 3743,621 55,777 Drilling Y P Ljt bor formasi spi kedalaman 1141 m (ROP 6 mnt/m, lith 30% SST, 70% Shale).
2. Drill Actual
Ljt bor formasi spi kedalaman 1162 m (ROP 12 mnt/m, lith 40% Shale, 60 SST).
04:00 06:00 2:00 3743,621 3812,522 68,901 Drilling Y P
Indikasi tekanan naik 2500 psi, normal 1500 psi, string buntu.
POOH 12-1/4" PDC + BHA Rotary spi kedalaman 123 m. OP 10-15 klbs @ 1116, 989,
06:00 16:00 10:00 3812,522 3812,522 0 Drilling N NP 23. Other
960, 738 m.
Ljt POOH 12-1/4" PDC + BHA Rotary spi permukaan, terdapat potongan DP Screen
16:00 17:00 1:00 3812,522 3812,522 0 Drilling N NP 23. Other
plate lingkaran ukuran 2 inch di atas Totco Ring.
RIH 12-1/4" PDC + BHA Rotary spi kedalaman 583 m, rangkaian duduk 10klbs @
17:00 00:00 7:00 3812,522 3812,522 0 Drilling N NP 23. Other
432m, 465m, 525m. Reaming down interval 432 - 448m, 465 - 486m, 525 - 544m.
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBER Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 130 130
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 20
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig RG-750 / JML-03 Avg WOB klbs 5 AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM 130 Daily Cost US 43.497,69
Current MD ft 3.897,83 Torque lb.ft 3.000,00 Cum. Cost US 928.910,15
Progress MD ft 85,31 Stand Pipe Press Psi 1500 Daily Mud Cost US 9.625,84
PTMD ft Flow Rate gpm 750 Cum. Mud Cost US 121.665,75
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Rizkiansyah
Release Date Rotating Weight lbs Night Supervisor Rizkiansyah
Planned Days 30 Total Drilling Time hrs 24,00 Engineer Dian Permana
Days from Spud 19 Circulating Press psi Geologist -
RIH 12-1/4" PDC + BHA Rotary spi kedalaman 1162 m. Ljt bor formasi spi kedalaman 1188 m. Sirkulasi kondisikan lumpur SG 1.18 (ECD). Short Trip spi shoe @ 197 m. RIH 12-
24 Hours Summary
1/4" PDC + BHA Rotary spi kedalaman 1182 m.
24 Hours Forecast Ljt RIH 12-1/4" PDC + BHA Rotary spi kedalaman 1188 m. POOH 12-1/4" PDC + BHA Rotary spi permukaan. OH Logging 12-1/4" Interval 700 - 1188 m.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
00:00 02:30 2:30 3812,522 3812,522 0 Drilling Y P 6. Trips RIH 12-1/4" PDC + BHA Rotary spi kedalaman 1114m, duduk 15 klbs.
02:30 03:00 0:30 3812,522 3812,522 0 Drilling Y P 6. Trips Washdown & work on pipe interval 1114 - 1140 m, OK.
03:00 04:00 1:00 3812,522 3812,522 0 Drilling Y P 6. Trips Reaming down interval 1140 - 1162 m, rangkaian duduk 10 klbs.
2. Drill Actual Ljt bor formasi spi kedalaman 1188 m (Csg Point 9-5/8"). (ROP 14 mnt/m, Lith 80%
04:00 09:00 5:00 3812,522 3897,828 85,306 Drilling Y P
Shale, 10% Coal, 10% SST)
5. Condition Mud
09:00 11:00 2:00 3897,828 3897,828 0 Drilling Y P & Circulate Sirkulasi kondisikan lumpur, naikan berat sebesar ECD 1.18 SG
5. Condition Mud
11:00 12:00 1:00 3897,828 3897,828 0 Drilling Y P & Circulate
Swept out hi vis 30 bbls & sirkulasi bersih.
6. Trips Short trip, POOH 12-1/4" PDC + BHA Rotary spi kedalaman 564 m. OP 15 klbs @
12:00 16:00 4:00 3897,828 3897,828 0 Drilling Y P
1013, 774, 754 m.
16:00 18:00 2:00 3897,828 3897,828 0 Drilling Y P 6. Trips Ljt short trip, POOH 12-1/4" PDC + BHA Rotary spi shoe @ 197 m.
5. Condition Mud
18:00 18:30 0:30 3897,828 3897,828 0 Drilling Y P & Circulate
Sirkulasi bersih
18:30 20:00 1:30 3897,828 3897,828 0 Drilling Y P 6. Trips RIH 12-1/4" PDC + BHA Rotary spi kedalaman 548 m, duduk 10 klbs.
20:00 20:30 0:30 3897,828 3897,828 0 Drilling Y P 6. Trips Washdown interval 548 - 564 m.
20:30 23:30 3:00 3897,828 3897,828 0 Drilling Y P 6. Trips Ljt RIH 12-1/4" PDC + BHA Rotary spi kedalaman 1174 m, duduk 15 klbs.
23:30 00:00 0:30 3897,828 3897,828 0 Drilling Y P 6. Trips Reaming down interval 1174 - 1182 m.
01:30 02:00 0:30 3897,828 3897,828 0 Drilling Y P 23. Other Jatuhkan Totco Survey
02:00 04:00 2:00 3897,828 3897,828 0 Drilling Y P 6. Trips POOH 12-1/4" PDC + BHA Rotary spi kedalaman 815 m.
Bit Record BHA - 1 BHA - 2 Casing
Bit - 1 Bit - 2 BHA Number BHA Run BHA Number BHA Run Last Size in 13-3/8
Bit Number 1 OD Length OD Length Set MD ft 196
Bit Size in 12-1/4 in ft in ft Next Size in 9-5/8
Bit Run R Drill Collar 8 Set MD ft
Manufacturer Varel Stabilizer 12,25 Last LOT EMW ppg
IADC Code - Crossover TOL ft
Jets 1,052 Drill Collar 6,25 Mud Volumes
Serial # 4292 Start bbl
Depth Out ft Lost Surface bbl
Depth In ft Lost DH bbl
Meterage ft Dumped bbl
Bit Hours hrs Built bbl
Nozzles in 7 x 14 Ending bbl
Dull Grade - Gas
Cumulative Max. Gas
Footage ft Conn. Gas
Bit Hours hrs Trip Gas
ROP ft/hrs Back Gas
Drilling Fluid Mud Additive
1 2 3 1 2 3 Type Amount
Mud Type KCL-POLYMER Solids % 7,0 Annular Velocity ft/min
Time HH:MM Sand % 0,2 Pb psi
MW in ppg 10,08 Water % Sys HHP
MW out ppg 10,08 Oil % HHPb hp
Temp in degF 125 HGS % HSI hp/in2 2,1
Temp out degF 120 LGS % %psib %
Pres. Grad psi/ft LTLP bbl Jet Velocity ft/sec
Visc sec 58 HTHP bbl Impact force lbs
PV cP 19 Cake mm IF/area lb/in2 1,052
YP lbf/100ft2 36 E Stb V
Gels 10 sec 14 PF
Gels 10 min 18 MF
Fluid Loss mL/30min 4,8 PM
pH 9 ECD ppg
Bulk Materials
Type Material Name UOM Received Consumed Returned Adjust Ending
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBER Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 130 130
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
31-Des-2009 D RIL LING D EP A RT M E NT
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 21
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig RG-750 / JML-03 Avg WOB klbs 5 AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM 130 Daily Cost US 28.581,28
Current MD ft 3.897,83 Torque lb.ft 3.000,00 Cum. Cost US 957.491,43
Progress MD ft Stand Pipe Press Psi 1500 Daily Mud Cost US 856,24
PTMD ft Flow Rate gpm 750 Cum. Mud Cost US 122.521,99
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Rizkiansyah
Release Date Rotating Weight lbs Night Supervisor Rizkiansyah
Planned Days 30 Total Drilling Time hrs 24,00 Engineer Dian Permana
Days from Spud 20 Circulating Press psi Geologist -
Ljt reaming down spi kedalaman 1188 m, sirkulasi SG 1.21 (ECD). Jatuhkan Totco Survey. POOH 12-1/4" PDC + BHA Rotary spi permukaan, Totco survey 1.5 deg. RIH 12-1/4" PDC
24 Hours Summary
+ BHA Rotary spi kedalaman 1188 m. Sirkulasi bersih. POOH 12-1/4" PDC + BHA Rotary spi 133 m.
24 Hours Forecast Ljt RIH 12-1/4" PDC + BHA Rotary spi kedalaman 1188 m. POOH 12-1/4" PDC + BHA Rotary spi permukaan. OH Logging 12-1/4" Interval 700 - 1188 m.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
6. Trips
00:00 01:00 1:00 3897,828 3897,828 0 Drilling Y P Lanjut reaming down interval 1182 - 1188 m, sambil sirkulasi naikan SG 1.21 (ECD).
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBERG Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 130 130
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
01-Jan-2010 D RIL LING D EP A RT M E NT
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 22
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig RG-750 / JML-03 Avg WOB klbs 5 AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM 130 Daily Cost US 34.974,06
Current MD ft 3.897,83 Torque lb.ft 3.000,00 Cum. Cost US 992.465,49
Progress MD ft Stand Pipe Press Psi 1500 Daily Mud Cost US 4.714,14
PTMD ft Flow Rate gpm 750 Cum. Mud Cost US 127.236,13
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Rizkiansyah
Release Date Rotating Weight lbs Night Supervisor Rizkiansyah
Planned Days 30 Total Drilling Time hrs 24,00 Engineer Dian Permana
Days from Spud 21 Circulating Press psi Geologist -
24 Hours Summary Ljt POOH 12-1/4" PDC (Open Nozzle) + BHA Rotary spi permukaan. Run Logging#1 (DLL-BHC-MSFL-GR) & Logging#2 (LDL-CNL-GR). Round Trip.
24 Hours Forecast Persiapan Csg Handling Tools 9-5/8". RIH Casing 9-5/8", K55, 36#, R3.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
00:00 02:00 2:00 3897,828 3897,828 0 Drilling Y P 6. Trips Ljt POOH 12-1/4" PDC (Open Nozzle) + BHA Rotary spi permukaan.
02:00 03:00 1:00 3897,828 3897,828 0 Drilling Y P 23. Other Persiapan & RIH logging #1 (DLL-BHC-MSFL-GR)
03:00 04:00 1:00 3897,828 3897,828 0 Drilling Y P 23. Other Run Logging #1 (DLL-BHC-MSFL-GR)
04:00 08:00 4:00 3897,828 3897,828 0 Drilling Y P 23. Other Ljt run logging#1 (DLL-BHC-MSFL-GR). Interval log 700 - 1183.1 m.
08:00 09:00 1:00 3897,828 3897,828 0 Drilling Y P 23. Other Persiapan & RIH logging #2 (LDL-CNL-GR)
09:00 12:00 3:00 3897,828 3897,828 0 Drilling Y P 23. Other Run Logging #2 (LDL-CNL-GR), Interval log 700 - 1185.5 m.
12:00 12:30 0:30 3897,828 3897,828 0 Drilling Y P 23. Other R/D Wireline Elnusa
12:30 16:00 3:30 3897,828 3897,828 0 Drilling Y P 6. Trips Round Trip, M/U & RIH 12-1/4" PDC (open Nozzle) + BHA Rotary spi kedalaman 718 m.
6. Trips Ljt round Trip, M/U & RIH 12-1/4" PDC (open Nozzle) + BHA Rotary spi kedalaman 1173 m,
16:00 17:30 1:30 3897,828 3897,828 0 Drilling Y P
duduk 15 klbs.
5. Condition Mud &
17:30 18:00 0:30 3897,828 3897,828 0 Drilling Y P Circulate
Washdown spi kedalaman 1180 m.
5. Condition Mud &
18:00 19:00 1:00 3897,828 3897,828 0 Drilling Y P Circulate
Sirkulasi kondisikan lumpur SG 1.23 (ECD)
5. Condition Mud &
19:00 20:00 1:00 3897,828 3897,828 0 Drilling Y P Circulate
Swept out hi vis 30 bbls & spot hi vis 30 bbls di dasar
20:00 00:00 4:00 3897,828 3897,828 0 Drilling Y P 6. Trips POOH 12-1/4" PDC (Open Nozzle) + BHA Rotary spi kedalaman 352 m.
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBERG Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 130 130
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 23
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig RG-750 / JML-03 Avg WOB klbs 5 AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM 130 Daily Cost US 131.126,98
Current MD ft 3.897,83 Torque lb.ft 3.000,00 Cum. Cost US 1.123.592,47
Progress MD ft Stand Pipe Press Psi 1500 Daily Mud Cost US 3.243,21
PTMD ft Flow Rate gpm 750 Cum. Mud Cost US 130.479,34
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Rizkiansyah
Release Date Rotating Weight lbs Night Supervisor Rizkiansyah
Planned Days 30 Total Drilling Time hrs 24,00 Engineer Dian Permana
Days from Spud 22 Circulating Press psi Geologist -
24 Hours Summary Ljt POOH 12-1/4" PDC spi permukaan. RIH Casing 9-5/8 K55 36# R3 spi kedalaman shoe @1186 m; Collar @1162.95 m. Cementing Jobs Casing 9-5/8".
24 Hours Forecast ljt Cementing Jobs Casing 9-5/8". Flush line dari kontaminasi semen. TSK
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
6. Trips
00:00 04:00 4:00 3897,828 3897,828 0 Drilling Y P Ljt POOH 12-1/4" PDC (Open Nozzle) + BHA Rotary spi permukaan & L/D 4 jts DC 8".
5. Condition Mud
17:00 18:00 1:00 3897,828 3897,828 0 Drilling Y P Sirkulasi bersih di dasar.
& Circulate
12. Run Casing
18:00 19:30 1:30 3897,828 3897,828 0 Drilling Y P M/U Cementing Head & Cementing Line
& Cement
5. Condition Mud
19:30 20:30 1:00 3897,828 3897,828 0 Drilling Y P Sirkulasi kondisikan lumpur, turunkan YP.
& Circulate
12. Run Casing PJSM, Flush line 5 bbls, Pressure Test 2000 psi/5mnt. Pompakan 50 bbls Spacer 1.4
& Cement SG (Mud Push 2100 gal; D020 275 lbs, D047 14 gal), jatuhkan bottom plug.
Pompakan 134.5 bbls Lead 1.65 SG (560 sxs semen, D124 5292 lbs; D047 6 gal;
20:30 00:00 3:30 3897,828 3897,828 0 Drilling Y P
D153 155 lbs; D145A 138 gal; D193 221 gal; S001 934 lbs) & 277.13 bbls Tail 1.9 SG
(1600 sxs semen, D047 14 gal; D153 203 lbs; D145A 215.4 gal; D193 934 gal, S001
405 lbs). Jatuhkan top plug.
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBER Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 130 130
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 24
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig RG-750 / JML-03 Avg WOB klbs AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM Daily Cost US 86.823,53
Current MD ft 3.897,83 Torque lb.ft Cum. Cost US 1.210.416,00
Progress MD ft Stand Pipe Press Psi Daily Mud Cost US 350,00
PTMD ft Flow Rate gpm Cum. Mud Cost US 130.829,34
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Rizkiansyah
Release Date Rotating Weight lbs Night Supervisor Rizkiansyah
Planned Days 30 Total Drilling Time hrs Engineer Dian Permana
Days from Spud 23 Circulating Press psi Geologist -
24 Hours Summary Cementing job casing 9-5/8". TSK. N/D Cementing head. BOP Job & Function test. Perbaikan Top Drive. Pressure Test BOP Group 13-5/8" x 5K.
24 Hours Forecast RIH 8-1/2" PDC, tag cement. Ljt bor semen, formasi spi kedalaman 1426 m.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
12. Run Casing &
Cement Ljt Cementing Jobs Csg 9-5/8" : dorong semen dengan 295 bbls lumpur, pemompaan
00:00 02:00 2:00 3897,828 3897,828 0 Drilling Y P
ke 240 bbls, tidak ada aliran balik. Ljt pompa spi 295 bbls, tdk tercapai tekanan bentur.
02:00 03:00 1:00 3897,828 3897,828 0 Drilling Y P 23. Other Flushing line dari kontaminasi semen.
13. Wait On
03:00 04:00 1:00 3897,828 3897,828 0 Drilling Y P Cement
TSK (Tunggu Semen Keras)
13. Wait On
04:00 07:30 3:30 3897,828 3897,828 0 Drilling Y P Cement
Lanjut TSK.
13. Wait On
07:30 08:00 0:30 3897,828 3897,828 0 Drilling Y P Cement
Jajak puncak semen di annulus casing 13-3/8" - 9-5/8", TOC 9 m.
08:00 09:30 1:30 3897,828 3897,828 0 Drilling Y P 23. Other N/D Cementing Head.
09:30 11:00 1:30 3897,828 3897,828 0 Drilling Y P 23. Other Gantung BOP Group 13-5/8 x 5K, & Lakukan Sack Jobs dengan 2 sxs semen.
11:00 15:00 4:00 3897,828 3897,828 0 Drilling Y P 23. Other Pasang Slip Hanger & Potong Casing 9-5/8".
15:00 17:00 2:00 3897,828 3897,828 0 Drilling Y P 23. Other N/U Wellhead Sec B (13-5/8" x 11" x 3 K)
14. Nipple Up N/U DSAF 11" x 3K, Riser Spool 11" x 13-5/8" x 3 K, Drilling Spool 13-5/8" x 3K x 5K,
17:00 21:30 4:30 3897,828 3897,828 0 Drilling Y P B.O.P BOP Group 13-5/8" x 5K, & Bell Nipple. Function test Annular, Pipe ram, HCR OK.
(NPT Rig = 0.5 Jam, kum 96 jam)
21:30 22:30 1:00 3897,828 3897,828 0 Drilling N NP 8. Repair Rig Perbaikan Top Drive : Ganti Actuator Valve, OK. (NPT Rig = 1 Jam, kum 97 jam).
15. Test B.O.P Press Test dgn tester cup Annular low/high 500/1500 psi 10 mnt,baik. Pipe ram
22:30 23:30 1:00 3897,828 3897,828 0 Drilling Y P
500/1500 psi 10 mnt,baik. (NPT Rig = 0.5 jam, kum 97.5 jam).
23:30 00:00 0:30 3897,828 3897,828 0 Drilling Y P 23. Other Stand up DP 5" tambahan, sebanyak 40 jts.
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBER Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 130 130
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 25
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig RG-750 / JML-03 Avg WOB klbs 5 - 10 AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs 8,00 AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM 100 Daily Cost US 56.928,11
Current MD ft 3.956,89 Torque lb.ft Cum. Cost US 1.267.344,11
Progress MD ft 59,06 Stand Pipe Press Psi 1000 Daily Mud Cost US 6.896,15
PTMD ft Flow Rate gpm 550 Cum. Mud Cost US 137.725,49
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Rizkiansyah
Release Date Rotating Weight lbs Night Supervisor Rizkiansyah
Planned Days 30 Total Drilling Time hrs Engineer Dian Permana
Days from Spud 24 Circulating Press psi Geologist -
Stand up DP 5", kum 40 jts. M/U & RIH 8-1/2" PDC + BHA Rotary, tag TOC @1125m. Ljt bor plug, float collar, semen shoe track, float shoe, formasi spi kedalaman 1192 m.
24 Hours Summary
MOT SG eq = 1.5. Ljt bor formasi spi kedalaman 1206 m.
24 Hours Forecast Ljt bor formasi spi kedalaman 1426 m.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
00:00 04:00 4:00 3897,828 3897,828 0 Drilling Y P 23. Other Ljt stand up DP 5" tambahan sebanyak 28 jts kum 30 jts.
04:00 04:30 0:30 3897,828 3897,828 0 Drilling Y P 23. Other Ljt stand up DP 5", tambahan sebanyak 10 jts kum 40 jts
04:30 09:00 4:30 3897,828 3897,828 0 Drilling Y P 2. Drill Actual M/U & RIH 8-1/2" PDC (Open Nozzle) + BHA Rotary, tag TOC @ 1125 m.
09:00 09:30 0:30 3897,828 3897,828 0 Drilling Y P 23. Other Tes tekanan selubung 1000 psi/10 mnt, baik.
09:30 16:00 6:30 3897,828 3897,828 0 Drilling Y P 2. Drill Actual Ljt bor plug, semen shoe track spi kedalaman 1170 m.
16:00 17:30 1:30 3897,828 3897,828 0 Drilling Y P 2. Drill Actual Ljt bor plug, semen shoe track spi kedalaman 1180 m.
17:30 18:00 0:30 3897,828 3897,828 0 Drilling Y P 23. Other Tes tekanan selubung 1000 psi/10 mnt, baik.
18:00 20:30 2:30 3897,828 3897,828 0 Drilling Y P 2. Drill Actual Ljt bor semen, float shoe, formasi spi kedalaman 1192 m.
5. Condition Mud
20:30 21:00 0:30 3897,828 3897,828 0 Drilling Y P Sirkulasi kondisikan lumpur Sgin/out = 1.08.
& Circulate
21:00 21:30 0:30 3897,828 3897,828 0 Drilling Y P 2. Drill Actual POOH 8-1/2" PDC (Open Nozzle)spi shoe @ 1186 m. MOT SG eq 1.50.
21:30 00:00 2:30 3897,828 3956,886 59,058 Drilling Y P 2. Drill Actual Ljt bor formasi spi kedalaman 1206 m (ROP 6 mnt/m, lith 70% Shale, 30% SST)
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBER Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 130 130
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 26
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig RG-750 / JML-03 Avg WOB klbs 2-5 AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs 8,00 AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM 100 Daily Cost US 39.570,69
Current MD ft 3.956,89 Torque lb.ft 3.200,00 Cum. Cost US 1.306.914,80
Progress MD ft 59,06 Stand Pipe Press Psi 1000 Daily Mud Cost US 13.870,07
PTMD ft Flow Rate gpm 550 Cum. Mud Cost US 151.595,56
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Rizkiansyah
Release Date Rotating Weight lbs Night Supervisor Rizkiansyah
Planned Days 30 Total Drilling Time hrs Engineer Dian Permana
Days from Spud 25 Circulating Press psi Geologist -
24 Hours Summary Ljt bor formasi spi kedalaman 1268 m, loss total. Combating loss. Ljt blind drilling spi kedalaman 1295 m.
24 Hours Forecast Ljt bor formasi spi kedalaman 1426 m.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
00:00 04:00 4:00 3897,828 4019,225 121,4 Drilling Y P 2. Drill Actual Ljt bor formasi spi kedalaman 1225 m (ROP 5 mnt/m, lith 60% Shale, 40% SST).
04:00 12:00 8:00 4019,225 4157,027 137,8 Drilling Y P 2. Drill Actual Ljt bor formasi spi kedalaman 1267 m.
8. Repair Rig
12:00 13:00 1:00 4157,027 4157,027 0 Drilling Y P Perbaikan Top Drive : Seal Reversed Torque bocor (NPT Rig = 1 Jam, kum 98 jam).
2. Drill Actual Ljt bor formasi spi kedalaman 1268 m (ROP 10 mnt/m, Lith: 80% SST, 20% Shale),
13:00 13:30 0:30 4157,027 4160,308 3,281 Drilling Y P
Loss Total.
13:30 14:00 0:30 4160,308 4160,308 0 Drilling N NP 23. Other Combat loss#1 : spot 60 ppb LCM (Kwikseal M-C) 50 bbls, aliran balik normal.
14:00 14:30 0:30 4160,308 4163,589 3,281 Drilling Y P 2. Drill Actual Ljt bor formasi spi kedalaman 1269 m (ROP 6 mnt/m, lith: 80% SST, 20% Shale).
14:30 15:30 1:00 4163,589 4186,556 22,967 Drilling Y P 2. Drill Actual Ljt blind drilling spi kedalaman 1276 m (tidak ada aliran balik).
15:30 16:00 0:30 4186,556 4186,556 0 Drilling N NP 23. Other Combat loss#2 : spot 60 ppb LCM (Kwikseal M-C) 100 bbls, tdk ada aliran balik.
16:00 16:30 0:30 4186,556 4186,556 0 Drilling N NP 6. Trips POOH 8-1/2" PDC (Open Nozzle)spi shoe @ 1186 m.
16:30 19:00 2:30 4186,556 4186,556 0 Drilling Y P 2. Drill Actual Tunggu Air , sambil Mixing LCM (NPT Tunggu Air = 2.5 jam)
19:00 19:30 0:30 4186,556 4186,556 0 Drilling Y P 2. Drill Actual RIH 8-1/2" PDC (Open Nozzle) + BHA Rotary spi kedalaman 1276 m.
2. Drill Actual Combat loss#3 : Campuran 40 ppb LCM (CaCO3 M-C) 280 bbls kedalaman sistem,
19:30 22:00 2:30 4186,556 4248,895 62,339 Drilling Y P
sambil ljt blind drilling spi kedalaman 1295 m, tidak ada aliran balik.
22:00 22:30 0:30 4248,895 4248,895 0 Drilling N NP 23. Other Combat loss#4 : spot 60 ppb LCM (Kwikseal M-C), 100 bbls.
22:30 23:00 0:30 4248,895 4248,895 0 Drilling N NP 6. Trips POOH 8-1/2" PDC (Open Nozzle)spi shoe @ 1186 m.
23:00 00:00 1:00 4248,895 4248,895 0 Drilling N NP 23. Other Tunggu Air , sambil Mixing LCM (NPT Tunggu Air = 1 jam, kum 3.5 jam).
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBER Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 130 130
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 27
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig RG-750 / JML-03 Avg WOB klbs AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM Daily Cost US 35.855,65
Current MD ft 4.294,83 Torque lb.ft Cum. Cost US 1.342.770,45
Progress MD ft Stand Pipe Press Psi Daily Mud Cost US 13.027,70
PTMD ft Flow Rate gpm Cum. Mud Cost US 164.623,26
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Rizkiansyah
Release Date Rotating Weight lbs Night Supervisor Rizkiansyah
Planned Days 30 Total Drilling Time hrs Engineer Dian Permana
Days from Spud 26 Circulating Press psi Geologist -
24 Hours Summary Combating Loss. RIH ROE spi kedalaman 1308 m. Cementing Plug dengan semen karbonat. POOH ROE spi 800 m.
24 Hours Forecast Ljt bor formasi spi kedalaman 1426 m.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
00:00 03:30 3:30 4294,829 4294,829 0 Drilling N NP 23. Other Ljt Tunggu Air , sambil Mixing LCM (NPT Tunggu Air = 3.5 jam, kum 7 jam)
03:30 04:00 0:30 4294,829 4294,829 0 Drilling N NP 6. Trips RIH 8-1/2" PDC (Open Nozzle) + BHA Rotary spi kedalaman 1295 m.
23. Other Combat loss#5 : Campuran 40 ppb LCM (CaCO3 M-C) 300 bbls kedalam sistem,
04:00 07:00 3:00 4294,829 4294,829 0 Drilling N NP
sambil ljt blind drilling spi kedalaman 1309 m, tidak ada aliran balik.
07:00 07:30 0:30 4294,829 4294,829 0 Drilling N NP 23. Other Combat loss#6 : spot 50 ppb LCM (Kwikseal M-C) 100 bbls, tidak ada aliran balik.
07:30 13:00 5:30 4294,829 4294,829 0 Drilling N NP 6. Trips POOH 8-1/2" PDC (Open Nozzle) spi permukaan.
13:00 16:00 3:00 4294,829 4294,829 0 Drilling N NP 6. Trips RIH ROE spi kedalaman 859 m, sambil persiapan penyemenan karbonat.
16:00 17:00 1:00 4294,829 4294,829 0 Drilling N NP 6. Trips Ljt RIH ROE spi kedalaman 1186 m.
17:00 19:00 2:00 4294,829 4294,829 0 Drilling N NP 23. Other Ljt mixing semen karbonat.
19:00 19:30 0:30 4294,829 4294,829 0 Drilling N NP 6. Trips Ljt RIH ROE spi kedalaman 1308 m.
19:30 20:00 0:30 4294,829 4294,829 0 Drilling N NP 23. Other M/U Circulating head & treating line .
23. Other PJSM, flush line, pressure test 2500 psi/10', OK. Pompakan 20 bbls water ahead, 50
20:00 21:30 1:30 4294,829 4294,829 0 Drilling N NP bbls cement carbonat SG 1.60 (125 sxs semen, D047 1 gal, D020 451 lbs, D145A 10
gal, D081 gal). Dorong dengan 60 bbls air.
21:30 22:30 1:00 4294,829 4294,829 0 Drilling N NP 6. Trips POOH ROE spi kedalaman 1000 m.
23. Other Pompakan 50 bbls cement carbonat SG 1.60 (125 sxs semen, D047 1 gal, D020 451
22:30 23:00 0:30 4294,829 4294,829 0 Drilling N NP lbs, D145A 10 gal, D081 4.8 gal). Dorong dengan 10 bbls air pertama, ada aliran
balik. Ljt dorong dengan air spi 50 bbls (aliran balik normal).
23:00 23:30 0:30 4294,829 4294,829 0 Drilling N NP 6. Trips POOH ROE spi kedalaman 800 m.
23:30 00:00 0:30 4294,829 4294,829 0 Drilling N NP 23. Other Sirkulasi keluar kontaminasi semen.
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBER Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 130 130
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 28
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig RG-750 / JML-03 Avg WOB klbs AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM Daily Cost US 24.887,02
Current MD ft 4.294,83 Torque lb.ft Cum. Cost US 1.367.657,47
Progress MD ft Stand Pipe Press Psi Daily Mud Cost US 484,49
PTMD ft Flow Rate gpm Cum. Mud Cost US 165.107,75
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Herman R Siagian
Release Date Rotating Weight lbs Night Supervisor Herman R Siagian
Planned Days 30 Total Drilling Time hrs Engineer Dian Permana
Days from Spud 27 Circulating Press psi Geologist -
POOH ROE spi permukaan. M/U & RIH 8-1/2" PDC + BHA spi kedalaman 505 m. Lanjut TSK. Lanjut RIH 8-1/2" PDC + BHA dari 505 m spi 824 m, jajak puncak semen. Bor
24 Hours Summary
semen dari 824 m spi 1055 m dengan GPM/SPP = 550/700 psi, ROPavg = 1.80. Observasi, tidak ada loss.
24 Hours Forecast Ljt bor formasi spi kedalaman 1426 m.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
00:00 03:00 3:00 4294,829 4294,829 0 Drilling N NP 13. Wait On CemenPOOH ROE spi permukaan.
03:00 06:00 3:00 4294,829 4294,829 0 Drilling N NP 13. Wait On CemenM/U & RIH 8-1/2" PDC + BHA spi kedalaman 505 m.
06:00 10:00 4:00 4294,829 4294,829 0 Drilling N NP 13. Wait On CemenLanjut TSK.
10:00 11:00 1:00 4294,829 4294,829 0 Drilling N NP 13. Wait On CemenLanjut RIH 8-1/2" PDC + BHA dari 505 m spi 824 m, jajak puncak semen.
2. Drill Actual Bor semen dari 824 m spi 1055 m dengan GPM/SPP = 550/700 psi, ROPavg = 1.80.
11:00 00:00 13:00 4294,829 4294,829 0 Drilling N NP
Observasi, tidak ada loss.
Morning Status, 08-Jan-2010
2. Drill Actual Bor semen dari 1055 m spi 1125 m dengan GPM/SPP = 550/700 psi, ROPavg = 1.85.
00:00 04:00 4:00 4294,829 4294,829 0 Drilling N NP
Observasi, tidak ada loss.
Bit Record BHA - 1 BHA - 2 Casing
Bit - 1 Bit - 2 BHA Number BHA Run BHA Number BHA Run Last Size in 9-5/8"
Bit Number 1 OD Length OD Length Set MD ft 3891,266
Bit Size in 8-1/2" in ft in ft Next Size in 7"
Bit Run Drill Collar 6,25 184,3922 Set MD ft 4678,706
Manufacturer Chuankee Last LOT EMW ppg
IADC Code - TOL ft
Jets Mud Volumes
Serial # Start bbl
Depth Out ft Lost Surface bbl
Depth In ft Lost DH bbl
Meterage ft Dumped bbl
Bit Hours hrs Built bbl
Nozzles in 4 x 32/32 Ending bbl
Dull Grade - Gas
Cumulative Max. Gas
Footage ft Conn. Gas
Bit Hours hrs Trip Gas
ROP ft/hrs Back Gas
Drilling Fluid Mud Additive
1 2 3 1 2 3 Type Amount
Mud Type KCL-POLYMER Solids % Annular Velocity ft/min
Time HH:MM Sand % Pb psi
MW in ppg 8,41 Water % Sys HHP
MW out ppg 8,41 Oil % HHPb hp
Temp in degF HGS % HSI hp/in2
Temp out degF LGS % %psib %
Pres. Grad psi/ft LTLP bbl Jet Velocity ft/sec
Visc sec HTHP bbl Impact force lbs
PV cP Cake mm IF/area lb/in2
YP lbf/100ft2 E Stb V
Gels 10 sec PF
Gels 10 min MF
Fluid Loss mL/30min PM
pH ECD ppg
Bulk Materials
Type Material Name UOM Received Consumed Returned Adjust Ending
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBER Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 130 130
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 29
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig RG-750 / JML-03 Avg WOB klbs AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM Daily Cost US 33.903,78
Current MD ft 4.501,53 Torque lb.ft Cum. Cost US 1.401.561,24
Progress MD ft 206,70 Stand Pipe Press Psi Daily Mud Cost US 6.536,18
PTMD ft Flow Rate gpm Cum. Mud Cost US 171.643,93
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Herman R Siagian
Release Date Rotating Weight lbs Night Supervisor Herman R Siagian
Planned Days 30 Total Drilling Time hrs Engineer Dian Permana
Days from Spud 28 Circulating Press psi Geologist -
Bor semen dari 1055 m spi 1309 m dengan GPM/SPP = 450-550/600-700 psi, ROPavg = 1.85. Sirkulasi bersikan lubang, swept out 30 bbl hi-vis. Observasi, tidak ada loss.
24 Hours Summary Lanjut bor formasi dari 1309 m spi 1329 m dengan GPM/SPP = 500/600 psi, ROPavg 2.5 mpm, Lithologi 100% Sand. Terjadi loss total di 1329 m. Blind drilling formasi dari
1329 m spi 1372 m, tidak ada aliran. Spot 60 bbl LCM-7 (Kwikseal + CaCO3) 60 pbb, tidak ada aliran.
24 Hours Forecast Combat loss dengan semen karbonat. Ljt bor formasi spi kedalaman 1426 m.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
2. Drill Actual Bor semen dari 1055 m spi 1309 m dengan GPM/SPP = 450-550/600-700 psi, ROPavg
00:00 12:30 12:30 4294,829 4294,829 0 Drilling N NP
= 1.85.
12:30 13:00 0:30 4294,829 4294,829 0 Drilling N NP 13. Wait On CemenSirkulasi bersikan lubang, swept out 30 bbl hi-vis. Observasi, tidak ada loss.
2. Drill Actual Lanjut bor formasi dari 1309 m spi 1329 m dengan GPM/SPP = 500/600 psi, ROPavg
13:00 15:00 2:00 4294,829 4360,449 65,62 Drilling Y P
2.5 mpm, Lithologi 100% Sand. Terjadi loss total di 1329 m.
15:00 23:30 8:30 4360,449 4501,532 141,083 Drilling Y P 2. Drill Actual Blind drilling formasi dari 1329 m spi 1372 m, tidak ada aliran.
23. Other
23:30 00:00 0:30 4501,532 4501,532 0 Drilling N NP Spot 60 bbl LCM-7 (Kwikseal + CaCO3) 60 pbb, tidak ada aliran.
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBER Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 130 130
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 30
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig RG-750 / JML-03 Avg WOB klbs AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM Daily Cost US 30.528,51
Current MD ft 4.501,53 Torque lb.ft Cum. Cost US 1.432.089,75
Progress MD ft Stand Pipe Press Psi Daily Mud Cost US 7.107,10
PTMD ft Flow Rate gpm Cum. Mud Cost US 178.751,03
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Herman R Siagian
Release Date Rotating Weight lbs Night Supervisor Herman R Siagian
Planned Days 30 Total Drilling Time hrs Engineer Dian Permana
Days from Spud 29 Circulating Press psi Geologist -
Cabut rangkaian PDC 8-1/2" + BHA dari 1372 m spi permukaan. Masuk rangkaian open end dari permukaan spi 1370 m. Sirkulasi kondisikan lumpur, tidak ada aliran.
24 Hours Summary
Penyemenan karbonat plug balance #2 untuk combat loss int (1372-1309) m. Masuk rangkaian PDC 8-1/2" + BHA spi 1141 m, gantung rangkaian. TSK.
24 Hours Forecast Lanut jajak puncak semen. Bor semen spi 1372 m dan formasi spi 1426 m.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
00:00 05:00 5:00 4501,532 4501,532 0 Drilling N NP 23. Other Cabut rangkaian PDC 8-1/2" + BHA dari 1372 m spi permukaan.
05:00 09:00 4:00 4501,532 4501,532 0 Drilling N NP 23. Other Masuk rangkaian open end dari permukaan spi 1370 m.
Drilling 23. Other Sirkulasi kondisikan lumpur, tidak ada aliran.
09:00 09:30 0:30 4501,532 4501,532 0 N NP
23. Other
Penyemenan karbonat plug balance #2 untuk combat loss int (1372-1309) m dengan
prosedur : PJSM. Mixing 60 bbl cement slurry SG 1.60. M/U cementing head, test
09:30 11:00 1:30 4501,532 4501,532 0 Drilling N NP cementing line 2000 psi/5 mnt baik. Pompakan 20 bbl water ahead. Pompakan 60 bbl
cement slurry SG 1.60 (125 sx semen + add). Displace cement slurry dengan 62.5 bbl
air, setelah displace 48 bbl diperoleh aliran.
23. Other Cabut rangkaian open end, rangkaian stuck. Cabut rangkaian dengan WOP 0 - 115
ton, tidak berhasil. Putar rangkaian, tidak bisa. Cabut rangkaian dengan WOP 0 - 115
11:00 11:30 0:30 4501,532 4501,532 0 Drilling N NP
ton sambil pompakan air dengan GPM/SPP 125/550 psi, rangkaian berhasil dicabut
(berat rangkaian open end 55 ton, over pull 60 ton).
23. Other Cabut rangkaian open end dari 1370 m spi 985 m. Sirkulasi lurus, diperoleh
11:30 13:30 2:00 4501,532 4501,532 0 Drilling N NP
kontaminasi semen. Observasi loss stat 0 bpm.
13:30 16:00 2:30 4501,532 4501,532 0 Drilling N NP 23. Other Lanjut cabut rangkaian dari 985 m spi permukaan, rangkaian terangkat semua.
16:00 20:00 4:00 4501,532 4501,532 0 Drilling N NP 23. Other Masuk rangkaian PDC 8-1/2" + BHA spi 1141 m. Sirkulasi, gantung rangkaian.
20:00 00:00 4:00 4501,532 4501,532 0 Drilling N NP 23. Other TSK.
Morning Status, 10-Jan-2010
00:00 03:00 3:00 4501,532 4501,532 0 Drilling N NP 6. Trips Lanjut TSK, sampel semen belum keras.
6. Trips Lanjut masuk rangkaian PDC 8-1/2" + BHA dari 1141 m spi 1270 m, jajak puncak
03:00 04:00 1:00 4501,532 4501,532 0 Drilling N NP
semen.
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBER Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 130 130
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
Daily Operations Report lambang oil company
Operator PT. PERTAMINA EP Contractor PT. JAYA MIMIKA LESTARI (JML) Rpt. # 31
Well Name TT-28 Type Development Field TTM-SA1 Env. Onshore
Latitude E = 322,571,90 Longitude N = 9,759,448.09 WD ft
General Drilling Parameters AFE
Rig Type / Name Land Rig RG-750 / JML-03 Avg WOB klbs AFE Number 09-3930
Rig Power hp 750 Avg ROP ft/hs AFE Cost US 2.177.840,38
KB Elevation ft 23 Avg RPM Daily Cost US 26.359,35
Current MD ft 4.629,49 Torque lb.ft Cum. Cost US 1.458.449,11
Progress MD ft 127,96 Stand Pipe Press Psi Daily Mud Cost US 2.157,05
PTMD ft Flow Rate gpm Cum. Mud Cost US 180.908,08
Spud Date 11-Des-2009 String Weight lbs Day Supervisor Herman R Siagian
Release Date Rotating Weight lbs Night Supervisor Herman R Siagian
Planned Days 30 Total Drilling Time hrs Engineer Dian Permana
Days from Spud 30 Circulating Press psi Geologist -
Lanjut TSK, sampel semen belum keras. Lanjut masuk rangkaian PDC 8-1/2" + BHA dari 1141 m spi 1270 m, jajak puncak semen. Bor semen dari 1270 m spi 1372 m dengan
24 Hours Summary GPM/SPP : 500/600 psi. Sirkulasi bersikan lubang, swept out 30 bbl hi-vis. Observasi, loss stat : 0 bpm. Bor formasi dari 1372 m spi 1411 m dengan GPM/SPP: 500/600 psi,
ROPavg: 9.0 mpm, litologi shale 100%. Terjadi loss total di 1411 m.
24 Hours Forecast Combat loss. Trip. Logging.
Time Breakdown
Time hh:mm Measured Depth Length Task
Start End Elapsed Start End ft Category P NPT Code
00:00 03:00 3:00 4501,532 4501,532 0 Drilling N NP 23. Other Lanjut TSK, sampel semen belum keras.
23. Other Lanjut masuk rangkaian PDC 8-1/2" + BHA dari 1141 m spi 1270 m, jajak puncak
03:00 04:00 1:00 4501,532 4501,532 0 Drilling N NP
semen.
04:00 15:00 11:00 4501,532 4501,532 0 Drilling N NP 23. Other Bor semen dari 1270 m spi 1372 m dengan GPM/SPP : 500/600 psi.
15:00 16:00 1:00 4501,532 4501,532 0 Drilling N NP 23. Other Sirkulasi bersikan lubang, swept out 30 bbl hi-vis. Observasi, loss stat : 0 bpm
23. Other Bor formasi dari 1372 m spi 1411 m dengan GPM/SPP: 500/600 psi, ROPavg: 9.0
16:00 00:00 8:00 4501,532 4629,491 127,959 Drilling Y P
mpm, litologi shale 100%. Terjadi loss total di 1411 m.
Morning Status, 11-Jan-2010
00:00 04:00 4:00 4629,491 4691,83 62,339 Drilling Y P 6. Trips Blind drilling dari 1411 m spi TD di 1430 m, tidak ada aliran.
HSE
Stop Safety Flag
Cards LTA Spill H2S Test HSE Mtg Kick-Trip Kick-Drill Fire
Directional Survey
MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg) MD (ft) Incl. (deg) Azm (deg)
Personnel Pumps
Company People Company People Pump Name MP#1 MP#2
PT. PERTAMINA EP 2 SECURITY 1 Time hh:mm 00:00 00:00
PT. DOWELL SCHLUMBER Slow Speed? y/n
PT. SCOMI 2 Circulate
PT. ESLOG 4 Strokes SPM 130 130
PT. JML 13 Pressure psi
PT. TESCO 2 Liner Size in 5 5
PT. PATRAKOM 1 Efficiency % 90 90
PARAMEDIC 0
Weather
Temperature (degF) Chill Wind Barometric Sea Condition
Road Condition Visibility
High Low Factor Speed (knot) Direction (deg) Pres (atm) Wave Height Current Speed
DAILY WORKOVER / COMPLETION REPORT : AFE : 08.3930 DATE : FEB 03, 2010
REPORT # : 1 RIG # : EPI - 35
WELL NAME :TT- 028 KB ELEV : 67.81 m TOOLPUSHER : BAHARUDIN / SUKARDI
OBJECTIVES : - PERFORATE KB - CF : 6.42 m RIG SUPT : SURATNO
- SWAB TEST TD : 1440.0 m COMPANY MAN : SUPRAPTO
- PROD Ca, Cb, C1 ZONES PBTD (TOC) : 1434.0 m DAILY RIG COST : 5358,0
CSG. SIZE : 13 3/8", K 55 WEIGHT : 54.5 PPF DEPTH : 196.0 m CUMM RIG COST : 5358,0
CSG. SIZE : 9 5/8", K 55 WEIGHT : 36.0 PPF DEPTH : 1186.0 m DAILY COST : 6148
CSG. SIZE : 7", J 55 WEIGHT : 23.0 PPF DEPTH : 1439.0 m CUMM COST : 6.148
TBG SIZE : 3 1/2" WEIGHT : 9.3 PPF DEPTH : PERFORATION
# OF TBGS : BHP TYPE : ZONE - Ca -
ROD SIZE : BHP NO : ZONE Cb -
# OF RODS : PKR : ZONE - C1 -
# ROD GUIDE : TAIL END :
SICP ( psi ) :
06:00 - 17:30 11,50 R/M F/ WS- 024 TO TT- 028 C/W EQUIPMENT, WHILE RIG MOVE REPAIRED LOCATION TT- 028 BY UTILITIS (START 13:15 HRS TO 16:00 HRS)
17:30 - 19:30 2,00 PRE JOB SAFETY MEETING, R/U & TENSION GUYLINES, INSTALLED SURFACE LINE, OBS WELL, SITP & SICP = 0 PSI
19:30 - 23:30 4,00 REMOVED MASTER VALVE C/W 3000 PSI x3" FLANGE, N/U & FUNCT TEST 7 1/16" - 3000 PSI RAM TYPE BOP & 7 1/16" x 3000 PSI ANN BOP
23:30 - 00:00 0,50 R/U WORKFLOOR & TBG POWER TONG WHILE MIXED 80 BBLS 2% KCL WATER, USED 5 SAX KCL
00:00 - 00:30 0,50 M/U 6 1/8" BIT, 7" CSG SCRAPER, X/O (EPI OWN), 1 - 2 7/8" EU PJ , X/O, 3 1/2" CHECK VALVE
00:30 - 05:00 4,50 RIH W/ 60 - 3 1/2" EU TBG (TALLIED, DRIFTED, FILL UP TBG VOL W/ KCL WATER & PRESS TEST TBG EVERY 20 JTS TBG DOWN
TO 1500 PSI/ 5 MINS, LAST PRESS TEST TBG TO 1500 PSI PRESS DROP TO 0 PSI, TBG LEAK INDICATION) TO 565.0.mKB
05:00 - 06:00 1,00 POH 7" CSG SCRAPER F/ CHECK TBG LEAK W/ STD BACK 30 - 3 1/2" EU TBG TO 285.0 mKB
PLAN : CONT POH 7" CSG SCRAPER UNTIL FOUND TBG LEAK, RE RIH TO TAG FILL & PRESS TEST TBG TO 1500 PSI
1 TANGIBLE COSTS
2 CASING
3 CASING ACCESORIES
4 TUBING
5 WELL EQPT - SURF
6 WELL EQPT - SUBSURF
7 OTHER TANGIBLE COSTS
10 INTANGIBLE COSTS
11 PREPARATION & TERMINATION
12 SURVEY
13 LOCATION STAKING & POSITIONING
14 WELL SITE & ACCESS ROAD PREP'N
15 SERVICE LINES & COMMUNICATIONS
16 WATER SYSTEMS
17 RIGGING UP / DOWN
20 DRILLING / WORKOVER OPERATIONS :
21 CONTRACT RIG 5.358 5.358
23 MUD CHEMICAL & ENGINEERING SERVICES 271 271
25 BITS, REAMERS, COREHEADS
26 EQUIPMENT RENTAL
27 DIRECTIONAL DRILLING
29 CASING INSTALLATION
30 CEMENT, CEMENTING & PUMP FEETS
31 OTHER ( SWAB RUBBER,ETC )
37 OPEN HOLE ELECTRICAL LOGGING SERVICES
COMPLETION
42 CEMENT, CEMENTING & PUMP FEETS
43 CASED HOLE ELECTRICAL LOGGING SERVICES
44 PERFORATING & WIRELINE SERVICES
45 STIMULATION TREATMENT
47 OTHER 4 1/2" BP AND CR
49 GENERAL
50 SUPERVISION 200 200
51 INSURANCE
52 WATER TRANSPORTATION
55 LAND TRANSPORTATION
56 OTHER TRANSPORTATION (WATER)
57 FUEL & LUBRICATION 319 319
60 CAMP FACILITIES
61 ALLOCATED OVERHEAD-FIELD OFFICE
61 JKT OFFICE
61 OVERSEAS
TOTAL COST (US $) 5.558 590 6.148
06:00 - 06:30 0,50 CONT POH 7" CSG SCRAPER W/ STD BACK 8 - 3 1/2" EU TBG, FOUND TBG LEAK (TBG SPLIT @ JT #22, 2.15 M F/ PIN END, 8 CM LENGTH)
06:30 - 14:00 7,50 RE RIH 7" CSG SCRAPER W/ 99 - 3 1/2" EU TBG (TALLIED, DRIFTED, FILL UP TBG VOL W/ KCL WTR & PRESS TEST TBG TO 1500 PSI/ 5 MINS
EVERY 20 JTS TBG DOWN), TAGGED @ 1130.50 mKB
14:00 - 15:00 1,00 ATTEMPTED TO GO DOWN CSG SCRAPER W/ WORK PIPE SEVERAL TIMES, NO SUCCESS
15:00 - 19:30 4,50 POH 7" CSG SCRAPER W/ L/D 1 - 3 1/2" EU TBG, STD BACK 121 - 3 1/2" EU TB, L/D CSG SCRAPER ASSY
19:30 - 21:00 1,50 M/U 6 1/8" TOOTH BIT, 4 3/4" BIT SUB, 4 - 4 3/4" DC, X/O (BHA #1)
21:00 - 01:00 4,00 RIH W/ 117 - 3 1/2" EU TBG TAGGED @ 1130.5 mKB, WHILE MIXED 80 BBLS 2% KCL WATER
01:00 - 02:00 1,00 M/U POWER SWIVEL & TBG STRIPPER
02:00 - 03:30 1,50 WORK PIPE INT 1130.5 - 1135.0 mKB, 2000# TO NORMAL DRAG DOWN, L/D POWER SWIVEL & TBG STRIPER
03:30 - 05:00 1,50 CONT RIH 6 1/8" TOOTH BIT W/ 32 - 3 1/2" EU TBG TAGGED @ 1431.25 mKB
05:00 - 06:00 1,00 POH 6 1/8" TOOTH BIT W/ L/D 1 - 3 1/2" EU TBG, STD BACK 32 - 3 1/2" EU TBG TO 1130.0 mKB
PLAN : CONT POH 6 1/8" TOOTH BIT & RIH 7" CSG SCRAPER
1 TANGIBLE COSTS
2 CASING
3 CASING ACCESORIES
4 TUBING
5 WELL EQPT - SURF
6 WELL EQPT - SUBSURF
7 OTHER TANGIBLE COSTS
10 INTANGIBLE COSTS
11 PREPARATION & TERMINATION
12 SURVEY
13 LOCATION STAKING & POSITIONING
14 WELL SITE & ACCESS ROAD PREP'N
15 SERVICE LINES & COMMUNICATIONS
16 WATER SYSTEMS
17 RIGGING UP / DOWN
20 DRILLING / WORKOVER OPERATIONS :
21 CONTRACT RIG 6.038 5.358 11.396
23 MUD CHEMICAL & ENGINEERING SERVICES 271 271 542
25 BITS, REAMERS, COREHEADS
26 EQUIPMENT RENTAL
27 DIRECTIONAL DRILLING
29 CASING INSTALLATION
30 CEMENT, CEMENTING & PUMP FEETS
31 OTHER ( SWAB RUBBER,ETC )
37 OPEN HOLE ELECTRICAL LOGGING SERVICES
COMPLETION
42 CEMENT, CEMENTING & PUMP FEETS
43 CASED HOLE ELECTRICAL LOGGING SERVICES
44 PERFORATING & WIRELINE SERVICES
45 STIMULATION TREATMENT
47 OTHER 4 1/2" BP AND CR
49 GENERAL
50 SUPERVISION 200 200 400
51 INSURANCE
52 WATER TRANSPORTATION
55 LAND TRANSPORTATION
56 OTHER TRANSPORTATION (WATER)
57 FUEL & LUBRICATION 410 319 729
60 CAMP FACILITIES
61 ALLOCATED OVERHEAD-FIELD OFFICE
61 JKT OFFICE
61 OVERSEAS
TOTAL COST (US $) 6.238 681 6.148 13.067
06:00 - 10:30 4,50 CONT POH 6 1/8" TOOTH BIT W/ STD BACK 116 - 3 1/2" EU TBG TO 40.0 mKB
10:30 - 12:00 1,50 L/D X/O, 4 - 4 3/4" DC, 4 3/4" BIT SUB, 6 1/8" TOOTH BIT (BHA #1)
12:00 - 13:00 1,00 SERVICED ROUTINE ENGINE DRAWWORKS
13:00 - 13:30 0,50 M/U 6 1/8" BIT, 7" CSG SCRAPER, X/O (EPI OWN), 1 - 2 7/8" EU PJ , X/O, 3 1/2" CHECK VALVE
13:30 - 18:30 5,00 RIH W/ 153 - 3 1/2" EU TBG TAGGED @ 1431.25 mKB (FILL UP TBG VOL W/ KCL WATER & PRESS TEST TBG EVERY 30 JTS TBG DOWN
TO 1500 PSI/ 5 MINS, INTV : 1130.50 - 1130.55 mKB W/ 2000# DRAG DOWN & SLOW ROTATE, P/U NO OVERPULL)
18:30 - 00:00 5,50 POH 7" CSG SCRAPER W/ L/D 15 - 3 1/2" EU TBG, STD BACK 138 - 3 1/2" EU TBG TO 285.0 mKB, L/D CSG SCRAPER ASSY
00:00 - 00:30 0,50 M/U & RIH 2 - 3 1/2" EU TBG, LANDED W/ TBG HANGER, TAIL END @ 22.0 mKB
00:30 - 06:00 5,50 W/O DAYLIGHT F/ PERFORATE
1 TANGIBLE COSTS
2 CASING
3 CASING ACCESORIES
4 TUBING
5 WELL EQPT - SURF
6 WELL EQPT - SUBSURF
7 OTHER TANGIBLE COSTS
10 INTANGIBLE COSTS
11 PREPARATION & TERMINATION
12 SURVEY
13 LOCATION STAKING & POSITIONING
14 WELL SITE & ACCESS ROAD PREP'N
15 SERVICE LINES & COMMUNICATIONS
16 WATER SYSTEMS
17 RIGGING UP / DOWN
20 DRILLING / WORKOVER OPERATIONS :
21 CONTRACT RIG 5.761 11.396 17.157
23 MUD CHEMICAL & ENGINEERING SERVICES 542 542
25 BITS, REAMERS, COREHEADS
26 EQUIPMENT RENTAL
27 DIRECTIONAL DRILLING
29 CASING INSTALLATION
30 CEMENT, CEMENTING & PUMP FEETS
31 OTHER ( SWAB RUBBER,ETC )
37 OPEN HOLE ELECTRICAL LOGGING SERVICES
COMPLETION
42 CEMENT, CEMENTING & PUMP FEETS
43 CASED HOLE ELECTRICAL LOGGING SERVICES
44 PERFORATING & WIRELINE SERVICES
45 STIMULATION TREATMENT
47 OTHER 4 1/2" BP AND CR
49 GENERAL
50 SUPERVISION 200 400 600
51 INSURANCE
52 WATER TRANSPORTATION
55 LAND TRANSPORTATION
56 OTHER TRANSPORTATION (WATER) 100 100
57 FUEL & LUBRICATION 455 729 1.184
60 CAMP FACILITIES
61 ALLOCATED OVERHEAD-FIELD OFFICE
61 JKT OFFICE
61 OVERSEAS
TOTAL COST (US $) 5.961 555 13.067 19.583
06:00 - 08:30 2,50 STD BY (ELNUSA OPEN HOLE LOGGING JOB @ TT- 026)
08:30 - 09:00 0,50 POH KILL STRING W/ 2 - 3 1/2" EU TBG, M/U WIRE LINE LUBRICATOR & PRESS TEST TO 500 PSI, OK
09:00 - 09:30 0,50 SET ELNUSA WIRELINE UNIT & ELNUSA TOOLS, PRE JOB SAFETY MEETING
09:30 - 14:30 5,00 M/U & RIH 4 1/2" WIRELINE CSG GUNS LOADED WITH 34BX, 22.7 GRAM RDX XDP, 6 SPF SPACED TO PERFORATE PROD ZONE
("Ca, Cb & C1" ZONES) AS FOLLOW :
- RUN # 1 : PERF "C1" ZONE INTV : 1325.0 - 1327.0 m,FIRED @ 10:37 HRS (SNL AFL FULL BEFORE & AFTER FIRED)
- RUN # 2 : PERF "Cb" ZONE INTV : 1316.0 - 1320.0 m,FIRED @ 11:49 HRS (SNL AFL FULL BEFORE & AFTER FIRED)
- RUN # 3 : PERF "Cb" ZONE INTV : 1309.0 - 1314.0 m,FIRED @ 12:58 HRS (SNL AFL FULL BEFORE & AFTER FIRED)
- RUN # 4 : PERF "Ca" ZONE INTV : 1284.0 - 1290.0 m,FIRED @ 14:12 HRS (SNL AFL 30 m BEFORE & 44 m AFTER FIRED)
CORRELATION ON DEPTH TO CBL-VDL-GR-CCL, DATE JAN 20, 2010
14:30 - 15:00 0,50 R/D ELNUSA WIRE LINE TOOLS & WIRE LINE LUBRICATOR
15:00 - 15:30 0,50 M/U 7" RBP, RETRIEVE TOOL, 1 - 2 7/8" EU PJ, X/O
15:30 - 19:30 4,00 RIH W/ 139 - 3 1/2" EU TBG & SET RBP @ 1297.0 mKB W/ 20.000# COMP, 12.000# TENSION (RE DRIFTED, TEST SET & PRESS TEST RBP
@ 471.61 mKB TO 500 PSI, OK)
19:30 - 23:00 3,50 POH 5 1/2" RBP RETRIEVE TOOL W/ L/D 1 - 3 1/2" EU TBG, STD BACK 138 - 3 1/2" EU TBG & 3 1/2" TBG COLLAR (X/O 3 1/2" EU PIN x 2 7/8" EU
PIN, RETRIEVE TOOL & RBP LEFT IN HOLE)
23:00 - 03:00 4,00 M/U 3 1/2" EU TBG COLLAR & RIH W/ 139 - 3 1/2" EU TBG TAGGED & RECONNECTED RETRIEVE TOOL, P/U TO 30.000# (21.000# WOS)
03:00 - 04:00 1,00 ATTEMPTED TO RELEASE RETRIEVE TOOL, OK
04:00 - 06:00 2,00 POH 5 1/2" RBP RETRIEVE TOOL W/ L/D 1 - 3 1/2" EU TBG, STD BACK 86 - 3 1/2" EU TBG TO 480 mKB
PLAN : CONT POH 5 1/2" RBP RETRIEVE TOOL, RIH 7" HD PKR
1 TANGIBLE COSTS
2 CASING
3 CASING ACCESORIES
4 TUBING
5 WELL EQPT - SURF
6 WELL EQPT - SUBSURF
7 OTHER TANGIBLE COSTS
10 INTANGIBLE COSTS
11 PREPARATION & TERMINATION
12 SURVEY
13 LOCATION STAKING & POSITIONING
14 WELL SITE & ACCESS ROAD PREP'N
15 SERVICE LINES & COMMUNICATIONS
16 WATER SYSTEMS
17 RIGGING UP / DOWN
20 DRILLING / WORKOVER OPERATIONS :
21 CONTRACT RIG 5.635 17.157 22.792
23 MUD CHEMICAL & ENGINEERING SERVICES 542 542
25 BITS, REAMERS, COREHEADS
26 EQUIPMENT RENTAL
27 DIRECTIONAL DRILLING
29 CASING INSTALLATION
30 CEMENT, CEMENTING & PUMP FEETS
31 OTHER ( SWAB RUBBER,ETC )
37 OPEN HOLE ELECTRICAL LOGGING SERVICES
COMPLETION
42 CEMENT, CEMENTING & PUMP FEETS
43 CASED HOLE ELECTRICAL LOGGING SERVICES
44 PERFORATING & WIRELINE SERVICES
45 STIMULATION TREATMENT
47 OTHER 4 1/2" BP AND CR
49 GENERAL
50 SUPERVISION 200 600 800
51 INSURANCE
52 WATER TRANSPORTATION
55 LAND TRANSPORTATION
56 OTHER TRANSPORTATION (WATER) 100 100
57 FUEL & LUBRICATION 387 1.184 1.571
60 CAMP FACILITIES
61 ALLOCATED OVERHEAD-FIELD OFFICE
61 JKT OFFICE
61 OVERSEAS
TOTAL COST (US $) 5.835 387 19.583 25.805
RUN TIME TIME TANK VOL TANK VOL VOL FLUID SWAB
NO. IN OUT BEFORE AFTER REC LEVEL DEPTH RIG TANK RESULT SAMPLE REMARKS
INCHES INCHES BBLS m m CI - pH WTR OIL Cl-
LAST CUMM. =
10 17:15 17:30 9,0 9,0 1275 1.275 CHANGE 1 EA NITRILE SWAB CUP
SUMMARY
HOURS SWAB TOTAL REC IFL FFL SWAB DEPTH REC OIL ACID CTM FORM WTR CUMM R CUMM REC
( BBLS ) (m) (m) (m) ( BBLS ) ( BBLS ) ( BBLS ) ( BBLS )
3,50 30,71 94 1.169 1275 30,71 30,71 30,71
DAILY WORKOVER / COMPLETION REPORT : AFE : 08.3930 DATE : FEB 07, 2010
REPORT # : 5 RIG # : EPI - 35
WELL NAME :TT- 028 KB ELEV : 67.81 m TOOLPUSHER : BAHARUDIN / AMAT TANGKIL
OBJECTIVES : - PERFORATE KB - CF : 6.42 m RIG SUPT : SURATNO
- SWAB TEST TD : 1440.0 m COMPANY MAN : SUPRAPTO
- PROD Ca, Cb, C1 ZONES PBTD (TOC) : 1434.0 m DAILY RIG COST : 5459,0
CSG. SIZE : 13 3/8", K 55 WEIGHT : 54.5 PPF DEPTH : 196.0 m CUMM RIG COST : 28251,0
CSG. SIZE : 9 5/8", K 55 WEIGHT : 36.0 PPF DEPTH : 1186.0 m DAILY COST : 7120
CSG. SIZE : 7", J 55 WEIGHT : 23.0 PPF DEPTH : 1439.0 m CUMM COST : 32.925
TBG SIZE : 3 1/2" WEIGHT : 9.3 PPF DEPTH : 1277.15 m PERFORATION
# OF TBGS : 136 JTS & 2 JTS PJ BHP TYPE : 7" HD PKR ZONE - Ca 1284.0 - 1290.0 m
ROD SIZE : BHP NO : PTM OWN ZONE - Cb 1309.0 - 1320.0 m
# OF RODS : PKR : 1278.75 m ZONE - C1 1325.0 - 1327.0 m
# ROD GUIDE : TAIL END : 1280.40 m
RBP : 1297.0 m
SICP ( psi ) :
PRES. OPN : PREPARING F/ CONT SWAB TEST Ca ZONE
06:00 - 07:30 1,50 CONT POH 5 1/2" RBP RETRIEVE TOOL W/ STD BACK 52 - 3 1/2" EU TBG, L/D X/O & RBP RETRIEVE TOOL
07:30 - 08:00 0,50 M/U 2 7/8" BELL SHOE, 1 - 2 7/8" EU PJ, 7" HD PKR, 2 7/8" PSN, X/O
08:00 - 12:00 4,00 RIH W/ 138 - 3 1/2" EU TBG, 2 - 3 1/2" EU PJ (RE DRIFTED) TO 1294.0 mKB (WHILE RIH TEST SET & PRESS TEST HD PACKER AT BLANK CSG
@ 471.20 mKB TO 500 PSI/ 5 MINS- OK)
12:00 - 13:00 1,00 SET 7" HD PKR @ 1293.33 mKB W/ 15000# COMP, TAIL END @ 1294.98 mKB, FILL UP TBG VOL W/ 2.0 BBLS 6 % KCL WTR, PRESS TEST
RBP TO 1500 PSI / 10 MINS
13:00 - 14:00 1,00 UNSET & RAISED PKR W/ L/D 2 - 3 1/2" EU TBG, ADDED 2 - 3 1/2" EU PJ,
SET PKR @ 1278.75 mKB W/ 15.000# COMP, LANDED STRING
W/ CONV TBG HANGER,TAIL END @ 1280.40 mKB,FILL UP CSG ANN VOL W/ 4 BBLS 6% KCL WATER & PRESS TEST PKR TO 500 PSI, OK
14:00 - 15:00 1,00 M/U SWAB HD, SWAB LUBRICATOR & SWAB SINKER
15:00 18:30 3,50 SWABBED TEST "Ca" ZONE W/ 11 SWABS IN 3.5 HRS, SWAB DEPTH : 1275 mWLM, IFL = 94 m, FFL = 1169 m, REC : 30.70 BBLS WATER,
USE : 1 EA NITRILE OIL SAVER & 3 EA NITRILE SWAB CUP
18:30 - 06:00 11,50 W/O DAYLIGHT F/ CONT SWAB TEST Ca ZONE, WHILE OBS WELL, SITP & SICP = 0 PSI
1 TANGIBLE COSTS
2 CASING
3 CASING ACCESORIES
4 TUBING
5 WELL EQPT - SURF
6 WELL EQPT - SUBSURF 979,27 979
7 OTHER TANGIBLE COSTS
10 INTANGIBLE COSTS
11 PREPARATION & TERMINATION
12 SURVEY
13 LOCATION STAKING & POSITIONING
14 WELL SITE & ACCESS ROAD PREP'N
15 SERVICE LINES & COMMUNICATIONS
16 WATER SYSTEMS
17 RIGGING UP / DOWN
20 DRILLING / WORKOVER OPERATIONS :
21 CONTRACT RIG 5.459 22.792 28.251
23 MUD CHEMICAL & ENGINEERING SERVICES 542 542
25 BITS, REAMERS, COREHEADS
26 EQUIPMENT RENTAL
27 DIRECTIONAL DRILLING
29 CASING INSTALLATION
30 CEMENT, CEMENTING & PUMP FEETS
31 OTHER ( SWAB RUBBER,ETC )
37 OPEN HOLE ELECTRICAL LOGGING SERVICES
COMPLETION
42 CEMENT, CEMENTING & PUMP FEETS
43 CASED HOLE ELECTRICAL LOGGING SERVICES
44 PERFORATING & WIRELINE SERVICES
45 STIMULATION TREATMENT
47 OTHER 4 1/2" BP AND CR
49 GENERAL
50 SUPERVISION 200 800 1.000
51 INSURANCE
52 WATER TRANSPORTATION
55 LAND TRANSPORTATION
56 OTHER TRANSPORTATION (WATER) 100 100
57 FUEL & LUBRICATION 482 1.571 2.053
60 CAMP FACILITIES
61 ALLOCATED OVERHEAD-FIELD OFFICE
61 JKT OFFICE
61 OVERSEAS
TOTAL COST (US $) 5.659 1.461 25.805 32.925
RUN TIME TIME TANK VOL TANK VOL VOL FLUID SWAB
NO. IN OUT BEFORE AFTER REC LEVEL DEPTH RIG TANK RESULT SAMPLE REMARKS
INCHES INCHES BBLS m m CI - pH WTR OIL Cl-
LAST CUMM. = 30,70
USE 1 EA OIL SAVER & 2 EA NITRILESWAB CUP
SUMMARY
HOURS SWAB TOTAL REC IFL FFL SWAB DEPTH REC OIL ACID CTM FORM WTR CUMM R CUMM REC
( BBLS ) (m) (m) (m) ( BBLS ) ( BBLS ) ( BBLS ) ( BBLS )
12,50 6,16 1.222 1.275 1275 6,16 6,16 36,86
DAILY WORKOVER / COMPLETION REPORT : AFE : 08.3930 DATE : FEB 08, 2010
REPORT # : 6 RIG # : EPI - 35
WELL NAME :TT- 028 KB ELEV : 67.81 m TOOLPUSHER : BAHARUDIN / AMAT TANGKIL
OBJECTIVES : - PERFORATE KB - CF : 6.42 m RIG SUPT : SURATNO
- SWAB TEST TD : 1440.0 m COMPANY MAN : SUPRAPTO
- PROD Ca, Cb, C1 ZONES PBTD (TOC) : 1434.0 m DAILY RIG COST : 6038,0
CSG. SIZE : 13 3/8", K 55 WEIGHT : 54.5 PPF DEPTH : 196.0 m CUMM RIG COST : 34289,0
CSG. SIZE : 9 5/8", K 55 WEIGHT : 36.0 PPF DEPTH : 1186.0 m DAILY COST : 6860
CSG. SIZE : 7", J 55 WEIGHT : 23.0 PPF DEPTH : 1439.0 m CUMM COST : 39.785
TBG SIZE : 3 1/2" WEIGHT : 9.3 PPF DEPTH : 1025.43 m PERFORATION
# OF TBGS : 110 JTS BHP TYPE : ZONE - Ca 1284.0 - 1290.0 m
ROD SIZE : BHP NO : ZONE - Cb 1309.0 - 1320.0 m
# OF RODS : PKR : ZONE - C1 1325.0 - 1327.0 m
# ROD GUIDE : TAIL END : 1026.0 m
RBP : 1323.0 m
SICP ( psi ) :
PRES. OPN : POH 5 1/2" RBP RETRIEVE TOOL
06:00 - 18:30 12,50 CONT SWABBED TEST "Ca" ZONE W/ 12 SWABS IN 12.5 HRS, SWAB DEPTH : 1275 mWLM, IFL = 1222 m, FFL = 1222 m, REC : 6.14 BBLS WTR,
& TRC OIL (CUMM : 36.84 BBLS), LAST SWAB AFTER OBS WELL F/ 2 HRS, REC 1.54 BBLS, USE : 1 EA NITRILE OIL SAVER & 4 EA NITRILE
SWAB CUP
18:30 - 19:30 1,00 L/D SWAB LUBRICATOR, SWAB SINKER & SWAB HD
19:30 - 23:30 4,00 UNSET & POH 7" HD PKR W/ L/D 2 - 3 1/2" EU PJ, STD BACK 136 - 3 1/2" EU TBG, L/D X/O, PSN, PKR, 1 - 2 7/8" EU PJ C/W BELLSHOE (RUBBER
PKR STILL GOOD COND)
23:30 - 04:00 4,50 M/U 5 1/2" RBP RETRIEVE TOOL, X/O & RIH W/ 139 - 3 1/2" EU TBG TAGGED & CAUGHT RBP @ 1297.0 mKB
04:00 - 05:00 1,00 LOWER RBP W/ 3 - 3 1/2" EU TBG, SET RBP @ 1323.0 mKB W/ 20.000# COMP, 10.000# TENSION, RELEASED RETRIEVE TOOL
05:00 - 06:00 1,00 POH 5 1/2" RBP RETRIEVE TOOL W/ L/D 2 - 3 1/2" EU TBG, STD BACK 30 - 3 1/2" EU TBG TO 1026.0 mKB
PLAN : CONT POH 5 1/2" RBP RETRIEVE TOOL & RIH 7" HD PKR
1 TANGIBLE COSTS
2 CASING
3 CASING ACCESORIES
4 TUBING
5 WELL EQPT - SURF
6 WELL EQPT - SUBSURF 171,91 979 1.151
7 OTHER TANGIBLE COSTS
10 INTANGIBLE COSTS
11 PREPARATION & TERMINATION
12 SURVEY
13 LOCATION STAKING & POSITIONING
14 WELL SITE & ACCESS ROAD PREP'N
15 SERVICE LINES & COMMUNICATIONS
16 WATER SYSTEMS
17 RIGGING UP / DOWN
20 DRILLING / WORKOVER OPERATIONS :
21 CONTRACT RIG 6.038 28.251 34.289
23 MUD CHEMICAL & ENGINEERING SERVICES 542 542
25 BITS, REAMERS, COREHEADS
26 EQUIPMENT RENTAL
27 DIRECTIONAL DRILLING
29 CASING INSTALLATION
30 CEMENT, CEMENTING & PUMP FEETS
31 OTHER ( SWAB RUBBER,ETC )
37 OPEN HOLE ELECTRICAL LOGGING SERVICES
COMPLETION
42 CEMENT, CEMENTING & PUMP FEETS
43 CASED HOLE ELECTRICAL LOGGING SERVICES
44 PERFORATING & WIRELINE SERVICES
45 STIMULATION TREATMENT
47 OTHER 4 1/2" BP AND CR
49 GENERAL
50 SUPERVISION 200 1.000 1.200
51 INSURANCE
52 WATER TRANSPORTATION
55 LAND TRANSPORTATION
56 OTHER TRANSPORTATION (WATER) 100 100
57 FUEL & LUBRICATION 450 2.053 2.503
60 CAMP FACILITIES
61 ALLOCATED OVERHEAD-FIELD OFFICE
61 JKT OFFICE
61 OVERSEAS
TOTAL COST (US $) 6.238 622 32.925 39.785
RUN TIME TIME TANK VOL TANK VOL VOL FLUID SWAB
NO. IN OUT BEFORE AFTER REC LEVEL DEPTH RIG TANK RESULT SAMPLE REMARKS
INCHES INCHES BBLS m m CI - pH WTR OIL Cl-
LAST CUMM. =
SUMMARY
HOURS SWAB TOTAL REC IFL FFL SWAB DEPTH REC OIL ACID CTM FORM WTR CUMM R CUMM REC
( BBLS ) (m) (m) (m) ( BBLS ) ( BBLS ) ( BBLS ) ( BBLS )
2,00 23,03 294 894 1000 23,03 23,03 23,03
DAILY WORKOVER / COMPLETION REPORT : AFE : 08.3930 DATE : FEB 09, 2010
REPORT # : 7 RIG # : EPI - 35
WELL NAME :TT- 028 KB ELEV : 67.81 m TOOLPUSHER : SUKARDI / BAHARUDIN
OBJECTIVES : - PERFORATE KB - CF : 6.42 m RIG SUPT : SURATNO
- SWAB TEST TD : 1440.0 m COMPANY MAN : SUPRAPTO
- PROD Ca, Cb, C1 ZONES PBTD (TOC) : 1434.0 m DAILY RIG COST : 5459,0
CSG. SIZE : 13 3/8", K 55 WEIGHT : 54.5 PPF DEPTH : 196.0 m CUMM RIG COST : 39748,0
CSG. SIZE : 9 5/8", K 55 WEIGHT : 36.0 PPF DEPTH : 1186.0 m DAILY COST : 6123
CSG. SIZE : 7", J 55 WEIGHT : 23.0 PPF DEPTH : 1439.0 m CUMM COST : 45.908
TBG SIZE : 3 1/2" WEIGHT : 9.3 PPF DEPTH : 1302.95 m PERFORATION
# OF TBGS : 139 JTS & 1 JT PJ BHP TYPE : 7" HD PKR ZONE - Ca 1284.0 - 1290.0 m
ROD SIZE : BHP NO : PTM OWN ZONE - Cb 1309.0 - 1320.0 m
# OF RODS : PKR : 1304.31 m ZONE - C1 1325.0 - 1327.0 m
# ROD GUIDE : TAIL END : 1305.59 m
RBP : 1323.0 m
SICP ( psi ) :
PRES. OPN : PREPARING F/ CONT SWAB Cb ZONE
06:00 - 09:30 3,50 CONT POH 5 1/2" RBP RETRIEVE TOOL W/ STD BACK 110 - 3 1/2" EU TBG, L/D X/O & RETRIEVE TOOL
09:30 - 10:00 0,50 M/U 2 7/8" PSN NO GO (ID : 1.75, BELLSHOE END), 7" HD PKR, X/O
10:00 - 14:30 4,50 RIH W/ 141 - 3 1/2" EU TBG, 1 - 3 1/2" EU PJ,SET PKR @ 1321.30 mKB W/ 15.000# COMP (WHILE RIH TEST SET PKR @ 378.70 mKB)
14:30 - 15:00 0,50 FILL UP TBG VOL W/ 9 BBLS 6% KCL WATER & PRESS TEST RBP TO 1000 PSI/ 6 MINS, PRESS DECREASE & HOLD @ 600 PSI
15:00 - 15:30 0,50 UNSET PKR, RAISED W/ 2 - 3 1/2" EU TBG, ADDED 1 - 3 1/2" EU PJ &
SET PKR @ 1304.31 mKB W/ 15.000# COMP, LANDED STRING W/ CONV
TBG HANGER,TAIL END @ 1305.59 mKB
15:30 - 16:30 1,00 M/U SWAB HD, SWAB SINKER & SWAB LUBRICATOR
16:30 - 18:30 2,00 SWABBED TEST "Cb" ZONE W/ 7 SWABS IN 2 HRS, SWAB DEPTH : 1000 mWLM, IFL = 294 m, FFL = 894 m, REC : 23.03 BBLS WATER,
USE : 1 EA NITRILE OIL SAVER & 1 EA NITRILE SWAB CUP
18:30 - 06:00 11,50 W/O DAYLIGHT F/ CONT SWAB TEST Cb ZONE, WHILE OBS WELL, SITP & SICP = 0 PSI
1 TANGIBLE COSTS
2 CASING
3 CASING ACCESORIES
4 TUBING
5 WELL EQPT - SURF
6 WELL EQPT - SUBSURF 54,37 1.151 1.205
7 OTHER TANGIBLE COSTS
10 INTANGIBLE COSTS
11 PREPARATION & TERMINATION
12 SURVEY
13 LOCATION STAKING & POSITIONING
14 WELL SITE & ACCESS ROAD PREP'N
15 SERVICE LINES & COMMUNICATIONS
16 WATER SYSTEMS
17 RIGGING UP / DOWN
20 DRILLING / WORKOVER OPERATIONS :
21 CONTRACT RIG 5.459 34.289 39.748
23 MUD CHEMICAL & ENGINEERING SERVICES 542 542
25 BITS, REAMERS, COREHEADS
26 EQUIPMENT RENTAL
27 DIRECTIONAL DRILLING
29 CASING INSTALLATION
30 CEMENT, CEMENTING & PUMP FEETS
31 OTHER ( SWAB RUBBER,ETC )
37 OPEN HOLE ELECTRICAL LOGGING SERVICES
COMPLETION
42 CEMENT, CEMENTING & PUMP FEETS
43 CASED HOLE ELECTRICAL LOGGING SERVICES
44 PERFORATING & WIRELINE SERVICES
45 STIMULATION TREATMENT
47 OTHER 4 1/2" BP AND CR
49 GENERAL
50 SUPERVISION 200 1.200 1.400
51 INSURANCE
52 WATER TRANSPORTATION
55 LAND TRANSPORTATION
56 OTHER TRANSPORTATION (WATER) 100 100
57 FUEL & LUBRICATION 410 2.503 2.913
60 CAMP FACILITIES
61 ALLOCATED OVERHEAD-FIELD OFFICE
61 JKT OFFICE
61 OVERSEAS
TOTAL COST (US $) 5.659 464 39.785 45.908
06:00 - 18:30 12,50 PREPARED & CONT SWABBED TEST "Cb" ZONE W/ 23 SWABS IN 12.5 HRS, SWAB DEPTH : 1300 mWLM, IFL = 547 m, FFL = 1247 m,
REC : 73.68 BBLS (0.68 BBLS OIL, 73.0 BBLS WATER, CUMM : 96.71 BBLS / 0.68 BBLS OIL & 96.03 BBLS WATER), USE : 1 EA NITRILE OIL
SAVER & 5 EA NITRILE SWAB CUP
18:30 - 06:00 11,50 W/O DAYLIGHT F/ CONT SWAB TEST "Cb" ZONE, WHILE OBS WELL, SITP = 8 PSI & SICP = 0 PSI
1 TANGIBLE COSTS
2 CASING
3 CASING ACCESORIES
4 TUBING
5 WELL EQPT - SURF
6 WELL EQPT - SUBSURF 211,09 1.205 1.416
7 OTHER TANGIBLE COSTS
10 INTANGIBLE COSTS
11 PREPARATION & TERMINATION
12 SURVEY
13 LOCATION STAKING & POSITIONING
14 WELL SITE & ACCESS ROAD PREP'N
15 SERVICE LINES & COMMUNICATIONS
16 WATER SYSTEMS
17 RIGGING UP / DOWN
20 DRILLING / WORKOVER OPERATIONS :
21 CONTRACT RIG 5.459 39.748 45.207
23 MUD CHEMICAL & ENGINEERING SERVICES 542 542
25 BITS, REAMERS, COREHEADS
26 EQUIPMENT RENTAL
27 DIRECTIONAL DRILLING
29 CASING INSTALLATION
30 CEMENT, CEMENTING & PUMP FEETS
31 OTHER ( SWAB RUBBER,ETC )
37 OPEN HOLE ELECTRICAL LOGGING SERVICES
COMPLETION
42 CEMENT, CEMENTING & PUMP FEETS
43 CASED HOLE ELECTRICAL LOGGING SERVICES
44 PERFORATING & WIRELINE SERVICES
45 STIMULATION TREATMENT
47 OTHER 4 1/2" BP AND CR
49 GENERAL
50 SUPERVISION 200 1.400 1.600
51 INSURANCE
52 WATER TRANSPORTATION
55 LAND TRANSPORTATION
56 OTHER TRANSPORTATION (WATER) 100 100
57 FUEL & LUBRICATION 378 2.913 3.291
60 CAMP FACILITIES
61 ALLOCATED OVERHEAD-FIELD OFFICE
61 JKT OFFICE
61 OVERSEAS
TOTAL COST (US $) 5.659 589 45.908 52.156
RUN TIME TIME TANK VOL TANK VOL VOL FLUID SWAB
NO. IN OUT BEFORE AFTER REC LEVEL DEPTH RIG TANK RESULT SAMPLE REMARKS
INCHES INCHES BBLS m m CI - pH WTR OIL Cl-
LAST CUMM. = 23,03
USE 1 EA OIL SAVER & 1 EA NITRILESWAB CUP
11 09:15 09:35 13,0 14,0 3,07 1094 1.200 CHANGE 1 EA NITRILE RUBBER SWAB
12 09:35 09:55 14,0 15,0 3,07 1194 1.300
13 09:55 10:15 15,0 15,0 0 1300 1.300
- 10:15 11:15 OBS WELL F/ 1 HR
14 11:15 11:35 15,0 15,0 0 1300 1.300
- 11:35 12:35 OBS WELL F/ 1 HR
15 12:35 13:00 15,0 16,0 3,07 1194 1.300 100 0 SAMPLE #2
20 16:40 17:05 20,0 20,5 1,54 1247 1.300 CHANGE 1 EA NITRILE RUBBER SWAB
21 17:05 17:30 20,5 22,0 4,61 1141 1.300
22 17:30 17:55 22,0 23,5 4,61 1141 1.300
23 17:55 18:20 23,5 24,0 1,54 1247 1.300 98 2 SAMPLE #5
SUMMARY
HOURS SWAB TOTAL REC IFL FFL SWAB DEPTH REC OIL ACID CTM FORM WTR CUMM R CUMM REC
( BBLS ) (m) (m) (m) ( BBLS ) ( BBLS ) ( BBLS ) ( BBLS )
12,50 73,71 547 1.247 1300 0,68 73,03 73,71 96,74
DAILY WORKOVER / COMPLETION REPORT : AFE : 08.3930 DATE : FEB 11, 2010
REPORT # : 9 RIG # : EPI - 35
WELL NAME :TT- 028 KB ELEV : 67.81 m TOOLPUSHER : SUKARDI / BAHARUDIN
OBJECTIVES : - PERFORATE KB - CF : 6.42 m RIG SUPT : SURATNO
- SWAB TEST TD : 1440.0 m COMPANY MAN : SUPRAPTO
- PROD Ca, Cb, C1 ZONES PBTD (TOC) : 1434.0 m DAILY RIG COST : 6038,0
CSG. SIZE : 13 3/8", K 55 WEIGHT : 54.5 PPF DEPTH : 196.0 m CUMM RIG COST : 51245,0
CSG. SIZE : 9 5/8", K 55 WEIGHT : 36.0 PPF DEPTH : 1186.0 m DAILY COST : 6969
CSG. SIZE : 7", J 55 WEIGHT : 23.0 PPF DEPTH : 1439.0 m CUMM COST : 59.125
TBG SIZE : 3 1/2" WEIGHT : 9.3 PPF DEPTH : 1327.03 m PERFORATION
# OF TBGS : 142 JTS BHP TYPE : 5 1/2" RBP RETRIEVE TOOL ZONE - Ca 1284.0 - 1290.0 m
ROD SIZE : BHP NO : ZONE - Cb 1309.0 - 1320.0 m
# OF RODS : PKR : ZONE - C1 1325.0 - 1327.0 m
# ROD GUIDE : TAIL END : 1328.0 m
RBP : 1333.0 m
SICP ( psi ) :
PRES. OPN : POH 5 1/2" RBP RETRIEVE TOOL
06:00 - 18:30 12,50 PREPARED & CONT SWABBED TEST "Cb" ZONE (DAY OF TREE) W/ 35 SWABS IN 12.5 HRS, SWAB DEPTH : 1300 mWLM, IFL = 1247 m,
FFL = 1247 m, REC : 104.38 BBLS (8.0 BBLS OIL, 96.38 BBLS WATER, CUMM : 201.09 BBLS / 8.68 BBLS OIL & 192.41 BBLS WATER),
USE : 2 EA NITRILE OIL SAVER & 8 EA NITRILE SWAB CUP
18:30 - 19:30 1,00 L/D SWAB LUBRICATOR, SWAB SINKER & SWAB HD
19:30 - 20:30 1,00 ATTEMPTED TO UNSET 7" HD PKR W/ WORK PIPE, 45.000# MAX TENSION (24.000# NORMAL WEIGHT STRING), OK
20:30 - 01:00 4,50 POH 7" HD PKR W/ L/D 1 - 3 1/2" EU PJ, STD BACK 139 - 3 1/2" EU TBG, L/D X/O, PKR, PSN C/W BELLSHOE (RUBBER PKR STILL GOOD COND)
01:00 - 05:30 4,50 M/U 5 1/2" RBP RETRIEVE TOOL, X/O & RIH W/ 142 - 3 1/2" EU TBG TAGGED & CAUGHT RBP @ 1323.0 mKB
05:30 - 06:00 0,50 LOWER RBP W/ 1 - 3 1/2" EU TBG, SET RBP @ 1333.0 mKB W/ 20.000# COMP & 10.000# TENSION, RELEASED RETRIEVE TOOL
POH 5 1/2" RBP RETRIEVE TOOL W/ L/D 1 - 3 1/2" EU TBG TO 1328.0 mKB
PLAN : CONT POH 5 1/2" RBP RETRIEVE TOOL & RIH 7" HD PKR
1 TANGIBLE COSTS
2 CASING
3 CASING ACCESORIES
4 TUBING
5 WELL EQPT - SURF
6 WELL EQPT - SUBSURF 343,82 1.416 1.760
7 OTHER TANGIBLE COSTS
10 INTANGIBLE COSTS
11 PREPARATION & TERMINATION
12 SURVEY
13 LOCATION STAKING & POSITIONING
14 WELL SITE & ACCESS ROAD PREP'N
15 SERVICE LINES & COMMUNICATIONS
16 WATER SYSTEMS
17 RIGGING UP / DOWN
20 DRILLING / WORKOVER OPERATIONS :
21 CONTRACT RIG 6.038 45.207 51.245
23 MUD CHEMICAL & ENGINEERING SERVICES 542 542
25 BITS, REAMERS, COREHEADS
26 EQUIPMENT RENTAL
27 DIRECTIONAL DRILLING
29 CASING INSTALLATION
30 CEMENT, CEMENTING & PUMP FEETS
31 OTHER ( SWAB RUBBER,ETC )
37 OPEN HOLE ELECTRICAL LOGGING SERVICES
COMPLETION
42 CEMENT, CEMENTING & PUMP FEETS
43 CASED HOLE ELECTRICAL LOGGING SERVICES
44 PERFORATING & WIRELINE SERVICES
45 STIMULATION TREATMENT
47 OTHER 4 1/2" BP AND CR
49 GENERAL
50 SUPERVISION 200 1.600 1.800
51 INSURANCE
52 WATER TRANSPORTATION
55 LAND TRANSPORTATION
56 OTHER TRANSPORTATION (WATER) 100 100
57 FUEL & LUBRICATION 387 3.291 3.678
60 CAMP FACILITIES
61 ALLOCATED OVERHEAD-FIELD OFFICE
61 JKT OFFICE
61 OVERSEAS
TOTAL COST (US $) 6.238 731 52.156 59.125
RUN TIME TIME TANK VOL TANK VOL VOL FLUID SWAB
NO. IN OUT BEFORE AFTER REC LEVEL DEPTH RIG TANK RESULT SAMPLE REMARKS
INCHES INCHES BBLS m m CI - pH WTR OIL Cl-
LAST CUMM. =
SUMMARY
HOURS SWAB TOTAL REC IFL FFL SWAB DEPTH REC OIL ACID CTM FORM WTR CUMM R CUMM REC
( BBLS ) (m) (m) (m) ( BBLS ) ( BBLS ) ( BBLS ) ( BBLS )
1,50 13,83 1.041 1.161 1320 13,83 13,83 13,83
DAILY WORKOVER / COMPLETION REPORT : AFE : 08.3930 DATE : FEB 12, 2010
REPORT # : 10 RIG # : EPI - 35
WELL NAME :TT- 028 KB ELEV : 67.81 m TOOLPUSHER : SUKARDI / BAHARUDIN
OBJECTIVES : - PERFORATE KB - CF : 6.42 m RIG SUPT : SURATNO
- SWAB TEST TD : 1440.0 m COMPANY MAN : SUPRAPTO
- PROD Ca, Cb, C1 ZONES PBTD (TOC) : 1434.0 m DAILY RIG COST : 5459,0
CSG. SIZE : 13 3/8", K 55 WEIGHT : 54.5 PPF DEPTH : 196.0 m CUMM RIG COST : 56704,0
CSG. SIZE : 9 5/8", K 55 WEIGHT : 36.0 PPF DEPTH : 1186.0 m DAILY COST : 6931
CSG. SIZE : 7", J 55 WEIGHT : 23.0 PPF DEPTH : 1439.0 m CUMM COST : 66.056
TBG SIZE : 3 1/2" WEIGHT : 9.3 PPF DEPTH : 1320.82 m PERFORATION
# OF TBGS : 141 JTS & 1 PJ BHP TYPE : 7" HD PKR ZONE - Ca 1284.0 - 1290.0 m
ROD SIZE : BHP NO : PTM OWN ZONE - Cb 1309.0 - 1320.0 m
# OF RODS : PKR : 1322.42 m ZONE - C1 1325.0 - 1327.0 m
# ROD GUIDE : TAIL END : 1324.07 m
RBP : 1333.0 m
SICP ( psi ) :
PRES. OPN : PREPARE SWAB TEST "C1" ZONE
06:00 - 10:30 4,50 CONT POH 5 1/2" RBP RETRIEVE TOOL W/ STD BACK 142 - 3 1/2" EU TBG, L/D X/O & RETRIEVE TOOL
10:30 - 11:00 0,50 M/U 1 - 2 7/8" EU PJ (BELLSHOE END), 7" HD PKR (CHANGE PKR), PSN NO GO (ID : 1.75"), X/O
11:00 - 15:30 4,50 RIH W/ 142 - 3 1/2" EU TBG,SET PKR @ 1328.63 mKB W/ 15.000# COMP (WHILE RIH TEST SET PKR @ 378.70 mKB)
15:30 - 16:00 0,50 FILL UP TBG VOL W/ 27 BBLS 6% KCL WATER & PRESS TEST RBP TO 1000 PSI/ 10 MINS
16:00 - 16:30 0,50 UNSET PKR, RAISED W/ 1 - 3 1/2" EU TBG, ADDED 1 - 3 1/2" EU PJ &
SET PKR @ 1322.42 mKB W/ 15.000# COMP, LANDED STRING W/ CONV
TBG HANGER,TAIL END @ 1324.07 mKB
16:30 - 17:00 0,50 M/U SWAB HD, SWAB SINKER & SWAB LUBRICATOR, WHILE MIXED 30 BBLS 6% KCL WATER, USE 5 SAX KCL
17:00 - 18:30 1,50 SWABBED TEST "C1" ZONE W/ 5 SWABS IN 1.5 HRS, SWAB DEPTH : 1320 mWLM, IFL = 1041 m, FFL = 1161 m, REC : 13.82 BBLS WATER,
USE : 2 EA NITRILE OIL SAVER & 2 EA NITRILE SWAB CUP
18:30 - 06:00 11,50 W/O DAYLIGHT F/ CONT SWAB TEST "C1" ZONE, WHILE OBS WELL, SITP & SICP = 0 PSI
1 TANGIBLE COSTS
2 CASING
3 CASING ACCESORIES
4 TUBING
5 WELL EQPT - SURF
6 WELL EQPT - SUBSURF 533,87 1.760 2.294
7 OTHER TANGIBLE COSTS
10 INTANGIBLE COSTS
11 PREPARATION & TERMINATION
12 SURVEY
13 LOCATION STAKING & POSITIONING
14 WELL SITE & ACCESS ROAD PREP'N
15 SERVICE LINES & COMMUNICATIONS
16 WATER SYSTEMS
17 RIGGING UP / DOWN
20 DRILLING / WORKOVER OPERATIONS :
21 CONTRACT RIG 5.459 51.245 56.704
23 MUD CHEMICAL & ENGINEERING SERVICES 271 542 813
25 BITS, REAMERS, COREHEADS
26 EQUIPMENT RENTAL
27 DIRECTIONAL DRILLING
29 CASING INSTALLATION
30 CEMENT, CEMENTING & PUMP FEETS
31 OTHER ( SWAB RUBBER,ETC )
37 OPEN HOLE ELECTRICAL LOGGING SERVICES
COMPLETION
42 CEMENT, CEMENTING & PUMP FEETS
43 CASED HOLE ELECTRICAL LOGGING SERVICES
44 PERFORATING & WIRELINE SERVICES
45 STIMULATION TREATMENT
47 OTHER 4 1/2" BP AND CR
49 GENERAL
50 SUPERVISION 200 1.800 2.000
51 INSURANCE
52 WATER TRANSPORTATION
55 LAND TRANSPORTATION
56 OTHER TRANSPORTATION (WATER) 50 100 150
57 FUEL & LUBRICATION 417 3.678 4.095
60 CAMP FACILITIES
61 ALLOCATED OVERHEAD-FIELD OFFICE
61 JKT OFFICE
61 OVERSEAS
TOTAL COST (US $) 5.659 1.272 59.125 66.056
06:00 - 18:30 12,50 PREPARED & CONT SWABBED TEST "C1" ZONE W/ 13 SWABS IN 12.5 HRS, SWAB DEPTH : 1320 mWLM, IFL = 1147 m, FFL = 1320 m,
REC : 16.89 BBLS WTR + OIL TRC (CUMM REC = 30.71 BBLS WATER & OIL TRC), LAST SWAB AFTER OBS WELL DURING 7.0 HRS, NO REC
(DRY), USE : 2 EA NITRILE OIL SAVER & 4 EA NITRILE SWAB CUP
18:30 - 19:30 1,00 L/D SWAB LUBRICATOR, SWAB SINKER & SWAB HD, M/U CIRC HD, WHILE MIXED 60 BBLS 6% KCL WATER, USE 10 SAX KCL
19:30 - 21:00 1,50 PREPARED & PERFORMED INJECTIVITY TEST "C1" ZONE, FILL UP TBG VOL W/ 37.5 BBLS 6% KCL WTR & PUMPED 24.0 BBLS 6% KCL WTR
TOTAL 61.5 BBLS), RATE : 3 BPM, PRESS : 1200 PSI, DECREASE TO 400 PSI, SNL AFL 1218 m BEFORE, 1046 m DURING & 977 m AFTER PUMP,
INDICATED PKR LEAK
21:00 - 22:00 1,00 REMOVED CIRC HD, ADDED COMP PKR TO 22.000#, M/U CIRC HD & 2" SURFACE LINE
22:00 - 22:30 0,50 BUILT UP & MIXED 60 BBLS 2% KCL WATER, USE 4 SAX KCL
22:30 - 23:00 0,50 PERFORMED INJECTIVITY TEST "C1" ZONE, FILLED UP TBG VOL W/ 22.0 BBLS KCL WATER & PUMPED 5.0 BBLS KCL WATER (TOTAL 27 BBLS)
PRESS INCREASE TO 1500 PSI, NO RATE, BLED OFF PRESS, SNL AFL 844 m BEFORE & 846 m AFTER PUMP, PKR GOOD SET
23:00 - 03:30 4,50 UNSET & POH 7" HD PKR W/ L/D 1 - 3 1/2" EU PJ, STD BACK 141 - 3 1/2" EU TBG, L/D X/O, PSN, PKR, 1 - 2 7/8" EU PJ C/W BELLSHOE
(RUBBER PKR STILL GOOD COND)
03:30 - 06:00 2,50 M/U 5 1/2" RBP RETRIEVE TOOL, X/O & RIH W/ 136 - 3 1/2" EU TBG TO 1270 mKB
PLAN : CONT RIH 5 1/2" RBP RETRIEVE TOOL & CATCH RBP @ 1333.0 mKB
1 TANGIBLE COSTS
2 CASING
3 CASING ACCESORIES
4 TUBING
5 WELL EQPT - SURF
6 WELL EQPT - SUBSURF 187,10 2.294 2.481
7 OTHER TANGIBLE COSTS
10 INTANGIBLE COSTS
11 PREPARATION & TERMINATION
12 SURVEY
13 LOCATION STAKING & POSITIONING
14 WELL SITE & ACCESS ROAD PREP'N
15 SERVICE LINES & COMMUNICATIONS
16 WATER SYSTEMS
17 RIGGING UP / DOWN
20 DRILLING / WORKOVER OPERATIONS :
21 CONTRACT RIG 6.038 56.704 62.742
23 MUD CHEMICAL & ENGINEERING SERVICES 760 813 1.573
25 BITS, REAMERS, COREHEADS
26 EQUIPMENT RENTAL
27 DIRECTIONAL DRILLING
29 CASING INSTALLATION
30 CEMENT, CEMENTING & PUMP FEETS
31 OTHER ( SWAB RUBBER,ETC )
37 OPEN HOLE ELECTRICAL LOGGING SERVICES
COMPLETION
42 CEMENT, CEMENTING & PUMP FEETS
43 CASED HOLE ELECTRICAL LOGGING SERVICES
44 PERFORATING & WIRELINE SERVICES
45 STIMULATION TREATMENT
47 OTHER 4 1/2" BP AND CR
49 GENERAL
50 SUPERVISION 200 2.000 2.200
51 INSURANCE
52 WATER TRANSPORTATION
55 LAND TRANSPORTATION
56 OTHER TRANSPORTATION (WATER) 50 150 200
57 FUEL & LUBRICATION 501 4.095 4.596
60 CAMP FACILITIES
61 ALLOCATED OVERHEAD-FIELD OFFICE
61 JKT OFFICE
61 OVERSEAS
TOTAL COST (US $) 6.238 1.498 66.056 73.792
06:00 - 06:30 0,50 CONT RIH 5 1/2" RBP RETRIEVE TOOL W/ 7 - 3 1/2" EU TBG TAGGED & CAUGHT RBP @ 1333.0 mKB
06:30 - 17:00 10,50 POH 7" RBP W/ L/D 143 - 3 1/2" EU TBG, RBP & RETRIEVE TOOL (EVERY 30 JTS TEST SET RBP F/ CHECK RBP, RUBBER RBP STILL GOOD COND)
17:00 - 18:00 1,00 M/U 2 - 3 1/2" EU TBG (CLOSE END), 3 1/2" CAVINS DESANDER SUB (NEW TYPE CAVINS D 3416), X/O, PSN, 2 1/2" x 18' THEM PUMP, TEST PUMP
W/ DISEL, OK
18:00 - 03:30 9,50 RIH W/ 147 - 2 7/8" EU TBG, 1 - 2 7/8" EU PJ (143 JTS NEW TBG & 4 JTS USED TBG, TALLIED, DRIFTED, FILLED UP TBG VOL EVERY 20 JTS TBG
DOWN & PRESS TEST TO 600 PSI/5 MINS, OK), LANDED TBG STRING W/ CONV TBG HANGER, PSN @ 1328.64 mKB, TAIL END @ 1348.70 mKB
03:30 - 06:00 2,50 N/D 7 1/16" - 3000 PSI ANN BOP & 7 1/16" - 3000 PSI RAM TYPE BOP, N/U PROD WELL HD
1 TANGIBLE COSTS
2 CASING
3 CASING ACCESORIES
4 TUBING 25.461 25.461
5 WELL EQPT - SURF
6 WELL EQPT - SUBSURF 2.481 2.481
7 OTHER TANGIBLE COSTS
10 INTANGIBLE COSTS
11 PREPARATION & TERMINATION
12 SURVEY
13 LOCATION STAKING & POSITIONING
14 WELL SITE & ACCESS ROAD PREP'N
15 SERVICE LINES & COMMUNICATIONS
16 WATER SYSTEMS
17 RIGGING UP / DOWN
20 DRILLING / WORKOVER OPERATIONS :
21 CONTRACT RIG 6.038 62.742 68.780
23 MUD CHEMICAL & ENGINEERING SERVICES 1.573 1.573
25 BITS, REAMERS, COREHEADS
26 EQUIPMENT RENTAL
27 DIRECTIONAL DRILLING
29 CASING INSTALLATION
30 CEMENT, CEMENTING & PUMP FEETS
31 OTHER ( SWAB RUBBER,ETC )
37 OPEN HOLE ELECTRICAL LOGGING SERVICES
COMPLETION
42 CEMENT, CEMENTING & PUMP FEETS
43 CASED HOLE ELECTRICAL LOGGING SERVICES
44 PERFORATING & WIRELINE SERVICES
45 STIMULATION TREATMENT
47 OTHER 4 1/2" BP AND CR
49 GENERAL
50 SUPERVISION 200 2.200 2.400
51 INSURANCE
52 WATER TRANSPORTATION
55 LAND TRANSPORTATION
56 OTHER TRANSPORTATION (WATER) 200 200
57 FUEL & LUBRICATION 491 4.596 5.087
60 CAMP FACILITIES
61 ALLOCATED OVERHEAD-FIELD OFFICE
61 JKT OFFICE
61 OVERSEAS
TOTAL COST (US $) 6.238 25.952 73.792 105.982
1 TANGIBLE COSTS
2 CASING
3 CASING ACCESORIES
4 TUBING 25.461 25.461
5 WELL EQPT - SURF
6 WELL EQPT - SUBSURF 19.140,26 2.481 21.621
7 OTHER TANGIBLE COSTS
10 INTANGIBLE COSTS
11 PREPARATION & TERMINATION
12 SURVEY
13 LOCATION STAKING & POSITIONING
14 WELL SITE & ACCESS ROAD PREP'N
15 SERVICE LINES & COMMUNICATIONS
16 WATER SYSTEMS
17 RIGGING UP / DOWN
20 DRILLING / WORKOVER OPERATIONS :
21 CONTRACT RIG 5.207 68.780 73.987
23 MUD CHEMICAL & ENGINEERING SERVICES 1.573 1.573
25 BITS, REAMERS, COREHEADS
26 EQUIPMENT RENTAL
27 DIRECTIONAL DRILLING
29 CASING INSTALLATION
30 CEMENT, CEMENTING & PUMP FEETS
31 OTHER ( SWAB RUBBER,ETC )
37 OPEN HOLE ELECTRICAL LOGGING SERVICES
COMPLETION
42 CEMENT, CEMENTING & PUMP FEETS
43 CASED HOLE ELECTRICAL LOGGING SERVICES
44 PERFORATING & WIRELINE SERVICES
45 STIMULATION TREATMENT
47 OTHER 4 1/2" BP AND CR
49 GENERAL
50 SUPERVISION 200 2.400 2.600
51 INSURANCE
52 WATER TRANSPORTATION
55 LAND TRANSPORTATION
56 OTHER TRANSPORTATION (WATER) 200 200
57 FUEL & LUBRICATION 419 5.087 5.506
60 CAMP FACILITIES
61 ALLOCATED OVERHEAD-FIELD OFFICE
61 JKT OFFICE
61 OVERSEAS
TOTAL COST (US $) 5.407 19.559 105.982 130.948
1 TANGIBLE COSTS
2 CASING
3 CASING ACCESORIES
4 TUBING 25.461 25.461
5 WELL EQPT - SURF
6 WELL EQPT - SUBSURF 21.621 21.621
7 OTHER TANGIBLE COSTS
10 INTANGIBLE COSTS
11 PREPARATION & TERMINATION
12 SURVEY
13 LOCATION STAKING & POSITIONING
14 WELL SITE & ACCESS ROAD PREP'N
15 SERVICE LINES & COMMUNICATIONS
16 WATER SYSTEMS
17 RIGGING UP / DOWN
20 DRILLING / WORKOVER OPERATIONS :
21 CONTRACT RIG 4.880 73.987 78.867
23 MUD CHEMICAL & ENGINEERING SERVICES 1.573 1.573
25 BITS, REAMERS, COREHEADS
26 EQUIPMENT RENTAL
27 DIRECTIONAL DRILLING
29 CASING INSTALLATION
30 CEMENT, CEMENTING & PUMP FEETS
31 OTHER ( SWAB RUBBER,ETC )
37 OPEN HOLE ELECTRICAL LOGGING SERVICES
COMPLETION
42 CEMENT, CEMENTING & PUMP FEETS
43 CASED HOLE ELECTRICAL LOGGING SERVICES
44 PERFORATING & WIRELINE SERVICES
45 STIMULATION TREATMENT
47 OTHER 4 1/2" BP AND CR
49 GENERAL
50 SUPERVISION 200 2.600 2.800
51 INSURANCE
52 WATER TRANSPORTATION
55 LAND TRANSPORTATION
56 OTHER TRANSPORTATION (WATER) 200 200
57 FUEL & LUBRICATION 391 5.506 5.897
60 CAMP FACILITIES
61 ALLOCATED OVERHEAD-FIELD OFFICE
61 JKT OFFICE
61 OVERSEAS
TOTAL COST (US $) 5.080 391 130.948 136.419
13:30 - 14:00 0,50 OBS'D WELL, SITP = 10 PSI, SICP = 0 PSI, BLED OFF PRESS
14:00 - 15:00 1,00 REMOVED HORSE HD, FLOW LINE, R/U WORK FLOOR
15:00 - 15:30 0,50 P/U ROD STRING TO 15000# (ROD WT 8500#) INDICATED PUMP PLUNGER STUCK, ATTEMPTED WORKED ROD STRING SEVERAL TIME NO SUCCESS
15:30 - 16:00 0,50 BACK OFF RODS STRING W/ SAFETY CLAMP, SUCCESS
16:00 - 18:00 2,00 POH RODS STRING W/ 2 - 1" PR, 52 - 1", 35 - 7/8" RODS (RODS CLEAN & GOOD COND)
18:00 - 19:00 1,00 REMOVED PROD WELL HD, N/U & FUNCT TEST 7 1/16" - 3000 PSI ANN BOP, R/U TBG POWER TONG
19:00 - 20:00 1,00 LOWERED TBG STRING W/ 10 - 2 7/8" EU TBG,TAGGED ON FILL @ 1439.0 mKB(TOP OF CEMENT), POH TBG LOWER
20:00 - 21:30 1,50 POH COMBO 2 1/2" x 18' THEM PUMP & 2 1/4" PUMP PLUNGER W/ 14 - 2 7/8" EU TBG TO 1187.0 mKB, FOUND OIL LEVEL IN TBG
21:30 - 22:00 0,50 M/U SWAB HD, SWAB SINKER & SWAB LUBRICATOR
22:00 - 22:30 0,50 SWABBED TBG VOL W/ 2 SWABS, SWAB DEPTH = 500 mWLM, RETURNED SWAB REC TO CSG ANN, L/D SWAB ASSY
22:30 - 01:00 2,50 CONT POH COMBO W/ 64 - 2 7/8" EU TBG (TOTAL 78) TO 616.0 mKB, FOUND TOP OF 7/8" ROD
01:00 - 02:00 1,00 BACK OF RODS STRING W/ SAFETY CLAMP & POH W/ 28 - 7/8" (TOTAL 63), RODS CLEAN & GOOD COND
02:00 - 06:00 4,00 CONT POH COMBO W/ 69 - 2 7/8" EU TBG (TOTAL 147), 47 - 3/4" RODS (4 TIMES BACK OF), L/D PUMP, PSN, X/O, 3 1/16" CAVINS DESANDER
SUB D3416, 2 - 3 1/2" MUD ANCHOR (MUD ANCHOR FILL W/ FINE SAND
+ 5 LTRS, PUMP PLUNGER STUCK IN PUMP BARREL)
PLAN : RIH 2 1/2" x 18' THEM PUMP, SET PSN @ 1325.0 mKB
1 TANGIBLE COSTS
2 CASING
3 CASING ACCESORIES
4 TUBING
5 WELL EQPT - SURF
6 WELL EQPT - SUBSURF
7 OTHER TANGIBLE COSTS
10 INTANGIBLE COSTS
11 PREPARATION & TERMINATION
12 SURVEY
13 LOCATION STAKING & POSITIONING
14 WELL SITE & ACCESS ROAD PREP'N
15 SERVICE LINES & COMMUNICATIONS
16 WATER SYSTEMS
17 RIGGING UP / DOWN
20 DRILLING / WORKOVER OPERATIONS :
21 CONTRACT RIG 4.151 4.151
23 MUD CHEMICAL & ENGINEERING SERVICES 271 271
25 BITS, REAMERS, COREHEADS
26 EQUIPMENT RENTAL
27 DIRECTIONAL DRILLING
29 CASING INSTALLATION
30 CEMENT, CEMENTING & PUMP FEETS
31 OTHER ( SWAB RUBBER,ETC )
37 OPEN HOLE ELECTRICAL LOGGING SERVICES
COMPLETION
42 CEMENT, CEMENTING & PUMP FEETS
43 CASED HOLE ELECTRICAL LOGGING SERVICES
44 PERFORATING & WIRELINE SERVICES
45 STIMULATION TREATMENT
47 OTHER 4 1/2" BP AND CR
49 GENERAL
50 SUPERVISION 138 138
51 INSURANCE
52 WATER TRANSPORTATION
55 LAND TRANSPORTATION
56 OTHER TRANSPORTATION (WATER)
57 FUEL & LUBRICATION 473 473
60 CAMP FACILITIES
61 ALLOCATED OVERHEAD-FIELD OFFICE
61 JKT OFFICE
61 OVERSEAS
TOTAL COST (US $) 4.289 744 5.033
06:00 - 07:00 1,00 M/U 2 - 3 1/2" EU TBG (OPEN END), 3 1/2" CAVINS DESANDER SUB D 3416, X/O, PSN, 2 1/2" x 16' THEM PUMP, TEST PUMP W/ DISEL, OK
07:00 - 13:00 6,00 RIH W/ 147 - 2 7/8" EU TBG (TALLIED, DRIFTED, FILLED UP TBG VOL EVERY 20 JTS TBG DOWN & PRESS TEST TO 600 PSI / 5 MINS, OK)
LANDED TBG STRING W/ CONV TBG HANGER,PSN @ 1327.68 mKB, TAIL END @ 1347.74 mKB
13:00 - 14:30 1,50 N/D 7 1/16" - 3000 PSI ANN BOP, N/U PROD WELL HD
14:30 - 15:00 0,50 M/U 2 1/4" THEM PUMP PLUNGER & TESTED TRAV VALVE W/ DIESEL OIL, OK
15:00 - 19:30 4,50 RIH W/ 47 - 3/4", 63 - 7/8", 52 - 1" RODS (C/W 2 EA ROD GUIDES EACH JT, TIGHTENED EVERY CONNECTION), 3 - 1" PR
19:30 - 20:30 1,00 R/D ROD PWR TONG, WORK FLOOR, M/U FLOW LINE
20:30 - 21:00 0,50 M/U HORSE HD, POLISH ROD C/W STFG BOX & SPACED OUT PUMP TO 30 Cm,
SNL AFL = 1087 m @ 15:12 HRS
21:00 - 21:30 0,50 START PUMP JACK @ 21:20 HRS, BUILT UP PRESS TO 400 PSI/ 1 STROKE, FLOWLINE PRESS : 30 - 40 PSI
21:30 - 22:00 0,50 WELL STILL NO PROD @ 21:38 HRS (PUMP STUCK INDICATED), ATTEMPTED TO FREE PUMP PLUNGER W/ WORKED ROD TO 18000 LBS
MAX TENSION SUCCESS (8000 LBS NORMAL WT), L/D POLISH ROD C/W STFG BOX
22:00 - 22:30 0,50 OBS'D WELL, SITP = 20 PSI, SICP = 0 PSI, BLED OFF PRESS, REMOVED HORSE HD, FLOW LINE, R/U WORK FLOOR
22:30 - 02:30 4,00 POH 2 1/4" PUMP PLUNGER W/ 3 - 1" PR, 52 - 1", 63 - 7/8", 47 - 3/4" RODS (ROD CLEAN, STD VALVE NO REC, PLUNGER SCRACTH CONDITION)
02:30 - 04:00 1,50 REMOVED PROD WELL HD, N/U & FUNCT TEST 7 1/16" - 3000 PSI ANN BOP, R/U TBG POWER TONG
04:00 - 06:00 2,00 POH 2 1/2" x 16' THEM PUMP W/ L/D 7 - 2 7/8" EU TBG, STD BACK 60 - 2 7/8" EU TBG TO 715.0 mKB
1 TANGIBLE COSTS
2 CASING
3 CASING ACCESORIES
4 TUBING
5 WELL EQPT - SURF
6 WELL EQPT - SUBSURF
7 OTHER TANGIBLE COSTS
10 INTANGIBLE COSTS
11 PREPARATION & TERMINATION
12 SURVEY
13 LOCATION STAKING & POSITIONING
14 WELL SITE & ACCESS ROAD PREP'N
15 SERVICE LINES & COMMUNICATIONS
16 WATER SYSTEMS
17 RIGGING UP / DOWN
20 DRILLING / WORKOVER OPERATIONS :
21 CONTRACT RIG 6.038 4.151 10.189
23 MUD CHEMICAL & ENGINEERING SERVICES 271 271 542
25 BITS, REAMERS, COREHEADS
26 EQUIPMENT RENTAL
27 DIRECTIONAL DRILLING
29 CASING INSTALLATION
30 CEMENT, CEMENTING & PUMP FEETS
31 OTHER ( SWAB RUBBER,ETC )
37 OPEN HOLE ELECTRICAL LOGGING SERVICES
COMPLETION
42 CEMENT, CEMENTING & PUMP FEETS
43 CASED HOLE ELECTRICAL LOGGING SERVICES
44 PERFORATING & WIRELINE SERVICES
45 STIMULATION TREATMENT
47 OTHER 4 1/2" BP AND CR
49 GENERAL
50 SUPERVISION 200 138 338
51 INSURANCE
52 WATER TRANSPORTATION
55 LAND TRANSPORTATION
56 OTHER TRANSPORTATION (WATER)
57 FUEL & LUBRICATION 282 473 755
60 CAMP FACILITIES
61 ALLOCATED OVERHEAD-FIELD OFFICE
61 JKT OFFICE
61 OVERSEAS
TOTAL COST (US $) 6.238 553 5.033 11.824
06:00 - 10:00 4,00 CONT POH 2 1/2" x 16' THEM PUMP W/ STD BACK 80 - 2 7/8" EU TBG (TOTAL 147), L/D PUMP, PSN, X/O, 3 1/16" CAVINS DESANDER SUB D 3416,
2 - 3 1/2" EU TBG MUD ANCHOR (OPEN END)
10:00 - 10:30 0,50 M/U 3 1/8" SAND BAILER & RIH W/ SAND LINE TAGGED FILL @ 1431.10 mWLM
10:30 - 11:30 1,00 BAILED SAND F/ 1431.10 TO 1431.25 mWLM (PROGRESS : 0.15 m), W/ 3 BAILS, REC : 3 LTRS FINE SAND, L/D SAND BAILER
11:30 - 15:00 3,50 W/O TRANSPORT 2 1/2" x 20' THEM PUMP F/ PUMP SHOP
15:00 - 16:00 1,00 M/U 2 7/8" DUMP VALVE NEW (D.V 2875), X/O, 2 - 3 1/2" EU TBG, 3 1/2" CAVINS DESANDER SUB D 3416, X/O, PSN, 2 1/2" x 20' THEM PUMP,
TEST PUMP W/ DIESEL, OK
16:00 - 21:30 5,50 RIH W/ 141 - 2 7/8" EU TBG (TALLIED, DRIFTED, FILLED UP TBG VOL EVERY 20 JTS TBG DOWN & PRESS TEST TO 600 PSI / 5 MINS, OK)
LANDED TBG STRING W/ CONV TBG HANGER,PSN @ 1273.36 mKB, TAIL END @ 1293.80 mKB
21:30 - 23:00 1,50 N/D 7 1/16" - 3000 PSI ANN BOP, N/U PROD WELL HD
23:00 - 23:30 0,50 M/U 2 1/4" THEM PUMP PLUNGER & TESTED TRAV VALVE W/ DIESEL OIL, OK
23:30 - 04:00 4,50 RIH W/ 43 - 3/4", 57 - 7/8", 56 - 1" RODS (C/W 2 EA ROD GUIDES EACH JT), 1 - 1" PR
04:00 - 05:00 1,00 R/D ROD PWR TONG, WORK FLOOR, M/U FLOW LINE
05:00 - 05:30 0,50 M/U HORSE HD, POLISH ROD C/W STFG BOX & SPACED OUT PUMP TO 30 Cm,
SNL AFL = 1074 m @ 00:08 HRS
05:30 - 06:00 0,50 START PUMP JACK @ 05:55 HRS, BUILT UP PRESS TO 400 PSI/ 1 STROKE, FLOWLINE PRESS : 20 - 30 PSI
1 TANGIBLE COSTS
2 CASING
3 CASING ACCESORIES
4 TUBING
5 WELL EQPT - SURF
6 WELL EQPT - SUBSURF
7 OTHER TANGIBLE COSTS
10 INTANGIBLE COSTS
11 PREPARATION & TERMINATION
12 SURVEY
13 LOCATION STAKING & POSITIONING
14 WELL SITE & ACCESS ROAD PREP'N
15 SERVICE LINES & COMMUNICATIONS
16 WATER SYSTEMS
17 RIGGING UP / DOWN
20 DRILLING / WORKOVER OPERATIONS :
21 CONTRACT RIG 5.861 10.189 16.050
23 MUD CHEMICAL & ENGINEERING SERVICES
25 BITS, REAMERS, COREHEADS
26 EQUIPMENT RENTAL
27 DIRECTIONAL DRILLING
29 CASING INSTALLATION
30 CEMENT, CEMENTING & PUMP FEETS
31 OTHER ( SWAB RUBBER,ETC )
37 OPEN HOLE ELECTRICAL LOGGING SERVICES
COMPLETION
42 CEMENT, CEMENTING & PUMP FEETS
43 CASED HOLE ELECTRICAL LOGGING SERVICES
44 PERFORATING & WIRELINE SERVICES
45 STIMULATION TREATMENT
47 OTHER 4 1/2" BP AND CR
49 GENERAL
50 SUPERVISION 200 338 538
51 INSURANCE
52 WATER TRANSPORTATION
55 LAND TRANSPORTATION
56 OTHER TRANSPORTATION (WATER)
57 FUEL & LUBRICATION 421 755 1.176
60 CAMP FACILITIES
61 ALLOCATED OVERHEAD-FIELD OFFICE
61 JKT OFFICE
61 OVERSEAS
TOTAL COST (US $) 6.061 421 11.282 17.764
06:00 - 12:00 6,00 OBS WELL UNTIL NORMAL PROD, FLOW LINE PRESS 40 - 60 PSI, WHILE CLEANED WELL HD & WELL SITE AREA
12:00 - 13:00 1,00 REMOVED GUYLINES & R/D @ TT- 028
TURN OVER WELL TO PROD OPERATION, FINAL REPORT
1 TANGIBLE COSTS
2 CASING
3 CASING ACCESORIES
4 TUBING
5 WELL EQPT - SURF
6 WELL EQPT - SUBSURF
7 OTHER TANGIBLE COSTS
10 INTANGIBLE COSTS
11 PREPARATION & TERMINATION
12 SURVEY
13 LOCATION STAKING & POSITIONING
14 WELL SITE & ACCESS ROAD PREP'N
15 SERVICE LINES & COMMUNICATIONS
16 WATER SYSTEMS
17 RIGGING UP / DOWN
20 DRILLING / WORKOVER OPERATIONS :
21 CONTRACT RIG 1.409 16.050 17.459
23 MUD CHEMICAL & ENGINEERING SERVICES
25 BITS, REAMERS, COREHEADS
26 EQUIPMENT RENTAL
27 DIRECTIONAL DRILLING
29 CASING INSTALLATION
30 CEMENT, CEMENTING & PUMP FEETS
31 OTHER ( SWAB RUBBER,ETC )
37 OPEN HOLE ELECTRICAL LOGGING SERVICES
COMPLETION
42 CEMENT, CEMENTING & PUMP FEETS
43 CASED HOLE ELECTRICAL LOGGING SERVICES
44 PERFORATING & WIRELINE SERVICES
45 STIMULATION TREATMENT
47 OTHER 4 1/2" BP AND CR
49 GENERAL
50 SUPERVISION 58 538 596
51 INSURANCE
52 WATER TRANSPORTATION
55 LAND TRANSPORTATION
56 OTHER TRANSPORTATION (WATER)
57 FUEL & LUBRICATION 100 1.176 1.276
60 CAMP FACILITIES
61 ALLOCATED OVERHEAD-FIELD OFFICE
61 JKT OFFICE
61 OVERSEAS
TOTAL COST (US $) 1.467 100 17.764 19.331
WELL : TT-28
LOCATION : TTM-SA1
DRILLING - 2009
Doc No. : EP1012/Form/DSpv/05
BIT RECORD
DR ILL ING DEPARTMENT Form Rev : 02
Well : TT-28
Location : TTM-SA1
Rig : RG-750 / JML-03
RUN BHA SIZE IADC SERIAL DEPTH CUMM. OBT CUM. ROP WOB RPM SPP MUD DULL GRADE
MAKE TYPE NOZZLES MTRG GPM REMARKS
No. No. INCH CODE No IN OUT MTRG hrs hrs mnt/m klbs MM TABLE (Psi) MW VIS PV/YP I/O/D/L/B/G/O/R
1 1 26" VAREL L111 111 997476 3x20 0 28 28 28 7,8 7,8 16,7 1-4 - 40-90 250 630 1,02 - 1/1/1 Bor Stove Pipe
2 2 17-1/2" VAREL Type 535J - 150142 3x20 28 197 169 169 17,0 17,0 6,0 5-10 - 100 600 800 1,05 48 10-23 2/1/1 Bor formasi
0/ 1/ WT/ OT/ X/ 1/16/ Bor semen, plug, shoe dan formasi dari
4 4 8-1/2" CHUANKE G6056 - 1613737 4x32 1188 1440 252 252 30,5 30,5 9,0 5-10 - 70-110 650 500 1.01-1.07 45 16-21
NO/ TD 1188-1440 m.
WELL : TT-28
LOCATION : TTM-SA1
DRILLING - 2009
Doc No. : EP1012/Form/DSpv/09
CASING TALLY
DRILLIN G DEPARTMENT
20 INCH Form Rev : 0
Well : TT-28
Location : TANJUNG (TTM-SA1)
Rig : RG-750/JML-03
Centralizer -
Joint Welded : Csg No. 1 & 2
Mengetahui
Tanjung, 9 Desember 2009
Ast. Man. Operasi Region KTI Drilling Supervisor
Keterangan Khusus
Centralizer : 4 pcs (lihat tanda ( ) dipasang di body casing).
Sambungan dilas : Shoe (tack 4 sisi), Shoe Track (tack 4 sisi) , Collar (tack 4 sisi), 2 jts diatas collar (tack 4 sisi).
PERINCIAN SUSUNAN CASING
*) Kedalaman tubular dibaca dari ujung bawah tubular tersebut. Panjang Total 196,98 -0,50
KETERANGAN : Up 0,50
JUMLAH CASING TOTAL DI RAK 20 jts Pocket 1,02
CASING YANG MASUK 17 jts Total Bor 197,50
SISA DI RAK 3 jts Shoe 196,48
Collar 183,64
WELL : TT-28
LOCATION : TTM-SA1
DRILLING - 2009
TALLY 2 7/8" EU NEW TBG - 6.5 PPF
TT-028, FEBRUARI 13, 2010
WELL : TT-28
LOCATION : TTM-SA1
DRILLING - 2009
Doc No. : EP1012/Form/DSpv/11
LAPORAN MATERIAL PEMBORAN
Form Rev. : 02
DRILLING DEPARTMENT
NO MATERIAL UNIT OF
LINE TERIMA PAKAI SISA KETERANGAN
ISSUE
AFE NAMA
2 CASING :
1 jts + 2 jts sisa potong, dikembalikan
20" CSG K-55, 94.0 PPF, BTC, R-3 JTS 4 3 1 (baru) ke logistik Tanjung pada tgl 04
Januari 2010
3 jts + 1 jt sisa potong dikembalikan
13.3/8" CSG, K-55, 54.50 PPF, BTC, R-3 20 17 3 (baru) ke logistik Tanjung pada tgl 04
Januari 2010
1 8 jts + 1 jt sisa potong, dikembalikan
9.5/8" CSG, K-55, 36.00 PPF, BTC, R-3 JTS 120 102 18 (baru) ke logistik Tanjung pada tgl 04
Januari 2010
7" CSG, K-55, 23.00 PPF, BTC, R-3 JTS 140 123 17 MASIH DI LOKASI TT-28
3 CASING ACCESSORIES
SHOE 13.3/8", N-80, 48-68 PPF, BTC (WEATHERFORD) PCS 1 1 0 Habis dipakai
SHOE 9.5/8" DFU, N-80, 40-43.5 PPF, BTC (WEATHERFORD) PCS 1 1 0 Habis dipakai
ALUMINIUM STEARAT KG 0 0 0
BARITE LB 1320 1320 0
BENTONITE LB 556 556 0
BLck Mgic sft LB 0 0 0
BREAK-FREE NW GAL 0 0 0
CALCIUM CARBONATE C KG 480 480 0
CALCIUM CARBONATE F KG 610 610 0
CALCIUM CARBONATE M KG 440 440 0
CAUSTIC SODA KG 15 15 0
DEFOAMER GAL 1 1 0
DRILLING DETERGENT GAL 7 7 0
GLUTARALDEHYDE GAL 0 0 0
HYDRO-CAP L GAL 25 25 0
HYDRO-LUBE GAL 6 6 0
HYDRO-PAC LV KG 152 152 0
H:\titipan jaka\2. TT-28(TTM-SA1)\F.Data Pendukung\LAp Material\Lap Material Bor\Lap Material Sumur TT-28\(EP1012-form-DSpv-11) Lap Material Bor_TT-28 Hal 1 dari 3
Doc No. : EP1012/Form/DSpv/11
LAPORAN MATERIAL PEMBORAN
Form Rev. : 02
DRILLING DEPARTMENT
NO MATERIAL UNIT OF
LINE TERIMA PAKAI SISA KETERANGAN
ISSUE
AFE NAMA
HYDRO-PAC R KG 161 161 0
HYDRO-REZ KG 40 40 0
HYDRO-STAR NF KG 276 276 0
HYDRO-THIN L GAL 10 10 0
HYDRO-ZAN KG 130 130 0
KWIK-SEAL C / LCM BLEND C KG 180 180 0
KWIK-SEAL F / LCM BLEND F KG 115 115 0
KWIK-SEAL M / LCM BLEND M KG 650 650 0
NUTPLUG C KG 0 0 0
NUTPLUG F KG 0 0 0
NUTPLUG M KG 0 0 0
OX-SCAV KG 0 0 0
POTASSIUM CHLORIDES KG 1019 1019 0
POTASSIUM HYDROXIDE KG 43 43 0
SAPP KG 0 0 0
SHALE-STAB LB 100 100 0
SODA ASH LB 0 0 0
SODIUM BICARBONATE LB 0 0 0
DIASEAL M LB 112 112 0
MUD, CHEMICAL (PT. PERTAMINA-EP)
0 0 0
COMPLETION FLUID CHEMICALS (PT. PERTAMINA-EP)
PAHAT PDC 8-1/2" - SOFT TO MED (CHUANKE) pcs 1 1 1 MASIH DI LOKASI TT-28
CEMENT ACCESORIES 0 0 0
1 EA dikembalikan ke Logistik Tanjung
CENTRALIZER 13.3/8" Pcs 5 3 2
(15 Des 2009) + 1 EA Hilang.
1 EA dikembalikan ke Logistik Tanjung
STOP RING 13 3/8" Pcs 5 0 5
(15 Des 2009) + 4 EA Hilang.
7 EA dikembalikan ke logistik Tanjung
CENTRALIZER 9.5/8" Pcs 15 8 7
pada tgl 04 Januari 2010
19 EA dikembalikan ke logistik Tanjung
STOP RING 9 5/8" Pcs 19 0 19
pada tgl 04 Januari 2010
H:\titipan jaka\2. TT-28(TTM-SA1)\F.Data Pendukung\LAp Material\Lap Material Bor\Lap Material Sumur TT-28\(EP1012-form-DSpv-11) Lap Material Bor_TT-28 Hal 2 dari 3
Doc No. : EP1012/Form/DSpv/11
LAPORAN MATERIAL PEMBORAN
Form Rev. : 02
DRILLING DEPARTMENT
NO MATERIAL UNIT OF
LINE TERIMA PAKAI SISA KETERANGAN
ISSUE
AFE NAMA
RIZKIANSYAH/ HERMAN RS
H:\titipan jaka\2. TT-28(TTM-SA1)\F.Data Pendukung\LAp Material\Lap Material Bor\Lap Material Sumur TT-28\(EP1012-form-DSpv-11) Lap Material Bor_TT-28 Hal 3 dari 3
No. Dok : EP1012/Form/DS/02/10
LAPORAN STOCK DAN POTONG SEMEN
Revisi Form :0
(a) (b) (c) (d) = (b) - (d) (e) (f) = (d) - (f)
6-Dec-09 0 400 400 -400 216 216 184 PENYEMENAN CSG 20"
7-Dec-09 800 800 400 400 216 184
12-Dec-09 400 2000 800 1200 800 819 1035 165 PENYEMENAN CSG 13-3/8"
13-Dec-09 2000 220 1420 580 220 1255 165 Top Job Csg 13-3/8" I & II
14 Dec 09
14-Dec-09 2000 1420 580 1255 165
2-Jan-10 4400 3620 780 560 1815 1805 PENYEMENAN CSG 9-5/8"
3-Jan-10 4400 3620 780 1600 3415 205
6-Jan-10 4400 400 4020 380 250 3665 355 Penyemenan Karbonat - 1
7-Jan-10 4400 4020 380 3665 355
H:\titipan jaka\2. TT-28(TTM-SA1)\F.Data Pendukung\LAp Material\Lap Material Bor\Laporan Material Semen TT-28\(EP1012-form-DSpv-11) Lap Material Semen_TT-28 HaL. 1 / 2
No. Dok : EP1012/Form/DS/02/10
LAPORAN STOCK DAN POTONG SEMEN
Revisi Form :0
(a) (b) (c) (d) = (b) - (d) (e) (f) = (d) - (f)
9-Jan-10 4400 4020 380 125 3790 230 Penyemenan Karbonat - 2
10-Jan-10 4400 4020 380 3790 230
16-Jan-10 200 4600 520 4540 60 580 4495 45 PENYEMENAN CSG 7"
17 J 10
17-Jan-10 4600 4540 60 4495 45
H:\titipan jaka\2. TT-28(TTM-SA1)\F.Data Pendukung\LAp Material\Lap Material Bor\Laporan Material Semen TT-28\(EP1012-form-DSpv-11) Lap Material Semen_TT-28 HaL. 2 / 2
BERITA ACARA & MOM
WELL : TT-28
LOCATION : TTM-SA1
DRILLING - 2009
MUD ENGINEERING REPORT
WELL : TT-28
LOCATION : TTM-SA1
DRILLING - 2009
FINAL WELL REPORT
WELL
TT-28
PT.PERTAMINA - UBEP
TANJUNG
Well : TTM-SA1 / T T-28
Prepared for SCOMI Oiltools – Jakarta by : Verified for SCOMI OIltools by: Approved for PT. PERTAMINA – UBEP TANJUNG by :
Dody OP / Andy Drill Eng Name
Content Page:
Item Title Page
Cover Page X
Content Page X
1. Well Details X
2. Well Data & Cost X
3. Section Comments X
4. Daily Operations Activities xx
Attachment(s) Chemicals Tracking xx
Cost Breakdown xx
Mud Usage xx
Daily Mud Properties xx
Summary of Mud Properties xx
Graphics xx
Bit Record xx
Field : Tanjung
Location/ Block : Tapian Timur
Well Name : TTM-SA1 / TT-28
Well type : Development well
17-1/2” 28 - 197 169 1.03 – 1.06 180.86 22.83 175.66 22.17 30,564.96 29,685.76
12-1/4” 197 – 1188 991 1.09 – 1.23 92.25 35.02 79.63 30.23 91,514.38 78,996.77
A 800 bbls KCl Polymer mud was made up to filled all mud tank full and continue built volume as hole
needed. Dump and dilution was done to avoid flocculation due to high solid contamination. To counter
clay swelling add KCl for cat ion exchange.
All drilling operation need Solid Control with excellent condition and good maintenance to keep is ability
in separating solids. Flow line and mud tank position has to be improved too, to get the easy way to
manage the mud system. In this section De silter and De sander wasn’t working properly and Shale shaker.
Mud engineer explain how important the solid control equipment for maintaining mud properties (specially
Mud weight ).
Back RIH 12-/14" bit, sit @ 548 M, wash down to 563 M, cont'd RIH 12-1/4" bit, sit 1174 M, reaming to
1188 M. Swept out 30 bbl hivis, CHC, spot 30 bbl hivis, drop Totco, Spot hiden. POOH 12-1/4" bit to
surface. Back RIH 12-1/4" bit to 1174 M, reaming to 1188 M, circulation, swept out hivis, CHC. Spoted
Hiden in string. POOH 12-1/4" bit to surface.
Prepare & logging job by Elnusa Logging #1 DLL-MSFL-BHC-GR-SP to 1182 M, Logging #2 LDL-
CNL-GR to 1183 M. RIH 12-1/4" bit, sit @ 1173 M, reaming to 1188 M, circulation mud condition,
increase MW to 1.23 SG in/out, swept out 30 bbl hivis,CHC, spot 30 bbl hivis. POOH 12-1/4" bit to
surface. RIH 9-5/8" Casing Casing, sit @ 1174 M, wash down to 1186 M (shoe). Circulation, prepare
cementing job, M/U cementing head, circulation, pre job safety meeting before cementing job. Test line,
cementing job 9-5/8" Casing, displace with 240 bbl mud, no return, loss indication, cont'd displace 50 bbl
mud. WOC. N/D cementing head, hang up BOP. Prepare & top job cementing. Install 9-5/8" casing
hanger. N/D 13-5/8" 3000 x 13-5/8" 3000 spool & N/D Belt Nipple. Cut 9-5/8" Casing Excess.N/U casing
head 13-5/8 X 3000 X 11". N/U DSAF 13-/8" X 3000 X11". N/U drilling spool 13-5/8" X 3000 & N/U
Belt Nipple. Change regulator valve top drive. Test Annular, HCR 4" 500 - 1500 Psi, pipe ram and manual
gate valve 500 - 1500 Psi. Stand up 5" DP.
Maintain K+ 30000 ppm for reactive clay & shale, reduce sloughing coal with 1.23 SG.
The three panel shale shaker was using 125 x 110 x 100 mesh screen while drilling this section.
As the primary solid control equipment this shaker must need more attention and maintenance to
keep its ability.
A package of hydro cyclone was used, except Desander which was not working properly,
resulting cyclone produce like rope flow form, not sprayed the mud and can’t separate sand from
mud, so desander tank was used for settling tank.Even in this limited condition De silter always
ran when drilling or Circulation to maximized solids removal. Run centrifuge sometime for
reduce drill solid, used barite for weighting agent, not drill solid to prevent mud pump rubber
piston.
After fill up water all tank while mix LCM. RIH 8.5" bit to 1295 M, blind drill formation with water-LCM
to 1308 M. POOH 8.5" bit to surface. Prepare & RIH 3.5" Tbg OE 3 jtn, followed by 5" DP to 1308 M,
prepare & cementing plug job #1, raise up string to 1004 M, cementing plug job #2, raise up to 800 M,
circulation, return cement contaminant, POOH string to surface. WOC while prepare & RIH 8.5" bit to
824.5 M (TOC), DOC to 1308 M, drill formation with water to 1329 M, total loss. Cont'd blind drill
formation with water-LCM-Water to 1373 M, pump 30 bbl hivis, raise up to 1334 M, back RIH 8.5" bit to
1373 M, circulation, no return, spotted 60 bbl LCM @ bottom, POOH 8.5" bit to surface, Prepare & RIH
3.5" Tbg OE followed with 5" DP to 1370 M. Prepare & cementing plug job, raise up 20 stnd, circulation,
dump cement contaminant from hole, POOH 3.5" Tbg OE to surface. While WOC ,Prepared and Running
hole 8-1/2” PDC Bit to top of cement at 1270 m. Drilled out cement and formation f/1270 m to 1440 m.
During drilling formation f/1270 to 1440 m used water due to still loss total problem but in every 3 stand
drilling hole always swept with Hi-Vis 35 bbls to clean up hole.
Before POOH 8-1/2” PDC Bit f/1440 m to surface, circulated hole clean. Running hole 5” DP + 3-1/2” DP
OE for cement plug the open hole to combat loss problem and perhaps top of cement ( TOC ) at 1170 m in
casing 9-5/8”.
After cement plug, Running 8-1/2” PDC Bit to drilled cement plug f/ 1252 m ( in open hole ) as TOC to
1440 m. When drilled out cement got partial loss and then pumped Diasel M as LCM fluid with 40 bbls.
Checked and finally Dynamic and static loss was stop. Then Water-KCl pumped to replace water in hole.
POOH 8-1/2” PDC bit to surface. Running hole Logging tools but couldn’t lower then 1270 m.POOH
logging tools and Re-Run 8-1/2 PDC Bit to bottom hole and tag at 1260 m. Suggest to Co-man added
viscuosifier into Water-KCl. Reaming and wash down f/ 1260 m to 1440.CHC.POOH 8-1/2” PDC Bit to
surface.Re-Run logging tools and smooth lower to 1438 m.After that RIH and POOH 8-1/2” PDC Bit
condition hole after logging job.Running in hole casing 7” to 1439 m. Tag at 1432 m and lower to 1439 m
with circulation.Circulated hole clean and cementing casing 7” job with Two Stage Cementing system.
Prepared and built up KCl-Brine for Complation fluid. Mud engineers released after finish make up KCl-
Brine.
This is 8 ½” hole section, it has formation that much different pore pressure, at depth 700m to 1200m,
formation needs SG: 1.07 – 1.12 to improve hole stability ( coal and shale formation ), but at 1270m needs
low SG, it’s under 1.01 at sand formation ( formation press : 1733psi at 1270 ), we got total loss at that
depth using mud with SG : 1.01 – 1.04, so very important that we set casing 9 5/8” more deep than 1000m
for covering high pore press formation before drill low press formation.
Maintain chloride 20,000 – 30,000 ppm when drill shale formation, for prevent sticky cutting and not to
high to prevent sloughing brittle shale. Suggest to Company man when drilling this area mud Engineer has
built up LCM with 80 ppb in reserved tank before get the loss problem.
YP
Mud PV Gel Strength API FL
SG (Ib/100ft pH FV
Properties (cPs) 2) 10 sec/10 min (ml/30 min)
The three panel shale shaker was using 125 x 110 x 100 mesh screen while drilling this section.
As primary solid control equipment this shaker must need more maintenance to keep its ability.
Desander which was not working properly ( sometime press under 30psi), resulting cyclone
produce like rope flow form, not sprayed the mud and can’t separate sand from mud, so desander
tank was used for settling tank.Even in this limited condition Desilter always run when drilling or
Circulation to maximized solids removal ( maintain press more than 35 psi ).
This radiant utama #12 rig was not equipped with decanting centrifuge and mud cleaner.
SG, swept out 30 bbl hivis. POOH 12- Add Hydro Plast for shale stability.
1/4" bit to 179 M for wiper trip (over Control pH by KOH. Made Hivis by
pull 1013 M; 773 M; 754 M), break Hydro Zan. Made 100 bbl KCl
circulation. Back RIH 12-/14" bit, sit @ Polymer 1.21 SG to keep vol. Material
548 M, wash down to 563 M, cont'd Received DN : TLDF-0912-301;
RIH 12-1/4" bit, sit 1174 M, reaming to TLDF-0912-303; TLDF-0912-305.
1188 M. Swept out 30 bbl hivis, CHC,
spot 30 bbl hivis, drop Totco, Spot
hiden. POOH 12-1/4" bit.
31-Dec-09 1,188 Cont'd POOH 12-1/4" bit to surface. Made Hivis b Hydro Zan, made hiden
Back RIH 12-1/4" bit to 1174 M, in slug tank, add Hydro Cap L for hole
reaming to 1188 M, circulation, swept stability.
out hivis, CHC. Spotted Hiden in
string. POOH 12-1/4" bit to surface.
Prepare & logging job by Elnusa.
1-Jan-10 1,188 Cont'd Run Logging #1 DLL-MSFL- Increase MW to 1.23 SG in/out. Mix
BHC-GR-SP to 1182 M. Prepare & Hydro Plast for shale stability. Control
Run Logging #2 LDL-CNL-GR to 1183 pH by KOH. Made Hivis by Hydro
M. Prepare & RIH 12-1/4" bit, sit @ Zan. Add Hydro Lube as lubricity.
1173 M, reaming to 1188 M, Made Hident in slug tank. Material
circulation mud condition, increase Received : TLDF-1001-001 ; TLDF-
MW to 1.23 SG in/out, swept out 30 1001-002.
bbl hivis,CHC, spot 30 bbl hivis.
POOH 12-1/4" bit to surface. Prepare
& RIH 9-5/8" Casing.
2-Jan-10 1,188 Cont'd RIH 9-5/8" Casing, sit @ 1174 Used Barite for Cementing Job by
M, wash down to 1186 M (shoe). Dowel Cementing Slb. Reduce YP by
Circulation, prepare cementing job, thiner & Hydro Rez. Return 330 bbl
M/U cementing head, circulation, pre mud from hole, dump 294 bbl mud
job safety meeting before cementing from hole cause over mud tank
job. Test line, cementing job 9-5/8" volume (over gauge hole from caliper
Casing, displace with 240 bbl mud, no log). Material Received : TLDF-1001-
return, loss indication, cont'd displace 003
50 bbl mud. WOC.
3-Jan-10 1,188 Cont'd WOC. N/D cementing head, Dump & Clean Up Sandtrap & Setling
hang up BOP. Prepare & top job tank. Switch On centrifuge. Material
cementing. Install 9-5/8" casing Received : TLDF-1001-006.
hanger. N/D 13-5/8" 3000 x 13-5/8"
3000 spool & N/D Belt Nipple. Cut 9-
5/8" Casing Excess. N/U casing head
13-5/8 X 3000 X 11". N/U DSAF 13-
/8" X 3000 X11". N/U drilling spool 13-
5/8" X 3000 & N/U Belt Nipple.
Change regulator valve top drive. Test
Annular, HCR 4" 500 - 1500 Psi, pipe
ram and manual gate valve 500 -
1500 Psi. Stand up 5" DP.
4-Jan-10 1,225 Cont'd Stand up DP. Prepare RIH 8.5" Made 150 Polymer unweighted mud.
bit+BHA to 1125 M (TOC). DOC- Dump sandtrap for reduce solid.
collar-shoe & formation to 1192 M, Transfer form reserve to active for
circulation mud condition, MOT with decrease MW & Cl- while run
1.10 SG in/out 650 psi, EMW 1.5 SG. centrifuge. Made 100 bbl prevent
Cont'd drill formation to 1225 M. LCM 60 ppb in reserve as per coman
order. Control fluid loss by Hydro Star,
maintain vis by Hydro Pac R, control
rheology by Hydro Zan, add Hydro
Plast for shale stability, add Hydro
Cap L for cutting encapsulated as
Page 1 SCOMI Oiltools
FINAL WELL REPORT
WELL
TT-28
formation to 1426 M.
11-Jan-10 1,440 Cont’d Drilling f/ 1426 m to 1440 Add LCM 60 ppb concentration in
m.Circulation hole clean.Swept Hi-Vis reserve as per Co-man order by kwik
30 bbls.Spot Diasel M as LCM fluid 40 seal. Made Hivis by Hydro Pac-R.
bbls.POOH 8-1/2” PDC Bit to Made 70 bbl LCM Diaseal M. Made
surface.Prepared and RIH 5” DP + KCl Brine 24000 ppm. Used 160 sx of
3.5” DP Open End to 1438 CaCO3-F and 10 sx of Bentonite by
m.Prepared and M/U cementing head Dowell Cementing for cement
for cement plug job. carbonat plug job.
12-Jan-10 1,440 Cont’d Prepared cement plug Dumped water return from hole when
job.Cement plug Job by Dowell displace cement plug job. Checked
Schlumberger cementing cement return at flow line while
unit.Pumped cement Slurry 60 bbls circulated hole clean.Added KCl to
with 1.6 SG, displace with water 62.4 increased Cl – in active tank f/ 24000
bbls. POOH 5” DP 18 stand ( 1081 ppm to 25000 ppm as per co-man
m.). Circulated hole clean.Hold hole order.
with pressures 100 psi.WOC. RIH 8-
1/2” PDC Bit at 1170 m.
13-Jan-10 1,440 Cont’d WOC.Lower 8-1/2” PDC Bit to Made up Hi-Vis 70 bbls.Added Diasel
top of cement at 1252 m.Circulated M as LCM fluid to reserved tank .
and Drill out cement f/ 1252 m to 1440
m.Swept HiVis 35 bbls every drilling 3
stand.Circulated hole clean.swept Hi-
Vis 35 bbls.Short trip 8-1/2” PDC Bit f/
1440 m to 1373 m.Spot LCM-Diasel
M at 1373 m..Cont’d POOH 8-1/2”
PDC Bit f/ 1373 m to
1186m.Circulated and Lower 8-1/2”
PDC bit f/ 9-5/8” casing shoe at 1186
m to 1440 m.
14-Jan-10 1,440 Cont'd Lower 8-1/2" PDC bit to 1440 Increased Cl- content f/ 25000 ppm to
m.Circulated hole clean.Swept Hi-Vis 26000 ppm. KCl-Brine in active tank
35 bbls.Displaced water in hole by #2 as per Co-man order.Pumping
KCl-Brine with Cl- content 26000 KCl-Brine with 26000 ppm content
ppm.POOH 8-1/2" PDC Bit to into hole for displace water. Received
surface.Prepared and Runing hole material on Jan 14,2010 with : TLDF
Logging tools.Logging tools tag at 1001-030,TLDF 1001-031.TLDF
1270 m.Attempted to lower logging 1001-032 and TLDF 1001-033.M/U
tool to bottom but no progress.POOH KCl-Brine 110 bbls with Cl- content
logging tools to surface.Prepared and 26000 ppm.
RIH 8-1/2" PDC Bit to 600 m.Break
circulation.Cont'd RIH 8-1/2" PDC Bit
f/600 m to 1250 m.Reaming and
Wash down 8-1/2" PDC Bit f/1250 m
to 1440 m.POOH 8-1/2" PDC Bit to
surface.
15-Jan-10 1,440 Cont'd POOH 8-1/2" PDC bit to Add Hydrozan for rheology. Increased
surface. Prepared and running hole Cl- content to 26000 ppm by KCl. Add
logging tools. Run#1 for DLL-BHC- Hydro Pac R and Bentonite as
MSFL-GR-CAL-SP. Run#2 for LDL- viscosifier. Made 70 bbls hivis by
CNL-GR-CAL. POOH and L/D logging Hydro-zan.
tools. RIH 8-1/2" PDC bit and tag at
1431m. Break circulation. Reaming
and wash down 8-1/2 " PDC bit f/
1431m to 1440 m. Circulated hole
clean. Swept out 30 bbls hivis.
Spotted 40 bbls hivis and displaced
with 73 bbls water. Drop totco survey.
POOH 8-1/2" PDC bit to surface.
16-Jan-10 1,440 Cont'd POOH 8-1/2" PDC bit to Decreased PV and YP for cementing
surface. Prepared and Running hole job.Dowell cemnting unit used 80 sax
Casing 7" to 1438 m. Circulation hole Barite for cementing casing 7" Job.
clean.Prepared and M/U Cementing
Head by Dowell
Schlumberger.Flushing and test
cementing line with 2500
psi.Ok.Mixing and Pumping cement
slurry 120 bbls stage #1.Dropped
Opening boom DSCC casing
7".Circulated with mud trhu DSCC to
surface.while L/D DP 5" ,W.O.C
17-Jan-10 1,440 Cont'd L/D DP 5" while Watched and check ed cement return
WOC.Prepared and Mixing Cement on flow line.Dumped water and clean
for Cement job stage #2.Cementing up on Active tank #2.Prepared and
job Stage #2 with DSCC at 1131 m by built up KCl-Brine as Complation Fluid
Dowell Schlumberger cementing with 2% KCl as per Co-man Program.
unit.Flushing and N/D BOP.N/U X-
mas tree.Cont'd L/D 5".MUD
ENGINEER RELEASED ON
JANUARY 17,2009
YP, lb/100 ft2 18 #N/A #N/A Btm Up min/stk 2 504 Solid Control
Gels 10 sec/10 min/30 min 6/8/0 #N/A #N/A Suc - Surf min/stk 2 518 Dump
600/300 rpm 34 26 #N/A #N/A #N/A #N/A Total min/stk 55 13,290 Behind Casing
200/100 rpm 18 12 #N/A #N/A #N/A #N/A Misc. Loss 10.00 bbl 10.00 bbl
6/3 rpm 6 5 #N/A #N/A #N/A #N/A Mud Returned
API Filtrate, ml/30 min 7 #N/A #N/A @ MD Total Losses 10.00 bbl 10.0 bbl
HTHP ml/30 min @ °F #N/A #N/A MUD TREATMENTS
Cake API/HTHP, 32nd in 1 #N/A #N/A #N/A #N/A Mud Engineer arrived at TT-28 location on December 10th, 2009. Report to Co. Man & Safety induction by HSE. Chemical
Solids, % by vol 1.5 #N/A #N/A Inventory & check pit tank area, mix KCl Polymer as per prog
Oil / Water, % by vol 98.5 #N/A #N/A #N/A #N/A
Sand, % by vol #N/A #N/A
MBT, ppb 7.5 #N/A #N/A DRILLING ACTIVITY
pH @ °F 9.5 #N/A #N/A Prepare & Drill surface with 26" bit to 28 m for stove pipe, run 20" casing to 28 m, cementing job. WOC. Ceremonial for TT-28
Alkalinity Mud, (PM) #N/A #N/A well. Cut exces 20" casing. M/U 17.5"+BHA, RIH 17.5" bit to 28 m Top of Formation, displace new mud in hole while dump old
Alkalinity Filtrate, (Pf/Mf) #N/A #N/A #N/A #N/A mud in hole. Spud in on December 11, 2009 at 00.00 WIB. Drill formation to 32 m at mud eng time report.
Chlorides, mg/l 14000 #N/A #N/A
Total Hard. Calcium, mg/l 120 #N/A #N/A DAILY PRODUCT USAGE
LGS/HGS, % by vol 0.2 0.3 #N/A #N/A #N/A #N/A UNITS Starting RECEIVED USED
PRODUCT RETURN ON HAND COST
LGS/HGS, ppb 1.5 5.1 #N/A #N/A #N/A #N/A Prices #/Unit Inv DAILY CUM DAILY CUM
ASG 3.7 #N/A #N/A BARITE $ 10.99 100 LB 120 120 120 $ -
K+, mg/l 15000 #N/A #N/A BENTONITE $ 14.04 100 LB 180 180 30 30 150 $ 421.20
WBM Add 2 #N/A #N/A CAUSTIC SODA $ 26.24 25 KG 30 30 2 2 28 $ 52.48
TIME OPERATION HYDRO-PAC LV $ 88.29 25 KG 70 70 30 30 40 $ 2,648.70
DESCRIPTION DAILY TOTAL DESCRIPTION DAILY TOTAL HYDRO-PAC R $ 96.53 25 KG 50 50 10 10 40 $ 965.30
Drilling N/U BOPs HYDRO-STAR NF $ 29.86 25 KG 40 40 40 $ -
RIH Bit RIH Scraper 7" HYDRO-ZAN $ 134.49 25 KG 45 45 5 5 40 $ 672.45
POOH Bit Reaming POTASSIUM CHLORIDES$ 65.00 50 KG 100 100 50 50 50 $ 3,250.00
Circulating Coring Job #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Logging Rig Service #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Casing Short Trip #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Cementing Other 24 24 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
WOCement Total Hrs. 24 24 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
PIT VOLUME ANCILLARY CHARGES
FLUID TYPES PIT No. MW VOLUME Mud Engineer I $ 250.00
KCl Polymer Sand Trap 1.03 80 bbl Mud Boy $ 100.00
KCl Polymer Setling Tank 1.03 50 bbl COST SUMMARY
KCl Polymer Desander Tank 1.03 135 bbl Previous Product Cost
KCl Polymer Desilter Tank 1.03 140 bbl Daily Product Cost : $ 8,010.13
KCl Polymer Active Tank 1.03 355 bbl Cum. Product Cost : $ 8,010.13
Previous Engineer Charge
Daily Engineer Charge : $ 350.00
Cum. Engineer Charge : $ 350.00
Scomi Total Cost : $ 8,360.13
YP, lb/100 ft2 21 18 #N/A Btm Up min/stk 6 1,906 Solid Control 50.00 bbl 50.00 bbl
Gels 10 sec/10 min/30 min 7 / 10 / 0 5/7/0 #N/A Suc - Surf min/stk 6 1,965 Dump
600/300 rpm 41 31 38 28 #N/A #N/A Total min/stk 42 13,981 Behind Casing
200/100 rpm 19 12 19 14 #N/A #N/A Misc. Loss 133.00 bbl 143.00 bbl
6/3 rpm 8 6 4 3 #N/A #N/A Mud Returned
API Filtrate, ml/30 min 6 6 #N/A @ MD Total Losses 193.00 bbl 203.0 bbl
HTHP ml/30 min @ °F #N/A MUD TREATMENTS
Cake API/HTHP, 32nd in 1 1 #N/A #N/A Build up 200 bbl KCl Polymer to keep vol. Add KCl for reactive clay. Control fluid loss by hydro star.
Solids, % by vol 2 3 #N/A
Oil / Water, % by vol 98 97 #N/A #N/A
Sand, % by vol 0.1 0.1 #N/A
MBT, ppb 12.5 10 #N/A DRILLING ACTIVITY
pH @ °F 9.5 9 #N/A Cont'd drill formation to 140 M
Alkalinity Mud, (PM) #N/A
Alkalinity Filtrate, (Pf/Mf) #N/A #N/A
Chlorides, mg/l 19000 24000 #N/A
Total Hard. Calcium, mg/l 120 120 #N/A DAILY PRODUCT USAGE
LGS/HGS, % by vol 0.2 0.5 1.2 0.1 #N/A #N/A UNITS Starting RECEIVED USED
PRODUCT RETURN ON HAND COST
LGS/HGS, ppb 1.8 7.0 11.3 1.5 #N/A #N/A Prices #/Unit Inv DAILY CUM DAILY CUM
ASG 3.7 2.7 #N/A BENTONITE $ 14.04 100 LB 150 180 30 60 120 $ 421.20
K+, mg/l 20000 20000 #N/A CAUSTIC SODA $ 26.24 25 KG 28 30 4 6 24 $ 104.96
WBM Add 2 #N/A HYDRO-PAC LV $ 88.29 25 KG 40 70 20 50 20 $ 1,765.80
TIME OPERATION HYDRO-PAC R $ 96.53 25 KG 40 30 80 10 20 60 $ 965.30
DESCRIPTION DAILY TOTAL DESCRIPTION DAILY TOTAL HYDRO-REZ $ 32.13 25 KG 40 40 40 $ -
Drilling 24 24 N/U BOPs HYDRO-STAR NF $ 29.86 25 KG 40 30 70 40 40 30 $ 1,194.40
RIH Bit RIH Scraper 7" HYDRO-ZAN $ 134.49 25 KG 40 45 10 15 30 $ 1,344.90
POOH Bit Reaming POTASSIUM CHLORIDES$ 65.00 50 KG 50 140 240 130 180 60 $ 8,450.00
Circulating Coring Job SHALE-STAB $ 36.08 50 LB 40 40 40 $ -
Logging Rig Service #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Casing Short Trip #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Cementing Other 24 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
WOCement Total Hrs. 24 48 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
PIT VOLUME ANCILLARY CHARGES
FLUID TYPES PIT No. MW VOLUME Mud Engineer I $ 250.00
KCl Polymer Sand Trap 1.03 80 bbl Mud Boy $ 100.00
KCl Polymer Setling Tank 1.03 50 bbl COST SUMMARY
KCl Polymer Desander Tank 1.03 130 bbl Previous Product Cost : $ 8,010.13
KCl Polymer Desilter Tank 1.03 135 bbl Daily Product Cost : $ 14,246.56
KCl Polymer Active Tank 1.03 320 bbl Cum. Product Cost : $ 22,256.69
Hivis Slug 1.02 30 bbl Previous Engineer Charge : $ 350.00
KCl Polymer Reserve 1 1.02 50 bbl Daily Engineer Charge : $ 350.00
KCl Polymer Reserve 2 1.02 80 bbl Cum. Engineer Charge : $ 700.00
KCl Polymer Trip Tank 1.05 30 bbl Scomi Total Cost : $ 22,956.69
YP, lb/100 ft2 23 #N/A #N/A Btm Up min/stk Solid Control 30.00 bbl 120.00 bbl
Gels 10 sec/10 min/30 min 9 / 15 / 0 #N/A #N/A Suc - Surf min/stk Dump 150.00 bbl 150.00 bbl
600/300 rpm 43 33 #N/A #N/A #N/A #N/A Total min/stk Behind Casing
200/100 rpm 27 20 #N/A #N/A #N/A #N/A Misc. Loss 120.00 bbl 390.00 bbl
6/3 rpm 8 7 #N/A #N/A #N/A #N/A Mud Returned
API Filtrate, ml/30 min 6 #N/A #N/A @ MD Total Losses 300.00 bbl 675.0 bbl
HTHP ml/30 min @
#N/A °F #N/A #N/A MUD TREATMENTS
Cake API/HTHP, 32nd in 1 #N/A #N/A #N/A #N/A Used Barite for Cementing Job by Dowel Slb. Dump & clean up sandtrap & setling tank.
Solids, % by vol 3 #N/A #N/A
Oil / Water, % by vol 97 #N/A #N/A #N/A #N/A
Sand, % by vol 0.1 #N/A #N/A
MBT, ppb 12.5 #N/A #N/A DRILLING ACTIVITY
pH @ #N/A °F 9 #N/A #N/A Cont'd run 13-3/8" casing to 196 m (shoe). Install Circulating head, Circulation, L/D circulating head, M/U cementing head.
Alkalinity Mud, (PM) #N/A #N/A Prepare cementing job 13-3/8" casing. Intermiten return, no cement return. WOC. L/D Cementing head, RIH 1" macaroni pipe
Alkalinity Filtrate, (Pf/Mf) #N/A #N/A #N/A #N/A between 20" - 13-3/8" casing, tag TOC @ 23.60 m, POH macaroni pipe & set @ 18.50 m. R.U cementing line. Prepare &
cementing top job.
Chlorides, mg/l 22000 #N/A #N/A
Total Hard. Calcium, mg/l 120 #N/A #N/A DAILY PRODUCT USAGE
LGS/HGS, % by vol 0.8 0.7 #N/A #N/A #N/A #N/A UNITS Starting RECEIVED USED
PRODUCT RETURN ON HAND COST
LGS/HGS, ppb 6.8 10.6 #N/A #N/A #N/A #N/A Prices #/Unit Inv DAILY CUM DAILY CUM
ASG 3.4 #N/A #N/A BARITE $ 10.99 100 LB 120 120 80 80 40 $ 879.20
K+, mg/l 18000 #N/A #N/A #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
WBM Add 2 #N/A #N/A #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
TIME OPERATION #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
DESCRIPTION DAILY TOTAL DESCRIPTION DAILY TOTAL #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Drilling 36 N/U BOPs #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Bit 2 RIH Scraper 7" #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
POOH Bit 4 Reaming #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Circulating 4 6 Coring Job #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Logging Rig Service #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Casing 3 6 Short Trip #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Cementing 2.5 2.5 Other 10.5 35.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
WOCement 4 4 Total Hrs. 24 96 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
PIT VOLUME ANCILLARY CHARGES
FLUID TYPES PIT No. MW VOLUME Mud Engineer I $ 250.00
Mud Boy $ 100.00
KCl Polymer Setling Tank 1.06 50 bbl COST SUMMARY
KCl Polymer Desander Tank 1.06 135 bbl Previous Product Cost : $ 29,685.76
KCl Polymer Desilter Tank 1.06 140 bbl Daily Product Cost : $ 879.20
KCl Polymer Active Tank 1.06 200 bbl Cum. Product Cost : $ 30,564.96
Previous Engineer Charge : $ 1,050.00
Daily Engineer Charge : $ 350.00
KCl Polymer Reserve 2 1.02 40 bbl Cum. Engineer Charge : $ 1,400.00
Scomi Total Cost : $ 31,964.96
YP, lb/100 ft2 23 #N/A #N/A Btm Up min/stk Solid Control 30.00 bbl 120.00 bbl
Gels 10 sec/10 min/30 min 9 / 15 / 0 #N/A #N/A Suc - Surf min/stk Dump 150.00 bbl 150.00 bbl
600/300 rpm 43 33 #N/A #N/A #N/A #N/A Total min/stk Behind Casing
200/100 rpm 27 20 #N/A #N/A #N/A #N/A Misc. Loss 120.00 bbl 390.00 bbl
6/3 rpm 8 7 #N/A #N/A #N/A #N/A Mud Returned
API Filtrate, ml/30 min 6 #N/A #N/A @ MD Total Losses 300.00 bbl 675.0 bbl
HTHP ml/30 min @
#N/A °F #N/A #N/A MUD TREATMENTS
Cake API/HTHP, 32nd in 1 #N/A #N/A #N/A #N/A Used Barite for Cementing Job by Dowel Slb. Dump & clean up sandtrap & setling tank.
Solids, % by vol 3 #N/A #N/A
Oil / Water, % by vol 97 #N/A #N/A #N/A #N/A
Sand, % by vol 0.1 #N/A #N/A
MBT, ppb 12.5 #N/A #N/A DRILLING ACTIVITY
pH @ #N/A °F 9 #N/A #N/A Cont'd run 13-3/8" casing to 196 m (shoe). Install Circulating head, Circulation, L/D circulating head, M/U cementing head.
Alkalinity Mud, (PM) #N/A #N/A Prepare cementing job 13-3/8" casing. Intermiten return, no cement return. WOC. L/D Cementing head, RIH 1" macaroni pipe
Alkalinity Filtrate, (Pf/Mf) #N/A #N/A #N/A #N/A between 20" - 13-3/8" casing, tag TOC @ 23.60 m, POH macaroni pipe & set @ 18.50 m. R.U cementing line. Prepare &
cementing top job.
Chlorides, mg/l 22000 #N/A #N/A
Total Hard. Calcium, mg/l 120 #N/A #N/A DAILY PRODUCT USAGE
LGS/HGS, % by vol 0.8 0.7 #N/A #N/A #N/A #N/A UNITS Starting RECEIVED USED
PRODUCT RETURN ON HAND COST
LGS/HGS, ppb 6.8 10.6 #N/A #N/A #N/A #N/A Prices #/Unit Inv DAILY CUM DAILY CUM
ASG 3.4 #N/A #N/A BARITE $ 10.99 100 LB 120 120 80 80 40 $ 879.20
K+, mg/l 18000 #N/A #N/A #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
WBM Add 2 #N/A #N/A #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
TIME OPERATION #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
DESCRIPTION DAILY TOTAL DESCRIPTION DAILY TOTAL #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Drilling 36 N/U BOPs #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Bit 2 RIH Scraper 7" #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
POOH Bit 4 Reaming #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Circulating 4 6 Coring Job #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Logging Rig Service #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Casing 3 6 Short Trip #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Cementing 2.5 2.5 Other 10.5 35.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
WOCement 4 4 Total Hrs. 24 96 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
PIT VOLUME ANCILLARY CHARGES
FLUID TYPES PIT No. MW VOLUME Mud Engineer I $ 250.00
Mud Boy $ 100.00
KCl Polymer Setling Tank 1.06 50 bbl COST SUMMARY
KCl Polymer Desander Tank 1.06 135 bbl Previous Product Cost : $ 29,685.76
KCl Polymer Desilter Tank 1.06 140 bbl Daily Product Cost : $ 879.20
KCl Polymer Active Tank 1.06 200 bbl Cum. Product Cost : $ 30,564.96
Previous Engineer Charge : $ 1,050.00
Daily Engineer Charge : $ 350.00
KCl Polymer Reserve 2 1.02 40 bbl Cum. Engineer Charge : $ 1,400.00
Scomi Total Cost : $ 31,964.96
YP, lb/100 ft2 23 #N/A #N/A Btm Up min/stk Solid Control 120.00 bbl
Gels 10 sec/10 min/30 min 9 / 15 / 0 #N/A #N/A Suc - Surf min/stk Dump 150.00 bbl
600/300 rpm 43 33 #N/A #N/A #N/A #N/A Total min/stk Behind Casing
200/100 rpm 27 20 #N/A #N/A #N/A #N/A Misc. Loss 390.00 bbl
6/3 rpm 8 7 #N/A #N/A #N/A #N/A Mud Returned
API Filtrate, ml/30 min 6 #N/A #N/A @ MD Total Losses 675.0 bbl
HTHP ml/30 min @
#N/A °F #N/A #N/A MUD TREATMENTS
Cake API/HTHP, 32nd in 1 #N/A #N/A #N/A #N/A Cont'd clean up sand trap & setling tank. None chemical used. Material Received TLDF-0912-275.
Solids, % by vol 3 #N/A #N/A
Oil / Water, % by vol 97 #N/A #N/A #N/A #N/A
Sand, % by vol 0.1 #N/A #N/A
MBT, ppb 12.5 #N/A #N/A DRILLING ACTIVITY
pH @ #N/A °F 9 #N/A #N/A WOC. Cut 20" exces casing. Prepare & Cementing top job #2, WOC. Clean up cement at cellar.
Alkalinity Mud, (PM) #N/A #N/A
Alkalinity Filtrate, (Pf/Mf) #N/A #N/A #N/A #N/A
Chlorides, mg/l 22000 #N/A #N/A
Total Hard. Calcium, mg/l 120 #N/A #N/A DAILY PRODUCT USAGE
LGS/HGS, % by vol 0.8 0.7 #N/A #N/A #N/A #N/A UNITS Starting RECEIVED USED
PRODUCT RETURN ON HAND COST
LGS/HGS, ppb 6.8 10.6 #N/A #N/A #N/A #N/A Prices #/Unit Inv DAILY CUM DAILY CUM
ASG 3.4 #N/A #N/A DEFOAMER $ 463.73 55 GAL 4 4 4 $ -
K+, mg/l 18000 #N/A #N/A DRILLING DETERGENT $ 192.72 55 GAL 4 4 4 $ -
WBM Add 2 #N/A #N/A HYDRO-LUBE $ 424.14 55 GAL 4 4 4 $ -
TIME OPERATION #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
DESCRIPTION DAILY TOTAL DESCRIPTION DAILY TOTAL #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Drilling 36 N/U BOPs #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Bit 2 RIH Scraper 7" #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
POOH Bit 4 Reaming #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Circulating 6 Coring Job #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Logging Rig Service #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Casing 6 Short Trip #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Cementing 1 3.5 Other 15 50.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
WOCement 8 12 Total Hrs. 24 120 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
PIT VOLUME ANCILLARY CHARGES
FLUID TYPES PIT No. MW VOLUME Mud Engineer I $ 250.00
Mud Boy $ 100.00
KCl Polymer Setling Tank 1.06 50 bbl COST SUMMARY
KCl Polymer Desander Tank 1.06 135 bbl Previous Product Cost : $ 30,564.96
KCl Polymer Desilter Tank 1.06 140 bbl Daily Product Cost
KCl Polymer Active Tank 1.06 200 bbl Cum. Product Cost : $ 30,564.96
Previous Engineer Charge : $ 1,400.00
Daily Engineer Charge : $ 350.00
KCl Polymer Reserve 2 1.02 40 bbl Cum. Engineer Charge : $ 1,750.00
Scomi Total Cost : $ 32,314.96
YP, lb/100 ft2 23 #N/A #N/A Btm Up min/stk Solid Control 120.00 bbl
Gels 10 sec/10 min/30 min 9 / 15 / 0 #N/A #N/A Suc - Surf min/stk Dump 150.00 bbl
600/300 rpm 43 33 #N/A #N/A #N/A #N/A Total min/stk Behind Casing
200/100 rpm 27 20 #N/A #N/A #N/A #N/A Misc. Loss 390.00 bbl
6/3 rpm 8 7 #N/A #N/A #N/A #N/A Mud Returned
API Filtrate, ml/30 min 6 #N/A #N/A @ MD Total Losses 675.0 bbl
HTHP ml/30 min @
#N/A °F #N/A #N/A MUD TREATMENTS
Cake API/HTHP, 32nd in 1 #N/A #N/A #N/A #N/A None chemical used. Material Received : TLDF-0917-276 ; TLDF-0917-277. Transfer Material Barite to TT-27 : 03/0547.
Solids, % by vol 3 #N/A #N/A
Oil / Water, % by vol 97 #N/A #N/A #N/A #N/A
Sand, % by vol 0.1 #N/A #N/A
MBT, ppb 12.5 #N/A #N/A DRILLING ACTIVITY
pH @ #N/A °F 9 #N/A #N/A Install & welded bottom flange, wait for cooling down of weld. N/U BOP's group. Function test BOP's group. R/U Top Drive.
Alkalinity Mud, (PM) #N/A #N/A
Alkalinity Filtrate, (Pf/Mf) #N/A #N/A #N/A #N/A
Chlorides, mg/l 22000 #N/A #N/A
Total Hard. Calcium, mg/l 120 #N/A #N/A DAILY PRODUCT USAGE
LGS/HGS, % by vol 0.8 0.7 #N/A #N/A #N/A #N/A UNITS Starting RECEIVED USED
PRODUCT RETURN ON HAND COST
LGS/HGS, ppb 6.8 10.6 #N/A #N/A #N/A #N/A Prices #/Unit Inv DAILY CUM DAILY CUM
ASG 3.4 #N/A #N/A BARITE $ 10.99 100 LB 40 120 240 80 80 80 $ -
K+, mg/l 18000 #N/A #N/A HYDRO-PAC R $ 96.53 25 KG 55 30 110 25 85 $ -
WBM Add 2 #N/A #N/A POTASSIUM CHLORIDES$ 65.00 50 KG 175 50 465 240 225 $ -
TIME OPERATION #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
DESCRIPTION DAILY TOTAL DESCRIPTION DAILY TOTAL #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Drilling 36 N/U BOPs 8 8 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Bit 2 RIH Scraper 7" #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
POOH Bit 4 Reaming #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Circulating 6 Coring Job #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Logging Rig Service #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Casing 6 Short Trip #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Cementing 3.5 Other 16 66.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
WOCement 12 Total Hrs. 24 144 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
PIT VOLUME ANCILLARY CHARGES
FLUID TYPES PIT No. MW VOLUME Mud Engineer I $ 250.00
Mud Boy $ 100.00
KCl Polymer Setling Tank 1.06 50 bbl COST SUMMARY
KCl Polymer Desander Tank 1.06 135 bbl Previous Product Cost : $ 30,564.96
KCl Polymer Desilter Tank 1.06 140 bbl Daily Product Cost
KCl Polymer Active Tank 1.06 200 bbl Cum. Product Cost : $ 30,564.96
Previous Engineer Charge : $ 1,750.00
Daily Engineer Charge : $ 350.00
KCl Polymer Reserve 2 1.02 40 bbl Cum. Engineer Charge : $ 2,100.00
Scomi Total Cost : $ 32,664.96
YP, lb/100 ft2 23 22 #N/A Btm Up min/stk 6 1,182 Solid Control 10.00 bbl 130.00 bbl
Gels 10 sec/10 min/30 min 9 / 15 / 0 8 / 13 / 0 #N/A Suc - Surf min/stk 7 1,265 Dump 150.00 bbl
600/300 rpm 43 33 46 34 #N/A #N/A Total min/stk 60 11,095 Behind Casing
200/100 rpm 27 20 28 21 #N/A #N/A Misc. Loss 2.00 bbl 392.00 bbl
6/3 rpm 8 7 8 6 #N/A #N/A Mud Returned
API Filtrate, ml/30 min 6 6 #N/A @ MD Total Losses 13.00 bbl 688.0 bbl
HTHP ml/30 min @
#N/A °F #N/A MUD TREATMENTS
Cake API/HTHP, 32nd in 1 1 #N/A #N/A Control Fluid loss by Hydro Star & Hydro Pac L. Maintain vis by Hydo Pac R. Add Hydro Zan for Rheology. Increase K+ by KCl.
Solids, % by vol 3 3 #N/A Change shale shaker screen.
Oil / Water, % by vol 97 97 #N/A #N/A
Sand, % by vol 0.1 0.1 #N/A
MBT, ppb 12.5 12.5 #N/A DRILLING ACTIVITY
pH @ #N/A °F 9 9 #N/A Cont'd R/U Top Drive, fungtion test top drive. Stand up 5" DP. M/U 12-1/4" PDC+BHA, RIH 12-1/4" PDC to 181 m (TOC).
Alkalinity Mud, (PM) #N/A DOC, top plug, bottom plug to 192 M, casing test 1000 psi hold 5' ok. Cont'd drill to 196 m (shoe) at mud eng time report.
Alkalinity Filtrate, (Pf/Mf) #N/A #N/A
Chlorides, mg/l 22000 26000 #N/A
Total Hard. Calcium, mg/l 120 200 #N/A DAILY PRODUCT USAGE
LGS/HGS, % by vol 0.8 0.7 0.5 0.7 #N/A #N/A UNITS Starting RECEIVED USED
PRODUCT RETURN ON HAND COST
LGS/HGS, ppb 6.8 10.6 4.3 10.6 #N/A #N/A Prices #/Unit Inv DAILY CUM DAILY CUM
ASG 3.4 3.6 #N/A HYDRO-PAC LV $ 88.29 25 KG 30 100 10 80 20 $ 882.90
K+, mg/l 18000 24000 #N/A HYDRO-PAC R $ 96.53 25 KG 85 110 3 28 82 $ 289.59
WBM Add 2 #N/A HYDRO-STAR NF $ 29.86 25 KG 60 100 10 50 50 $ 298.60
TIME OPERATION HYDRO-ZAN $ 134.49 25 KG 24 45 3 24 21 $ 403.47
DESCRIPTION DAILY TOTAL DESCRIPTION DAILY TOTAL POTASSIUM CHLORIDES$ 65.00 50 KG 225 465 50 290 175 $ 3,250.00
Drilling 5 41 N/U BOPs 8 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Bit 4 6 RIH Scraper 7" #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
POOH Bit 4 Reaming #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Circulating 1 7 Coring Job #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Logging Rig Service #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Casing 6 Short Trip #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Cementing 3.5 Other 14 80.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
WOCement 12 Total Hrs. 24 168 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
PIT VOLUME ANCILLARY CHARGES
FLUID TYPES PIT No. MW VOLUME Mud Engineer I $ 250.00
KCl Polymer Sand Trap 1.06 50 bbl Mud Boy $ 100.00
KCl Polymer Setling Tank 1.06 50 bbl COST SUMMARY
KCl Polymer Desander Tank 1.06 140 bbl Previous Product Cost : $ 30,564.96
KCl Polymer Desilter Tank 1.06 145 bbl Daily Product Cost : $ 5,124.56
KCl Polymer Active Tank 1.06 200 bbl Cum. Product Cost : $ 35,689.52
Previous Engineer Charge : $ 2,100.00
Daily Engineer Charge : $ 350.00
KCl Polymer Reserve 2 1.02 Cum. Engineer Charge : $ 2,450.00
Scomi Total Cost : $ 38,139.52
YP, lb/100 ft2 21 23 #N/A Btm Up min/stk 5 1,881 Solid Control 30.00 bbl 160.00 bbl
Gels 10 sec/10 min/30 min 5/9/0 9 / 15 / 0 #N/A Suc - Surf min/stk 6 2,069 Dump 150.00 bbl
600/300 rpm 43 32 49 36 #N/A #N/A Total min/stk 33 11,395 Behind Casing
200/100 rpm 23 16 27 19 #N/A #N/A Misc. Loss 14.00 bbl 406.00 bbl
6/3 rpm 5 4 8 6 #N/A #N/A Mud Returned
API Filtrate, ml/30 min 5.8 5.6 #N/A @ MD Total Losses 54.00 bbl 742.0 bbl
HTHP ml/30 min @
#N/A °F #N/A MUD TREATMENTS
Cake API/HTHP, 32nd in 1 1 #N/A #N/A Build up 100 bbl KCl Polymer. Control fluid loss by Hydro Star, maintain vis by Hydro Pac R, add Hydrozan for rheology, add
Solids, % by vol 4 4 #N/A drilling detergent for clean the bit in clay formation. Add KCl for reactive clay. Material Received : TLDF-0912-279. Material
Oil / Water, % by vol 96 96 #N/A #N/A Received from TT-27 : MT-03/0390
Sand, % by vol 0.2 0.5 #N/A
MBT, ppb 7.5 10 #N/A DRILLING ACTIVITY
pH @ #N/A °F 10.5 9.5 #N/A Cont'd drill formation to 200 m. MOT with 1.06 SG in/out 150 psi, EMW 1.59 SG. Cont'd drill formation to 298 M. (pump ivis :
Alkalinity Mud, (PM) #N/A 257 m; 294 m)
Alkalinity Filtrate, (Pf/Mf) #N/A #N/A
Chlorides, mg/l 32000 43000 #N/A
Total Hard. Calcium, mg/l 200 180 #N/A DAILY PRODUCT USAGE
LGS/HGS, % by vol 1.5 0.3 0.1 1.0 #N/A #N/A UNITS Starting RECEIVED USED
PRODUCT RETURN ON HAND COST
LGS/HGS, ppb 13.2 5.1 0.7 14.3 #N/A #N/A Prices #/Unit Inv DAILY CUM DAILY CUM
ASG 2.9 4.1 #N/A BARITE $ 10.99 100 LB 80 40 280 80 120 $ -
K+, mg/l 30000 31000 #N/A BENTONITE $ 14.04 100 LB 90 16 196 10 100 96 $ 140.40
WBM Add 2 #N/A CALCIUM CARBONATE C$ 7.84 25 KG 40 40 40 $ -
TIME OPERATION CALCIUM CARBONATE F$ 7.84 25 KG 40 40 40 $ -
DESCRIPTION DAILY TOTAL DESCRIPTION DAILY TOTAL CAUSTIC SODA $ 26.24 25 KG 22 5 35 8 27 $ -
Drilling 24 65 N/U BOPs 8 DEFOAMER $ 463.73 55 GAL 4 2 6 6 $ -
RIH Bit 6 RIH Scraper 7" DRILLING DETERGENT $ 192.72 55 GAL 4 3 7 1 1 6 $ 192.72
POOH Bit 4 Reaming GLUTARALDEHYDE $ 58.08 5 GAL 30 30 30 $ -
Circulating 7 Coring Job HYDRO-CAP L $ 50.65 5 GAL 52 52 52 $ -
Logging Rig Service HYDRO-LUBE $ 424.14 55 GAL 4 4 8 8 $ -
RIH Casing 6 Short Trip HYDRO-PAC LV $ 88.29 25 KG 20 52 152 10 90 62 $ 882.90
Cementing 3.5 Other 80.5 HYDRO-PAC R $ 96.53 25 KG 82 32 142 12 40 102 $ 1,158.36
WOCement 12 Total Hrs. 24 192 HYDRO-STAR NF $ 29.86 25 KG 50 56 156 20 70 86 $ 597.20
PIT VOLUME ANCILLARY CHARGES
FLUID TYPES PIT No. MW VOLUME Mud Engineer I $ 250.00
KCl Polymer Sand Trap 1.08 50 bbl Mud Boy $ 100.00
KCl Polymer Setling Tank 1.08 50 bbl COST SUMMARY
KCl Polymer Desander Tank 1.08 125 bbl Previous Product Cost : $ 35,689.52
KCl Polymer Desilter Tank 1.08 130 bbl Daily Product Cost : $ 13,528.52
KCl Polymer Active Tank 1.08 200 bbl Cum. Product Cost : $ 49,218.04
Hivis Slug 1.08 50 bbl Previous Engineer Charge : $ 2,450.00
KCl Polymer Reserve 1 1.05 Daily Engineer Charge : $ 350.00
KCl Polymer Cum. Engineer Charge : $ 2,800.00
Scomi Total Cost : $ 52,018.04
YP, lb/100 ft2 31 29 #N/A Btm Up min/stk Solid Control 30.00 bbl 190.00 bbl
Gels 10 sec/10 min/30 min 7 / 10 / 0 8 / 10 / 0 #N/A Suc - Surf min/stk Dump 120.00 bbl 270.00 bbl
600/300 rpm 71 51 55 42 #N/A #N/A Total min/stk Behind Casing
200/100 rpm 42 30 33 23 #N/A #N/A Misc. Loss 17.00 bbl 423.00 bbl
6/3 rpm 9 6 9 7 #N/A #N/A Mud Returned
API Filtrate, ml/30 min 5.4 5.2 #N/A @ MD Total Losses 169.00 bbl 911.0 bbl
HTHP ml/30 min @ °F #N/A MUD TREATMENTS
Cake API/HTHP, 32nd in 1 1 #N/A #N/A Build up 200 bbl KCl Polymer. Dump & dilute for reduce solid while maintain MW. Control fluid loss by Hydro Pac L & Hydro
Solids, % by vol 5 4 #N/A Star, maintain vis by Hydro Pac R, add Hydro zan for rheology & made hivis, add KCl for reactive clay. Add drilling detergent for
Oil / Water, % by vol 95 96 #N/A #N/A clean the bit, add Hydro Lube as lubricity.
Sand, % by vol 0.6 0.6 #N/A
MBT, ppb 10 10 #N/A DRILLING ACTIVITY
pH @ °F 9 9 #N/A Cont'd drill formation to 380 m, circulation, swept out 30 bbl hivis, CHC. POOH 12-1/4" bit to shoe while pump. Cont'd POOH
Alkalinity Mud, (PM) #N/A 12-1/4" bit to surface. L/D 2 jts 8" DC & 2 jts stabilizer. RIH 12-1/4" bit+8" DC to 180 for safety. Repair mud pump.
Alkalinity Filtrate, (Pf/Mf) #N/A #N/A
Chlorides, mg/l 44000 40000 #N/A
Total Hard. Calcium, mg/l 180 180 #N/A DAILY PRODUCT USAGE
LGS/HGS, % by vol 1.4 0.6 0.9 0.3 #N/A #N/A UNITS Starting RECEIVED USED
PRODUCT RETURN ON HAND COST
LGS/HGS, ppb 12.9 8.8 8.2 5.1 #N/A #N/A Prices #/Unit Inv DAILY CUM DAILY CUM
ASG 3.1 3.0 #N/A BENTONITE $ 14.04 100 LB 96 196 10 110 86 $ 140.40
K+, mg/l 30000 29000 #N/A DRILLING DETERGENT $ 192.72 55 GAL 6 7 1 2 5 $ 192.72
WBM Add 2 #N/A HYDRO-LUBE $ 424.14 55 GAL 8 8 1 1 7 $ 424.14
TIME OPERATION HYDRO-PAC LV $ 88.29 25 KG 62 152 30 120 32 $ 2,648.70
DESCRIPTION DAILY TOTAL DESCRIPTION DAILY TOTAL HYDRO-PAC R $ 96.53 25 KG 102 142 6 46 96 $ 579.18
Drilling 14 79 N/U BOPs 8 HYDRO-STAR NF $ 29.86 25 KG 86 30 186 35 105 81 $ 1,045.10
RIH Bit 6 RIH Scraper 7" HYDRO-ZAN $ 134.49 25 KG 25 55 4 34 21 $ 537.96
POOH Bit 5 9 Reaming POTASSIUM CHLORIDES$ 65.00 50 KG 75 50 565 75 515 50 $ 4,875.00
Circulating 1 8 Coring Job POTASSIUM HYDROXIDE$ 53.74 25 KG 47 47 3 3 44 $ 161.22
Logging Rig Service 3 3 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Casing 6 Short Trip #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Cementing 3.5 Other 1 81.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
WOCement 12 Total Hrs. 24 216 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
PIT VOLUME ANCILLARY CHARGES
FLUID TYPES PIT No. MW VOLUME Mud Engineer I $ 250.00
KCl Polymer Mud Boy $ 100.00
KCl Polymer Setling Tank 1.07 40 bbl COST SUMMARY
KCl Polymer Desander Tank 1.07 120 bbl Previous Product Cost : $ 49,218.04
KCl Polymer Desilter Tank 1.07 125 bbl Daily Product Cost : $ 10,604.42
KCl Polymer Active Tank 1.07 180 bbl Cum. Product Cost : $ 59,822.46
Hivis Slug 1.09 40 bbl Previous Engineer Charge : $ 2,800.00
KCl Polymer Reserve 1 1.09 80 bbl Daily Engineer Charge : $ 350.00
KCl Polymer Cum. Engineer Charge : $ 3,150.00
Scomi Total Cost : $ 62,972.46
YP, lb/100 ft2 29 27 #N/A Btm Up min/stk 10 2,967 Solid Control 15.00 bbl 205.00 bbl
Gels 10 sec/10 min/30 min 8 / 10 / 0 5/7/0 #N/A Suc - Surf min/stk 11 3,282 Dump 270.00 bbl
600/300 rpm 55 42 63 45 #N/A #N/A Total min/stk 39 11,601 Behind Casing
200/100 rpm 33 23 31 26 #N/A #N/A Misc. Loss 9.00 bbl 432.00 bbl
6/3 rpm 9 7 6 4 #N/A #N/A Mud Returned
API Filtrate, ml/30 min 5.2 5.3 #N/A @ MD Total Losses 29.00 bbl 940.0 bbl
HTHP ml/30 min @
#N/A °F #N/A MUD TREATMENTS
Cake API/HTHP, 32nd in 1 1 #N/A #N/A Build 100 bbl KCl Polymer, dump & dilute for reduce solid & maintain MW. Control fluid loss by Hydro Pac L, maintain vis by
Solids, % by vol 4 5 #N/A Hydro Pac R, made hivis by Hydro Zan. Add KCl for reactive clay.
Oil / Water, % by vol 96 95 #N/A #N/A
Sand, % by vol 0.6 0.7 #N/A
MBT, ppb 10 7.5 #N/A DRILLING ACTIVITY
pH @ #N/A °F 9 9 #N/A Cont'd repaire mud pump, W/O mud pump engine spare part, repair engine mud pump #1. RIH 12-1/4" bit to 380 m.
Alkalinity Mud, (PM) #N/A circulation, drill formation to 447 M.
Alkalinity Filtrate, (Pf/Mf) #N/A #N/A
Chlorides, mg/l 40000 41000 #N/A
Total Hard. Calcium, mg/l 180 180 #N/A DAILY PRODUCT USAGE
LGS/HGS, % by vol 0.9 0.3 1.6 0.6 #N/A #N/A UNITS Starting RECEIVED USED
PRODUCT RETURN ON HAND COST
LGS/HGS, ppb 8.2 5.1 14.7 8.8 #N/A #N/A Prices #/Unit Inv DAILY CUM DAILY CUM
ASG 3.0 3.0 #N/A BENTONITE $ 14.04 100 LB 86 196 5 115 81 $ 70.20
K+, mg/l 29000 29000 #N/A DRILLING DETERGENT $ 192.72 55 GAL 5 7 1 3 4 $ 192.72
WBM Add 2 #N/A HYDRO-PAC LV $ 88.29 25 KG 32 152 13 133 19 $ 1,147.77
TIME OPERATION HYDRO-PAC R $ 96.53 25 KG 96 142 5 51 91 $ 482.65
DESCRIPTION DAILY TOTAL DESCRIPTION DAILY TOTAL HYDRO-STAR NF $ 29.86 25 KG 81 30 216 10 115 101 $ 298.60
Drilling 10 89 N/U BOPs 8 HYDRO-ZAN $ 134.49 25 KG 21 55 1 35 20 $ 134.49
RIH Bit 3 9 RIH Scraper 7" POTASSIUM CHLORIDES$ 65.00 50 KG 50 50 615 50 565 50 $ 3,250.00
POOH Bit 9 Reaming #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Circulating 1 9 Coring Job #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Logging Rig Service 10 13 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Casing 6 Short Trip #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Cementing 3.5 Other 81.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
WOCement 12 Total Hrs. 24 240 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
PIT VOLUME ANCILLARY CHARGES
FLUID TYPES PIT No. MW VOLUME Mud Engineer I $ 250.00
KCl Polymer Sand Trap 1.09 50 bbl Mud Boy $ 100.00
KCl Polymer Setling Tank 1.09 50 bbl COST SUMMARY
KCl Polymer Desander Tank 1.09 115 bbl Previous Product Cost : $ 59,822.46
KCl Polymer Desilter Tank 1.09 120 bbl Daily Product Cost : $ 5,576.43
KCl Polymer Active Tank 1.09 160 bbl Cum. Product Cost : $ 65,398.89
Hivis Slug 1.09 40 bbl Previous Engineer Charge : $ 3,150.00
KCl Polymer Reserve 1 1.09 80 bbl Daily Engineer Charge : $ 350.00
KCl Polymer Reserve 2 1.07 40 bbl Cum. Engineer Charge : $ 3,500.00
Scomi Total Cost : $ 68,898.89
YP, lb/100 ft2 29 36 #N/A Btm Up min/stk Solid Control 15.00 bbl 220.00 bbl
Gels 10 sec/10 min/30 min 6/8/0 8 / 11 / 0 #N/A Suc - Surf min/stk Dump 270.00 bbl
600/300 rpm 65 47 82 59 #N/A #N/A Total min/stk Behind Casing
200/100 rpm 39 28 49 35 #N/A #N/A Misc. Loss 12.00 bbl 444.00 bbl
6/3 rpm 8 6 10 7 #N/A #N/A Mud Returned
API Filtrate, ml/30 min 5.2 5 #N/A @ MD Total Losses 32.00 bbl 972.0 bbl
HTHP ml/30 min @
#N/A °F #N/A MUD TREATMENTS
Cake API/HTHP, 32nd in 1 1 #N/A #N/A Transfer from reserve to active for maintain mud vol system. Control fluid loss by Hydro Pac L, maintain vis by Hydro Pac R, add
Solids, % by vol 6 6 #N/A Hydro Zan for rheology & made hivis. Mix KCl for reactive clay.
Oil / Water, % by vol 94 94 #N/A #N/A
Sand, % by vol 0.7 0.8 #N/A
MBT, ppb 7.5 7.5 #N/A DRILLING ACTIVITY
pH @ #N/A °F 9 9 #N/A Cont'd drill formation to 545 M. Circulation with pump #3 while repair pump #1 & #2, POOH 12-1/4" to shoe while repair mud
Alkalinity Mud, (PM) #N/A pump #1 & #2.
Alkalinity Filtrate, (Pf/Mf) #N/A #N/A
Chlorides, mg/l 42000 46000 #N/A
Total Hard. Calcium, mg/l 180 180 #N/A DAILY PRODUCT USAGE
LGS/HGS, % by vol 2.3 0.8 2.1 0.8 #N/A #N/A UNITS Starting RECEIVED USED
PRODUCT RETURN ON HAND COST
LGS/HGS, ppb 21.2 12.5 18.8 12.5 #N/A #N/A Prices #/Unit Inv DAILY CUM DAILY CUM
ASG 3.0 3.1 #N/A HYDRO-PAC LV $ 88.29 25 KG 19 152 9 142 10 $ 794.61
K+, mg/l 29000 31000 #N/A HYDRO-PAC R $ 96.53 25 KG 91 142 4 55 87 $ 386.12
WBM Add 2 #N/A HYDRO-ZAN $ 134.49 25 KG 20 55 4 39 16 $ 537.96
TIME OPERATION POTASSIUM CHLORIDES$ 65.00 50 KG 50 615 25 590 25 $ 1,625.00
DESCRIPTION DAILY TOTAL DESCRIPTION DAILY TOTAL #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Drilling 19 108 N/U BOPs 8 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Bit 2 11 RIH Scraper 7" #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
POOH Bit 2 11 Reaming #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Circulating 1 10 Coring Job #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Logging Rig Service 13 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Casing 6 Short Trip #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Cementing 3.5 Other 81.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
WOCement 12 Total Hrs. 24 264 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
PIT VOLUME ANCILLARY CHARGES
FLUID TYPES PIT No. MW VOLUME Mud Engineer I $ 250.00
KCl Polymer Sand Trap 1.11 45 bbl Mud Boy $ 100.00
KCl Polymer Setling Tank 1.11 40 bbl COST SUMMARY
KCl Polymer Desander Tank 1.11 115 bbl Previous Product Cost : $ 65,398.89
KCl Polymer Desilter Tank 1.11 120 bbl Daily Product Cost : $ 3,343.69
KCl Polymer Active Tank 1.11 175 bbl Cum. Product Cost : $ 68,742.58
Hivis Slug 1.11 40 bbl Previous Engineer Charge : $ 3,500.00
KCl Polymer Reserve 1 1.1 40 bbl Daily Engineer Charge : $ 350.00
KCl Polymer Cum. Engineer Charge : $ 3,850.00
Scomi Total Cost : $ 72,592.58
YP, lb/100 ft2 33 31 #N/A Btm Up min/stk 17 4,138 Solid Control 20.00 bbl 240.00 bbl
Gels 10 sec/10 min/30 min 7 / 10 / 0 6 / 10 / 0 #N/A Suc - Surf min/stk 18 4,624 Dump 270.00 bbl
600/300 rpm 77 55 69 50 #N/A #N/A Total min/stk 54 13,615 Behind Casing
200/100 rpm 45 32 40 30 #N/A #N/A Misc. Loss 95.00 bbl 539.00 bbl
6/3 rpm 9 5 8 6 #N/A #N/A Mud Returned
API Filtrate, ml/30 min 5 5 #N/A @ MD Total Losses 125.00 bbl 1,097.0 bbl
HTHP ml/30 min @
#N/A °F #N/A MUD TREATMENTS
Cake API/HTHP, 32nd in 1 1 #N/A #N/A Control pH by KOH. Made 150 bbls KCl Polymer, transfer to active tank to maintain mud system volume. Made Hi-vis by Hydro
Solids, % by vol 6 6 #N/A Pac-R. Material received : TLDF 0912 282. Run centrifuge for reduce solid. Changed damage shale shaker screen.
Oil / Water, % by vol 94 94 #N/A #N/A
Sand, % by vol 0.8 0.8 #N/A
MBT, ppb 7.5 7.5 #N/A DRILLING ACTIVITY
pH @ #N/A °F 9 9 #N/A Cont'd repaire mud pump #1 & #2. RIH 12-1/4" bit, sit at 409 M. Circulation, reaming to 545 M. Drilled formation to 622 M.
Alkalinity Mud, (PM) #N/A
Alkalinity Filtrate, (Pf/Mf) #N/A #N/A
Chlorides, mg/l 44000 41000 #N/A
Total Hard. Calcium, mg/l 180 180 #N/A DAILY PRODUCT USAGE
LGS/HGS, % by vol 2.2 0.8 2.4 0.8 #N/A #N/A UNITS Starting RECEIVED USED
PRODUCT RETURN ON HAND COST
LGS/HGS, ppb 20.0 12.5 21.8 12.5 #N/A #N/A Prices #/Unit Inv DAILY CUM DAILY CUM
ASG 3.0 3.0 #N/A BENTONITE $ 14.04 100 LB 81 196 21 136 60 $ 294.84
K+, mg/l 30000 29000 #N/A HYDRO-PAC LV $ 88.29 25 KG 10 152 10 152 $ 882.90
WBM Add 2 #N/A HYDRO-PAC R $ 96.53 25 KG 87 142 7 62 80 $ 675.71
TIME OPERATION HYDRO-STAR NF $ 29.86 25 KG 101 216 20 135 81 $ 597.20
DESCRIPTION DAILY TOTAL DESCRIPTION DAILY TOTAL HYDRO-ZAN $ 134.49 25 KG 16 55 2 41 14 $ 268.98
Drilling 13 121 N/U BOPs 8 POTASSIUM CHLORIDES$ 65.00 50 KG 25 75 690 50 640 50 $ 3,250.00
RIH Bit 1 12 RIH Scraper 7" POTASSIUM HYDROXIDE$ 53.74 25 KG 44 47 3 6 41 $ 161.22
POOH Bit 11 Reaming 3.5 3.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Circulating 1 11 Coring Job #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Logging Rig Service 4.5 17.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Casing 6 Short Trip #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Cementing 3.5 Other 1 82.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
WOCement 12 Total Hrs. 24 288 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
PIT VOLUME ANCILLARY CHARGES
FLUID TYPES PIT No. MW VOLUME Mud Engineer I $ 250.00
KCl Polymer Sand Trap 1.11 50 bbl Mud Boy $ 100.00
KCl Polymer Setling Tank 1.11 50 bbl COST SUMMARY
KCl Polymer Desander Tank 1.11 120 bbl Previous Product Cost : $ 68,742.58
KCl Polymer Desilter Tank 1.11 125 bbl Daily Product Cost : $ 6,130.85
KCl Polymer Active Tank 1.11 190 bbl Cum. Product Cost : $ 74,873.43
Hivis Slug 1.11 40 bbl Previous Engineer Charge : $ 3,850.00
KCl Polymer Daily Engineer Charge : $ 350.00
KCl Polymer Cum. Engineer Charge : $ 4,200.00
KCl Polymer Scomi Total Cost : $ 79,073.43
YP, lb/100 ft2 32 28 #N/A Btm Up min/stk 19 4,910 Solid Control 30.00 bbl 270.00 bbl
Gels 10 sec/10 min/30 min 7 / 11 / 0 6/9/0 #N/A Suc - Surf min/stk 22 5,509 Dump 270.00 bbl
600/300 rpm 70 51 66 47 #N/A #N/A Total min/stk 57 14,500 Behind Casing
200/100 rpm 40 30 39 29 #N/A #N/A Misc. Loss 48.00 bbl 587.00 bbl
6/3 rpm 8 6 6 9 #N/A #N/A Mud Returned
API Filtrate, ml/30 min 5 5 #N/A @ MD Total Losses 88.00 bbl 1,185.0 bbl
HTHP ml/30 min @ °F #N/A MUD TREATMENTS
Cake API/HTHP, 32nd in 1 1 #N/A #N/A Build up 200 bbl KCl Polymer to keep vol. Made hivis by Hydro Pac R. Material Received TDLF 0912-283
Solids, % by vol 5 6 #N/A
Oil / Water, % by vol 95 94 #N/A #N/A
Sand, % by vol 0.8 0.8 #N/A
MBT, ppb 7.5 7.5 #N/A DRILLING ACTIVITY
pH @ °F 9 9 #N/A Cont'd drill formation to 737 M.
Alkalinity Mud, (PM) #N/A
Alkalinity Filtrate, (Pf/Mf) #N/A #N/A
Chlorides, mg/l 44000 42000 #N/A
Total Hard. Calcium, mg/l 180 180 #N/A DAILY PRODUCT USAGE
LGS/HGS, % by vol 0.2 1.8 2.3 0.8 #N/A #N/A UNITS Starting RECEIVED USED
PRODUCT RETURN ON HAND COST
LGS/HGS, ppb 1.5 27.2 21.2 12.5 #N/A #N/A Prices #/Unit Inv DAILY CUM DAILY CUM
ASG 4.1 3.0 #N/A BARITE $ 10.99 100 LB 120 280 40 120 80 $ 439.60
K+, mg/l 30000 31000 #N/A BENTONITE $ 14.04 100 LB 60 196 15 151 45 $ 210.60
WBM Add 2 #N/A HYDRO-PAC R $ 96.53 25 KG 80 142 8 70 72 $ 772.24
TIME OPERATION HYDRO-STAR NF $ 29.86 25 KG 81 216 15 150 66 $ 447.90
DESCRIPTION DAILY TOTAL DESCRIPTION DAILY TOTAL HYDRO-ZAN $ 134.49 25 KG 14 55 2 43 12 $ 268.98
Drilling 24 145 N/U BOPs 8 POTASSIUM CHLORIDES$ 65.00 50 KG 50 75 765 50 690 75 $ 3,250.00
RIH Bit 12 RIH Scraper 7" POTASSIUM HYDROXIDE$ 53.74 25 KG 41 47 1 7 40 $ 53.74
POOH Bit 11 Reaming 3.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Circulating 11 Coring Job #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Logging Rig Service 17.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Casing 6 Short Trip #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Cementing 3.5 Other 82.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
WOCement 12 Total Hrs. 24 312 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
PIT VOLUME ANCILLARY CHARGES
FLUID TYPES PIT No. MW VOLUME Mud Engineer I $ 250.00
KCl Polymer Sand Trap 1.11 50 bbl Mud Boy $ 100.00
KCl Polymer Setling Tank 1.11 50 bbl COST SUMMARY
KCl Polymer Desander Tank 1.11 120 bbl Previous Product Cost : $ 74,873.43
KCl Polymer Desilter Tank 1.11 125 bbl Daily Product Cost : $ 5,443.06
KCl Polymer Active Tank 1.11 190 bbl Cum. Product Cost : $ 80,316.49
Hivis Slug 1.11 40 bbl Previous Engineer Charge : $ 4,200.00
KCl Polymer Daily Engineer Charge : $ 350.00
KCl Polymer Reserve 2 1.1 60 bbl Cum. Engineer Charge : $ 4,550.00
Scomi Total Cost : $ 84,866.49
YP, lb/100 ft2 31 29 #N/A Btm Up min/stk Solid Control 50.00 bbl 320.00 bbl
Gels 10 sec/10 min/30 min 6/9/0 7/9/0 #N/A Suc - Surf min/stk Dump 270.00 bbl
600/300 rpm 65 48 65 47 #N/A #N/A Total min/stk Behind Casing
200/100 rpm 39 28 39 28 #N/A #N/A Misc. Loss 158.00 bbl 745.00 bbl
6/3 rpm 8 6 9 6 #N/A #N/A Mud Returned
API Filtrate, ml/30 min 5 5 #N/A @ MD Total Losses 213.00 bbl 1,398.0 bbl
HTHP ml/30 min @ °F #N/A MUD TREATMENTS
Cake API/HTHP, 32nd in 1 1 #N/A #N/A Build up 300 bbl KCl Polymer in reserve, transfer to active for maintain mud system volume while maintain MW. Control fluid
Solids, % by vol 5 5 #N/A loss by Hydra Star. Control alkalinity by KOH. Change shale shaker screen.
Oil / Water, % by vol 95 95 #N/A #N/A
Sand, % by vol 0.7 0.7 #N/A
MBT, ppb 7.5 7.5 #N/A DRILLING ACTIVITY
pH @ °F 9 9 #N/A Cont'd drill formation to 796 M. Crculation, swept out hivis, CHC. POOH while pump out 12-1/4" bit.
Alkalinity Mud, (PM) #N/A
Alkalinity Filtrate, (Pf/Mf) #N/A #N/A
Chlorides, mg/l 41000 41000 #N/A
Total Hard. Calcium, mg/l 180 180 #N/A DAILY PRODUCT USAGE
LGS/HGS, % by vol 0.4 1.8 0.4 1.8 #N/A #N/A UNITS Starting RECEIVED USED
PRODUCT RETURN ON HAND COST
LGS/HGS, ppb 3.3 27.2 3.3 27.2 #N/A #N/A Prices #/Unit Inv DAILY CUM DAILY CUM
ASG 3.9 3.9 #N/A BARITE $ 10.99 100 LB 80 280 40 160 40 $ 439.60
K+, mg/l 31000 31000 #N/A BENTONITE $ 14.04 100 LB 45 196 10 161 35 $ 140.40
WBM Add 2 #N/A DRILLING DETERGENT $ 192.72 55 GAL 4 7 1 4 3 $ 192.72
TIME OPERATION HYDRO-LUBE $ 424.14 55 GAL 7 8 1 2 6 $ 424.14
DESCRIPTION DAILY TOTAL DESCRIPTION DAILY TOTAL HYDRO-PAC R $ 96.53 25 KG 72 142 8 78 64 $ 772.24
Drilling 16 161 N/U BOPs 8 HYDRO-STAR NF $ 29.86 25 KG 66 216 24 174 42 $ 716.64
RIH Bit 12 RIH Scraper 7" HYDRO-ZAN $ 134.49 25 KG 12 55 2 45 10 $ 268.98
POOH Bit 6 17 Reaming 3.5 POTASSIUM CHLORIDES$ 65.00 50 KG 75 765 50 740 25 $ 3,250.00
Circulating 1 12 Coring Job POTASSIUM HYDROXIDE$ 53.74 25 KG 40 47 3 10 37 $ 161.22
Logging Rig Service 17.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Casing 6 Short Trip #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Cementing 3.5 Other 1 83.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
WOCement 12 Total Hrs. 24 336 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
PIT VOLUME ANCILLARY CHARGES
FLUID TYPES PIT No. MW VOLUME Mud Engineer I $ 250.00
KCl Polymer Sand Trap 1.11 50 bbl Mud Boy $ 100.00
KCl Polymer Setling Tank 1.11 50 bbl COST SUMMARY
KCl Polymer Desander Tank 1.11 130 bbl Previous Product Cost : $ 80,316.49
KCl Polymer Desilter Tank 1.11 135 bbl Daily Product Cost : $ 6,365.94
KCl Polymer Active Tank 1.11 220 bbl Cum. Product Cost : $ 86,682.43
Hivis Slug 1.11 Previous Engineer Charge : $ 4,550.00
KCl Polymer Daily Engineer Charge : $ 350.00
KCl Polymer Reserve 2 1.1 Cum. Engineer Charge : $ 4,900.00
Scomi Total Cost : $ 91,582.43
YP, lb/100 ft2 30 #N/A #N/A Btm Up min/stk Solid Control 5.00 bbl 325.00 bbl
Gels 10 sec/10 min/30 min 7/9/0 #N/A #N/A Suc - Surf min/stk Dump 270.00 bbl
600/300 rpm 64 47 #N/A #N/A #N/A #N/A Total min/stk Behind Casing
200/100 rpm 39 28 #N/A #N/A #N/A #N/A Misc. Loss 10.00 bbl 755.00 bbl
6/3 rpm 9 6 #N/A #N/A #N/A #N/A Mud Returned
API Filtrate, ml/30 min 5 #N/A #N/A @ MD Total Losses 15.00 bbl 1,413.0 bbl
HTHP ml/30 min @ °F #N/A #N/A MUD TREATMENTS
Cake API/HTHP, 32nd in 1 #N/A #N/A #N/A #N/A Control pH by KOH. Material Received, DN: TLDF-0912-287.
Solids, % by vol 5 #N/A #N/A
Oil / Water, % by vol 95 #N/A #N/A #N/A #N/A
Sand, % by vol 0.6 #N/A #N/A
MBT, ppb 7.5 #N/A #N/A DRILLING ACTIVITY
pH @ °F 9 #N/A #N/A Cont'd POOH 12-/14" bit to shoe. Change liner mud pump #1, #2 & #3. Repair mud pump.
Alkalinity Mud, (PM) #N/A #N/A
Alkalinity Filtrate, (Pf/Mf) #N/A #N/A #N/A #N/A
Chlorides, mg/l 41000 #N/A #N/A
Total Hard. Calcium, mg/l 180 #N/A #N/A DAILY PRODUCT USAGE
LGS/HGS, % by vol 0.4 1.8 #N/A #N/A #N/A #N/A UNITS Starting RECEIVED USED
PRODUCT RETURN ON HAND COST
LGS/HGS, ppb 3.3 27.2 #N/A #N/A #N/A #N/A Prices #/Unit Inv DAILY CUM DAILY CUM
ASG 3.9 #N/A #N/A HYDRO-STAR NF $ 29.86 25 KG 42 30 246 174 72 $ -
K+, mg/l 31000 #N/A #N/A POTASSIUM CHLORIDES$ 65.00 50 KG 25 50 815 740 75 $ -
WBM Add 2 #N/A #N/A POTASSIUM HYDROXIDE$ 53.74 25 KG 37 47 3 13 34 $ 161.22
TIME OPERATION #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
DESCRIPTION DAILY TOTAL DESCRIPTION DAILY TOTAL #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Drilling 161 N/U BOPs 8 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Bit 12 RIH Scraper 7" #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
POOH Bit 1 18 Reaming 3.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Circulating 1 13 Coring Job #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Logging Rig Service 22 39.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Casing 6 Short Trip #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Cementing 3.5 Other 83.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
WOCement 12 Total Hrs. 24 360 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
PIT VOLUME ANCILLARY CHARGES
FLUID TYPES PIT No. MW VOLUME Mud Engineer I $ 250.00
KCl Polymer Sand Trap 1.11 50 bbl Mud Boy $ 100.00
KCl Polymer Setling Tank 1.11 50 bbl COST SUMMARY
KCl Polymer Desander Tank 1.11 125 bbl Previous Product Cost : $ 86,682.43
KCl Polymer Desilter Tank 1.11 130 bbl Daily Product Cost : $ 161.22
KCl Polymer Active Tank 1.11 215 bbl Cum. Product Cost : $ 86,843.65
Hivis Slug 1.11 Previous Engineer Charge : $ 4,900.00
KCl Polymer Daily Engineer Charge : $ 350.00
KCl Polymer Reserve 2 1.1 Cum. Engineer Charge : $ 5,250.00
Scomi Total Cost : $ 92,093.65
YP, lb/100 ft2 30 32 #N/A Btm Up min/stk 18 4,458 Solid Control 15.00 bbl 340.00 bbl
Gels 10 sec/10 min/30 min 7/9/0 7 / 10 / 0 #N/A Suc - Surf min/stk 20 5,010 Dump 270.00 bbl
600/300 rpm 64 47 64 48 #N/A #N/A Total min/stk 53 13,059 Behind Casing
200/100 rpm 39 28 40 30 #N/A #N/A Misc. Loss 13.00 bbl 768.00 bbl
6/3 rpm 9 6 9 7 #N/A #N/A Mud Returned
API Filtrate, ml/30 min 5 4.8 #N/A @ MD Total Losses 28.00 bbl 1,441.0 bbl
HTHP ml/30 min @ °F #N/A MUD TREATMENTS
Cake API/HTHP, 32nd in 1 1 #N/A #N/A Control fluid loss by Hydro Star and maintain viscosity by Hydro Pac-R. Add Hydrozan for rheology. Made hivis by Hydro Pac-R.
Solids, % by vol 5 6 #N/A Add barite as weightening agent. Material received : TDLF 0912-290. Switch off centrifuge while increase MW to 1.14 SG
Oil / Water, % by vol 95 94 #N/A #N/A
Sand, % by vol 0.6 0.4 #N/A
MBT, ppb 7.5 7.5 #N/A DRILLING ACTIVITY
pH @ °F 9 9 #N/A Cont'd repair mud pump. RIH 12-1/4", sit at 408 M, circulation, reaming down to 409 M, raise up to 390 M, repair hose MP #3,
Alkalinity Mud, (PM) #N/A back RIH to 409 M, reaming down to 733 M
Alkalinity Filtrate, (Pf/Mf) #N/A #N/A
Chlorides, mg/l 41000 40000 #N/A
Total Hard. Calcium, mg/l 180 180 #N/A DAILY PRODUCT USAGE
LGS/HGS, % by vol 0.4 1.8 0.6 2.7 #N/A #N/A UNITS Starting RECEIVED USED
PRODUCT RETURN ON HAND COST
LGS/HGS, ppb 3.3 27.2 5.4 40.0 #N/A #N/A Prices #/Unit Inv DAILY CUM DAILY CUM
ASG 3.9 3.9 #N/A BARITE $ 10.99 100 LB 40 120 400 120 280 40 $ 1,318.80
K+, mg/l 31000 30000 #N/A HYDRO-PAC R $ 96.53 25 KG 64 142 3 81 61 $ 289.59
WBM Add 2 #N/A HYDRO-STAR NF $ 29.86 25 KG 72 246 20 194 52 $ 597.20
TIME OPERATION HYDRO-ZAN $ 134.49 25 KG 10 55 7 52 3 $ 941.43
DESCRIPTION DAILY TOTAL DESCRIPTION DAILY TOTAL POTASSIUM HYDROXIDE$ 53.74 25 KG 34 47 1 14 33 $ 53.74
Drilling 161 N/U BOPs 8 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Bit 12 RIH Scraper 7" #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
POOH Bit 18 Reaming 16 19.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Circulating 13 Coring Job #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Logging Rig Service 7 46.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Casing 6 Short Trip #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Cementing 3.5 Other 1 84.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
WOCement 12 Total Hrs. 24 384 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
PIT VOLUME ANCILLARY CHARGES
FLUID TYPES PIT No. MW VOLUME Mud Engineer I $ 250.00
KCl Polymer Sand Trap 1.14 50 bbl Mud Boy $ 100.00
KCl Polymer Setling Tank 1.14 50 bbl COST SUMMARY
KCl Polymer Desander Tank 1.14 125 bbl Previous Product Cost : $ 86,843.65
KCl Polymer Desilter Tank 1.14 130 bbl Daily Product Cost : $ 3,200.76
KCl Polymer Active Tank 1.14 215 bbl Cum. Product Cost : $ 90,044.41
Previous Engineer Charge : $ 5,250.00
Daily Engineer Charge : $ 350.00
Cum. Engineer Charge : $ 5,600.00
Scomi Total Cost : $ 95,644.41
YP, lb/100 ft2 31 36 #N/A Btm Up min/stk 19 4,840 Solid Control 5.00 bbl 345.00 bbl
Gels 10 sec/10 min/30 min 7 / 10 / 0 10 / 13 / 0 #N/A Suc - Surf min/stk 22 5,448 Dump 270.00 bbl
600/300 rpm 65 48 70 53 #N/A #N/A Total min/stk 49 12,156 Behind Casing
200/100 rpm 41 32 44 34 #N/A #N/A Misc. Loss 28.00 bbl 796.00 bbl
6/3 rpm 9 7 11 8 #N/A #N/A Mud Returned
API Filtrate, ml/30 min 5 5 #N/A @ MD Total Losses 33.00 bbl 1,474.0 bbl
HTHP ml/30 min @ °F #N/A MUD TREATMENTS
Cake API/HTHP, 32nd in 1 1 #N/A #N/A Control pH by KOH, control fluid loss by Hydrostar, maintain viscosity byHydro Pac-R, add Hydrozan for rheology. Made hivis by
Solids, % by vol 6 6 #N/A Hydrozan. Change broken shale shaker screen. Run centriuge for reduce solid. Add drilling detergent for clean the bit, add
Oil / Water, % by vol 94 94 #N/A #N/A Hydro Lube as lubricity. Material Received : TLDF 0912-094
Sand, % by vol 0.5 0.2 #N/A
MBT, ppb 7.5 7.5 #N/A DRILLING ACTIVITY
pH @ °F 9 9 #N/A Cont'd reaming down to 796 m, circulation, swept out 30 bbl hivis. Drill formation to 864 M.
Alkalinity Mud, (PM) #N/A
Alkalinity Filtrate, (Pf/Mf) #N/A #N/A
Chlorides, mg/l 40000 38000 #N/A
Total Hard. Calcium, mg/l 180 180 #N/A DAILY PRODUCT USAGE
LGS/HGS, % by vol 0.6 2.7 0.7 2.7 #N/A #N/A UNITS Starting RECEIVED USED
PRODUCT RETURN ON HAND COST
LGS/HGS, ppb 5.4 40.0 6.6 40.0 #N/A #N/A Prices #/Unit Inv DAILY CUM DAILY CUM
ASG 3.9 3.9 #N/A BARITE $ 10.99 100 LB 40 80 480 280 120 $ -
K+, mg/l 31000 31000 #N/A DRILLING DETERGENT $ 192.72 55 GAL 3 7 1 5 2 $ 192.72
WBM Add 2 #N/A HYDRO-LUBE $ 424.14 55 GAL 6 8 1 3 5 $ 424.14
TIME OPERATION HYDRO-PAC R $ 96.53 25 KG 61 142 4 85 57 $ 386.12
DESCRIPTION DAILY TOTAL DESCRIPTION DAILY TOTAL HYDRO-STAR NF $ 29.86 25 KG 52 246 15 209 37 $ 447.90
Drilling 21 182 N/U BOPs 8 HYDRO-ZAN $ 134.49 25 KG 3 30 85 4 56 29 $ 537.96
RIH Bit 12 RIH Scraper 7" POTASSIUM CHLORIDES$ 65.00 50 KG 75 815 25 765 50 $ 1,625.00
POOH Bit 18 Reaming 3 22.5 POTASSIUM HYDROXIDE$ 53.74 25 KG 33 47 4 18 29 $ 214.96
Circulating 13 Coring Job #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Logging Rig Service 46.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Casing 6 Short Trip #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Cementing 3.5 Other 84.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
WOCement 12 Total Hrs. 24 408 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
PIT VOLUME ANCILLARY CHARGES
FLUID TYPES PIT No. MW VOLUME Mud Engineer I $ 250.00
KCl Polymer Sand Trap 1.14 50 bbl Mud Boy $ 100.00
KCl Polymer Setling Tank 1.14 50 bbl COST SUMMARY
KCl Polymer Desander Tank 1.14 95 bbl Previous Product Cost : $ 90,044.41
KCl Polymer Desilter Tank 1.14 100 bbl Daily Product Cost : $ 3,828.80
KCl Polymer Active Tank 1.14 180 bbl Cum. Product Cost : $ 93,873.21
Hivis Slug 1.14 40 bbl Previous Engineer Charge : $ 5,600.00
Daily Engineer Charge : $ 350.00
Cum. Engineer Charge : $ 5,950.00
Scomi Total Cost : $ 99,823.21
YP, lb/100 ft2 31 34 #N/A Btm Up min/stk 22 5,651 Solid Control 10.00 bbl 355.00 bbl
Gels 10 sec/10 min/30 min 8 / 12 / 0 9 / 12 / 0 #N/A Suc - Surf min/stk 25 6,377 Dump 270.00 bbl
600/300 rpm 67 49 70 52 #N/A #N/A Total min/stk 52 13,579 Behind Casing
200/100 rpm 41 32 45 34 #N/A #N/A Misc. Loss 4.00 bbl 800.00 bbl
6/3 rpm 9 7 11 9 #N/A #N/A Mud Returned
API Filtrate, ml/30 min 5.2 5 #N/A @ MD Total Losses 19.00 bbl 1,493.0 bbl
HTHP ml/30 min @ °F #N/A MUD TREATMENTS
Cake API/HTHP, 32nd in 1 1 #N/A #N/A Control pH by KOH. Maintain viscosity by Hydro Pac R, control fluid loss by Hydro Star NF and Hydro Plast for shale stability.
Solids, % by vol 6 6 #N/A Build 100 bbls KCL Polymer in reserve, transfer to active for maintain mud system volume. Made Hivis by Hydrozan.
Oil / Water, % by vol 94 94 #N/A #N/A
Sand, % by vol 0.3 0.3 #N/A
MBT, ppb 7.5 7.5 #N/A DRILLING ACTIVITY
pH @ °F 9 9 #N/A Cont'd drill formation to 1008 M.
Alkalinity Mud, (PM) #N/A
Alkalinity Filtrate, (Pf/Mf) #N/A #N/A
Chlorides, mg/l 38000 39000 #N/A
Total Hard. Calcium, mg/l 140 140 #N/A DAILY PRODUCT USAGE
LGS/HGS, % by vol 0.7 2.7 0.7 2.7 #N/A #N/A UNITS Starting RECEIVED USED
PRODUCT RETURN ON HAND COST
LGS/HGS, ppb 6.6 40.0 6.0 40.0 #N/A #N/A Prices #/Unit Inv DAILY CUM DAILY CUM
ASG 3.9 3.9 #N/A BARITE $ 10.99 100 LB 120 480 80 360 40 $ 879.20
K+, mg/l 30000 30000 #N/A BENTONITE $ 14.04 100 LB 35 196 10 171 25 $ 140.40
WBM Add 2 #N/A HYDRO-PAC R $ 96.53 25 KG 57 142 5 90 52 $ 482.65
TIME OPERATION HYDRO-STAR NF $ 29.86 25 KG 37 246 20 229 17 $ 597.20
DESCRIPTION DAILY TOTAL DESCRIPTION DAILY TOTAL HYDRO-ZAN $ 134.49 25 KG 29 85 8 64 21 $ 1,075.92
Drilling 24 206 N/U BOPs 8 POTASSIUM CHLORIDES$ 65.00 50 KG 50 815 25 790 25 $ 1,625.00
RIH Bit 12 RIH Scraper 7" POTASSIUM HYDROXIDE$ 53.74 25 KG 29 47 1 19 28 $ 53.74
POOH Bit 18 Reaming 22.5 SHALE-STAB $ 36.08 50 LB 120 120 20 20 100 $ 721.60
Circulating 13 Coring Job #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Logging Rig Service 46.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Casing 6 Short Trip #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Cementing 3.5 Other 84.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
WOCement 12 Total Hrs. 24 432 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
PIT VOLUME ANCILLARY CHARGES
FLUID TYPES PIT No. MW VOLUME Mud Engineer I $ 250.00
KCl Polymer Sand Trap 1.14 50 bbl Mud Boy $ 100.00
KCl Polymer Setling Tank 1.14 50 bbl COST SUMMARY
KCl Polymer Desander Tank 1.14 115 bbl Previous Product Cost : $ 93,873.21
KCl Polymer Desilter Tank 1.14 115 bbl Daily Product Cost : $ 5,575.71
KCl Polymer Active Tank 1.14 180 bbl Cum. Product Cost : $ 99,448.92
Hivis Slug 1.14 40 bbl Previous Engineer Charge : $ 5,950.00
Daily Engineer Charge : $ 350.00
Cum. Engineer Charge : $ 6,300.00
Scomi Total Cost : $ 105,748.92
YP, lb/100 ft2 34 34 #N/A Btm Up min/stk 25 6,399 Solid Control 15.00 bbl 370.00 bbl
Gels 10 sec/10 min/30 min 10 / 13 / 0 11 / 15 / 0 #N/A Suc - Surf min/stk 28 7,236 Dump 270.00 bbl
600/300 rpm 66 50 68 51 #N/A #N/A Total min/stk 56 14,649 Behind Casing
200/100 rpm 43 33 44 34 #N/A #N/A Misc. Loss 11.00 bbl 811.00 bbl
6/3 rpm 11 9 13 10 #N/A #N/A Mud Returned
API Filtrate, ml/30 min 5.2 5 #N/A @ MD Total Losses 31.00 bbl 1,524.0 bbl
HTHP ml/30 min @ °F #N/A MUD TREATMENTS
Cake API/HTHP, 32nd in 1 1 #N/A #N/A Build up 100 bbl KCl Polymer 1.14 SG to keep vol. Control fluid loss by Hydro Plast/shale stab. Add Hydrozan for rheology.
Solids, % by vol 6 6 #N/A Add drilling detergent for clean the bit. Change shale shaker screen. Materal received : TLDF 0912-298, TLDF 0912-299.
Oil / Water, % by vol 94 94 #N/A #N/A
Sand, % by vol 0.3 0.3 #N/A
MBT, ppb 7.5 7.5 #N/A DRILLING ACTIVITY
pH @ °F 9 9 #N/A Cont'd drill formation to 1068 M. Raise up 2 stand to 1046 M, Repair Top Drive while Circulation. Wash down to 1068 M. Cont'd
Alkalinity Mud, (PM) #N/A drill formation to 1141 M.
Alkalinity Filtrate, (Pf/Mf) #N/A #N/A
Chlorides, mg/l 38000 41000 #N/A
Total Hard. Calcium, mg/l 140 140 #N/A DAILY PRODUCT USAGE
LGS/HGS, % by vol 0.7 2.7 0.5 2.7 #N/A #N/A UNITS Starting RECEIVED USED
PRODUCT RETURN ON HAND COST
LGS/HGS, ppb 6.6 40.0 4.8 40.0 #N/A #N/A Prices #/Unit Inv DAILY CUM DAILY CUM
ASG 3.9 3.9 #N/A BARITE $ 10.99 100 LB 40 200 680 40 400 200 $ 439.60
K+, mg/l 29000 31000 #N/A BENTONITE $ 14.04 100 LB 25 196 10 181 15 $ 140.40
WBM Add 2 #N/A DRILLING DETERGENT $ 192.72 55 GAL 2 7 1 6 1 $ 192.72
TIME OPERATION HYDRO-PAC R $ 96.53 25 KG 52 142 4 94 48 $ 386.12
DESCRIPTION DAILY TOTAL DESCRIPTION DAILY TOTAL HYDRO-STAR NF $ 29.86 25 KG 17 246 5 234 12 $ 149.30
Drilling 19 225 N/U BOPs 8 HYDRO-ZAN $ 134.49 25 KG 21 85 6 70 15 $ 806.94
RIH Bit 12 RIH Scraper 7" POTASSIUM CHLORIDES$ 65.00 50 KG 25 25840 25 815 25 $ 1,625.00
POOH Bit 18 Reaming 22.5 POTASSIUM HYDROXIDE$ 53.74 25 KG 28 47 1 20 27 $ 53.74
Circulating 2 15 Coring Job SHALE-STAB $ 36.08 50 LB 100 120 20 40 80 $ 721.60
Logging Rig Service 46.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Casing 6 Short Trip #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Cementing 3.5 Other 3 87.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
WOCement 12 Total Hrs. 24 456 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
PIT VOLUME ANCILLARY CHARGES
FLUID TYPES PIT No. MW VOLUME Mud Engineer I $ 250.00
KCl Polymer Sand Trap 1.14 50 bbl Mud Boy $ 100.00
KCl Polymer Setling Tank 1.14 50 bbl COST SUMMARY
KCl Polymer Desander Tank 1.14 125 bbl Previous Product Cost : $ 99,448.92
KCl Polymer Desilter Tank 1.14 125 bbl Daily Product Cost : $ 4,515.42
KCl Polymer Active Tank 1.14 175 bbl Cum. Product Cost : $ 103,964.34
Hivis Slug 1.14 40 bbl Previous Engineer Charge : $ 6,300.00
KCl Polymer Reserve 1 1.14 Daily Engineer Charge : $ 350.00
Cum. Engineer Charge : $ 6,650.00
Scomi Total Cost : $ 110,614.34
YP, lb/100 ft2 33 33 #N/A Btm Up min/stk 25 6,518 Solid Control 15.00 bbl 385.00 bbl
Gels 10 sec/10 min/30 min 11 / 16 / 0 11 / 16 / 0 #N/A Suc - Surf min/stk 28 7,371 Dump 270.00 bbl
600/300 rpm 69 51 65 49 #N/A #N/A Total min/stk 58 14,996 Behind Casing
200/100 rpm 44 34 43 33 #N/A #N/A Misc. Loss 57.00 bbl 868.00 bbl
6/3 rpm 13 10 13 10 #N/A #N/A Mud Returned
API Filtrate, ml/30 min 5 5 #N/A @ MD Total Losses 75.00 bbl 1,599.0 bbl
HTHP ml/30 min @ °F #N/A MUD TREATMENTS
Cake API/HTHP, 32nd in 1 1 #N/A #N/A Build up 100 bbl KCl Polymer 1.14 SG to keep volume. Control fluid loss by Hydro Plast. Made hivis by Hydrozan. Switch on
Solids, % by vol 6 6 #N/A centrifuge to keep MW in 1.14 SG. Desander cone was broken.
Oil / Water, % by vol 94 94 #N/A #N/A
Sand, % by vol 0.3 0.2 #N/A
MBT, ppb 7.5 7.5 #N/A DRILLING ACTIVITY
pH @ °F 9 9 #N/A Cont'd drill formation to 1162 M, circulation. POOH 12-1/4 bit to 133 M, repair rig engine. Cont'd POOH 12-1/4" bit to surface,
Alkalinity Mud, (PM) #N/A (overpull @ 1116 M, 989 M, 960 M, 941 M, and 738 M). RIH back 12-1/4" bit to 196 M, break circulation. Cont'd RH12-1/4"bit,
Alkalinity Filtrate, (Pf/Mf) #N/A #N/A sit at 432 M, wash down at 432- 1162 M.
Chlorides, mg/l 41000 38000 #N/A
Total Hard. Calcium, mg/l 140 140 #N/A DAILY PRODUCT USAGE
LGS/HGS, % by vol 0.5 2.7 0.7 2.7 #N/A #N/A UNITS Starting RECEIVED USED
PRODUCT RETURN ON HAND COST
LGS/HGS, ppb 4.8 40.0 6.6 40.0 #N/A #N/A Prices #/Unit Inv DAILY CUM DAILY CUM
ASG 3.9 3.9 #N/A BENTONITE $ 14.04 100 LB 15 196 10 191 5 $ 140.40
K+, mg/l 30000 30000 #N/A HYDRO-STAR NF $ 29.86 25 KG 12 246 10 244 2 $ 298.60
WBM Add 2 #N/A HYDRO-ZAN $ 134.49 25 KG 15 85 3 73 12 $ 403.47
TIME OPERATION POTASSIUM HYDROXIDE$ 53.74 25 KG 27 47 1 21 26 $ 53.74
DESCRIPTION DAILY TOTAL DESCRIPTION DAILY TOTAL SHALE-STAB $ 36.08 50 LB 80 120 5 45 75 $ 180.40
Drilling 3 228 N/U BOPs 8 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Bit 6 18 RIH Scraper 7" #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
POOH Bit 6 24 Reaming 5 27.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Circulating 1 16 Coring Job #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Logging Rig Service 2 48.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
RIH Casing 6 Short Trip #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
Cementing 3.5 Other 1 88.5 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
WOCement 12 Total Hrs. 24 480 #N/A #N/A ### #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
PIT VOLUME ANCILLARY CHARGES
FLUID TYPES PIT No. MW VOLUME Mud Engineer I $ 250.00
KCl Polymer Sand Trap 1.14 50 bbl Mud Boy $ 100.00
KCl Polymer Setling Tank 1.14 50 bbl COST SUMMARY
KCl Polymer Desander Tank 1.14 130 bbl Previous Product Cost : $ 103,964.34
KCl Polymer Desilter Tank 1.14 130 bbl Daily Product Cost : $ 1,076.61
KCl Polymer Active Tank 1.14 180 bbl Cum. Product Cost : $ 105,040.95
Hivis Slug 1.14 40 bbl Previous Engineer Charge : $ 6,650.00
Daily Engineer Charge : $ 350.00
Cum. Engineer Charge : $ 7,000.00
Scomi Total Cost : $ 112,040.95
WELL : TT-28
LOCATION : TTM-SA1
DRILLING - 2009
FORMATION LOGGING REPORT NO : 1
MORNING REPORT
BACKGROUND
RIG OPERATION :
16 DESEMBER 2009
00:00 - 06:00 Exlog PPG#03 Rig UP tanggal 13 Desember 2009, OPR R/U Top Drive, Kedalaman pemboran 197 mKB
06:00 - 13:00 Lanjut R/U Top drive
13:00 - 18:00 Persiapan dan stand up 90 joints 5"DP (45 stand)
18:00 - 20:30 Lanjut stand up 10 joint 5"DP ( 5 stand - Total 50 stand), 14 jts 5"HWDP
20:30 - 23:30 Persiapan dan masuk rangkaian dengan menggunakan 12-1/4"pahat + BHA sampai kedalaman 181 mKB (TOC)
23:30 - 24:00 Sirkulasi sambil kondisikan lumpur, Bor plug, collar dan semen sampai kedakaman 182 mKB
17 DESEMBER 2009
00:00 - 01:30 Lanjut Bor plug, collar dan semen dari kedalaman 182 mKB sampai kedakaman 192 mKB
01:30 - 02:00 Sirkulasi bersihkan lubang, Uji tekan casing 1000 Psi/ 5 menit (Baik)
02:00 - 03:00 Lanjut Bor semen + dari kedalaman 192 mKB sampai kedakaman 200 mKB
SHOWS
INTERVAL GAS SHOWS %STAIN CUT
LITHOLOGY ROP DITCH SHOW
FROM/TO C1 C2 C3 iC4 nC4 INTEN,COLOR,FLUOR INTEN,COLOR,FLUOR
1080 - 1081 Sandstone 2 75 3825 89 70 44 - 5 - 10% pall yell flour crush cut flour Tr oil show
1083 -1084 Sandstone 2 93 4743 110 87 54 - 5 - 10% pall yell flour crush cut flour Tr oil show
1102 - 1104 Sandstone 2 4138 211038 4907 3849 2405 - 5 - 10% pall yell flour crush cut flour Tr oil show
1106 - 1108 Sandstone 3 4276 218076 5072 3979 2487 - 5 - 10% pall yell flour crush cut flour Tr oil show
1110 - 1112 Sandstone 2 2737 139587 3247 2546 1592 - 5 - 10% pall yell flour crush cut flour Tr oil show
1132 - 1134 Sandstone 2 110 5610 130 102 64 - 5 - 10% pall yell flour crush cut flour Tr oil show
1150 - 1152 Sandstone 2 2054 104754 4236 1908 1193 - 5 - 10% pall yell flour crush cut flour Tr oil show
1156 - 1158 Sandstone 2 1153 58803 1368 1073 670 - 5 - 10% pall yell flour crush cut flour Tr oil show
1164 - 1166 Sandstone 2-3 1958 139383 99858 2322 1822 - 5 - 10% pall yell flour crush cut flour Tr oil show
17 DESEMBER 2009
00:00 - 01:30 Lanjut Bor plug, collar dan semen dari kedalaman 182 mKB sampai kedakaman 192 mKB
01:30 - 02:00 Sirkulasi bersihkan lubang, Uji tekan casing 1000 Psi/ 5 menit (Baik)
02:00 - 03:00 Lanjut Bor semen + dari kedalaman 192 mKB sampai kedakaman 197 mKB, bor formasi dari 197mKB sampai 200mKB
03:00 - 03:30 sirkulasi bersihkan lubang SG in/out 1.06,cabut rangkaian 5 meter diatas shoe, MOT dengan pompa Rig, MW 1.06 SG
Pressure 150 Psi EMW 1.59 SG
03:30 - 06:00 Lanjut formasi dari kedalaman 200 mKB sampai kedakaman 220 mKB
06:00 - 15:00 Lanjut formasi dari kedalaman 220 mKB sampai kedakaman 259 mKB, (Pompa Hivis @ 257mKB 30 bbls)
15:00 - 24:00 Lanjut formasi dari kedalaman 259 mKB sampai kedakaman 290 mKB
18 DESEMBER 2009
00:00 - 03:30 Lanjut formasi dari kedalaman 290 mKB sampai kedakaman 298 mKB (Pompa Hivis @ 294mKB 30 bbls)
SHOWS
INTERVAL GAS SHOWS %STAIN CUT
LITHOLOGY ROP DITCH SHOW
FROM/TO C1 C2 C3 iC4 nC4 INTEN,COLOR,FLUOR INTEN,COLOR,FLUOR
1080 - 1081 Sandstone 75 3825 89 70 44 - 5 - 10% pall yell flour crush cut flour Tr oil show
1083 -1084 Sandstone 93 4743 110 87 54 - 5 - 10% pall yell flour crush cut flour Tr oil show
1102 - 1104 Sandstone 4138 211038 4907 3849 2405 - 5 - 10% pall yell flour crush cut flour Tr oil show
1106 - 1108 Sandstone 4276 218076 5072 3979 2487 - 5 - 10% pall yell flour crush cut flour Tr oil show
1110 - 1112 Sandstone 2737 139587 3247 2546 1592 - 5 - 10% pall yell flour crush cut flour Tr oil show
1132 - 1134 Sandstone 110 5610 130 102 64 - 5 - 10% pall yell flour crush cut flour Tr oil show
1150 - 1152 Sandstone 2054 104754 4236 1908 1193 - 5 - 10% pall yell flour crush cut flour Tr oil show
1156 - 1158 Sandstone 1153 58803 1368 1073 670 - 5 - 10% pall yell flour crush cut flour Tr oil show
1164 - 1166 Sandstone 2-3 1958 139383 99858 2322 1822 - 5 - 10% pall yell flour crush cut flour Tr oil show
18 DESEMBER 2009
00:00 - 03:00 Lanjut formasi dari kedalaman 290 mKB sampai kedakaman 298 mKB (Pompa Hivis @ 294mKB 30 bbls)
03:00 - 06:00 Lanjut formasi dari kedalaman 298 mKB sampai kedakaman 332 mKB
06:00 - 15:00 Lanjut formasi dari kedalaman 332mKBsampai kedalaman 377mKB (Pompa Hivis 30 bbls @ 332 mKB)
15:00 - 18:00 Lanjut formasi dari kedalaman 377mKBsampai kedalaman 380mKB
18:00 - 19:00 Sirkulasi bersih, pompa Hivis 30 bbls, lanjut sirkulasi
19:00 - 23:00 Cabut Rangkaian pipa bor sampai permukaan (Ganti BHA - L/D 2 JTS 8"DC DAN 2 JTS Stabilizer 12-1/4")
23:00 - 24:00 Persiapan dan masuk rangkaian 12-1/4"Pahat + BHA sampai kedalaman 96mKB
19 DESEMBER 2009
00:00 - 00:30 Lanjut Masuk Rangkaian dari kedalaman 96 mKB sampai kedalaman 180 mKB
00:30 - 03:00 Pebaikan dishcarge mesin pompa lumpur no 1
SHOWS
INTERVAL GAS SHOWS %STAIN CUT
LITHOLOGY ROP DITCH SHOW
FROM/TO C1 C2 C3 iC4 nC4 INTEN,COLOR,FLUOR INTEN,COLOR,FLUOR
1080 - 1081 Sandstone 75 3825 29,9 70 44 - 5 - 10% pall yell flour crush cut flour Tr oil show
1083 -1084 Sandstone 93 4743 110 87 54 - 5 - 10% pall yell flour crush cut flour Tr oil show
1102 - 1104 Sandstone 4138 211038 4907 3849 2405 - 5 - 10% pall yell flour crush cut flour Tr oil show
1106 - 1108 Sandstone 4276 218076 5072 3979 2487 - 5 - 10% pall yell flour crush cut flour Tr oil show
1110 - 1112 Sandstone 2737 139587 3247 2546 1592 - 5 - 10% pall yell flour crush cut flour Tr oil show
1132 - 1134 Sandstone 110 5610 130 102 64 - 5 - 10% pall yell flour crush cut flour Tr oil show
1150 - 1152 Sandstone 2054 104754 4236 1908 1193 - 5 - 10% pall yell flour crush cut flour Tr oil show
1156 - 1158 Sandstone 1153 58803 1368 1073 670 - 5 - 10% pall yell flour crush cut flour Tr oil show
1164 - 1166 Sandstone 2-3 1958 139383 99858 2322 1822 - 5 - 10% pall yell flour crush cut flour Tr oil show
19 DESEMBER 2009
00:00 - 00:30 Lanjut Masuk Rangkaian dari kedalaman 96 mKB sampai kedalaman 180 mKB
00:30 - 06:00 Pebaikan dishcarge mesin pompa lumpur no 1
06:00 - 14:00 Lanjut Pebaikan dishcarge mesin pompa lumpur no 1
14:00 - 15:00 Sirkulasi di shoe
15:00 - 16:00 Lanjut masuk Rangkaian dari kedalaman 180 mKB sampai kedalaman 380 mKB
16:00 - 24:00 Lanjut bor formasi dari kedalaman 380 mKB sampai kedalaman 423 mKB ROP 5 Mnt/M,
Lithology Coal 80% Claystone 10% Sand 20 %
20 DESEMBER 2009
00:00 - 03:00 Lanjut bor formasi dari kedalaman 423 mKB sampai kedalaman 447 mKB
SHOWS
INTERVAL GAS SHOWS %STAIN CUT
LITHOLOGY ROP DITCH SHOW
FROM/TO C1 C2 C3 iC4 nC4 INTEN,COLOR,FLUOR INTEN,COLOR,FLUOR
1080 - 1081 Sandstone 75 3825 29,9 70 44 - 5 - 10% pall yell flour crush cut flour Tr oil show
1083 -1084 Sandstone 93 4743 110 87 54 - 5 - 10% pall yell flour crush cut flour Tr oil show
1102 - 1104 Sandstone 4138 211038 4907 3849 2405 - 5 - 10% pall yell flour crush cut flour Tr oil show
1106 - 1108 Sandstone 4276 218076 5072 3979 2487 - 5 - 10% pall yell flour crush cut flour Tr oil show
1110 - 1112 Sandstone 2737 139587 3247 2546 1592 - 5 - 10% pall yell flour crush cut flour Tr oil show
1132 - 1134 Sandstone 110 5610 130 102 64 - 5 - 10% pall yell flour crush cut flour Tr oil show
1150 - 1152 Sandstone 2054 104754 4236 1908 1193 - 5 - 10% pall yell flour crush cut flour Tr oil show
1156 - 1158 Sandstone 1153 58803 1368 1073 670 - 5 - 10% pall yell flour crush cut flour Tr oil show
1164 - 1166 Sandstone 2-3 1958 139383 99858 2322 1822 - 5 - 10% pall yell flour crush cut flour Tr oil show
20 DESEMBER 2009
00:00 - 03:00 Lanjut bor formasi dari kedalaman 423 mKB sampai kedalaman 447 mKB
03:00 - 06:00 Lanjut bor formasi dari kedalaman 447 mKB sampai kedalaman 471mKB
06:00 - 15:00 Lanjut bor formasi dari kedalaman 471 mKB sampai kedalaman 518 mKB
15:00 - 19:00 Lanjut bor formasi dari kedalaman 581 mKB sampai kedalaman 545 mKB
19:00 - 20:00 Sirkulasi dengan pompa no 3 sambil Perbaikan pompa lumpur no 1 dan no 2
20:00 - xx:00 Cabut rangkaian sampai shoe, perbaikan pompa lumpur no 1 dan no 2
21 DESEMBER 2009
00:00 - 03:00 Lanjut perbaikan pompa no 2
SHOWS
INTERVAL GAS SHOWS %STAIN CUT
LITHOLOGY ROP DITCH SHOW
FROM/TO C1 C2 C3 iC4 nC4 INTEN,COLOR,FLUOR INTEN,COLOR,FLUOR
1080 - 1081 Sandstone 75 3825 29,9 70 44 - 5 - 10% pall yell flour crush cut flour Tr oil show
1083 -1084 Sandstone 93 4743 110 87 54 - 5 - 10% pall yell flour crush cut flour Tr oil show
1102 - 1104 Sandstone 4138 211038 4907 3849 2405 - 5 - 10% pall yell flour crush cut flour Tr oil show
1106 - 1108 Sandstone 4276 218076 5072 3979 2487 - 5 - 10% pall yell flour crush cut flour Tr oil show
1110 - 1112 Sandstone 2737 139587 3247 2546 1592 - 5 - 10% pall yell flour crush cut flour Tr oil show
1132 - 1134 Sandstone 110 5610 130 102 64 - 5 - 10% pall yell flour crush cut flour Tr oil show
1150 - 1152 Sandstone 2054 104754 4236 1908 1193 - 5 - 10% pall yell flour crush cut flour Tr oil show
1156 - 1158 Sandstone 1153 58803 1368 1073 670 - 5 - 10% pall yell flour crush cut flour Tr oil show
1164 - 1166 Sandstone 2-3 1958 139383 99858 2322 1822 - 5 - 10% pall yell flour crush cut flour Tr oil show
21 DESEMBER 2009
00:00 - 03:00 Lanjut perbaikan pompa no 2
03:00 - 05:30 Lanjut perbaikan pompa no 3
05:30 - 07:30 Test pompa no 1 dengan 120 SPM dan pompa no 3 dengan 120 SPM - OK
07:30 - 08:30 Masuk rangkaian sampai kedalaman 409mKB (Duduk)
08:30 - 13:00 Reaming dari kedalaman 409mKB sampai kedalaman 545mKB
13:00 - 15:00 Lanjut bor formasi dari kedalaman 545 mKB sampai 551 mKB
15:00 - 18:00 Lanjut bor formasi dari kedalaman 551 mKB sampai 567 mKB
18:00 - 24:00 Lanjut bor formasi dari kedalaman 567 mKB sampai 602 mKB ( ROP 4 min/Hrs, Coal 80%, Clyst 10%, Sst 10 % )
22 DESEMBER 2009
00:00 - 02:30 Lanjut bor formasi dari kedalaman 602 mKB sampai 621 mKB
02:30 - 03:00 Sweep Hivis 30 bbls, lanjut bor formasi sampai kedalaman 622 mKB
LITHOLOGY Sandstone : 40 % Shale : %
Claystone : 50 % Coal : 10 %
SHOWS
INTERVAL GAS SHOWS %STAIN CUT
LITHOLOGY ROP DITCH SHOW
FROM/TO C1 C2 C3 iC4 nC4 INTEN,COLOR,FLUOR INTEN,COLOR,FLUOR
1080 - 1081 Sandstone 75 3825 29,9 70 44 - 5 - 10% pall yell flour crush cut flour Tr oil show
1083 -1084 Sandstone 93 4743 110 87 54 - 5 - 10% pall yell flour crush cut flour Tr oil show
1102 - 1104 Sandstone 4138 211038 4907 3849 2405 - 5 - 10% pall yell flour crush cut flour Tr oil show
1106 - 1108 Sandstone 4276 218076 5072 3979 2487 - 5 - 10% pall yell flour crush cut flour Tr oil show
1110 - 1112 Sandstone 2737 139587 3247 2546 1592 - 5 - 10% pall yell flour crush cut flour Tr oil show
1132 - 1134 Sandstone 110 5610 130 102 64 - 5 - 10% pall yell flour crush cut flour Tr oil show
1150 - 1152 Sandstone 2054 104754 4236 1908 1193 - 5 - 10% pall yell flour crush cut flour Tr oil show
1156 - 1158 Sandstone 1153 58803 1368 1073 670 - 5 - 10% pall yell flour crush cut flour Tr oil show
1164 - 1166 Sandstone 2-3 1958 139383 99858 2322 1822 - 5 - 10% pall yell flour crush cut flour Tr oil show
22 DESEMBER 2009
00:00 - 02:30 Lanjut bor formasi dari kedalaman 602 mKB sampai 621 mKB
02:30 - 03:00 Sweep Hivis 30 bbls, lanjut bor formasi sampai kedalaman 622 mKB
03:00 - 06:00 Lanjut bor formasi dari kedalaman 622 mKB sampai 641 mKB
06:00 - 09:00 Lanjut bor formasi dari kedalaman 641 mKB sampai kedalaman 660 mKB,sweep Hivis 30 bbls
09:00 - 15:00 Lanjut bor formasi dari kedalaman 660 mKB sampai kedalaman 679 mKB
15:00 - 18:00 Lanjut bor formasi dari kedalaman 679 mKB sampai kedalaman 695 mKB
18:00 - 19:00 Lanjut bor formasi dari kedalaman 695 mKB sampai kedalaman 699 mKB,sweep Hivis 30 bbls
19:00 - 24:00 Lanjut bor formasi dari kedalaman 699 mKB sampai kedalaman 719 mKB
ROP 5 M/Hrs Lithology 50% Coal 30% Clyst, 20 % Sst
23 DESEMBER 2009
00:00 - 03:00 Lanjut bor formasi dari kedalaman 719 mKB sampai kedalaman 737 mKB
SHOWS
INTERVAL GAS SHOWS %STAIN CUT
LITHOLOGY ROP DITCH SHOW
FROM/TO C1 C2 C3 iC4 nC4 INTEN,COLOR,FLUOR INTEN,COLOR,FLUOR
1080 - 1081 Sandstone 75 3825 29,9 70 44 - 5 - 10% pall yell flour crush cut flour Tr oil show
1083 -1084 Sandstone 93 4743 110 87 54 - 5 - 10% pall yell flour crush cut flour Tr oil show
1102 - 1104 Sandstone 4138 211038 4907 3849 2405 - 5 - 10% pall yell flour crush cut flour Tr oil show
1106 - 1108 Sandstone 4276 218076 5072 3979 2487 - 5 - 10% pall yell flour crush cut flour Tr oil show
1110 - 1112 Sandstone 2737 139587 3247 2546 1592 - 5 - 10% pall yell flour crush cut flour Tr oil show
1132 - 1134 Sandstone 110 5610 130 102 64 - 5 - 10% pall yell flour crush cut flour Tr oil show
1150 - 1152 Sandstone 2054 104754 4236 1908 1193 - 5 - 10% pall yell flour crush cut flour Tr oil show
1156 - 1158 Sandstone 1153 58803 1368 1073 670 - 5 - 10% pall yell flour crush cut flour Tr oil show
1164 - 1166 Sandstone 2-3 1958 139383 99858 2322 1822 - 5 - 10% pall yell flour crush cut flour Tr oil show
23 DESEMBER 2009
00:00 - 03:00 Lanjut bor formasi dari kedalaman 719 mKB sampai kedalaman 737 mKB, Sweep Hivis 30 bbls @ 737mKB
03:00 - 06:00 Lanjut bor formasi dari kedalaman 737 mKB sampai kedalaman 748 mKB
06:00 - 15:00 Lanjut bor formasi dari kedalaman 748 mKB sampai kedalaman 779mKB, Sweep Hivis 30 bbls @ 776 mKB
15:00 - 18:00 Lanjut bor formasi dari kedalaman 779 mKB sampai kedalaman 795 mKB
18:00 - 18:30 Lanjut bor formasi sampai kedalaman 796 mKB, sirkulasi sambil perbaikan pompa no 2, Sweep Hivis 30 bbls
18:30 - 20:30 Lanjut sirkulasi dengan menggunakan pompa 1 dan 2 sambil perbaikan pompa no 3 ( ganti rubber piston)
20:30 - 24:00 Cabut rangkaian sampai shoe ( Time 24:00 @ 467 mKB)
24 DESEMBER 2009
00:00 - 03:00 Lanjut cabut rangkaian sampai shoe
SHOWS
INTERVAL GAS SHOWS %STAIN CUT
LITHOLOGY ROP DITCH SHOW
FROM/TO C1 C2 C3 iC4 nC4 INTEN,COLOR,FLUOR INTEN,COLOR,FLUOR
1080 - 1081 Sandstone 75 3825 29,9 70 44 - 5 - 10% pall yell flour crush cut flour Tr oil show
1083 -1084 Sandstone 93 4743 110 87 54 - 5 - 10% pall yell flour crush cut flour Tr oil show
1102 - 1104 Sandstone 4138 211038 4907 3849 2405 - 5 - 10% pall yell flour crush cut flour Tr oil show
1106 - 1108 Sandstone 4276 218076 5072 3979 2487 - 5 - 10% pall yell flour crush cut flour Tr oil show
1110 - 1112 Sandstone 2737 139587 3247 2546 1592 - 5 - 10% pall yell flour crush cut flour Tr oil show
1132 - 1134 Sandstone 110 5610 130 102 64 - 5 - 10% pall yell flour crush cut flour Tr oil show
1150 - 1152 Sandstone 2054 104754 4236 1908 1193 - 5 - 10% pall yell flour crush cut flour Tr oil show
1156 - 1158 Sandstone 1153 58803 1368 1073 670 - 5 - 10% pall yell flour crush cut flour Tr oil show
1164 - 1166 Sandstone 2-3 1958 139383 99858 2322 1822 - 5 - 10% pall yell flour crush cut flour Tr oil show
PRESENT OPERATION (24:00 ) : CABUT RANGKAIAN SAMPAI SHOE ( Time 24:00 @ 467 mKB)
BOR FORMASI DARI KEDALAMAN ( 00:00 - 24:00) 719 mKB SAMPAI : 796 mKB
Bit Hrs : 15 Hrs Total Bit Hrs : 94 Hrs
Footage : 77 M Total Footage : 614 M
Maks Gas : 13 Units Conn Gas : Units
B/G Gas : 2-5 Units Trip Gas : Units
Stand Down Terakhir : 220 Menit Lithology (03:00) 20% Sand
Kedalaman pada pukul 24.00 : 796 Meter 796 mKB 30% Clyst
ROP terakhir 03:00 : 11 Mnt/M 50% Coal
FORMATION LOGGING REPORT NO : 9
MORNING REPORT
24 DESEMBER 2009
00:00 - 02:30 Lanjut cabut rangkaian sampai shoe sambil pompa ( with pump out), sirkulasi di shoe
02:30 - 06:00 Perbaikan pompa lumpur , ganti liner pompa 1,2 dan 3 ( linner 5-1/2" ke 6 ")
06:00 - 11:00 Lanjut ganti liner pompa 1,2 dan 3 ( linner 5-1/2" ke 6 ")
11:00 - 15:30 Perbaikan pompa lumpur no 2 ( Ganti dies clocth)
15:30 - 16:30 Test pompa lumpur no 1 dan 3 dengan 2 x 120 SPM (=716 GPM) - Pump Pressure 970 ) Ok
16:30 - 24:00 Lanjut perbaikan pompa lumpur no 2 (Ganti dies cloch plate) sambil menunggu bearing - pompa no 2
25 DESEMBER 2009
00:00 - 03:00 Pasang Dish cloch plate pompa no 2 sambil menunggu bearing pompa no 2
SHOWS
INTERVAL GAS SHOWS %STAIN CUT
LITHOLOGY ROP DITCH SHOW
FROM/TO C1 C2 C3 iC4 nC4 INTEN,COLOR,FLUOR INTEN,COLOR,FLUOR
1080 - 1081 Sandstone 75 3825 29,9 70 44 - 5 - 10% pall yell flour crush cut flour Tr oil show
1083 -1084 Sandstone 93 4743 110 87 54 - 5 - 10% pall yell flour crush cut flour Tr oil show
1102 - 1104 Sandstone 4138 211038 4907 3849 2405 - 5 - 10% pall yell flour crush cut flour Tr oil show
1106 - 1108 Sandstone 4276 218076 5072 3979 2487 - 5 - 10% pall yell flour crush cut flour Tr oil show
1110 - 1112 Sandstone 2737 139587 3247 2546 1592 - 5 - 10% pall yell flour crush cut flour Tr oil show
1132 - 1134 Sandstone 110 5610 130 102 64 - 5 - 10% pall yell flour crush cut flour Tr oil show
1150 - 1152 Sandstone 2054 104754 4236 1908 1193 - 5 - 10% pall yell flour crush cut flour Tr oil show
1156 - 1158 Sandstone 1153 58803 1368 1073 670 - 5 - 10% pall yell flour crush cut flour Tr oil show
1164 - 1166 Sandstone 2-3 1958 139383 99858 2322 1822 - 5 - 10% pall yell flour crush cut flour Tr oil show
PRESENT OPERATION (24:00 ) : Pasang Dish cloch plate pompa no 2 sambil menunggu bearing pompa no 2
BOR FORMASI DARI KEDALAMAN ( 00:00 - 24:00) 796 mKB SAMPAI : 796 mKB
Bit Hrs : Hrs Total Bit Hrs : 94 Hrs
Footage : M Total Footage : 614 M
Maks Gas : Units Conn Gas : Units
B/G Gas : Units Trip Gas : Units
Stand Down Terakhir : Menit Lithology (03:00) Sand
Kedalaman pada pukul 24.00 : 796 Meter mKB Clyst
ROP terakhir 03:00 : Mnt/M Coal
FORMATION LOGGING REPORT NO : 10
MORNING REPORT
25 DESEMBER 2009
00:00 - 03:00 Pasang Dish cloch plate pompa no 2 sambil menunggu bearing pompa no 2
04:30 - 06:00 RIH 12 1/4"PDC bit ,tight hole pada kedalaman 408 mKB
06:00 - 15:00 Lanjut masuk rangkaian pipa bor sampai kedalaman 408mKB ,Reaming dari kedalaman 408mKB
sampai kedalaman 602mKB
15:00 - 18:00 Lanjut reaming dari kedalaman 602mKB sampai kedalaman 646 mKB
18:00 - 24:00 Lanjut reaming dari kedalaman 646 mKB sampai kedalaman 726 mKB
26 DESEMBER 2009
00:00 - 03:00 Lanjut reaming dari kedalaman 726 mKB sampai kedalaman 773 mKB
SHOWS
INTERVAL GAS SHOWS %STAIN CUT
LITHOLOGY ROP DITCH SHOW
FROM/TO C1 C2 C3 iC4 nC4 INTEN,COLOR,FLUOR INTEN,COLOR,FLUOR
1080 - 1081 Sandstone 75 3825 29,9 70 44 - 5 - 10% pall yell flour crush cut flour Tr oil show
1083 -1084 Sandstone 93 4743 110 87 54 - 5 - 10% pall yell flour crush cut flour Tr oil show
1102 - 1104 Sandstone 4138 211038 4907 3849 2405 - 5 - 10% pall yell flour crush cut flour Tr oil show
1106 - 1108 Sandstone 4276 218076 5072 3979 2487 - 5 - 10% pall yell flour crush cut flour Tr oil show
1110 - 1112 Sandstone 2737 139587 3247 2546 1592 - 5 - 10% pall yell flour crush cut flour Tr oil show
1132 - 1134 Sandstone 110 5610 130 102 64 - 5 - 10% pall yell flour crush cut flour Tr oil show
1150 - 1152 Sandstone 2054 104754 4236 1908 1193 - 5 - 10% pall yell flour crush cut flour Tr oil show
1156 - 1158 Sandstone 1153 58803 1368 1073 670 - 5 - 10% pall yell flour crush cut flour Tr oil show
1164 - 1166 Sandstone 2-3 1958 139383 99858 2322 1822 - 5 - 10% pall yell flour crush cut flour Tr oil show
26 DESEMBER 2009
00:00 - 03:00 Lanjut reaming dari kedalaman 726 mKB sampai kedalaman 773 mKB
03:00 - 05:00 Lanjut reaming dari kedalaman 773 mKB sampai kedalaman 796 mKB
05:00 - 06:00 Sweep Hivis 30 bbls, sirkulasi
06:00 - 15:00 Lanjut bor formasi dari kedalaman 796 mKB sampai kedalaman 834 mKB
15:00 - 18:00 Lanjut bor formasi dari kedalaman 834 mKB sampai kedalaman 843 mKB
18:00 - 24:00 Lanjut bor formasi dari kedalaman 843 mKB sampai kedalaman 856 mKB
ROP 28 Mnt/M, Lithology 20% Shale, 20 % Coal, 60 % Sandstone
26 DESEMBER 2009
00:00 - 03:00 Lanjut bor formasi dari kedalaman 856 mKB sampai kedalaman 864 mKB
SHOWS
INTERVAL GAS SHOWS %STAIN CUT
LITHOLOGY ROP DITCH SHOW
FROM/TO C1 C2 C3 iC4 nC4 INTEN,COLOR,FLUOR INTEN,COLOR,FLUOR
1080 - 1081 Sandstone 75 3825 29,9 70 44 - 5 - 10% pall yell flour crush cut flour Tr oil show
1083 -1084 Sandstone 93 4743 110 87 54 - 5 - 10% pall yell flour crush cut flour Tr oil show
1102 - 1104 Sandstone 4138 211038 4907 3849 2405 - 5 - 10% pall yell flour crush cut flour Tr oil show
1106 - 1108 Sandstone 4276 218076 5072 3979 2487 - 5 - 10% pall yell flour crush cut flour Tr oil show
1110 - 1112 Sandstone 2737 139587 3247 2546 1592 - 5 - 10% pall yell flour crush cut flour Tr oil show
1132 - 1134 Sandstone 110 5610 130 102 64 - 5 - 10% pall yell flour crush cut flour Tr oil show
1150 - 1152 Sandstone 2054 104754 4236 1908 1193 - 5 - 10% pall yell flour crush cut flour Tr oil show
1156 - 1158 Sandstone 1153 58803 1368 1073 670 - 5 - 10% pall yell flour crush cut flour Tr oil show
1164 - 1166 Sandstone 2-3 1958 139383 99858 2322 1822 - 5 - 10% pall yell flour crush cut flour Tr oil show
27 DESEMBER 2009
00:00 - 03:00 Lanjut bor formasi dari kedalaman 856 mKB sampai kedalaman 864 mKB
03:00 - 06:00 Lanjut bor formasi dari kedalaman 864 mKB sampai kedalaman 886 mKB
06:00 - 09:30 Lanjut bor formasi dari kedalaman 886 mKB sampai kedalaman 902 mKB
09:30 - 10:30 Sirkulasi sambil perbaikan pompa no 1
10:30 - 15:00 Lanjut bor formasi dari kedalaman 902 mKB sampai kedalaman 922mKB
15:00 - 18:00 Lanjut bor formasi dari kedalaman 922 mKB sampai kedalaman 935mKB
18:00 - 24:00 Lanjut bor formasi dari kedalaman 935 mKB sampai kedalaman 983 mKB, pompa Hivis 30 bbls setiap 2 stand
ROP 11 Mnt/M, Lithology 60 % Shale, 40 % Sandstone
28 DESEMBER 2009
00:00 - 03:00 Lanjut bor formasi dari kedalaman 983 mKB sampai kedalaman 1008 mKB, pompa Hivis 30 bbls setiap 2 stand
SHOWS
INTERVAL GAS SHOWS %STAIN CUT
LITHOLOGY ROP DITCH SHOW
FROM/TO C1 C2 C3 iC4 nC4 INTEN,COLOR,FLUOR INTEN,COLOR,FLUOR
1080 - 1081 Sandstone 75 3825 29,9 70 44 - 5 - 10% pall yell flour crush cut flour Tr oil show
1083 -1084 Sandstone 93 4743 110 87 54 - 5 - 10% pall yell flour crush cut flour Tr oil show
1102 - 1104 Sandstone 4138 211038 4907 3849 2405 - 5 - 10% pall yell flour crush cut flour Tr oil show
1106 - 1108 Sandstone 4276 218076 5072 3979 2487 - 5 - 10% pall yell flour crush cut flour Tr oil show
1110 - 1112 Sandstone 2737 139587 3247 2546 1592 - 5 - 10% pall yell flour crush cut flour Tr oil show
1132 - 1134 Sandstone 110 5610 130 102 64 - 5 - 10% pall yell flour crush cut flour Tr oil show
1150 - 1152 Sandstone 2054 104754 4236 1908 1193 - 5 - 10% pall yell flour crush cut flour Tr oil show
1156 - 1158 Sandstone 1153 58803 1368 1073 670 - 5 - 10% pall yell flour crush cut flour Tr oil show
1164 - 1166 Sandstone 2-3 1958 139383 99858 2322 1822 - 5 - 10% pall yell flour crush cut flour Tr oil show
28 DESEMBER 2009
00:00 - 03:00 Lanjut bor formasi dari kedalaman 983 mKB sampai kedalaman 1008 mKB, pompa Hivis 30 bbls setiap 2 stand
03:00 - 06:00 Lanjut bor formasi dari kedalaman 1008 mKB sampai kedalaman 1027 mKB
06:00 - 11:30 Lanjut bor formasi dari kedalaman 1031 mKB sampai kedalaman 1068 mKB, valve kelly kock Top Drive bocor
11:30 - 12:00 cabut Rangkaian 2 stand 5"DP sampai kedalaman 1046mKB
12:00 - 15:30 Perbaikan Top Drive ( Ganti kelly kock) sambil sirkulasi dengan 715 GPM
15:30 - 16:00 Turunkan rangkaian (wash down) dari kedalaman 1046mKB sampai kedalaman 1068mKB
16:00 - 18:00 Lanjut bor formasi dari kedalaman 1068mKB sampai kedalaman 1085mKB
18:00 - 24:00 Lanjut bor formasi dari kedalaman 1085mKB sampai kedalaman 1124 mKB,pompa Hivis 30 bbl
ROP 6 Mnt/Hrs, Lithology 10 % Coal 20 % Shale 70 % Sandstone
28 DESEMBER 2009
00:00 - 03:00 Lanjut bor formasi dari kedalaman 1124 mKB sampai kedalaman 1141 mKB
SHOWS
INTERVAL GAS SHOWS %STAIN CUT
LITHOLOGY ROP DITCH SHOW
FROM/TO C1 C2 C3 iC4 nC4 INTEN,COLOR,FLUOR INTEN,COLOR,FLUOR
1080 - 1081 Sandstone 75 3825 29,9 70 44 - 5 - 10% pall yell flour crush cut flour Tr oil show
1083 -1084 Sandstone 93 4743 110 87 54 - 5 - 10% pall yell flour crush cut flour Tr oil show
1102 - 1104 Sandstone 4138 211038 4907 3849 2405 - 5 - 10% pall yell flour crush cut flour Tr oil show
1106 - 1108 Sandstone 4276 218076 5072 3979 2487 - 5 - 10% pall yell flour crush cut flour Tr oil show
1110 - 1112 Sandstone 2737 139587 3247 2546 1592 - 5 - 10% pall yell flour crush cut flour Tr oil show
1132 - 1134 Sandstone 110 5610 130 102 64 - 5 - 10% pall yell flour crush cut flour Tr oil show
1150 - 1152 Sandstone 2054 104754 4236 1908 1193 - 5 - 10% pall yell flour crush cut flour Tr oil show
1156 - 1158 Sandstone 1153 58803 1368 1073 670 - 5 - 10% pall yell flour crush cut flour Tr oil show
1164 - 1166 Sandstone 2-3 1958 139383 99858 2322 1822 - 5 - 10% pall yell flour crush cut flour Tr oil show
30 DESEMBER 2009
00:00 - 01:30 Lanjut masuk rangkaian dari kedalaman 583 mKB sampai kedalaman 1114 mKB (duduk - tight hole)
01:30 - 03:00 Masuk rangkaian (reaming) dari kedalaman 1114 mKB sampai 1162 mKB
1080 - 1081 Sandstone 75 3825 29,9 70 44 - 5 - 10% pall yell flour crush cut flour Tr oil show
1083 -1084 Sandstone 93 4743 110 87 54 - 5 - 10% pall yell flour crush cut flour Tr oil show
1102 - 1104 Sandstone 4138 211038 4907 3849 2405 - 5 - 10% pall yell flour crush cut flour Tr oil show
1106 - 1108 Sandstone 4276 218076 5072 3979 2487 - 5 - 10% pall yell flour crush cut flour Tr oil show
1110 - 1112 Sandstone 2737 139587 3247 2546 1592 - 5 - 10% pall yell flour crush cut flour Tr oil show
1132 - 1134 Sandstone 110 5610 130 102 64 - 5 - 10% pall yell flour crush cut flour Tr oil show
1150 - 1152 Sandstone 2054 104754 4236 1908 1193 - 5 - 10% pall yell flour crush cut flour Tr oil show
1156 - 1158 Sandstone 1153 58803 1368 1073 670 - 5 - 10% pall yell flour crush cut flour Tr oil show
1164 - 1166 Sandstone 2-3 1958 139383 99858 2322 1822 - 5 - 10% pall yell flour crush cut flour Tr oil show
PRESENT OPERATION (24:00 ) : MASUK RANGKAIAN DENGAN MNGGUNAKAN 12-1/4"BIT SAMPAI KEDALAMAN 583 mKB
BOR FORMASI DARI KEDALAMAN ( 00:00 - 24:00) 1124 mKB SAMPAI : 1162 mKB
Bit Hrs : 4,50 Hrs Total Bit Hrs : 146,35 Hrs
Footage : 38 M Total Footage : 980 M
Maks Gas : 68 Units Conn Gas : Units
B/G Gas : 5 Units Trip Gas : 68 Units
Stand Down Terakhir : 120 Menit Lithology (03:00) Sand 60%
Kedalaman pada pukul 24.00 : 1162 Meter 1162 mKB Shale 40%
ROP terakhir 03:00 : 12 Mnt/M Coal
FORMATION LOGGING REPORT NO : 15
MORNING REPORT
1080 - 1081 Sandstone 75 3825 29,9 70 44 - 5 - 10% pall yell flour crush cut flour Tr oil show
1083 -1084 Sandstone 93 4743 110 87 54 - 5 - 10% pall yell flour crush cut flour Tr oil show
1102 - 1104 Sandstone 4138 211038 4907 3849 2405 - 5 - 10% pall yell flour crush cut flour Tr oil show
1106 - 1108 Sandstone 4276 218076 5072 3979 2487 - 5 - 10% pall yell flour crush cut flour Tr oil show
1110 - 1112 Sandstone 2737 139587 3247 2546 1592 - 5 - 10% pall yell flour crush cut flour Tr oil show
1132 - 1134 Sandstone 110 5610 130 102 64 - 5 - 10% pall yell flour crush cut flour Tr oil show
1150 - 1152 Sandstone 2054 104754 4236 1908 1193 - 5 - 10% pall yell flour crush cut flour Tr oil show
1156 - 1158 Sandstone 1153 58803 1368 1073 670 - 5 - 10% pall yell flour crush cut flour Tr oil show
1164 - 1166 Sandstone 2-3 1958 139383 99858 2322 1822 - 5 - 10% pall yell flour crush cut flour Tr oil show
1080 - 1081 Sandstone 75 3825 29,9 70 44 - 5 - 10% pall yell flour crush cut flour Tr oil show
1083 -1084 Sandstone 93 4743 110 87 54 - 5 - 10% pall yell flour crush cut flour Tr oil show
1102 - 1104 Sandstone 4138 211038 4907 3849 2405 - 5 - 10% pall yell flour crush cut flour Tr oil show
1106 - 1108 Sandstone 4276 218076 5072 3979 2487 - 5 - 10% pall yell flour crush cut flour Tr oil show
1110 - 1112 Sandstone 2737 139587 3247 2546 1592 - 5 - 10% pall yell flour crush cut flour Tr oil show
1132 - 1134 Sandstone 110 5610 130 102 64 - 5 - 10% pall yell flour crush cut flour Tr oil show
1150 - 1152 Sandstone 2054 104754 4236 1908 1193 - 5 - 10% pall yell flour crush cut flour Tr oil show
1156 - 1158 Sandstone 1153 58803 1368 1073 670 - 5 - 10% pall yell flour crush cut flour Tr oil show
1164 - 1166 Sandstone 2-3 1958 139383 99858 2322 1822 - 5 - 10% pall yell flour crush cut flour Tr oil show
CHROMATOGRAPH RANGE :
C1 = - ppm iC4 = - ppm
C2 = - ppm nC4 = - ppm
C3 = - ppm C5 = - ppm
INTERVAL GAS SHOWS %STAIN CUT
LITHOLOGY ROP DITCH SHOW
FROM/TO C1 C2 C3 iC4 nC4 INTEN,COLOR,FLUOR INTEN,COLOR,FLUOR
1080 - 1081 Sandstone 75 3825 29,9 70 44 - 5 - 10% pall yell flour crush cut flour Tr oil show
1083 -1084 Sandstone 93 4743 110 87 54 - 5 - 10% pall yell flour crush cut flour Tr oil show
1102 - 1104 Sandstone 4138 211038 4907 3849 2405 - 5 - 10% pall yell flour crush cut flour Tr oil show
1106 - 1108 Sandstone 4276 218076 5072 3979 2487 - 5 - 10% pall yell flour crush cut flour Tr oil show
1110 - 1112 Sandstone 2737 139587 3247 2546 1592 - 5 - 10% pall yell flour crush cut flour Tr oil show
1132 - 1134 Sandstone 110 5610 130 102 64 - 5 - 10% pall yell flour crush cut flour Tr oil show
1150 - 1152 Sandstone 2054 104754 4236 1908 1193 - 5 - 10% pall yell flour crush cut flour Tr oil show
1156 - 1158 Sandstone 1153 58803 1368 1073 670 - 5 - 10% pall yell flour crush cut flour Tr oil show
1164 - 1166 Sandstone 2-3 1958 139383 99858 2322 1822 - 5 - 10% pall yell flour crush cut flour Tr oil show
2 JANUARI 2010
00:00 - 03:00 Lanjut cabut rangkaian dari kedalaman 352mKB sampai permukaan
03:00 - 05:00 Persiapan peralatan casing 9 5/8",N/D cup drilling nipple,mengganti link top drive
05:00 - 06:00 Masuk rangkaian Csg 9 5/8" + Csg shoe + 9 5/8" F/C + 17 jts Csg 9 5/8" sampai 196 mKB, Sirkulasi
06:00 - 16:00 Lanjut masuk rangkaian Csg 9 5/8"sampai kedalaman 1174mKB (duduk)
16:00 - 17:00 Pasang Circulating Head 9-5/8",sirkulasi, turunkan rangkaian (wash down) sampai kedalaman 1186mKB
17:00 - 18:00 Sirkulasi bersihkan lubang - Trip gas 76 Unit
18:00 - 20:00 Buka sub ver sub Top drive, pasang Cementing Head
20:00 - 20:30 Sirkulasi
20:30 - 24:00 Cementing Job, flush line, test line 2000 Psi Ok, pompa specer 50 bbl ( 1.4 SG) - Drop Bottom plug
3 JANUARI 2010
00:00 - 02:00 Lanjut mixing dan pompa lead slurry 135,5 bbl dengan SG 1.65 tail semen 277.13 bbl dengan SG 1.9
Drop Top plug sambil di displace oleh lumpur 295.2 bbl - cement tidak ada aliran
02:00 - 03:00 Turunkan Juction line schlumberger, Tunggu Semen kering ( TSK)
CHROMATOGRAPH RANGE :
C1 = - ppm iC4 = - ppm
C2 = - ppm nC4 = - ppm
C3 = - ppm C5 = - ppm
INTERVAL GAS SHOWS %STAIN CUT
LITHOLOGY ROP DITCH SHOW
FROM/TO C1 C2 C3 iC4 nC4 INTEN,COLOR,FLUOR INTEN,COLOR,FLUOR
1080 - 1081 Sandstone 75 3825 29,9 70 44 - 5 - 10% pall yell flour crush cut flour Tr oil show
1083 -1084 Sandstone 93 4743 110 87 54 - 5 - 10% pall yell flour crush cut flour Tr oil show
1102 - 1104 Sandstone 4138 211038 4907 3849 2405 - 5 - 10% pall yell flour crush cut flour Tr oil show
1106 - 1108 Sandstone 4276 218076 5072 3979 2487 - 5 - 10% pall yell flour crush cut flour Tr oil show
1110 - 1112 Sandstone 2737 139587 3247 2546 1592 - 5 - 10% pall yell flour crush cut flour Tr oil show
1132 - 1134 Sandstone 110 5610 130 102 64 - 5 - 10% pall yell flour crush cut flour Tr oil show
1150 - 1152 Sandstone 2054 104754 4236 1908 1193 - 5 - 10% pall yell flour crush cut flour Tr oil show
1156 - 1158 Sandstone 1153 58803 1368 1073 670 - 5 - 10% pall yell flour crush cut flour Tr oil show
1164 - 1166 Sandstone 2-3 1958 139383 99858 2322 1822 - 5 - 10% pall yell flour crush cut flour Tr oil show
4 JANUARI 2010
00:00 - 03:00 Lanjut Stand up 5"DP
4 JANUARI 2010
00:00 - 04:30 Lanjut Stand up 5"DP
04:30 - 09:00 Persiapan dan masuk rangkaian dengan menggunakan 8-1/2" PDC Open nozle + BHA sampai kedalaman
Puncak semen (TOC) 1125 mKB
09:00 - 09:30 Sirkulasi dan Test Csg dengan 1000 psi ditahan 10 menit & Annular & Pipe Ram
09:30 - 15:00 Bor semen plug ,float collar sampai kedalaman 1167 mKB
15:00 - 17:30 Lanjut bor semenn,plug,collar sampai kedalaman 1180 mKB
17:30 - 18:00 Sirkulasi, test ulang casing dengan 1000 Psi/ 10 menit (Ok)
18:00 - 20:30 Lanjut bor semen dan formasi sampai kedalaman 1192mKB
20:30 - 21:00 Sirkulasi bersihkan lubang, sambil kondisikan lumpur SG in/out 1.08, cabut rangkaian sampai 1186mKB
MOT ( dengan menggunakan SG MW 1.08, Pressure 700 Psi EMW 1.5)
21:00 - 24:00 Masuk rangkaian sampai 1192mKB, lanjut bor formasi dari kedalaman 1192mKB sampai 1206mKB
ROP 6 Mnt/Meter Lithology 70% Shale 30% Sandstone
5 JANUARI 2010
00:00 - 03:00 Lanjut bor formasi dari kedalaman 1206 mKB sampai kedalaman 1225 mKB
CHROMATOGRAPH RANGE :
6 JANUARI 2010
00:00 - 03:00 Lanjut menunggu air (tranfer dari pit ke tangki ) sambil mixing LCM
6 JANUARI 2010
00:00 - 03:30 Lanjut menunggu air (tranfer dari pit ke tangki ) sambil mixing LCM
03:30 - 04:00 Masuk rangkaian sampai dasar lubang
04:00 - 06:49 Bor formasi (Blind drill) dari kedalaman 1295 mKB sampai kedalaman 1309 mKB
06:49 - 12:30 Cabut rangkaian sampai permukaan
12:30 - 16:30 Persiapan dan masuk rangkaian cement plug (3 joint tbg 2-7/8" + HWDP+ 5"DP) sampai shoe
16:30 - 19:00 Persiapan cement plug oleh Schlumberger
19:00 - 19:30 Lanjut masuk rangkaian sampai kedalaman 1308mKB
19:30 - 21:30 Pasang cementing line,flush line, test line dengan 2500 Psi, holding pressure dan beed off
pompa air 20 bbl, mixing dan pompa semen slurry 50 bbl @ SG 1.6, displace dengan air 60 bbl
21:30 - 22:30 Cabut rangkaian sampai 1004 mKB
22:30 - 23:00 Pasang cementing line,pompa sement slurry 50 bbl @ SG 1.6, displace dengan air 50 bbl
23:00 - 23:30 Cabut rangkaian sampai 800 mKB
23:00 - 24:00 sirkulasi bersihkan exces semen (2 x vol DP)
7 JANUARI 2010
00:00 - 00:30 Hesitate 1.2 bbl 200 Psi dan Bleed offf tekanan sampai 0 Psi
00:30 - 03:00 Cabut rangkaian sampai permukaan
7 JANUARI 2010
00:00 - 00:30 Hesitate 1.2 bbl 200 Psi dan Bleed offf tekanan sampai 0 Psi
00:30 - 03:00 Cabut rangkaian sampai permukaan
03:00 - 06:00 Masuk rangkaian dengan menggunakan 8-1/2"bit PDc + BHA sampai kedalaman 505 mKB
06:00 - 10:00 Tunggu semen kering (TSK) , pasang sirkulasi line
10:00 - 11:00 Masuk rangkaian dengan menggunakan 8 1/2" PDC (open nozzle) + BHA,TOC pada kedalaman 824.5 mKB
11:00 - 15:00 Bor semen dari kedalaman 824.5 mKB sampai kedalaman 914 mKB
15:00 - 18:00 Lanjut bor semen dari kedalaman 914 mKB sampai kedalaman 980 mKB
18:00 - 24:00 Lanjut bor semen dari kedalaman 980 mKB sampai kedalaman 1055 mKB
8 JANUARI 2010
00:00 - 03:00 Lanjut bor semen dari kedalaman 1055 mKB sampai kedalaman 1102 mKB
Catatan
Pada waktu mengebor semen ROP Rata-rata : 26.3 Meter / Jam = 2.28 Menit/Meter
Total Bit Hrs : 8.8 Hrs
Total Footage : 231.5 m
8 JANUARI 2010
00:00 - 03:00 Lanjut bor semen dari kedalaman 1055 mKB sampai kedalaman 1102 mKB
03:00 - 06:00 Lanjut bor semen dari kedalaman 1102 mKB sampai kedalaman 1175 mKB
06:00 - 12:00 Lanjut bor semen dari kedalaman 1175 mKB sampai kedalaman 1309 mKB
12:00 - 14:30 Bor formasi dari kedalaman 1309 mKB sampai kedalaman 1329 mKB, Loss Total
14:30 - 15:00 Sirkulasi (SPR) sambil mixing lumpur CaCO3 200 bbl
15:00 - 18:00 Lanjut bor formasi (blind drilling) dari kedalaman 1329 mKB sampai kedalaman 1353 mKB
18:00 - 21:00 Lanjut bor formasi (blind drilling) dari kedalaman 1353 mKB sampai kedalaman 1367 mKB
21:00 - 23:00 Lanjut bor formasi (blind drilling) dari kedalaman 1367 mKB sampai kedalaman 1372 mKB
23:00 - 23:30 Cabut rangkaian 2 stand (1334 nKB), masuk rangkaian ke dasar lubang (1372mKB)
23:30 - 24:00 Spot LCM 60 bbl CaCO3 displace 78 bbl air
9 JANUARI 2010
00:00 - 03:00 Cabut rangkaian sampai permukaan ( 03:00 @ 447 mKB)
9 JANUARI 2010
00:00 - 03:00 Cabut rangkaian sampai permukaan ( 03:00 @ 447 mKB)
03:00 - 04:30 Lanjut cabut rangkaian sampai permukaan
04:30 - 06:00 Persiapan dan masuk rangkaian 3-1/2" Open End sampai kedalaman 231mKB
06:00 - 09:00 Lanjut masuk rangkaian Open End sampai kedalaman 1370 mKB
09:00 - 10:00 Sirkulasi ( tidak ada return ) sambil pre job meeting & persiapan penyemenan
10:00 - 10:30 Pasang sirkulasi line, flush & tes tekanan pipa 2500 psi ~ ok, bleed off
10:30 -11:00 Pompa 20 bbl air, pompa semen slurry 60 bbls SG 1.6 ;Displace 62 bbls air
11:00 - 12:30 Sirkulasi sambil bersihkan sisa-sisa semen ;maximum gas 19 units
12:30 - 15:30 Cabut rangkaian sampai permukaan
15:30 - 18:00 Persiapan dan masuk rangkaian dengan menggunakan 8-1/2" Pahat Open Nozle + BHA sampai 928mKB
18:00 - 18:30 Sirkulasi
18:30 - 19:30 Lanjut masuk rangkaian Open End sampai kedalaman 1141 mKB
19:30 - 20:00 Sirkulasi sambil chek sampel semen
20:00 - 24:00 Tunggu Semen Kering
10 JANUARI 2010
00:00 - 03:00 Lanjut tunggu semen kering
PRESENT OPERATION (24:00 ) : LOSS TOTAL DI KEDALAMAN 1411 mKB, SIRKULASI SAMBIL OBSERVASI LUBANG BOR.
BOR FORMASI DARI KEDALAMAN ( 00:00 - 24:00 ) 1372 mKB SAMPAI : 1411 mKB
Bit Hrs : 4,80 Hrs Total Bit Hrs : 25,51 Hrs
Footage : 39 M Total Footage : 223 M
Maks Gas : 84 Units Conn Gas : Units
B/G Gas : 5-8 Units Trip Gas : 126 Units
Stand Down Terakhir : 210 Menit Lithology (03:00) Sand
Kedalaman pada pukul 24.00 : 1411 Meter mKB Shale
ROP terakhir 03:00 : 11 Mnt/M Coal
FORMATION LOGGING REPORT NO : 28
MORNING REPORT
PRESENT OPERATION (24:00 ) : MASUK RANGKAIAN 3-1/2"DP OPEN END + 5"DP SAMPAI KEDALAMAN 1178 mKB
BOR FORMASI DARI KEDALAMAN ( 00:00 - 24:00 ) 1411 mKB SAMPAI : 1440 mKB
Bit Hrs : 4,99 Hrs Total Bit Hrs : 30,50 Hrs
Footage : 29 M Total Footage : 252 M
Maks Gas : Units Conn Gas : Units
B/G Gas : Units Trip Gas : 127 Units
Stand Down Terakhir : 218 Menit Lithology (03:00) Sand
Kedalaman pada pukul 24.00 : 1440 Meter 1440 mKB Shale
ROP terakhir 03:00 : 5 Mnt/M Coal
FORMATION LOGGING REPORT NO : 29
MORNING REPORT
FIELD : TANJUNG - KALSEL 9-5/8 " AT 1186 MET ER W OBWE IGHT -ON-B IT V FUNNE L VI ST
ELEVATION : GL : 67.81 M KCL POLIMER 30 mKB TO 1270 mKB BG B ACK GROUND GAS CL S ALINIT Y - P P M
CUT
INTERPRETED
SHOW S
CORE
T EST
20 40 60 80 100 C1
C2
MUD DATA DESCRIPTION & REMARKS
100K
1000K
iC4
GOOD
GOOD
FAIR
FAIR
10
100
1K
10K
100K
1000
0 5 10 15 20 0 20 40 60 80 100
160
170
ALL DEPTH RECORDED TOTAL GAS CALIBRATION CHROMATOGRAPH CALI BRATION COMENCED LOGGIMG FROM 197mKB
ON METER FROM RKB ON 14 DECEMEBR'09 ON 14 DECEMBER' 09
1% = 100 UNITS 1 UNIT = 100 ppm
180
190
1000K
100K
20BIT 12-1/
40 4" VAREL
60 80 100 100 300 500
200
Clyst: gy-mdgy ,sft-firm,blky -sb
TYPE AO 7135
blky ,occ sb plty,tr carb mat
0.1
1
10
100
1K
10K
100K
1000K
0 5 10 15 20 0 20 40 60 80 100
S/N 4292
N/Z 7 X 14/32
specks,glauc inpt,slty ,sli-calc,
210
samples contaminated by cement
220
WOB : 5 - 10 Kl bs
RPM : 60 - 70
Coal: blk, sft firm, locc md hd, v itrous
SPM : 3 X 100 luster, w oody struct
230
Pp : 800 - 1300P
240
20 40 60 80 100
250
0 5 10 15 20
MW 1.07 Sst: clr, trnsp, trnsl, md hd-hd, vf m
VIS 53 gr, sbang-sbrnd, mod srtd, uncons, p
PV 11
260 v is por, qz, sli calc, no oil show
YP 21
GELS 5/ 9
FL 5.8
270
WOB : 5 - 10 Kl bs SOL 4
RPM : 60 - 70 pH 10. 5
SPM : 3 X 100 CL 32000
280 Coal: blk, sft firm, locc md hd, v itrous
Pp : 800 - 1300P
luster, w oody struct
290
DECEMBER 17' 2009
1000K
100K
20 40 60 80 100 100 300 500
300 Coal: blk, sft firm, locc md hd, v itrous
luster, w oody struct
0.1
1
10
100
1K
10K
100K
1000K
0 5 10 15 20 0 20 40 60 80 100
310
WOB : 5 - 10 Kl bs
RPM : 60 - 70
SPM : 3 X 100
320
Pp : 800 - 1300P
340
20 40 60 80 100
350
0 5 10 15 20
380
DECEMBER 18' 2009 MW 1.07
VIS 52
PV 13
390
YP 29
1000K
100K
GELS 8/ 10
20 40 60 80 100 100 300 500
400
FL 5.2 Coal: blk, sft firm, locc md hd, v itrous
SOL 4 luster, w oody struct
0.1
1
10
100
1K
10K
100K
1000K
0 5 10 15 20 0 20 40 60 80 100
pH 9
410
CL 40000
WOB : 5 - 10 Kl bs
RPM : 60 - 70
SPM : 3 X 100
420
Pp : 800 - 1300P Coal: blk, sft firm, locc md hd, v itrous
DECEMBER 19' 2009
luster, w oody struct
430
490
1000K
100K
10
100
1K
10K
100K
1000K
0 5 10 15 20 0 20 40 60 80 100
Sst: clr, trnsp, trnsl, md hd-hd, vf m
gr, sbang-sbrnd, mod srtd, uncons, p
510
WOB : 5 - 10 Kl bs MW 1.11 v is por, qz, sli calc, no oil show
RPM : 60 - 70 VIS 62
SPM : 2 X 120 PV 23
520
Pp : 800 - 1300P YP 36
GELS 8/ 11
FL 5
530
SOL 6
pH 9
Coal: blk, sft firm, locc md hd, v itrous
CL 46000
540
luster, w oody struct
20DECEMBER
40 20' 200980
60 100
550
0 5 10 15 20
560
WOB : 5 - 10 Kl bs MW 1.11
RPM : 70 - 80 VIS 58
SPM : 2 X 120 PV 19
570
Pp : 900 - 1000P YP 31 Sst: clr, trnsp, trnsl, md hd-hd, vf m
GELS 6/ 10 gr, sbang-sbrnd, mod srtd, uncons, p
FL 5 v is por, qz, sli calc, no oil show
580
SOL 6
pH 9
590 CL 41000
1000K
100K
20 40 60 80 100 100 300 500
600
0.1
1
10
100
1K
10K
100K
1000K
Coal: blk, sft firm, locc md hd, v itrous
0 5 10 15 20 0 20 40 60 80 100
DECEMBER 21' 2009
luster, w oody struct
610
WOB : 5 - 10 Kl bs
RPM : 70 - 80
SPM :2 X 130
620
Pp :900 - 1000Psi Clyst: gy-mdgy ,sft-firm,blky -sb
blky ,occ sb plty,tr carb mat
630 specks,glauc inpt,slty ,sli-calc
640
20 40 60 80 100
650
0 5 10 15 20 Sst: clr, trnsp, trnsl, md hd-hd, vf m
gr, sbang-sbrnd, mod srtd, uncons, p
660 v is por, qz, sli calc, no oil show
WOB : 5 - 10 Kl bs
RPM : 70 - 80
SPM :2 X 130
670
Pp :900 - 1000Psi
10
100
1K
10K
100K
1000K
0 5 10 15 20 0 20 40 60 80 100
Sst: clr, trnsp, trnsl, md hd-hd, vf m
gr, sbang-sbrnd, mod srtd, uncons, p
710
WOB : 5 - 10 Kl bs v is por, qz, sli calc, no oil show
RPM : 70 - 80
SPM :2 X 130
720 MW 1.11
Pp :900 - 1000Psi
VIS 54 Coal: blk, sft firm, locc md hd, v itrous
PV 19 luster, w oody struct
730
DECEMBER 22' 2009 YP 28
GELS 6/ 8
FL 5
740
SOL 6
pH 9
20 40 60 80 100 CL 42000
750
0 5 10 15 20 Coal: blk, sft firm, locc md hd, v itrous
luster, w oody struct
760
WOB : 5 - 10 Kl bs
RPM : 70 - 80
SPM :2 X 130
770
Pp :900 - 1000Psi
Clyst: gy-mdgy ,sft-firm,blky -sb
780 blky ,occ sb plty,tr carb mat
specks,glauc inpt,slty ,sli-calc
790
1000K
100K
10
100
1K
10K
100K
1000K
0 5 10 15 20 0 20 40 60 80 100
830
890
1000K
100K
20 40 60 80 100 100 300 500 Coal: blk, sft firm, locc md hd, v itrous
900
luster, w oody struct
0.1
1
10
100
1K
10K
100K
1000K
0 5 10 15 20 0 20 40 60 80 100
910
WOB : 5 - 10 Kl bs
RPM : 80 - 130
SPM :2 X 125
920
Shale:dkgy-gy ,md hd,sbblky -
Pp :1000 - 1200Psi sbplty ,sb fis,tr glauc,tr carb mat
specks, sdy , non sli - calc
930
940
20 40 60 80 100
950
0 5 10 15 20 Sst: clr, trnsp, trnsl, md hd-hd, vf m
gr, sbang-sbrnd, mod srtd, uncons, p
960 v is por, qz, sli calc, no oil show
WOB : 5 - 10 Kl bs
RPM : 80 - 130
SPM :2 X 125
970
Pp :1000 - 1200Psi
980
MW 1.14 Shale:dkgy-gy ,md hd,sbblky -
VIS 58
sbplty ,sb fis,tr glauc,tr carb mat
PV 18
990 specks, sdy , non sli - calc
YP 34
1000K
100K
GELS 9/ 12
20 40 60 80 100 100 300 500
FL 5
1000
SOL 6
0.1
1
10
100
1K
10K
100K
1000K
0 5 10 15 20 0 20 40 60 80 100
pH 9
Coal: blk, sft firm, locc md hd, v itrous
CL 39000
WOB : 5 - 10 Kl bs
1010
luster, w oody struct
RPM : 80 - 130
SPM :2 X 130
1020
Pp :1000 - 1200Psi
1030
1060
WOB : 5 - 10 Kl bs
RPM : 80 - 130 Sst: clr, trnsp, trnsl, md hd-hd, vf m
SPM :2 X 130 gr, sbang-sbrnd, mod srtd, uncons, p
1070
Pp :1000 - 1200Psi v is por, qz, sli calc, no oil show
1080
1090
1000K
100K
10
100
1K
10K
100K
1000K
0 5 10 15 20 0 20 40 60 80 100
v is por, qz, sli calc, no oil show
1110
1120
WOB : 5 - 10 Kl bs MW 1.14
RPM : 80 - 130 VIS 56
Coal: blk, sft firm, locc md hd, v itrous
SPM :2 X 130 PV 16
Pp :1000 - 1200Psi
1130
YP 33 luster, w oody struct
GELS 11/ 16
FL 5
1140
SOL 6
pH 9
20 40 60 80 100
CL 38000 Sst: clr, trnsp, trnsl, md hd-hd, vf m
1150
0 5 10 15 20
gr, sbang-sbrnd, mod srtd, uncons, p
v is por, qz, sli calc, no oil show
1160
WOB : 5 - 10 Kl bs
RPM : 80 - 130
SPM :2 X 130
1170
Pp :1000 - 1200Psi
1180
1000K
100K
TYPE 605 G
20 40 60 80 100 100 300 500
S/N 1613737
1200
N/Z OPEN NOZLE
0.1
1
10
100
1K
10K
100K
1000K
0 5 10 15 20 0 20 40 60 80 100
JANUARY 05' 2010 Coal: blk, sft firm, locc md hd, v itrous
1210
MW 1.09 luster, w oody struct
VIS 42
PV 9
1220
WOB : 5 - 10 Kl bs YP 19
RPM : 80 - 130 GELS 7/ 9
Sst: clr, trnsp, trnsl, md hd-hd, vf m
SPM :2 X 130 FL 6.8 gr, sbang-sbrnd, mod srtd, uncons, p
1230
Pp :1000 - 1200Psi SOL 46 v is por, qz, sli calc, no oil show
pH 9
CL 22000
1240
20 40 60 80 100
1250 Coal,blk,sft firm,loc mod hd,v itreous
0 5 10 15 20
luster,w oody struct
1260
20 40 60 80 100 100 300 500 LOSS TOTAL @1268.8 mKB Pump LCM
1300
RETURN 80% LCM 20% CUTTING
0.1
1
10
100
1K
10K
100K
1000K
0 5 10 15 20 0 20 40 60 80 100
1310
WOB : 5 - 10 Kl bs
RPM : 70 - 90 Sst: clr, trnsp, trnsl, fri - md hd, f-cgr,
94 UNITS @ 1316 mKB C1 - nC4
SPM :1 X 120
1320 sbang-sbrnd, mod w srtd, fr-gd v is
Pp : 0 Psi 78 UNITS @ 1322 mKB C1 - nC4
por, qtz, sli calc cmt, w /5 - 10% pall
y ell flour, milky w h, slow strmg,cut
1330
flour, tr oil show
1340
BLIND DRILL LOSS TOTAL @1329 mKB NO MUD
f/1329-1372 mKB RETURN
20 40 60 80 100
1350
NO MUD RETURN
0 5 10 15 20
1360
1370
WOB : 5 - 10 Kl bs
RPM : 70 - 90 1380 Sst: clr, trnsp, trnsl, fri - md hd, f-cgr,
74 UNITS @ 1382 mKB C1 - nC4
SPM :2 X 120 sbang-sbrnd, mod w srtd, fr-gd v is
Pp : 800 - 1000 Psi por, qtz, sli calc cmt, w /5 - 10% pall
1390 84 UNITS @ 1390 mKB C1 - nC4
y ell flour, milky w h, slow strmg,cut
1000K
100K
42 UNITS300
@ 1397 mKB500 C1 - i C4 flour, tr oil show
20 40 60 80 100 100
1400
48 UNITS
40 @ 60
1403 mKB C1 - i C4
0.1
1
10
100
1K
10K
100K
1000K
0 5 10 15 20 0 20 80 100
1410
JANUARY 11' 2010 LOSS TOTAL @1411 mKB NO MUD
BLIND DRILL RETURN
1420 f/1411-1440 mKB
NO MUD RETURN
1430
1440
1460
CEMENTING ENGINEERING REPORT
WELL : TT-28
LOCATION : TTM-SA1
DRILLING - 2009
CemCADE*
End of Well Report TTM-SA1
Prepared for : Jaka Sondang / Dian Permana/ Andry Sehang /Gondo Irawan/ Nataniel B.Sangka
Disclaimer Notice:
This information is presented in good faith, but no warranty is given by and Schlumberger assumes no liability for advice or recommendations made concerning results to be obtained from the
use of any product or service. The results given are estimates based on calculations produced by a computer model including various assumptions on the well, reservoir and treatment. The
results depend on input data provided by the Operator and estimates as to unknown data and can be no more accurate than the model, the assumptions and such input data. The information
presented is Schlumberger's best estimate of the actual results that may be achieved and should be used for comparison purposes rather than absolute values. The quality of input data, and
hence results, may be improved through the use of certain tests and procedures which Schlumberger can assist in selecting.
The Operator has superior knowledge of the well, the reservoir, the field and conditions affecting them. If the Operator is aware of any conditions whereby a neighboring well or wells might
be affected by the treatment proposed herein it is the Operator's responsibility to notify the owner or owners of the well or wells accordingly.
Prices quoted are estimates only and are good for 30 days from the date of issue. Actual charges may vary depending upon time, equipment, and material ultimately required to perform these
services.
Freedom from infringement of patents of Schlumberger or others is not to be inferred.
TTM-SA1-TT 28 Page 1
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
1. Abstract
Report ini untuk me-review pekerjaan cementing di sumur TTM-SA1 ( TT28 ). Termasuk method, permasalahan,
biaya, operational summary dan lesson-learned untuk sumur selanjutnya.
Kedalaman
Well Profile Ukuran Casing
Program Semen
Casing 20" @ 30 m
93 ppf K-55 BTC-R3
TTM-SA1-TT 28 Page 2
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
3. Operational Summary
No Date Field Job Type Well Location FTL # Operational Time Loss Time
1 10-Dec-10 Tapian Timur 20 in Stove Pipe TTM-SA1 TT-28 B4FL-0006 1.00 0
2 13-Dec-10 Tapian Timur 13 3/8 in Surface Casing TTM-SA1 TT-28 B4FL-00018 2.00 0
3 13-Dec-10 Tapian Timur Top up job #1 TTM-SA1 TT-28 B4FL-00019 1.00 0
4 14-Dec-10 Tapian Timur Top up job #2 TTM-SA1 TT-28 B4FL-00020 1.00 0
5 2-Jan-10 Tapian Timur 9 5/8 in Intermediate Casing TTM-SA1 TT-28 BBBA-00002 3.40 0
6 6-Jan-10 Tapian Timur 1st CaCO3 Plug TTM-SA1 TT-28 BBBA-00003 2.00 0
7 9-Jan-10 Tapian Timur 2nd CaCO3 Plug TTM-SA1 TT-28 BBBA-00004 1.00 0
8 11-Jan-10 Tapian Timur 3rd CaCO3 Plug TTM-SA1 TT-28 B1XT-00033 0.70 0
9 16-Jan-10 Tapian Timur 7 in Production Casing TTM-SA1 TT-28 B4FL-00025 2.40 0
14.50 0
4. Lesson Learned
Failure and Issue Root Cause and Action plan Recommendation for Improvement
Root
WOC of the surface sample is longer than the labCause
test : Provide Water Bath for next cement job
the lab test Temperature difference surface and down hole
Action Plan :
Good procedure of sampling the slurry
Kondisi well sebelum proses penyemenan mempunyai Caliper log reading sebesar 330 % (Reading dari caliper log sudah tidak
relevan karena caliper log hanya menggunakan satu arm dan reading sudah maximum hingga 23 in). Dari Drilling TEAM
menyarankan untuk menggunakan excess sebesar 350 %. Jika kita menggunakan excess saat itu komposisinya adalah LEAD
Slurry – 40 bbls dan Tail Slurry 60 bbls ).
Dengan kondisi well yang sudah wash out, dan caliper log reading yang tidak bisa menjadi acuan, maka kami memodifikasi dari
caliper log tersebut dan menambahkan excess sebesar 20 %. ( dari Caliper log data, OH id di 1400 menunjukkan 2 in saja , ini
terbukti dengan last casing joint stuck ). Komposisi dengan excess ini adalah LEAD Slurry 40 bbls dan Tail Slurry 80 bbls.
TTM-SA1-TT 28 Page 3
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
Proses penyemenan untuk tahap pertama berjalan dengan mendapatkan aliran balik, tidak ada loss circulation ( LiteCRETE* dan
CemNET * bekerja untuk cure loss circulation ) dilanjutkan dengan tail slurry + CemNET, tetap berjalan dengan lancar dan tidak
ada loss circulation.
LiteCRETE sample di surface temperature membutuhkan waktu yang lebih lama – Karena cement yang digunakan dalam blend
adalah sedikit ( lebih banyak waktu yang diperlukan untuk cement dan solid partikel lainnya membentuk compressive strength
nya ). Namun, sample di lapangan harus bebas dari goncangan dan getaran di sekelilingnya. Lesson learned untuk sample
disurface adalah:
1. Tempat yang aman dari Gangguan ( Goncangan dan Getaran ).
2. Water Bath ( untuk mengkondisikan temperature )
4.4.1. Centralizer
Dengan kondisi well yang wash out , centralizer dapat membantu dalam masalah wash out, Centralizer bisa membantu
dengan meningkatkan Max OD centralizer yang bisa lebih besar.
( max OD: 12”, min OD: smaller than 9 5/8” drift)
4.4.2. Mud
Perbandingan WBM dan OBM untuk optimize drilling practice dapat dilakukan. ( Schomi ).
TTM-SA1-TT 28 Page 4
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
Reviewed by:
Date:
This report is presented in good faith, but no warranty whatsoever is given and any user of this report agrees to absolve and hold
Schlumberger harmless against any consequences resulting from the use thereof
This report is based on confidential proprietary information and neither this report nor any part may be disclosed directly or indirectly
to any third party without the prior written authorization of Schlumberger
TTM-SA1-TT 28 Page 5
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
TTM-SA1-TT 28 Page 6
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
This report is presented in good faith, but no warranty whatsoever is given and any user of this report agrees to absolve and hold
Schlumberger harmless against any consequences resulting from the use thereof
This report is based on confidential proprietary information and neither this report nor any part may be disclosed directly or indirectly
to any third party without the prior written authorization of Schlumberger
TTM-SA1-TT 28 Page 7
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
400 20 5000
360 18 4500
320 16 4000
280 14 3500
Temperature (°F)
200 10 2500
160 8 2000
120 6 1500
80 4 1000
40 2 500
0 0 0
0:00 5:00 10:00 15:00 20:00
Time (HH:MM)
CHANDLER Test File Name: SN 131-0014 PERTAMINA TT 28 13 3-8 in tapian timur at 89 F.tst Page 1
ENG INEERING
TTM-SA1-TT 28 Page 8
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
This report is presented in good faith, but no warranty whatsoever is given and any user of this report agrees to absolve and hold
Schlumberger harmless against any consequences resulting from the use thereof
This report is based on confidential proprietary information and neither this report nor any part may be disclosed directly or indirectly
to any third party without the prior written authorization of Schlumberger
TTM-SA1-TT 28 Page 9
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
400 100
360 90
320 80
280 70
240 60
Temperature (°F)
Consistency (Bc)
200 50
160 40
120 30
80 20
40 10
0 0
0:00 2:00 4:00 6:00
Time (HH:MM)
CHANDLER Test File Na me: S ingle cell-0655 pertamina tapian t imur.tst Page 1
ENG IN EER I NG
TTM-SA1-TT 28 Page 10
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
TMF 6.46 gps ( 0.5604 m3/m3 ) TMF 5.055 gps ( 0.5864 m3/m3 )
Density 1.4 SG Density 1.65 SG (13.76 ppg) Density 1.9 SG
Yield 1.54 ft3/sk ( 0.9804 mTon/m3) Yield 1.15 ft3/sk ( 1.3068 mTon/m3)
Test schedules;
Rheology, Fluid loss, Thickening Time and Free Water tests as per API 10B/ISO 10426-1 (2003)
TT Schedules : on Fly for Lead slurry & BM 3:30 hrs for Tail slurry
Reviewed by:
Date:
This report is presented in good faith, but no warranty whatsoever is given and any user of this report agrees to absolve and hold
Schlumberger harmless against any consequences resulting from the use thereof
This report is based on confidential proprietary information and neither this report nor any part may be disclosed directly or indirectly
to any third party without the prior written authorization of Schlumberger
TTM-SA1-TT 28 Page 11
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
UCA CHART
400 20 5000
360 18 4500
320 16 4000
280 14 3500
Compressive Strength (psi)
Transit Time (microsec/in)
240 12 3000
Temperature (°F)
200 10 2500
160 8 2000
120 6 1500
80 4 1000
40 2 500
0 0 0
0:00 5:00 10:00 15:00 20:00
Time (HH:MM)
TTM-SA1-TT 28 Page 12
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
TMF 7.37
gps (0.5113 m3/m3) of blend TMF 8.20 gps (0.6183 m3/m3)
Density 1.2 SG Density SG 1.4 Density 1.6 SG
Yield 1.93
ft3/sk (0.8321 mTon/m3) of blend Yield 1.77 ft3/sk (0.8494 mTon/m3)
Rheology, r1b1, f=1
AM AC AM AC AM AC
300 31 29 300 rpm 93 70 300 rpm 30 43
200 28 25 200 rpm 66 49 200 rpm 22 32
100 22 20 100 rpm 38 32 100 rpm 13 22
60 18 17 60 rpm 25 19 60 rpm 10 18
30 15 14 30 rpm 14 12 30 rpm 5 15
6 9 9 6 rpm 6 5 6 rpm 3 13
3 7 7 3 rpm 3 3 3 rpm 2 12
10" gel strength 8 7 10" gel strength 4 4 10" gel strength 2 14
10' gel strength 15 10 10' gel strength 25 20 10' gel strength 30 35
YP (lbf/100ft2) 5.5 11.5 YP (lbf/100ft2) 10.5 13 YP (lbf/100ft2) 4.5 11.5
PV (cp) 31.5 31.5 PV (cp) 82.5 57 PV (cp) 25.5 31.5
Fluid loss (ml/30 mn) 14 Fluid loss (ml/30 mn) 40
Free water (ml/250 ml) Nil Free water (ml/250 ml) Nil
Thickening Time Tests
40 BC 6 : 08 hr:mn 40 BC 5 : 43 hr:mn
70 BC 6 : 26 hr:mn 70 BC 5 : 57 hr:mn
100 BC 6 : 43 hr:mn 100 BC 6 : 12 hr:mn
Compressive Strength at BHST
WOC (500 psi ) Inprogress hr:mn
C.S at 24 hrs:mn psi
Surface Tests
inprogress hrs set soft 16 hrs set soft
hrs hard set 18 hrs hard set
TT, rheology, FL, FW as per API 10B/ISO104261- 2003
..\..\..\..\Lab Procedures\JET_37-Cementing.pdf
This report is presented in good faith, but no warranty whatsoever is given and any user of this report agrees to absolve and hold
Schlumberger harmless against any consequences resulting from the use thereof
This report is based on confidential proprietary information and neither this report nor any part may be disclosed directly or indirectly
to any third party without the prior written authorization of Schlumberger
TTM-SA1-TT 28 Page 13
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
Thickening
Time
TTM-SA1-TT 28 Page 14
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
6.62
TMF gps (0.5682 m3/m3)
Density 1.2 SG Density
1.65 SG
1.56
Yield ft3/sk (0.9667 mTon/m3)
Rheology, r1b1, f=1
AM AC AM AC
300 31 29 300 rpm 76 85
200 28 25 200 rpm 54 58
100 22 20 100 rpm 29 34
60 18 17 60 rpm 19 20
30 15 14 30 rpm 10 12
6 9 9 6 rpm 4 3
3 7 7 3 rpm 2 2
10" gel strength 8 7 10" gel strength 3 3
10' gel strength 15 10 10' gel strength 29 10
YP (lbf/100ft2) 5.5 11.5 YP (lbf/100ft2) 5.5 8.5
PV (cp) 31.5 31.5 PV (cp) 70.5 76.5
Fluid loss (ml/30 mn) 110
Free water (ml/250 ml) Nil
Thickening Time
40 BC 5 : 36 hr:mn
70 BC 5 : 54 hr:mn
100 BC 6 : 08 hr:mn
Compressive Strength at BHST Surface test
WOC (500 psi ) Inprogress hr:mn inprogress hrs soft set
C.S at 24 hrs:mn psi hrs hard set
TT, rheology, FL, FW as per API 10B/ISO104261- 2003
..\..\..\..\Lab Procedures\JET_37-Cementing.pdf
This report is presented in good faith, but no warranty whatsoever is given and any user of this report agrees to absolve and hold
Schlumberger harmless against any consequences resulting from the use thereof
This report is based on confidential proprietary information and neither this report nor any part may be disclosed directly or indirectly
to any third party without the prior written authorization of Schlumberger
TTM-SA1-TT 28 Page 15
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
TTM-SA1-TT 28 Page 16
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
1 10-Dec-09 20 in Stove Pipe 12816.00 B4FL00017 Pumping Hour yang lebih lama
2 13-Dec-09 13 3/8 in 25560.92 B4FL-00018 Menghindari loss circulation, fluid loss system yang bagus
3 13-Dec-09 Top up job 1760.00 B4FL-00019 Penyemenan hingga semen sampai ke permukaan
4 14-Dec-09 Top up job 1772.00 B4FL-00020 Penyemenan hingga semen sampai ke permukaan
5 1-Jan-10 9 5/8 in 40,469.17 BBBA-0002 Perubahan TD menjadi lebih dalam
6 6-Jan-10 Plug loss job 1 4,938.00 BBBA-0003 Cure loss circulation
7 8-Jan-10 Plug loss job 2 2,613.00 BBBA-0004
8 11-Jan-10 Plug loss job 3 2,205.60 B1XT-00033
9 16-Jan-10 7 in 99,503.50 B4FL-00025 LiteCRETE* + cemNET*
TTM-SA1-TT 28 Page 17
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
7. Job Calculation
7. 1 Job Calculation (20 in Stove Pipe).
Stove Pipe Cement Job DATE : 10-Dec-09
RIG : JML#03
CEMENT FORMULATION
GAS TIGHT SLURRY (SG 1.40) - CEMENTED FROM SHOE UP TO DV
LEAD TAIL
STICK-UP BTC 0.63 mtr CLASS "G" INDO + 0 % BWOC D151 0
+ 0.000 GPS D/W 4.977
+ 0.00 GPS D047 0.01
+ 0.00 % BWOC D020 0
RT 0 mtr + 0.000 GPS D145A 0
+ 0.00 GPS D081 0
+ 0.00 % BWOC D095
24" CP
115.4 mtr
TTM-SA1-TT 28 Page 18
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
24" CP
115.4 mtr
Float Collar
1154.21 m
1313 FC -35 mtr
MATERIALS PREPARATION (CEMENT)
PRODUCT
LEAD TAIL
PIT
MIXING FLUID,bbls #DIV/0! 110
DISPLACEMENT m3 0.0
DISPLACE RATE 1600 LPM CMT-G NEAT,mT #DIV/0!
Sxs #DIV/0! 900.8
DISPLACE VOL. 93.43 bbl D/W bbl #DIV/0! 93.7
D124 mT #DIV/0!
D047 mT #DIV/0! 9.008
D153 Lb #DIV/0! 127.0
D145A GAL #DIV/0! 135.1
D193 GAL #DIV/0! 450.4
S001 Lb #DIV/0! 84.7
MAX. DISPLACE + 1/2 SHOE TRACK
93.43 + 3 = 96 bbl
TTM-SA1-TT 28 Page 19
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
RIG : JML#03
CEMENT FORMULATION
GAS TIGHT SLURRY (SG 1.40) - CEMENTED FROM SHOE UP TO DV
LEAD TAIL
STICK-UP BTC 0.63 mtr CLASS "G" INDO + 0 % BWOC D151 0
+ 0.000 GPS D/W 4.977
+ 0.00 GPS D047 0.01
+ 0.00 % BWOC D020 0
RT 0 mtr + 0.000 GPS D145A 0
+ 0.00 GPS D081 0
+ 0.00 % BWOC D095
24" CP
115.4 mtr 17.06 m³ 53.32 m³
TTM-SA1-TT 28 Page 20
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
Float Collar
1154.21 m
1313 FC -35 mtr 292.6 80 bbl 212.6
MATERIALS PREPARATION (CEMENT) 391 Sx 1038
PRODUCT 43.4 bbl 115.2
LEAD TAIL
PIT 47.0 bbl 124.9
MIXING FLUID,bbls 86 172
DISPLACEMENT m3 0.0
DISPLACE RATE 1600 LPM CMT-G NEAT,mT 23.5 51881
Sxs 551.9 1428.6
DISPLACE VOL. 293.00 bbl D/W bbl 80.1 158.6 286.2
DOWELL PUMP: D124 mT 2.4 5188.1
D047 mT 5.5 14.3 33.6 6.711
D153 Lb 103.8 134.3 238.1 9.522
D145A GAL 193.2 571.4 764.6 14.427 3.607
D193 GAL 276.0 928.6 1204.5 22.727 5.682
S001 Lb 622.6 402.9 1025.4 20.509
MAX. DISPLACE + 1/2 SHOE TRACK
293.00 + 3 = 296 bbl
TTM-SA1-TT 28 Page 21
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
RIG : JML-3
CEMENT FORMULATION
GAS TIGHT SLURRY (SG 1.40) - CEMENTED FROM SHOE UP TO DV
LEAD TAIL
STICK-UP BTC 0.63 mtr CLASS "G" INDO + 0 % BWOC D151 70
+ 0.000 GPS D/W 14.879
+ 0.00 GPS D047 0.01
+ 0.00 % BWOC D020 5
RT 0 mtr + 0.000 GPS D145A 0.1
+ 0.00 GPS D081 0.05
+ 0.00 % BWOC D095 0.64
24" CP
115.4 mtr
TTM-SA1-TT 28 Page 22
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
RIG : JML-3
CEMENT FORMULATION
GAS TIGHT SLURRY (SG 1.40) - CEMENTED FROM SHOE UP TO DV
LEAD TAIL
STICK-UP BTC 0.63 mtr CLASS "G" INDO + 0 % BWOC D151 70
+ 0.000 GPS D/W 14.879
+ 0.00 GPS D047 0.01
+ 0.00 % BWOC D020 5
RT 0 mtr + 0.000 GPS D145A 0.1
+ 0.00 GPS D081 0.05
+ 0.00 % BWOC D095 0.64
1350 mtr
13" 3/8 Casing T.T 40 BC = 0:00 hrs 4:10
YIELD = 0.0000 cuft/sx 2.91
SG = 0.00 SG 1.6
TMF = 0 GPS 18.172
SLURRY VOLUME
24" CHH 16.5 mtr LEAD TAIL
SLURRY bbl 60 bbl
Sx of Cement sx 116.0 sx
24" CP
115.4 mtr
1313 1370FC
mtr -35 mtr
MATERIALS PREPARATION (CEMENT)
PRODUCT
LEAD TAIL
PIT
MIXING FLUID,bbls 10 53
DISPLACEMENT m3 0.0
DISPLACE RATE 1600 LPM CMT-G NEAT,mT #DIV/0!
Sxs #DIV/0! 122.9
DISPLACE VOL. 64 bbl D/W bbl #DIV/0! 43.6
Under Displace 2 bbl D151 Lbs #DIV/0! 8089
62 bbl D047 GAL #DIV/0! 1
D020 GAL #DIV/0! 578
D145A GAL #DIV/0! 12
D081 GAL #DIV/0! 6.1
D095 GAL #DIV/0! 74
MAX. DISPLACE + 1/2 SHOE TRACK
64.00 + 3 = 67 bbl
TTM-SA1-TT 28 Page 23
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
Date : 28-Jan-10
Density 1.6 SG
Yield 2.91 Cf/sx
Spacer Ahead Base Fluid 14.879 gps
1087.4 m Tot. Mixing Fluid 18.172 gps
CSG Capacity
OH 8.5in 0.07018 bbl/ft
9 5/8 Csg 36 ppf 0.07731 bbl/ft
TTM-SA1-TT 28 Page 24
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
Date : 28-Jan-10
Wt of casing:
9 5/8 : 36 ppf Mengetahui
7 : 23 ppf
Sclhumberger Representative Company Man Representative
Annular Vol:
9.625 csg - 7 csg 0.02971 bbl/ft
8.5 hole - 7 csg 0.02259 bbl/ft
Arif Wibowo Herman Siagian
Casing Capacity
7 Csg 0.03936 bbl/ft
8 1/2 OH 0.07018 bbl/ft
TTM-SA1-TT 28 Page 25
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
Well : TT-028
Date : 28-Jan-10
1. Slurry : Excess
Ann Vol in CSG 9 5/8 " = 431.5 m x 0.0297 bbl/ft x 1 = 42.06 Bbls
Dead Volume Bacth mixer = 3.00 Bbls
Total Vol = 45.1 Bbls
Landing Collar
1414.90 m 3. MUDPUSH II : 30 Bbls (Dead Volume 3 bbls)
TD
1440.0 m
Wt of casing:
9 5/8 : 36 ppf Mengetahui
7 : 23 ppf
Sclhumberger Representative Company Man Representative
Annular Vol:
9.625 csg - 7 csg 0.02971 bbl/ft
8.5 hole - 7 csg 0.02259 bbl/ft
Arif Wibowo Herman Siagian
Casing Capacity
7 Csg 0.03936 bbl/ft
8 1/2 OH 0.07018 bbl/ft
TTM-SA1-TT 28 Page 26
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
TTM-SA1-TT 28 Page 27
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
TTM-SA1-TT 28 Page 28
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
TTM-SA1-TT 28 Page 29
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
TTM-SA1-TT 28 Page 30
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
TTM-SA1-TT 28 Page 31
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
TTM-SA1-TT 28 Page 32
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
TTM-SA1-TT 28 Page 33
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
TTM-SA1-TT 28 Page 34
Cementing End of Well Report
Client : Pertamina
Well : TTM-SA1
String : End of Well Report
District : Balikpapan
Country : Indonesia
TTM-SA1-TT 28 Page 35
Cementing End of Well Report
TTM-SA1 ( TT 28 ) 20" Stove Pipe 13 3/8 " Surface Casing Top Up Top Up 9 5/8 " Intermediate CaCO3 Cement Plug 7" Production Casing
Top Up Top Up Lead Tail Plug #1 Plug #2 Plug #3 1st Stage 2nd Stage
Date of Job 10-Dec-09 13-Dec-09 13-Dec-09 14-Dec-09 2-Jan-10 6-Jan-10 9-Jan-10 11-Jan-10 16-Jan-10
Cement Type G Neat G Neat G Neat G Neat Blend D124 G Neat G Neat + 100% CaCO3 LiteCRETE* Blend D124 Blend D124
Density SG 1.9 1.9 1.9 1.9 1.65 1.90 1.6 1.6 1.6 1.4 1.6 1.65
BHST ( F ) 80.0 89.0 80.0 80.0 135.0 135.0 151.0 151.0 151.0 151.0 151.0 151.0
BHCT ( F ) 80.0 85.0 80.0 80.0 97.0 97.0 118.0 118.0 118.0 114.0 114.0 114.0
MD ( m ) 30.0 198.0 50.0 50.0 1196.0 1196.0 1309.0 1370.0 1440.0 1440.0 1440.0 1440.0
TVD ( m ) 30.0 198.0 50.0 50.0 1196.0 1196.0 1309.0 1370.0 1440.0 1440.0 1440.0 1440.0
DV depth ( m )
Pumping Time (hrs) 1.0 2.0 1.0 1.0 3.4 2.0 1.0 0.7 2.4
Fluid Loss NA NA NA NA 150.0 40.0 NA NA NA 14.0 40.0 150.0
Compressive strength 24hr ( psi ) 1100.0 2100.0 1100.0 1100.0 2800.0 250.0 250.0 250.0 3000.0 2600.0
KSQR Risk Assesment Green Green Green Green Green Green Yellow Yellow Yellow Green Green Green
Composition UOM Lead Tail Lead Tail 2nd Stage
D145 A ( Dispersant ) gps 0.150 0.250 0.150 0.100 0.100 0.100 0.200 0.250 0.250
D047 ( Foam Preventer ) gps 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.050 0.010 0.010
D155 ( Bonding Additive ) gps 1.000 1.000
D193 ( Fluid Loss Additive ) gps 0.500 0.400 0.650 0.250 0.550 0.400
D081 ( Retarder ) gps 0.050 0.050 0.050
D153 ( Gelling Agent ) %BWOC 0.150 0.300 0.150 0.220 0.300 0.300
Spacer ( Mud Push ) gal 42.000
D020 ( Extender ) lb/bbl 5.500 5.000 5.000 5.000
D124 ( extender ) %BWOC 10.000 10.000
D095 ( cemNET ) lb/bbl 2.000 2.000
S001 (Accelerator) %BWOC 0.100 0.300 0.300 1.200 1.700 1.800
Yield ft3/sxs 1.140 ft3/sxs 1.150 ft3/sxs 1.140 ft3/sxs 1.140 ft3/sxs 1.540 ft3/sxs 1.150 ft3/sxs 3.390 ft3/sxs 3.390 ft3/sxs 3.390 ft3/sxs 1.860 ft3/sxs 1.770 ft3/sxs 1.550 ft3/sxs
Total Material sxs Lead and Tail Lead Tail 2nd stage
D145 A ( Dispersant ) gal 135.100 353.40 20.000 12.000 12.700 152.90
D047 ( Foam Preventer ) gal 3.000 9.000 0.500 0.500 34 2.000 1.000 1.300 31.70
D155 ( Bonding Additive ) gal 474.00
D193 ( Fluid Loss Additive ) gal 450.400 1155 410.00
D081 ( Retarder ) gal 9.600 5.800 6.400 491.00
D153 ( Gelling Agent ) lbs 231.000 359 178.00
Spacer ( Mud Push ) gal 1260.000 2100 3360.00
D020 ( Extender ) lbs 200.000 275.000 902.000 545.000 598.500 400.00
D124 ( extender ) lbs 5292.000 3919.80
LiteCRETE bbls 43.00
D095 ( cemNET ) lbs 245.17
S001 (Accelerator) lbs 84.700 1339.000 491.00
Cost Lead and Tail
D145 A ( Dispersant ) 2026.500 5301.00 300.000 180.000 190.500 2293.50
D047 ( Foam Preventer ) 66.00 198.00 11.00 11.00 748.00 44.00 22.00 28.60 697.40
D155 ( Bonding Additive ) 4740.00
D193 ( Fluid Loss Additive ) 6530.80 16747.50 5945.00
D081 ( Retarder ) 192.000 116.000 128.000 9820.00
D153 ( Gelling Agent ) 1732.50 2692.50 1335.00
Spacer ( Mud Push ) 252.000 420.00 672.00
D020 ( Extender ) 200.00 275.00 902.00 545.00 598.50 400.00
D124 ( extender ) 6350.40 4703.76
LiteCRETE bbls 18139.44
D095 ( cemNET ) lbs 34820.27
S001 (Accelerator) 121.12 1914.77 702.13
Pumping Hour Charge 1750.00 3500.00 1750.00 1750.00 0.00 3500.00 1750.00 1260.00 4235.00
Set Up Charge 11000.00 11000.00 0.00 0.00 0.00 0.00 0.00 0.00 11000.00
Total COST 12816.00 25560.92 1761.00 1761.00 34449.17 4938.00 2613.00 2205.60 99503.50
FTL Number B4FL-00006 B4FL-00018 B4FL-00019 B4FL-00020 BBBA-00002 BBBA-00003 BBBA-00004 B1XT-00033 B4FL-00025
Price
D145 A ( Dispersant ) 15.000
D047 ( Foam Preventer ) 22.000
D155 ( Bonding Additive ) 10.000
D193 ( Fluid Loss Additive ) 14.500
D081 ( Retarder ) 20.000
D153 ( Gelling Agent ) 7.500
Spacer ( Mud Push ) 0.200
D020 ( Extender ) 1.000
D124 ( Extender ) 1.200
LiteCRETE 421.848
D095 ( cemNET ) 142.025
S001 (Accelerator) 1.430
Pumping Hour 1750.000
DIRECTIONAL DRILLING &
MEASUREMENT REPORT
WELL : TT-28
LOCATION : TTM-SA1
DRILLING - 2009
EWLPP REPORT
WELL : TT-28
LOCATION : TTM-SA1
DRILLING - 2009
WELL PROGRAM
WELL : TT-28
LOCATION : TTM-SA1
DRILLING - 2009