Sei sulla pagina 1di 2

Chapter 10 Project Monitoring: Problems:

NOTE: Do this work on an MS Excel Spreadsheet - Include the


Questions.
1 (p. 466): Find the schedule and cost variances for a project that has
an actual cost as month 22 of $540,000, a scheduled cost of $523,000,
and an earned value of $535,000.
Show work and Answers on an Excel spreadsheet:
Please find the detailed answer as follows:
BCWP = Budgeted cost of work performed = (Earned Value)
ACWP = actual cost of work performed
BCWS = budgeted cost of work scheduled
Schedule Variance = BCWP - BCWS
CV = BCWP - ACWP
BCWP = $535,000
ACWP = $540,000
BCWS = $523,000
Schedule variance: 535,000 - 523,000 = $12,000
Cost variance: 535,000 - 540,000 = -$5,000
2 (p. 466): A sales project at mon5 had an actual cost of $34,000, a
planned cost of $42,000, and a value completed of $39,000. Find the
cost and schedule variances and the CPI and SPI.
Show work and Answers on an Excel spreadsheet:
Given actual cost or AC = 34,000, planned cost or PV = 42,000, and
value completed or earned value (EV) = 39,000
Cost Variance (CV)
CV = EV AC
CV = 39,000 34,000 = 5,000
Schedule Variance (SV)
SV = EV PV
SV = 39,000 42,000 = 3,000
Cost Performance Index (CPI)
The cost efficiency ratio of earned value to actual costs (CPI = EV/AC)
In PMPlan, the CPI is used to calculate Estimate at Completion (EAC)
(EAC = BAC/CPI)
CPI = EV/AC
CPI = 39,000/34,000 = 1.15
Schedule Performance Index (SPI)
The schedule efficiency ratio of earned value accomplished against
planned value (SPI = EV/PV). The SPI
describes what portion of the planned schedule was actually
accomplished.
SPI = EV/PV

SPI = 39,000/42,000 = 0.93


7 (p. 466): Given an activity in an advertising project whose planned
cost was $12,000 but actual cost to date is $10,000 so far and the
value completed is only 70 percent, calculate the cost and schedule
variances. Will the client be pleased or angry? Explain.
Schedule Variance = Earned Value - Planned Value = 12000*70% 12000 = -$3600
Cost Variance = Earned Value - Actual Cost = 12000*70% - 10000 = $1600
No, the client will not be please as the variances indicate "Overbudget"
for the client. At the same time, the actual value derived is less than
the valued planned,

Potrebbero piacerti anche