Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Reading 18 Worksheet-12
My Pre-exam Self Study Notes
25th March 2015
Understanding APIICP653
Reading 8 Worksheet-05 Part 2a of 2
My Pre-exam Self Study Notes
26th February 2015
AST Tanks
AST Tanks
http://allhotkeys.com/adobe_acrobat_reader_hotkeys.html
http://en.wikipedia.org/wiki/Table_of_keyboard_shortcuts
http://help.adobe.com/en_US/acrobat/using/WS58a04a822e3e50102bd615109794195ff-7aed.w.html
API Recommended Practice 575, Inspection of Atmospheric and LowPressure Storage Tanks, Third Edition, April 2014
API Recommended Practice 577 Welding Inspection and Metallurgy,
Second Edition, December 2013
API Standard 650, Welded Tanks for Oil Storage, Twelfth Edition, March
2013 with Addendum 1 (September 2014), Errata 1 (July 2013), and
Errata 2 (December 2014).
API Recommended Practice 651, Cathodic Protection of Aboveground
Petroleum Storage Tanks, Fourth Edition, September 2014.
API Recommended Practice 652, Lining of Aboveground Petroleum
Storage Tank Bottoms, Fourth Edition, September 2014
API Standard 653, Tank Inspection, Repair, Alteration, and
Reconstruction, Fifth Edition, November 2014.
http://independent.academia.edu/CharlieChong1
http://www.yumpu.com/zh/browse/user/charliechong
http://issuu.com/charlieccchong
http://greekhouseoffonts.com/
Open Books
Q1. A welder qualified in 6G position using SMAW process E-7018 (F-4 filler
metal) without backing may be qualified to weld for which of these during
production?
A) Only F1, F2, F3, & F4 filler metals without backing & F4 filler metal with
backing
B) Only F1, F2, F3, & F4 filler metals with backing & F4 filler metal without
backing
C) Only F1, F2, F3 filler metals with backing & F4 filler metal without backing
D) Only F1, F2, F3, & F4 filler metals with backing
Answer: B (ASME IX, QW-404.15, QW-433)
Q 2. Per ASME IX rules, a PQR coupon at 1.500 inches thick using SMAW
process qualifies a WPS for what thickness range?
A) 3/16 to 1.5 inches
B) 3/16 to 3 inches
C) 3/16 to 6 inches
D) 3/16 to 8 inches
Answer: D (ASME IX Table QW-451.1) Qualified thickness range = 3/16 to 8 inches
PQR Sample
Q3. What are the correct number and type of guided bend tests required
when evaluating a PQR (44.5 mm test plate) for compliance to ASME IX?
Select the statement below best summarizing the review as per ASME IX
requirements
A) The 2 face & 2 root bends are allowed and the maximum allowed defect
open to the surface is 3 mm. Therefore Root Bend # 2 with 3.5 mm of
porosity must be rejected
B) The 4 side bends option may be used in lieu of 2 face bends + 2 root
bends & a maximum allowed defect open to surface = 3 mm, so only Root
Bend # 2 is rejectable
C) The 2 face & 2 root bends are allowed & maximum allowed defect open to
surface is 3 mm (except for cracks). Therefore Root Bend # 2 & Face
Bend # 2 are rejectable
D) The 4 tests must be rejected because 4 side bends are mandatory, and
therefore the Root bend # 2 result (although rejectable per ASME IX) is
meaningless.
Ans: D (Ref: API 577, Pg 83 & APP. C, ASME IX, QW-160, QW-163, Table QW-451
Comment:: only root bend #2 is acceptable. (suggested answer)
Q4. What is the correct number & results for tensile testing performed on a
test plate that was verified to be A283 Gr. C having a thickness of 44.5
mm. Select the statement below best summarizing the review as per
ASME IX requirements.
A) 4 tensile tests are needed & results on specimens 3 & 4 do not meet
ASME IX reqmts
B) 2 tensile tests are needed & results on specimen 3 do not meet ASME IX
requirements
C) 4 tensile tests are needed & results on specimen 3 do not meet ASME IX
requirements
D) 2 tensile tests are needed & results on specimens 3 and 4 do not meet
ASME IX reqmts
Ans: C (Ref: API 577, APP. C, ASME IX, QW-151.1.b/d, QW-153, & Table
QW-451)
Note: Tensile specimen # 3 is 250 psi under the 95% rule for BM failures per
QW-153.d, i.e., Base metal failures may fail at 95% of the required tensile
strength.
Comments: Answer could be B?
Charlie Chong/ Fion Zhang
Q5. What is the essential wire required (assume film side IQI was used) for
radiography on a shell insert plate 1.500 inches thick in the as welded
condition?
A) Essential Wire # 8 is required
B) Essential Wire # 9 is required
C) Essential Wire # 10 is required
D) Essential Wire # 11 is required
Answer = C
Q6. A single wall exposure technique was used to make a radiograph using a
Cobalt-60 source. The minimum permitted density in the area of interest per
ASME V code is:
A) 1.3
B) 1.8
C) 2.0
D) None of these are correct
Answer: C (Reference: ASME V, Article 2, T-282.1) Cobalt-60 = gamma
radiation
Q7. When performing MT examination of welds using prod method, what is
the minimum recommended and maximum required prod spacing specified in
the ASME V code?
A) 2 to 8 inches
B) 3 to 8 inches
C) 4 to 8 inches, whenever t = in or less
D) No minimum exists, but the maximum = 8 inches if the technique is
acceptable to Inspector
ANS: B
Charlie Chong/ Fion Zhang
Q8. A stainless steel tank shell weld is being examined by LPE. What is the
minimum ASME V Code required penetrant dwell time for the examination
at a temperature of 48F (9C)?
A) 10 minutes for plates, 5 minutes for welds as a minimum Dwell time
= 10 minutes
B) 5 minutes for plate, 10 minutes for welds as a minimum Dwell time =
5 minutes
C) 5 minutes for plate and for welds as a minimum Dwell time = 5
minutes
D) None of the above is correct
Ans: D (ASME V, Art. 6, Table T-672)
Note 1
Plate= dwell time (10 mins) is doubled to 20 mins
Weld= dwell time ( 5 mins) is doubled to 10 mins
Q9. New shell insert plate is to be installed into an existing tank shell (both = 1.5
inches thick) Insert plate material and existing shell material are both A516 Gr.
65 plate normalized, killed, using fine Grain Practice. What is the minimum
design metal temperature (in F) that does not require impact testing for this
material and given thickness?
A. -12F
B. 20F
C. 42F
D. 50F
Answer = B
10. Using API 650 Figure 5-7b above & given the following information (1inch thick shell plate with 1-inch thick reinforcement pad), what is the required
manway nozzle thickness and the fillet weld size A for a 24-inch manway?
A) inch thick manway nozzle, and weld A = 3/8 inch fillet weld
B) 7/16 in thick manway nozzle, and weld A = 7/16 inch fillet weld
C) inch thick manway nozzle, and weld A = 7/16 inch fillet weld
D) 7/16 in thick manway nozzle, and weld A = 3/8 inch fillet weld
Ans = C (API 650, Fig 5-7b & Table 5-7b t & T row 1 in. Col 2 = in., Col 5 =
7/16 in.
My answer = B
Q12. What is the minimum dimension and minimum required corner radius for
a
replacement shell insert plate in a bottom shell course that is 1.750 inches
thick?
A) 21 inches is the minimum dimension and there must be at least a 10.5 inch
radius
B) 12 inches is the minimum dimension and there must be at least a 6 inch
radius
C) 21 inches is the minimum dimension and there must be at least a 2
inch radius
D) 8.75 inches (minimum) and there must be at least a 2 inch radius
Ans = A (653, Par. 9.2.2.1 & Fig 9.1) 12 in. or 12t (use greater = 21 in.) and
minimum radius = Dimension R = Greater of 6 inches or 6 t In this case,
its a 10.5 inch radius.
Q17. What are the required spacings between an existing nozzle (NPS 12 with
A)
B)
C)
D)
reinforcement) located to the left side of a proposed hot tap nozzle (NPS 12 with
reinforcement also) and a vertical shell weld (located to the right side of the
proposed hot tap location? Information: UT scan of proposed hot tap location in
first shell course revealed no laminations. A vertical weld to the right of proposed
hot tap location = 100% radiographed and no horizontal welds are in the
immediate area. Tank diameter is 90 feet and the shell plate on the first course in
the proposed area of the hot tap measures 0.750 inches. Formula = square root of
RT is used.
Spacing = 10 in. between both nozzle repad (and hot tap nozzle repad) and the
vertical weld
Spacing = 20 in. between nozzle repad (and hot tap nozzle repad) and 12 in. (?) to
vertical weld
Spacing = 28 in. between both nozzle repad (and hot tap nozzle repad) and the
vertical weld
Spacing = 10 inches between nozzle repad (and hot tap nozzle repad) & 6 in. to
vertical weld
API650: Figure 5.6Minimum Weld Requirements for Openings in Shells According to 5.7.3
Q21. For a tank out of service where an internal tank bottom settlement
survey is being performed, how many internal settlement survey points on the
tank floor must be checked given the additional information below and how
many diametrical lines will result from the survey?
Additional info: Tank diameter = 200 feet & circumference = ( D) or 628 feet
A) 101 survey points based upon 10 evenly spaced diametrical lines
B) 180 survey points based upon 20 evenly spaced diametrical lines
C) 221 survey points based upon 20 evenly spaced diametrical lines
D) None of these are correct
Answer: D (Ref: API 653, Figure B.2 & Note Section 12.5.1.2 rule)
Q22.
Q22. At an area near the very center of the 200 foot diameter tank during one
of many survey points (see the previous question), you found a deep
depression in the tank floor (having single pass welds) measuring 5.00
inches deep having a 15 foot radius. Evaluate depression values given
additional information below and select the best possible answer:
Additional info: Management position is that any depression found in great
excess of API 653 graph values will be repaired, and NO stress analysis
alternatives be allowed. This Management position is because the tank is
located near a river with a high water table and a previous disaster
occurred when a similar service tank floor failed (cracked). The radius of
inscribed circle in the depression measured exactly 15 feet. The length &
width of the depression was 40 feet by 30 feet or elliptical in shape. The
tank is 25 years old and every five years an internal inspection is done.
A. I would reject the depression because the formula and the graphic both
confirm that anything greater than 3.7 inches in 10 feet (BB = 0.37R
formula) is above the allowance, and I would also recommend removal of
the bottom for soil or geotechnical investigation
B. I would accept the depression based on BB = 0.37R formula which allows
5.55 inches, but I would recommend repairs at the earliest opportunity and
request a shortened inspection interval
C. I would reject the depression based on Figure B.10 graph and call for
repairs.
D. I would recommend a rigorous stress analysis assessment as per API 653
Ans: B (API 653, Annex B, Figure B.10 & Para. B3.3 & Formula BB = 0.37R)
Q23. At an area near the outer edge of a 160 foot diameter tank, a deep
depression in the floor that was obviously edge settlement with R
measuring exactly 5 feet from Breakover point and Value Bew = 4.00
inches deep (65% of the allowed 6.125 inches per the graph). Bottom lap
welds were noted as approximately parallel to shell per Fig. B.11.
Evaluate the depression given the additional information below & select
the best possible answer:
Added info: Management position = any depression exceeding API 653
values will be repaired. NO stress analysis alternatives are allowed.
Tank = 35 yrs old & Internal insp intervals = 10 yrs.
Q 25. Using API 653 rules to determine Inspection intervals, when is the next
required UT thickness inspection date after the last inspection in January
2011 determined that a .400 inch thickness remained in the bottom shell
course and 0.260 inches = t min, and given all of the other information in
question # 24 above.
A) January 2011 + 5 years (the required maximum interval) = January 2016
B) January 2011 + 8.75 yrs (the maximum required interval) = October 2019
C) January 2011 + 15 years (the required maximum interval) = January 2026
D) None of these is correct per API 653 rules
Answer = B
Corrosion rate=0.008/yr
Interval = RCA/2N = 0.400-0,260/(2x0.008) = 8.75years
Q28. What is hydrostatic test height of a tank built to API 650, 7th Edition,
Basic STD, 90 foot diameter, 50 feet total height, with a 48 feet maximum
design fill height, specific gravity = 1.0, five shell courses each at 10 feet high,
material A-516 Gr. 70 & t min required on the first shell course (to be used in
calcs) is 0.366 in.?
Additional information relevant to the pressure test: There is no overflow on
the tank & the maximum height to the top rim = 50 feet, 0 inches from the tank
bottom
A) 44.9 feet
B) 47.9 feet
C) 48 feet
D) 50 feet
Answer: H = StEtmin /(2.6xD) +1 = 52.615 used 50, ANS:D
St = 33000psi, E= 1
Closed Books
Q31. The maximum dimension along the shell for a welded on patch plate in
critical zone is:
A) 12 inches
B) 24 inches
C) 48 inches
D) 72 inches
Ans: B (Ref API 653, Para. 9.10.1.1 & Figure 9.9 & CRITICAL NOTE 3)
Q32. The maximum thickness for a welded on patch plate in the critical zone
is:
A) two inches
B) one inch
C) of an inch
D) inch
Ans: D (Ref API 653, Para. 9.10.1.2.a & Figure 9.9 Sect. A-A view) -in
maximum
NOTE 1
Dimensions given are from toe of fillet welds or to centerline of butt-weld and also
apply to new-to-existing welds.
NOTE 2
Minimum distance between two welded-on patch plates in the critical zone shall be
one half of the lesser of L1 or L2.
NOTE 3
The maximum dimension along the shell for welded-on patch plates in the critical zone
is 24 in.
NOTE 4
When the edge of a welded-on patch plate is approximately parallel to a bottom seam,
the edge shall be held at least 2 in. from weld seam.
NOTE 5
Patches over three-plate laps shall extend a minimum of 12 in. in all directions along
all laps beyond the three-plate lap.
NOTE 6
These rules apply to butt-welded bottoms, where applicable.
NOTE 7
Applies to shells of unknown toughness.
Figure 9.13Typical Welded-on Patch Plates on Tank Bottom Plates
f)
The bottom plate under the perimeter of a welded-on patch plate shall
meet the thickness requirements in 4.4. (0.05 or 0.1)
g) For tanks with shell plate of unknown toughness as defined in Section 3,
new fillet welds utilized to install a tombstone patch plate in the critical
zone shall be spaced at least the greater of 3 in. or 5t from existing
vertical weld joints in the bottom shell course, where t is the thickness of
the bottom shell course, in inches. See Figure 9.13 for further guidance
on weld spacing.
NOTE The bottom plate thickness at the attachment weld must be at least
0.1-in. thick before welding the welded-on patch plate to the bottom plate.
Refer to API 2207 for further information.
API RP 2207 (R2012) Preparing Tank Bottoms for Hot Work, Sixth Edition
Q 33. Before welding a welded on patch plate, the bottom plate thickness at
the attachment weld must be at least how thick?
A) .090 inches
B) .050 inches
C) .100 inches
D) As per 653 tables
Answer: C (Ref API 653, Para. 9.10.1.2.f (Note)
Q 34. A Galvanic Cathodic Protection system is a system that:
A) Uses a metal less active than the structure to stop corrosion
B) Uses a metal more active than the structure to stop corrosion
C) Uses a chemical to stop corrosion
D) Uses a coating to stop corrosion
Answer: B (Reference API 651, Para. 6.2.1) 3.26 Definitions for Galvanic
CP )
Q35. All new materials for repair, alterations or reconstruction shall conform
to:
A) As-built standard
B) Current applicable standard
C) Original construction standard (as a minimum requirement)
D) None of these is correct
Answer: B Reference (API 653, Par. 7.2)
Q37. According to ASME Sec. IX, welding filler metals are grouped into
groupings (based on their usability) as:
A) P-Numbers
B) F-numbers
C) Z-numbers
D) AWS specified
Answer: B (Reference: ASME IX, QW-422)
Q38. Which of the following tank roof types are used to reduce filling and
breathing loss by eliminating vapor space?
A) Cone roof
B) Umbrella-roof
C) Vapor-dome roof
D) Floating roof
Answer: D (Reference API 575, Para. 4.2.3 Third Paragraph)
Discussion:
Look similar RPS vs. RPB & Question 40.
Discuss the differences
Q 43. Upon completion of welding of the new tank bottom, the welds may be
inspected by which of the following methods?
A) Radiography
B) Vacuum-box test
C) Tracer Gas test only
D) Either a vacuum box test or a tracer gas test
Answer: D (Reference API 650, Para. 7.3.3 See Para. 8.6 & 8.11 for these
tests)
Q 44. Which of these are API 653 examples of types of Release Prevention
Barrier?
A) Undertank leak detection system designed to identify if a significant leak
occurs
B) Steel bottoms, synthetic materials, clay liners, concrete pads, and all other
barriers or combinations of barriers placed in a bottom of or under a tank
C) Coating systems applied to floors with CP systems used
D) None of these are correct
Answer: B Reference (API 653, Par. 4.4.3.5)
MFL
MFL
Q46. Unless a stress analysis is performed, the minimum tank bottom plate*
thickness in the critical zone of the tank must NEVER be less than:
A) The tmin value, as isolated pitting will not appreciably affect the strength of
the plate
B) 653 value in Bottom Plate Minimum Thickness table (depends on
foundation design)
C) 0.050 inches (*does not apply to annular plates)
D) 0.100 inches (*does not apply to annular plates)
Answer: D Reference (API 653, Par. 4.4.5.4)
Discussion:
Which is more Critical
a. The critical zone
b. The annular plate
Q 47. What is the required minimum thickness & minimum projection distance
of a bottom plate beyond the shell as measured from toe of outside
bottom-to-shell fillet weld? (Assume you are evaluating corroded
condition of the chime area)
A) Thickness shall not be less than .050 in. & projection of bottom plate = at
least 3/8 in.
B) Thickness shall not be less than .100 in. & bottom plate projection = at
least 3/8 in.
C) Thickness shall not be less than .050 in. & projection of bottom plate = at
least in.
D) Thickness shall not be less than .100 in. & projection of bottom plate = at
least in.
Answer: B Reference (API 653, Par. 4.4.5.7)
Q48. Reported incidents of tank failure due to brittle fracture failure occurred
during all of the following times EXCEPT:
A) Failure occurred shortly after erection during hydrostatic testing
B) Failure occurred upon the first filling of the tank in cold weather
C) Failure occurred after a change to higher temperature service
D) Failure occurred after a tank repair/alteration was done
Ans: C Ref (API 653, Par. 5.2.2) After a change to a lower temp service)
Q49. The purpose of Periodic in-service inspection of tanks is to:
A) Assure continued tank integrity
B) Assure proper operation of the tank
C) Meet jurisdictional requirements
D) None of these is correct per API 653
Answer: A Reference (API 653, Par. 6.1)
Q51. Items that should be documented in a Routine insp include all these
EXCEPT:
A) Signs of settlement and any evidence of shell distortions
B) Condition of foundation, appurtenances, and coating and insulation
systems
C) Condition of the RPB liners and any Undertank Leak Detection systems
D) Evidence of any leaks and corrosion
Answer: C Reference (API 653, Par. 6.3.1.3)
Q52. All tanks shall be given a visual external inspection by an authorized
inspector not to
exceed:
A) The lesser of 5 years or RCA 4N years
B) The greater of 5 years or RCA 4N years
C) The lesser of 5 years or RCA 2N years
D) The greater of 5 years or RCA 2N years
Answer: A Reference (API 653, Par. 6.3.2.1)
Q53. The tank for which corrosion rates are NOT known is called the:
A) Candidate Tank
B) Control Tank
C) Service Tank
D) Critical Tank
Answer: A Reference (API 653, Para. 3.6)
Q54. Where does the new nameplate need to be attached to a reconstructed
tank?
A) Above the manway at the access point (located so as to be seen clearly)
B) Adjacent to the existing nameplate (if one exists) on the tank shell
C) No new nameplate needs to be added
D) None of these are correct
Answer: B (Ref API 653, Para. 13.1.2)
Q55. Per API 653, when Controlled deposition welding methods are
employed in lieu of
PWHT, what is required after the finished repair weld has cooled to an
ambient
temperature?
A) Final post heat (hydrogen bake out treatment) must be performed ASAP
B) Final temper bead reinforcement layer shall be removed/made flush with
base metal
C) Final insp and NDT specified must then be completed & accepted by the
Inspector
D) None of these is correct regarding the Controlled Deposition welding
procedure
Answer: B Ref (API 653, Para. 11.3.2.e.9)
Q57. What finished welds do NOT require stamping of ID for welder (or
operator)?
A) Only floor plate welds and roof plate welds and flange to nozzle-neck
welds
B) Only roof plate welds and flange to nozzle-neck welds do not require ID
stamps
C) Only flange to nozzle-neck welds do not require welder (operator) ID
stamps
D) None of these! Finished welds must always be stamped by a welder
(operator)
Answer: B Reference (API 653, Para. 11.2.2)
Q58. Per API 653, if a material specification (steel from an existing tank) is
unknown or obsolete (no longer made), what is required to verify
weldability before making a PQR test coupon?
A) Nothing can be done in this case, and the material cannot be used for tank
B) PQR Test coupons shall be made from lowest strength material in API 650
Group I
C) PQR Test coupons shall be taken from a similar strength & similar API
650 Group
D) PQR Test coupons shall be taken from actual plate to be used
Answer: D Reference (API 653, Para. 11.1.1)
Q59. What type of settlement occurs when tank shell settles sharply around
the tank periphery, resulting in deformation of the bottom plate?
A) Uniform B) Edge
C) Planar tilting D) Tank Bottom
Ans: B (Ref API 653, Annex B, Par. B.2.3.1) 4 major types of settlement!
Q60. On a reconstructed tank, the cut lines along the floor and the shell
adjacent to the corner welds must be how far away (at least) from the corner
weld toe?
A) two inches B) one inch
C) of an inch D) inch
Ans: D (Ref API 653, Para. 10.3.3.3 & Figure 10.1) inch rule!
Q61. What is the maximum internal insp interval of an Asphalt Storage tank or
other tank storing highly viscous substances that solidify at temps below
110F?
A) 10 years B) 12 years
C) 15 years D) 20 years
Answer: A Ref (API 653, Par. 6.4.2.6) 6.4.2.1 & 6.4.2.2 RBI rules DO NOT
APPLY)(?)
Q66. A formal internal inspection must be conducted every (assume the time
is from initial internal inspection to the 2nd internal inspection with no RBI
or similar service assessment and only the corrosion rate procedures will
be used):
A) 5 years B) 10 years
C) 20 years D) 25 years
Answer: C Reference (API 653, Par. 6.4.2.2 & Table)
Q67. Primary reasons/requirements for doing internal inspections include all
of these EXCEPT:
A) Ensure that the bottom is not severely corroded and leaking
B) Gather data needed for minimum bottom & shell thickness assessments
(also using those external UT thickness readings obtained during any inservice inspections)
C) Identify and evaluate any tank bottom settlement that may be evident
D) Identify and evaluate any roof or floating roof underside corrosion or holing
Ans: D Reference (API 653, Par. 6.4.1.1) D is the correct answer
because it is not the PRIMARY concern The primary concern = the shell
and floor No release of product)
Charlie Chong/ Fion Zhang
Q68. Before doing a hot tap or adding a reinforcement plate, what NDT is
needed?
A) MT or PT exam B) UT thickness and lamination scan
C) RT and MT or PT D) Visual examination ONLY
Answer: B Reference (API 653, Par. 12.1.2.1)
Q69. Where exterior tank bottom corrosion is controlled by a cathodic
protection system, periodic surveys of the system shall be conducted in
accordance with API 651. Who is responsible to review the results of these
CP surveys?
A) Owner/operator B) Authorized Inspector
C) Storage Tank Engineer D) Authorized Insp Agency
Answer: A Reference (API 653, Par. 6.3.4.2 & API 651 Section 11.3.2)
Q73. When API 653 does not provide specific evaluation procedures or
acceptance criteria for a specific type of degradation or when API 653
explicitly allows the use of fitness-forservice criteria, WHAT DOCUMENT
MAY BE USED to evaluate the various types of degradation or test
requirements addressed in API 653?
A) API 579-1/ASME FFS-1
B) API 580
C) API 581
D) None of these are correct
Answer: A Ref (API 653, Par. 1.1.6) New question for 2012 exams
Q75. Where welding and hot work are involved, WHAT API DOCUMENT
states Except in areas specifically designated as safe for hot work, a hot
work permit shall be obtained before starting any work that can involve a
source of ignition.
A) API 2015
B) API 2201
C) API 2217A
D) API 2009
Answer: D Reference (API 653, Para. 1.4) New question for 2012 exams
API RP 2009 (R2007) Safe Welding and Cutting Practices in Refineries,
Gasoline Plants, and Petrochemicals Plants. standard by American
Petroleum Institute
Q76. The document for Personnel Qualification and Certification in NDT is:
A) ASNT SNT-TC-1A
B) ASME V, Article 1
C) ASNT CP-189
D) None of these
Ans: A Reference (API 653, Para. 2.1) Expect this to come up in OB (most
likely) or CB!
Q77. The standard used for repairs or alterations made after original
construction is the:
A) As-built standard
B) As-built standard only for those repairs or alterations
C) Construction STD only for those repairs or alterations
D) None of these are correct
Ans: B Ref (API 653, Par. 3.2 5th Sent of 5 in definition) New question
2012 exams
Q78. API 653 Annex A provides a list of API welded storage tank standards
that goes back to 1936 and the ALL-WELDED OIL STORAGE TANKS (All
Tanks before that were riveted). What was the name of the 1936 API
standard?
A) API 650
B) API 12B
C) API 620
D) API 12C
Ans: D Ref (API 653, Para. 3.2, Annex A & Table A.1) ) New question for
2012 exams
Note: 12A-Riveted, 12B=Bolted, 12C-Welded
Q79. The area on the tank bottom where the settlement begins is called:
A) Bulging Point
B) Settlement Point
C) Breakover Point
D) None of these
Answer: C Reference (API 653, Para. 3.5)
Q80. Installing a shell penetration larger than NPS 12 beneath design liquid
level is considered:
A) Alteration
B) Repair
C) Major alteration
D) None of these
Answer: C Reference (API 653, Para. 3.18)
Q81. Complete or partial (if more than of the weld thickness) removal &
replacement of more than 12 in. of vertical weld joining shell plates or radial
weld joining annular plate ring is:
A) Repair
B) Alteration
C) Major repair
D) None of these
Answer: C Reference (API 653, Para. 3.18)
Q82. Removing and replacing or adding a shell plate beneath the design
liquid level where the longest dimension of the replacement plate exceeds 12
inches is considered:
A) Repair
B) Alteration
C) Major repair
D) None of these
Answer: C Reference (API 653, Para. 3.18)
Rounded porosity
Storage Tank
Engineer- One or
More.
12.3.2.3.5 The root pass and final pass examination shall be in accordance
with 12.1.5. In addition, the finished weld shall be fully radiographed.
12.1.5 Shell Plate to Shell Plate Welds
12.1.5.1 New full penetration welds attaching existing shell plate to existing or
new shell plate shall be examined by
radiographic methods (see 12.2). In addition, for plate thicknesses greater
than 1 in., the back-gouged surface of the root pass and final pass (each side)
shall be examined for its complete length by magnetic particle or liquid
penetrant methods.
12.1.5.2 New welds joining new shell plate material to new shell plate
material (partial or full shell course replacement or addition) need only be
examined radiographically in accordance with API 650, Section 8.1.
Q94. In the absence of an initial settlement survey (to provide base readings
for future settlement evaluations) THE TANK SHALL BE ASSUMED TO
BE:
A) No assumptions may be made because it is critical to evaluate baseline
settlement readings
B) Initially out-of-level and out-of-tolerance
C) Initially level
D) None of these are correct
Answer: C Ref (API 653, Section 12.5 entire section)
That I can
read and be
happy while I
am reading,
is a great
blessing.
>| dsssa
Good Luck!