I.E.M.S.

LIQUID
PENETRANT
INSPECTION
PROCEDURE

Code

UAN (for QMHA)

Page

11-3090

1 of 6

LIQUID PENETRANT INSPECTION


PROCEDURE
Owner
: ENPC
Main contractor : Uhde
Project name
: AMMONIA UREA PROJECT

00
Rev

Status

CC Category Code:
1 = for approval
2 = for review
3 = for information
4 = for internal use
AC Acceptance Code:
1 = approved / reviewed
2 = approved / reviewed as
noted
3 = not accepted
4 = received

First Issue

11/6/2010

Emad Omar

11/6/2010

Hassan Basha

Description

Date

Prepared

Date

Checked

Status Code:
A = Issued for Design
D = Issued for Inquiry
E = Issued for Order
F = Issued for Prefabrication
G = Issued for Construction /
Fabrication
H = Issue for Work
Preparation
I = As- built

Date

Approved

Acc.

Space for Bar Code label

M = General Issue

Copyright 2007 Uhde GmbH

Doc. ID-Code
PT-BM-183-DC-00003

Category
1

I.E.M.S.A.

Code

LIQUID PENETRANT
INSPECTION
PROCEDURE

ENPC
UAN (for QMHA)

Page

11-3090

2 of 6

Liquid penetrant inspection procedure

1
2
3
4
5
6
7
8
9
10

CONTENTS
Scope
Reference codes
Personnel
Technique
Equipment
Surface preparation
Application
Post cleaning
Acceptance criteria
Reporting

Copyright 2007 Uhde GmbH

PAGE
3
3
3
3
3
3
4
5
5
6

Doc. ID-Code
PT-BM-183-DC-00003

Rev.

00

LIQUID PENETRANT
INSPECTION
PROCEDURE

I.E.M.S.A.

Code
ENPC
UAN (for QMHA)

Page

11-3090

3 of 6

1. Scope:
This procedure describe the requirement to carrying out the liquid Penetrant
inspection activity (open to surface defects) for the piping, during the execution of
AMMONIA UREA ENPC PROJECT.

2. References code:

EN 571-1
AD 2000- Merkblatt.

3. Personnel:
The personal for the examination / supervision shall fulfill the requirements according to
standard EN-473 or equivalent (Qualified and Certified according To ASNT- TC -1A
(LEVEL II))

4. Technique:Solvent Removable Technique

5. Equipment:5.1 Color Contrast Solvent Removable Penetrant Kits.


5.2 Wet Non Aqueous Developer Kits.
5.3 Solvent Cleaner Kits.
5.4 Dry Clothes For Wiping.
5.5 Calibrated Light Meter
5.6 Stop Watch
The Identification of Any Change in Type or Family Group of Penetrant Materials Including
Developer, Emulsifiers, Etc. shall be used as per the following table.

Penetrant Family No
DYE

Remarks

Penetrant Brand Name

MR 68C

BYCOTEST
RP20

Or Equivalent

Cleaner Brand Name

MR 85

BYCOTEST
D30

Or Equivalent

Developer Brand Name

MR 70

BYCOTEST
C5/C10

Or Equivalent

Note:
When used for tests on nickel base alloys, the sulfur content shall not exceed 1% of the
residue by weight; when used for tests on austenitic or duplex stainless steel, the chlorine
plus fluorine content shall not exceed 1% of the residue by weight

6. Surface Preparation:
Test Surface Shall Be Free From Extraneous Matter, Rust and Scale
Copyright 2007 Uhde GmbH

Doc. ID-Code
PT-BM-183-DC-00003

Rev.

00

I.E.M.S.A.

LIQUID PENETRANT
INSPECTION
PROCEDURE

Code
ENPC
UAN (for QMHA)

Page

11-3090

4 of 6

6.1 Pre Examination Cleaning:Solvent Cleaning (Allow 5 Min for Solvent Evaporation before Application)

7. Application
shall be as follow: 7.1 Method Of Applying Penetrant:Spraying (as per the manufacture recommendation)

7.2

Method Of Removing Excess Surface Penetrant:

By wiping with a cloth or absorbent paper, repeating this operation until


most traces of penetrant have been removed.

Cleaning the surface from excess penetrant by flushing solvent is


prohibited
Drying after penetrant removal (for the solvent removable technique)
may be by normal evaporation, blotting, wiping or forced air

7.3

Penetrant Dwelling Time

The dwelling time shall be according to the manufacturer recommends, (if it isn't
available) then the following time limits shall be use.
Minimum dwelling time of Penetrant is 10 min.

Maximum dwelling time of Penetrant is 20 min.

If the Penetrant allowed to dry during the examination the part must be re-cleaned
and the examination to be repeated.

7.4

Method of Applied Developer.

Spraying (as per the manufacture recommendation)

7.5

Developer dwelling Time

The dwelling time shall be accordance with the manufacturer recommends; (if it isn't
available) then the developer minimum dwelling time shall be 7 min.
Developer shall be applied lightly.

If necessary additional developer may be add to aide in interpretation.

Final interpretation shall be done within 7 to 30 min. of applying


developer

7.6

Lighting Requirements.

Either natural or artificial light however the minimum permissible lighting intensity
at the examination site is (350 LUX)

Copyright 2007 Uhde GmbH

Doc. ID-Code
PT-BM-183-DC-00003

Rev.

00

I.E.M.S.A.
7.7

LIQUID PENETRANT
INSPECTION
PROCEDURE

Code
ENPC
UAN (for QMHA)

Page

11-3090

5 of 6

Surface Temperature

The recommendations of the manufacture to be followed .

8. Post cleaning
Post cleaning shall be achieved by wipe surface with dry cloth, flush surface with an
approved solvent cleaner. Wipe as required a clean cloth an/or observant toilet paper
9. Acceptance Criteria
EN 1289 acceptence level 1 ISO 5817 group B
10. Reporting
See the attached form.

Copyright 2007 Uhde GmbH

Doc. ID-Code
PT-BM-183-DC-00003

Rev.

00

Code

LIQUID PENETRANT
LIQUID PENETRANT
INSPECTION
INSPECTION
REPORT
PROCEDURE

I.E.M.S.A.

ENPC
UAN (for QMHA)

Page

11-3090

6 of 6

Owner : ENPC
Main contractor : Uhde
Application code :EN571-1,1289ACC Level 1
Item no.:

Report no.:
Date :
Material :

Pentrant :
Developer:
Cleaner:
Material :

Dwell time :
Developing time :
Surface temperature:30oC

ISO/DWG NO.

PIPING
CLASS

IEMSA

Weld no.

Joint type

PWHT
Yes
No

PETROJET

Evaluation

UHDE

Remarks

ENPC

Name
Sign
Date
Abbreviation :

Acc. : accept

Copyright 2007 Uhde GmbH

Rep.: repair

Doc. ID-Code
PT-BM-183-DC-00003