Sei sulla pagina 1di 2

Back Energisation of Main Transformer - A. K. M.

Zillur Rahman

https://mail.egcb.com.bd/owa/#viewmodel=ReadMessageItem&ItemI...

DearMr.Angel
1)Asyourequested,PGCBpeoplecameat9:00amtodaybutthetestsstartedataround11:00am.A er
today'sworkthefollowingPGCBrequiredtestsares llpending:
PowerGridSide:
I.Closecircuitcheck(Remoteclosecmd.)
II.Harmonicsblockingcouldnotbetested
III.BreakerFailureRemotetripS/StoP/P
IV.BreakerFailureRemoteTripP/PtoS/S
V.IBF/CloseblockfromGCP(From50BFrelay,G60A,M3425
VI.DCearthfaultofS/S
VII.GSUTshortcircuittest
Pleaseletusknowwhenyouwillcompletethetests.
2)Aspercontract,EPCshouldno fy&inviteforwalkdownjointly(EGCB/OE&EPC)a ermechanical
comple onofanysubsystem.However,wedidnotgetanyinvita onforwitnessingthefollowingtests:
PowerPlantside:
a.Fullfunc onaltestsofallrelays(ExceptL90,L30)
b.Tramsformerselfprotec onTest(GSUT,UAT)
c.TransformerTest(GSUT,UAT)
i)Shortcircuit
ii)Opencircuit
iii)Magne cbalance
iv)Vectorgroup
v)Windingresistance
vi)Ra otest
vii)Insula onresistance
viii)BDVofoil
ix)Tan&test(fullandbushing)
d.TripMatrixTests

1 of 2

2/21/2016 7:48 PM

Back Energisation of Main Transformer - A. K. M. Zillur Rahman

https://mail.egcb.com.bd/owa/#viewmodel=ReadMessageItem&ItemI...

Pleaseletusknowwhenyouwillcompletethetests.
3)Thescheduleforbackchargingthetransformeris23rdFebruary2016.Butthetestsmen onedinitem1&
2notyetcompleted.Pleasereviewtheschedule&confirmthedateofbackenergiza on.
Regards
Md.NazmulAlam

2 of 2

2/21/2016 7:48 PM