Sei sulla pagina 1di 14

New Acrylic Acid Plant, Salavat, Bashkortostan Russia

Federation

Method Statement for


MOTORS
Issue
Date:

04/06/2
014

Doc.
Number:

RSAE-PRC-QA-

Revisio
n:

A1

Page:

1 of 14

DOCUMENT REVIEW AND COVER SHEET


Company:

Engineering Contractor:

Review:

Construction Contractor:

PROJECT

Gazprom Neftehim Salavat Acrylic Acid / Acrylates


Plant (RSAE) Project Bashkortostan, Russian
Federation

CONTRACT NO

88621 - December, 2012

DOCUMENT TITLE
DOCUMENT NUMBER
DOCUMENT
Status
DESCRIPTION
Status

METHOD STATEMENT for MOTORS


RSAE

- PRC

Revieved
Engineer:

NAME

Remarks or Comments:

REV.

A1

Quality Control Procedure


Code Description

Code

- QA

APPROVED WITHOUT COMMENT


REVISE AND RESUBMIT. WORK MAY PROCEED SUBJECT TO
INCORPORATON OF CHANGES INDICATED.
REJECTED. TO BE REVISED B: RESUBMITTED. WORK MAY NOT
PROCEED
INFORMATION ONLY. REVIEW NOT REQUIRED. WORK MAY
PROCEED
CANCELLED/SUPERSEDED
SIGN

DATE

New Acrylic Acid Plant, Salavat, Bashkortostan Russia


Federation

Method Statement for


MOTORS
Issue
Date:

A1

04/06/2
014

Doc.
Number:

RSAE-PRC-QA-

Revisio
n:

A1

Page:

2 of 14

Issued for Approval

Rev.

Amendment

Prepared

Checked

Approved

Date

Company:

Engineering Contractor:

Construction Contractor:

Project Title:

Gazprom Neftehim Salavat


Acrylic Acid / Acrylates Plant (RSAE) Project
Bashkortostan, Russian Federation

Document Title:

METHOD STATEMENT
FOR
MOTORS

New Acrylic Acid Plant, Salavat, Bashkortostan Russia


Federation

Method Statement for


MOTORS
Issue
Date:

04/06/2
014

Doc.
Number:

RSAE-PRC-QA-

Revisio
n:

A1

Page:

3 of 14

REVISION SHEET
Revisio
n
A1

Description of changes
First Issued For approval

Page

New Acrylic Acid Plant, Salavat, Bashkortostan Russia


Federation

Method Statement for


MOTORS
Issue
Date:

04/06/2
014

Doc.
Number:

RSAE-PRC-QA-

Revisio
n:

A1

Page:

4 of 14

Contents
1. PURPOSE 5
2. SCOPE......5
3. DEFINITIONS

4. RESPONSIBILITIES...6
5. PREREQUISITES and PRECAUTIONS....6
6. PROCEDURES...8
7. ACCEPTANCE CRITERIA...12
8. ATTACHMENTS.......13

New Acrylic Acid Plant, Salavat, Bashkortostan Russia


Federation

Method Statement for


MOTORS
Issue
Date:

04/06/2
014

Doc.
Number:

RSAE-PRC-QA-

Revisio
n:

A1

Page:

5 of 14

1. Purpose
This procedure provides a safe, standardized approach for the initial inspection, checkout,
testing, and data documentation of electric motors used to drive rotating equipment.
2. Scope
This procedure is applicable to the RSAE project Site and covers all motors. It applies to
AC MV and AC LV motor used to drive rotating mechanical equipment. Motors used as
operators for valves, gates, dampers, etc. are not within the scope of this procedure.
This procedure shall be implemented during initial uncoupled/unloaded operation of
applicable equipment, as well as during the initial coupled/loaded operation. However, it
may be used at any time during equipment operation.
3. Definitions

Project
: Gazprom Neftehim Salavat Acrylic / Acid Plant
Company
: Gazprom Neftehim Salavat
Construction
: Renaissance Construction (RC)
Supplier (Manufacturer/Vendor) : The supplier (Manufacturer/Vendor) is the party
that manufacturers or supplies equipment and services to perform the duties specified by
the Company or Contractor.
The word SHALL indicate a requirement.
The word SHOULD indicate recommendation.

Drive End (DE) - The end of the motor from which the shaft protrudes and is coupled to
the driven equipment. It may also be referred to as the inboard (IB) end of the motor.

Non Drive End (NDE) - The end of the motor that is opposite the DE. This end of the
motor usually has the motors cooling fan attached. It may also be referred to as the
opposite drive end (ODE) or outboard (OB) end of the motor.

Bump - To start and immediately stop a motor from a Local Control Switch or temporary
remote signal instead of DCS signal to verify direction of rotation.

Rotation - The rotation of a motor as viewed from behind the NDE, standing with line of
sight in-line with the rotor, looking toward the drive shaft of the driven equipment.

Magnetic Center - That position of Sleeve bearing type motor rotor where the magnetic
forces acting on the rotor are in balance during operation. In large motors during initial
run-in, the magnetic center is marked to allow positioning of the rotor at the magnetic
center for coupling alignment. Placement of the rotor at the magnetic center assures that
no thrust from the motor is transmitted to the driven equipment via the coupling.

New Acrylic Acid Plant, Salavat, Bashkortostan Russia


Federation

Method Statement for


MOTORS
Issue
Date:

04/06/2
014

Doc.
Number:

RSAE-PRC-QA-

Revisio
n:

A1

Page:

6 of 14

Motor Doweling - A practice on some large motors where the motor base is drilled and
dowels inserted to prevent movement of the motor. This is usually done to permanently
fix the final alignment position of the motor. In some cases the driven equipment may
also be doweled in place.
4.

Responsibilities

4.1

Test Program Manager


Has overall responsibility for test program and shall act as Test Program Manager.

4.2 Test Engineer


Has responsibility for detailed checkout and testing of electric motors and shall act as Test
Engineer. Coordinates with discipline engineers, operations, and test performers to
accomplish testing and completes the Motor Data Record. The Test Engineer performing
this procedure shall ultimately be responsible for all evolutions. Correct rotation of the
Motor (in relation to the driven equipment) must be verified by the Mechanical
Commissioning Engineer.
4.3

Health, Safety and Environmental (HSE) Representative


Participates in and provides input to Safety Task Analysis Risk Reduction Talk
(START)/Job Hazard Analysis (JHA). Provides HSE coverage for test activities and walk
downs.

5. PREREQUISITES AND PRECAUTIONS


5.1

Prerequisites
5.1.2 Verify that test equipment used for recording data are calibrated within their
calibration interval and document on the Motor Data Record. Temporary barricade not to
access the unauthorized person shall be provided around inspected motor before motor
operation
5.1.3 Verify that the equipment is correct (per data sheets, specifications, etc.) and
installed in accordance with project design documents and vendor manuals/drawings.
Also verify that the system installation is complete to the extent necessary to properly
support equipment operation. Review system/component punch list.
5.1.4 Review the vendors instruction manual(s) for special precautions or limitations
specific to the equipment/systems components. Note and observe the vendor's
precautions and limits, such as number of starts, run-in duration, vibration, load, etc.

New Acrylic Acid Plant, Salavat, Bashkortostan Russia


Federation

Method Statement for


MOTORS
Issue
Date:

04/06/2
014

Doc.
Number:

RSAE-PRC-QA-

Revisio
n:

A1

Page:

7 of 14

5.1.5 Verify that equipment lubrication is in accordance with the vendor's specifications,
and either a lubrication tag is attached or other documentation is verified.
5.1.6 Verify that protection systems, instrumentation, controls, and alarms associated
with the equipment under test are tested, calibrated, functional, and documented to the
extent necessary to support testing.
5.1.7 Verify that the motor bearing lubrication and cooling system, if any, is available
for operation. If applicable, also verify that auxiliary cooling fans have been checked out
and are available.
5.1.8 All LV and all MV Motors shall be uncoupled prior to initial start and run-in.
5.1.9 Verify that the motor supply breaker/switchgear has been functionally tested to
permit motor operation.
5.1.10 Ensure that motor filters are installed if applicable. Replace filters as required.
5.2 Precautions
5.2.1 Areas under test must be clean and free of loose debris and only authorized
personnel are permitted in test areas.
5.2.2 Systems (complete or partial) or equipment under initial test where high energy
will be introduced for the first time must be physically walked down to ensure
unauthorized personnel are removed from test areas. As required, personnel may be
stationed at designated locations to keep test areas free of unauthorized personnel.
Emergency egress routes must be identified and verified clear of obstructions.
5.2.3 Equipment Lock out / Tag out (LOTO) requirements in support of this activity
must be implemented
5.2.4 A pre-test briefing incorporating STARRT/JHA must be conducted. Discuss test
performance and expected results with involved personnel. Personal Protection
Equipment (PPE) identified in the STARRT/JHA is required to be worn during
performance of this test.
5.2.5 Special attention must be provided for protection of personnel and equipment.
Ensure precautions such as barriers, flagging, danger signs, horns, area restrictions, etc.,
are used to protect personnel and equipment.
NOTE: Special attention should be paid to areas parallel to rotating equipment shafts.
These zones are especially susceptible to debris launched tangentially from rotating
equipment during a failure.

New Acrylic Acid Plant, Salavat, Bashkortostan Russia


Federation

Method Statement for


MOTORS
Issue
Date:

04/06/2
014

Doc.
Number:

RSAE-PRC-QA-

Revisio
n:

A1

Page:

8 of 14

5.2.6 Immediately terminate testing if any unusual noises, smoke or anomalies occur, or
if design limits that may compromise the safety of personnel or equipment are exceeded.
Immediately notify the Lead Electrical Commissioning Engineer and the site HSE
representative (if applicable) of such occurrences.
5.2.7 Assure adequate access is provided to all required areas during the test. Where
permanent access is not provided, scaffolding or a man lift must be provided in
accordance with job site procedures.
5.2.8 Establish appropriate level of communication between test and HSE personnel.
5.2.9 Loose fitting clothing or long hair shall be properly secured to prevent
entanglement when working around moving equipment.
5.2.10 Rotating parts, such as couplings, pulleys, external fans, and unused shaft
extensions, should have permanent guards installed to prevent accidental contact with
hands or clothing. This is particularly important where the parts have surface irregularities
such as keys, keyways or setscrews.
5.2.11 Loose parts of the coupling that cannot be removed for the motor uncoupled run-in
shall be tied off or affixed in such a way that they shall not contact the motor shaft or any
other rotating part.
5.2.12 Equipment must not be operated unless its supervisory and protective devices are
calibrated, tested, and functional. No protective devices shall be de-rated or bypassed
unless temporary protection is provided.
6. Procedure
NOTE: The vendors instruction manual and vendor requirement takes precedence over
this procedure in the event of conflicts. Detailed equipment operation shall be according
to vendor manuals.
6.1 General
6.1.1 This test shall be performed concurrently with the Equipment Vibration Testing
Procedure. The Test Engineer will coordinate all activities as necessary.
6.1.2 Motor run-in time shall be as specified until bearing temperatures and winding
temperatures (as applicable) stabilize. A temperature is normally considered stable when
three successive readings taken at 10-minute intervals do not vary by more than 5
percent. A 4 hours run-in time shall be considered adequate for all motors with Motor
rated voltage: 380V AC.

6.1.3 During initial run-in, record those equipment parameters that have an accessible
indicator. Typical parameters that establish the motor's characteristics include bearing
temperatures, winding temperatures, lubrication flows and temperatures, etc. The data
should have a common time basis and be recorded at a specified interval. The following
are several acceptable recording methods:
Manual recording of local indicators/digital meter on MCC in
substation

New Acrylic Acid Plant, Salavat, Bashkortostan Russia


Federation

Method Statement for


MOTORS
Issue
Date:

04/06/2
014

Doc.
Number:

RSAE-PRC-QA-

Revisio
n:

A1

Page:

9 of 14

6.1.4 Use the Motor Data Record, to document test results and attach charts, graphs,
data printouts, etc. Data collection can be stopped when monitored parameters have
stabilized.

6.1.5 During the coupled run-in of variable or multi-speed equipment data should be
taken at:
Operational speed (60Hz)
NOTE: On variable speed equipment, particular attention should be exercised to
avoid operation at, or near, the equipment critical speed.
6.1.6 Temporary alterations installed during testing shall be recorded on Motor Data
Record. Temporary alterations that are to remain following completion of testing shall be
logged according to the requirements of the Control of Temporary Modifications
Procedure.

6.2 Inspection
6.2.1 Ensure that the motor is clean and dry. The motor and Tag plate shall be legible.
End bells, covers, filters, and accessories shall be firmly attached.
6.2.2 Record motor nameplate data on the Motor Data Record.
6.2.3 Verify that the voltage, phasing and the frequency of the motors power supply
agree with those on the motor nameplate and the appropriate drawings.
6.2.4 Verify that motor terminations are properly made up.
6.2.5 Verify that the motor is properly grounded in accordance with the project
grounding notes, symbols, and details. Standard drawing (3935 E206-00100)
6.2.6 Inspect collector rings and brushes. The collector rings shall be clean and free of
any mechanical damage. The brushes shall make good contact with the slip rings and the
brushes shall slide smoothly in their holders.
6.2.7 Verify that the motor protection circuits have been set.
Record the initial settings in the comment section of the Motor Data Record, Exhibit
1.6.2.8 Verify that all protective relays have been calibrated and functionally tested.
6.2.9 Inspect cable gland connections for instrument and power cables ensuring that
bushings are installed, tightly and cable protection cover (If necessary) are installed.

New Acrylic Acid Plant, Salavat, Bashkortostan Russia


Federation

Method Statement for


MOTORS
Issue
Date:

04/06/2
014

Doc.
Number:

RSAE-PRC-QA-

Revisio
n:

A1

Page:

10 of
14

6.3 Pre-Run Tests


6.3.1 The insulation of the motor windings and power cable should be meggered.
6.3.2 The winding resistance and the applied voltage shall be measured phase to earth.
6.3.3 Support systems, such as lube oil or cooling water, shall be placed into operation.
6.3.4 The motor shaft shall be manually rotated (if possible) to ensure that the rotor
moves freely, without rubbing.
6.3.5 Phase rotation may be initially checked using a motor phase rotation meter for any
motor. However, an initial check by actual motor rotation (bump) is mandatory for motors
because driven equipment that might be damaged by reverse rotation:
a. Supply the Lockout/Tagout on breaker of power supply.
b. Connect the leads of the phase rotation meter to the motor terminals at the motor
terminal box or feeder (load) terminals for the motor at the starter or switchgear.
c. Slowly rotate the motor shaft (rotor) in the proper direction of rotation for the driven
equipment and verify that the phase sequence on the meter matches the phase sequence of
the line (supply) connections.
d. If the phase sequence indicated on the meter does not match the design (line) phase
sequence, interchange the motor leads of two phases at motor internal wire.
NOTE: If leads need to be swapped all labels, tags, markings, etc. need to be revised to
match issued drawings.
e. Recheck the phase sequence of the motor winding using steps b. and c. above and
record the sequence on the Motor Data Record.
f. Remove the Lock out / Tag out.
6.3.6 For a motor supplied from a load center or switchgear bus, place the breaker in the
operating position (racked-in). For a motor equipped with a starter and supplied from a
motor control center and/or distribution panel, place the breaker in the closed position.
Verify that the motor space heaters, if supplied, are energized and note their operation in
the comment section of the Motor Data Record, Exhibit 1.
NOTE: Space heaters must energized for the minimum amount of time required by
the manufacturer prior to attempting a motor start. If no guidelines are given the
heater should be energized for 8 hours prior to attempting the start.
6.3.7 After the preliminary rotation verification all motors must be bumped for a final
verification of proper rotation.
6.3.8 Ensure that the safety switch adjacent to the motor is function checked before
starting motor.

New Acrylic Acid Plant, Salavat, Bashkortostan Russia


Federation

Method Statement for


MOTORS
Issue
Date:

04/06/2
014

Doc.
Number:

RSAE-PRC-QA-

Revisio
n:

A1

Page:

11 of
14

6.4 Motor Start and Run


6.4.1 If, at any time during the implementation of this procedure, any parameter or
condition is out of acceptable limits and cannot be readily corrected, the evolution in
progress shall be terminated and the system or component placed in a safe configuration.
Motor solo run shall be done all MV motor and installed outdoor LV motor.
But some motors are not dismantle mechanical coupling. Their motors shall not be
applied motor solo run test.
6.4.2 Clamp an ammeter on one of the motor leads at the breaker and set it to record the
maximum current draw. Alternatively if the motor manager or protection relay can record
starting current, this should be used instead of clamp on ammeter. Start the motor, locally
if possible. Record the starting current on the Motor Data Record, Exhibit 1.
6.4.3 As the motor comes up to speed, monitor it for smoothness of operation and for
any unusual or unexpected noises.
6.4.4 with the motor running: take running current on all phases, phase to phase
voltages, and motor rpm measurements and verify that the motor space heater is deenergized. Record readings on the Motor Data Record.
6.4.5 If applicable tune variable speed drive to the system attributes and verify
frequency settings.
6.4.6 Check that the motor bearings are being properly lubricated (e.g. bearing oil rings
are rotating, no excessive foaming, levels are correct). Monitor bearing temperatures as
the motor is run in. When they have stabilized, record the measurement.
6.4.7 Monitor motor winding temperatures, if available. When they have stabilized,
record measurements on the Motor Data Record, in the comment section.
6.4.8 Take vibration data as required. Refer to Equipment Vibration Testing Procedure.
Vibration readings that exceed limits may result in motor damage, and operation may
have to be secured.
6.4.9 Verify temperature, current, and vibration readings against any local or remote
indications.
6.4.10 Verify magnetic centre position indication, if applicable. Apply new mark after
vendor's confirmation if necessary.
6.4.11 When the vendors run-in criteria have been met or the temperatures are stable
secure the motor and monitor for smooth coast down.
6.4.12 Repeat the activities of the uncoupled motor start and run-in when the motor is
coupled. Record the data on the Motor Data Record.
6.4.13
After final alignment and motor and driven equipment run-in, the motor
may be doweled in position as required by the vendor.
6.4.14 Ensure that motor stops when local control stop button is put in off position and
cannot be started again from.

6.5. Restoration

New Acrylic Acid Plant, Salavat, Bashkortostan Russia


Federation

Method Statement for


MOTORS
Issue
Date:

04/06/2
014

Doc.
Number:

RSAE-PRC-QA-

Revisio
n:

A1

Page:

12 of
14

6.5.1 Verify that temporary alterations made during the performance of this test have
been restored or controlled according to Control of To be submitted in case restoration is
required.
6.5.2 Verify that temporary test equipment has been removed, and all system
connections and permanent equipment are replaced and secured. Ensure terminal box
cover is tight and has appropriate gasket installed.
6.5.3 Verify that equipment and system(s) affected by this procedure are restored to
conditions as specified by the person responsible for the system(s).
6.5.4 Verify that applicable previous data records have been completed.
7. Acceptance Criteria
All equipment operating parameters including vibration, currents, voltages, resistances,
and temperatures shall be within project design and vendor requirements and tolerances.
The motor operation shall be generally smooth.
Refer to the vendors manual. Insulation Resistance (Megger) Testing are within project
design and vendor requirements. In some cases the motor may be run for an extended
period of time to dry out the motor and allow the insulation resistance to increase over
time.
8. Attachments
AMotor Run Testing Process Map
BMotor Run Testing Process Map (contd.)

New Acrylic Acid Plant, Salavat, Bashkortostan Russia


Federation

Method Statement for


MOTORS
Issue
Date:

04/06/2
014

Test Organization
Home Office

Doc.
Number:

Test Program
Manager
Accept
turnover from
Construction

RSAE-PRC-QA-

Revisio
n:

A1

Attachment A
Test Engineer

Verify motor protection and control


circuits have been checked out.
Install Lockout & Tagout on
breaker for power supply

NO

Hand rotate shaft and


check for rubbing
Megger per 530-U07-00308
Insulation Resistance (Megger)
Testing
Measure winding resistance and
applied voltage Phase to Ground

Verify phase rotation with phase


rotation meter

To Page
2

Motor Run Testing Process Map

13 of
14

Construction

Inspect for correct insulation,


lubrication, cleanness, correct,
voltage, phasing & frequency etc.

Is motor 250V DC or 380V


AC of more than
50HP/37,5kW? (All
Motors

Page:

Uncouple
motor from
driven
equipment.
If possible

Engineering

New Acrylic Acid Plant, Salavat, Bashkortostan Russia


Federation

Method Statement for


MOTORS
Issue
Date:

04/06/2
014

Doc.
Number:

RSAE-PRC-QA-

Revisio
n:

A1

Attachment B
From
Page 1

Place support
system in service

Close breaker/rack- in switchgear


Remove Install Lockout & Tag out on breaker

Is rotation
Correct?

NO

Swap leads to
correct
rotation and
update
markings

Start and run motor. Taking data


and monitoring operation

Verify heater de energizes if


applicable

Run-in motor unit bearing and


winding temperatures are stable
and all other vendor run-in
criteria are met

Secure motor and monitor for


smooth coast down

END

Motor Run Testing Process Map (contd.)

Page:

14 of
14

Potrebbero piacerti anche