Sei sulla pagina 1di 1

Pre commissioning Electrical & HV Tests for Cable Circuits

A: The Circuit Names:


1. 110 KV Hawiyah 2 Taif Air Port
2. 110 KV Hawiyah 1 380 KV BSP SSID CKT -1
3. 110 KV Hawiyah 1 380 KV BSP SSID CKT -1
B: Electrical Tests
Day- 01: a: Cable Sheath Test
b: Cable Phase Checking
c: Cable Capacitance
d: Cable Conductor Resistance
e: Cable Sequences Impedances
f: Cable Insulation Resistance
Day- 02: a: X- bonding Check
b:: SVL Test
c: Contact Resistance
d: Earth Resistance
Day 03: RESERVE DAY
Day -04: Cable HV Test
C. Pre Test Preparation
1. Cable Access at GIS at both ends
2. GIS preparation before HV Test
3. HV Test Bushing