An Introduction to PRINCE2

28

2.

Distribute the Follow on Recommendations to the persons who will maintain the products
after the project.

3.

And the very last thing the Project Board does is to issue the Project Closure Notification,
which will announce to all stakeholders that the project will end on a certain date. This is
the same Project Closure Notification that was drafted by the Project Manager.

That's it, the project will be closed very soon. The Project Closure Notification is used to inform
people that the project is closing and to therefore submit any costs to the project budget before it is
closed.
Perhaps the Project Manager should invite out the project team out for a meal or drink and write
recommendations for people who performed well on the project, this will also help to motivate
people for future projects .