CRONOGRAMA DE DESEMBOLSOS:

TODOS LOS MODULOS

PROYECTO : INSTALACIN Y AMPLIACIN DE LA CAPACIDAD DE SERVICIO DE EDUCACIN


PRIMARIA EN LA I.E.P. 16527 - ALTAMIZA, DISTRITO DE SAN JOSE DE LOURDES, SAN IGNACIO CAJAMARCA
Local.: ALTAMIZA
Dist.: SAN JOSE DE LOURDES
Descripcion

Prov.:

SAN IGNACIO

Dep.:

CAJAMARCA

MES 1

MES 2

MES 3

MES 4

TOTAL

COSTO DIRECTO

174,810.86

247,605.08

304,978.13

268,024.33

995,307.40

GASTOS GENERALES DE LA OBRA 8%

13,984.87

19,808.41

24,398.25

21,441.95

79,624.59

UTILIDAD 7%

12,236.76

17,332.36

21,348.47

18,761.70

69,671.52

SUB TOTAL

201,032.49

284,745.84

350,724.85

308,227.98

1,144,603.51

IGV

36,185.85

51,254.25

63,130.47

55,481.04

206,028.63

5,025.81

7,118.65

8,768.12

6,164.56

28,615.09

422,623.44

369,873.58

1,379,247.23

VALOR REFERENCIAL
SUPERVISION 2.5%
TOTAL MENSUAL

242,244.15

343,118.74

TOTAL ACUMULADO

242,244.15

585,362.89

AVANCE MENSUAL

17.56%

24.88%

30.64%

26.92%

100.00%

AVANCE ACUMULADO

17.56%

42.44%

73.08%

100.00%

100.00%

1,007,986.33 1,377,859.91

1,379,247.23