An Introduction to PRINCE2

17

3.10 DP: Authorize the project


Authorize the project is the 2nd control point and 2nd Activity for the Project Board. The end of the
Initiation Stage is the trigger for the Authorize the project activity. The Project Board confirms the
projects objectives and the scope is clearly defined and understood. They can decide to stop the
project, ask for further information, or give authorization for the project to continue.
The Authorize the project activity has the following input and outputs:
Inputs
x Project Initiation documentation
x Request to Deliver a Project

Corp..

Outputs:
As you can see in the diagram, there is one authorization, one approval and one notification
x Authorization
: Authorize the Project so the project can start
x Approval : Approve the Project Initiation Documentation
x Notification : To the Corporate or Programme Management that the project has started

Project
Notification

Directing a Project (DP)

Next
Stage
Plan

-- Once during project


-- Once per stage
-- Many times during stage
-- Once per Work Package

Authorize a Stage
or Exception Plan

Auth.
2 Proceed
Auth.next
stage

Authorize Project
Approved PID

Authorize
the project

Project Init Docs


Req Deliver Project?

Auth. To Initiate

Project Brief + IS Plan

Authorize
initiation

Req to Initiate a Project

Management

Direction

Initiation
Notification

Initiating a
Project (IP)

Delivery

By Frank Turley
Management-Plaza.com

Corporate or Programme Management

End Stage Report


Next Stage Plan
or Exception Plan

(SB) Managing a
Stage Boundary

Controlling a Stage (CS)

DP : Au th o rize th e P ro je c t
- 2nd control point for Project Board
In p u ts
- Project Initiation Documentation
- Request to Deliver a Project?
Ou tp u ts
- Authorize the Project
- Approved PID
- Notification to Corp/Programme

DP : Au th o rize a S ta g e ...
- 3rd control point for Project Board
In p u ts
- End Stage Report
- The Next Stage Plan
Ou tp u ts
- Authorize next stage

Notification -- Notification/Authorization
Mgmt Prod -- Management Product

Fig 3.12 DP: Authorize the project