Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

Petroleum Development Oman L.L.C.


Specification for Pressure Vessels

Document ID

SP-2069

Document Type

Specification

Security

Unrestricted

Discipline

Owner

Issue Date

Version

Mechanical_Static

Abdulnabi Al-Balushi, UEP/1S

31-Dec 2012

1.0

Keywords: This document is the property of Petroleum Development Oman, LLC. Neither the whole
nor any part of this document may be disclosed to others or reproduced, stored in a retrieval system,
or transmitted in any form by any means (electronic, mechanical, reprographic recording or
otherwise) without prior written consent of the owner.

Page 1

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

This page was intentionally left blank

Page 2

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

Document Authorisation

Authorised For Issue

Page 3

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

ii Revision History
The following is a brief summary of the 4 most recent revisions to this document. Details of
all revisions prior to these are held on file by the issuing department.

Version No.

Date

Author

Scope / Remarks

Verison 0

Sep 08

E.S. Mahadevan, UEP/12M

Version 1

Dec 12

Basanagoud
UEP121S

Specification for Pressure Vessels Initial issue.


Second issue Some requirements
modified/added (See Appendix-9).

Biradar,

iii Related Business Processes


Code

Business Process (EPBM 4.0)

EP.64

Design, Construct, Modify and De-Commission Facilities

iv Related Corporate Management Frame Work (CMF)


Documents
The related CMF Documents can be retrieved from the Corporate Business Control
Documentation Register TAXI.
Refer to Section 2 Applicable Standards, Specifications and Codes of this Specification for
Related Corporate Frame Work (CMF) Documents

Page 4

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

TABLE OF CONTENTS
1

INTRODUCTION .............................................................................................................. 7
1.1

PURPOSE AND OBJECTIVES ................................................................................... 7

1.2

CHANGES TO THE SPECIFICATION ........................................................................ 7

1.3

DEFINITIONS AND ABBREVIATIONS ....................................................................... 8

1.4

USAGE ........................................................................................................................ 9

1.5

ADHERENCE TO SPECIFICATIONS ......................................................................... 9

1.6

HEALTH, SAFEY AND ENVIRONMENT .................................................................... 9

1.7

SUMMARY OF MAIN CHANGES ............................................................................. 10

APPLICABLE STANDARDS, SPECIFICATIONS AND CODES..................................... 11


2.1

COMPANY STANDARDS ......................................................................................... 11

2.2

SHELL GROUP STANDARDS.................................................................................. 11

2.3

SHELL STANDARD DRAWINGS ............................................................................. 12

2.4

INTERNATIONAL STANDARDS .............................................................................. 14

2.5

COMPANY AND SHELL GROUP STANDARD DATA / REQUISITION SHEETS .... 14

2.6

LIST OF COMPANY APPROVED SUB-VENDORS ................................................. 14

2.7

COMPLIANCE WITH STANDARDS ......................................................................... 15

2.8

LANGUAGE AND UNITS OF MEASUREMENT ....................................................... 15

2.9

CONFLICTING REQUIREMENTS ............................................................................ 15

SCOPE OF SUPPLY....................................................................................................... 16
3.1

MECHANICAL EQUIPMENT .................................................................................... 16

3.2

SERVICES ................................................................................................................ 16

3.3

SPARE PARTS ......................................................................................................... 16

3.4

ENGINEERING SERVICES ...................................................................................... 17

3.5

GUARANTEE / WARRANTY .................................................................................... 17

3.6

EXCLUSIONS ........................................................................................................... 18

DESIGN .......................................................................................................................... 19
4.1

MECHANICAL REQUIREMENTS ............................................................................. 19

4.2

MATERIALS OF CONSTRUCTION .......................................................................... 22

4.3

SURFACE PREPARATION AND PAINTING ............................................................ 22

QUALITY ASSURANCE ................................................................................................. 23


5.1

GENERAL ................................................................................................................. 23

5.2

QUALITY SYSTEM ................................................................................................... 23

INSPECTION & TESTING REQUIREMENTS ................................................................ 24


6.1

INSPECTION REQUIREMENTS .............................................................................. 24

6.2

TESTING REQUIREMENTS ..................................................................................... 26

6.2.1

Hydrostatic Test ....................................................................................... 26

6.2.2

Site Supervision for Testing & Commissioning ....................................... 26

DOCUMENTATION REQUIREMENTS .......................................................................... 27


7.1

Page 5

INFORMATION TO BE SUBMITTED ALONGWITH THE BID ................................. 27

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC


7.2

Revision: 1
Effective: Dec-12

INFORMATION TO BE SUBMITTED AFTER ORDER ............................................. 27

7.2.1

Drawings and Documents to be submitted after Order ........................... 27

7.2.2

Material Certificates ................................................................................. 27

7.2.3

Test Certificates ....................................................................................... 28

7.3

METHOD OF DOCUMENTATION TRANSMISSION ............................................... 28

7.4

IDENTIFICATION ...................................................................................................... 28

7.5

DATA ......................................................................................................................... 28

7.6

TRANSMITTAL ......................................................................................................... 28

7.7

MANUALS ................................................................................................................. 29

7.8

RECORD CARDS ..................................................................................................... 29

PACKAGING & PRESERVATION FOR SHIPMENT ...................................................... 30


8.1

PACKING REQUIREMENTS .................................................................................... 30

8.2

CRATING IDENTIFICATION..................................................................................... 30

PLANNING & SCHEDULING .......................................................................................... 32


9.1

GENERAL ................................................................................................................. 32

9.2

MEETINGS ................................................................................................................ 32

9.2.1

Kick-off Meeting ....................................................................................... 32

9.2.2

Vendor pre-manufacturing Meeting ......................................................... 32

9.2.3

Review Meetings...................................................................................... 33

9.3

REPORTING ............................................................................................................. 33

9.4

PURCHASE ORDERS .............................................................................................. 33

APPENDICES :....................................................................................................................... 34
APPENDIX-1

ENVIRONMENTAL & SITE CONDITIONS.............................................. 35

APPENDIX-2

EQUIPMENT DATASHEETS & DRAWINGS .......................................... 36

APPENDIX-3

REQUISITION FOR ENGINEERING DOCUMENTS (RED FORMS) ..... 45

APPENDIX-4

TABLE OF COMPLIANCE....................................................................... 55

APPENDIX-5

ALLOWABLE NOZZLE LOADS .............................................................. 58

APPENDIX-6

SPIR FORMAT ........................................................................................ 59

APPENDIX-7

USER FEEDBACK PAGE ....................................................................... 63

APPENDIX-8

INSPECTION AND TEST PLAN (ITP) FORMAT .................................... 64

APPENDIX-9

DOCUMENT CHANGE IDENTIFICATION TABLE ................................. 70

Page 6

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

1 INTRODUCTION
1.1

PURPOSE AND OBJECTIVES

Specifications (SP) contain information/requirements on PDO facilities that are either used
repeatedly, or that are retained for future reference. These documents are intended for use
by the Company and its nominated Consultants and Contractors. It is the responsibility of the
User to ensure that he is using latest revision of this specification
The SP system is intended to:
Publish guidelines or codes of practice.
Set the Company standards.
Form a basis of technical specifications for the procurement of equipment or technical
services.
Disseminate and record engineering information, experience and procedures.
This Document is fully restricted for PDO. The accessibility for this document shall be
maintained by PDO Mechanical Corporate Functional Discipline Head (CFDH) and his
technical focal point.
This specification together with standard drawings, SPs, DEPs as mentioned in section 2
sets out the minimum requirements for the design, engineering, supply of materials,
fabrication, assembly, inspection, testing, transportation, installation, commissioning
supervision, functionality and supply of Pressure Vessel package. It has been written in a
format that enables the Project engineer and the Consultant to easily and uniformly prepare a
requisition and purchase Pressure Vessels, storage (atmospheric) vessels, pressure parts of
filters, shell & tube heat exchangers etc. for a variety of applications in PDO.
For a specific purchase the Project Engineer / Consultant shall:
Follow this specification in general and do not require to produce additional specification. But
in case of any project or equipment specific requirements, which are different from the ones
specified in this specification, shall be prepared and attached as an amendment/addition to
the particular sections of this specification.
Ensure that the Vendor receives the applicable documentation listed in subsections 2.1, 2.2,
2.3 & 2.5.
Ensure that procedures for Vendor Drawings/Documentation are in accordance with
SP-2047 'Preparation and Content of Engineering Drawings' and Section 7 of this
specification.
This specification shall be used in conjunction with relevant equipment data sheets in the
DEP format attached in Appendix-2 and Environmental & Site Conditions attached in
Appendix-1. The User shall complete/follow these data sheets as applicable.

1.2

CHANGES TO THE SPECIFICATION

Custodian of this document is specified in Document Authorisation section of this document


in page 3. Any user of this document, who encounters an inaccuracy or an ambiguity, is
requested to notify the Custodian, using the SP User Feedback Page included in Appendix-7.
Reviews, modifications and adjustments to the document will normally be made by the
Corporate Functional Discipline Head (CFDH) for Mechanical Engineering every four years or
earlier when justified.

Page 7

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC


1.3

Revision: 1
Effective: Dec-12

DEFINITIONS AND ABBREVIATIONS

The following Definitions, terms and abbreviations used in this document, are defined below:
GENERAL DEFINITIONS
Shall
Should
May
Include,
Including

Includes,
-

Company /Principal Consultant


-

EPC Contractor
Contractor

/
-

Purchaser

Scope

User

Vendor/Supplier

Sub-Vendor

Inspector

Others

The word 'shall' is to be understood as mandatory.


The word 'should' is to be understood as strongly recommended.
The word 'may' is to be understood as indicating a possible course of
action.
If the word include or includes or including is used in any document and
this specification, it shall be taken as having the meaning including but not
limited to and shall not be considered as creating or inferring any limitation
on the description that follows if other components/equipments required
Petroleum Development Oman L.L.C. Muscat, Sultanate of Oman.
A contracted party by the Company who is responsible for providing
design engineering and other related consultancy service under a
contract.
A contracted party by the Company who is responsible for providing
design engineering, procurement and construction service under a
contract.
A party, who places the order on, or requests tender from, the Vendor/
Supplier. This can be the Company/ Contractor.
All works executed and all services carried out by the Vendor/Supplier in
accordance with this Specification and its referenced standards and data
sheets.
A responsible party who applies this Specification in the procurement of
specified equipment.
A party responsible for the supply of equipment, materials or productrelated services in accordance with this Specification and its referenced
standards and data sheets. All Sub-Vendors shall be subject to written
approval by the Company. All terms and conditions applicable to the
Vendor shall be applicable to the Sub-Vendor as well.
A party appointed by the Vendor for supply of equipment, materials or
product-related services in accordance with this Specification and its
referenced standards and data sheets.
Any person/party whom the Purchaser certifies as acting for and on
behalf of the Company to inspect items to be purchased and/or the work
done by the Vendor/Sub-Vendor.
Any party contracted by the Purchaser to supply equipment, services,
material which are not part of the scope mentioned in this specification.

GENERAL ABBREVIATIONS
API

American Petroleum Institute

ASME

American Society of Mechanical Engineers

CSR

Construction Site Representative

DEP

Design and Engineering Practice (Shell Group standard)

E-SPIR

Electronic Spare Parts Interchangeability Record (Company


standard)

HAZOP

Hazard and Operability Analysis

ISO

International Organisation for Standardisation

ITP

Inspection and Test Plan

PT

Liquid Penetrant Testing

PMI

Positive Material Identification

MESC

Materials and Equipment Standards and Code

Page 8

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

MT

Magnetic Particle Testing

NDT / NDE

Non-Destructive Testing / Non-Destructive Examination

PDO

Petroleum Development Oman LLC

PEFS

Process Engineering Flow Scheme

PR

Procedure

PWHT

Post Weld Heat Treatment

RED

Requisition for Engineering Documentation

RT

Radiographic Testing

SP

Specification (New Company standard)

TPI / TPIA

Third Party Inspector / Third Party Inspection Agency or Authority

UT

Ultrasonic Testing

NOTE: Contractors, Consultants, Suppliers, Vendors and users SHALL ensure the Company
is consulted for any deviations on "SHALL" and "SHOULD" requirements through
company variance tracking tool.

1.4

USAGE

This Specification together with the referenced standards and data sheets shall form the
purchase requisition package for Pressure Vessels, storage vessels, filters, etc. as required
by the Company.
The Consultant / EPC Contractor may consider augmenting this SP under exceptional
circumstances where it may not precisely meet either enquiry or purchase requirements (eg.
In case of special equipment). Nominally it is anticipated that this SP and data requisition
sheets should finalise fully meaningful enquiry and purchase without generating additional
documentation. Under certain exceptional cases the additional requirements, project or
equipment specific special requirements/changes shall be specified as a separate
amendment to this SP subjected to approval by the Company.

1.5

ADHERENCE TO SPECIFICATIONS

The Vendor shall provide an itemized list of any additional projects specific comments or
exceptions to this specification and its appendices. These shall be listed on the Table of
Compliance provided in Appendix-4 for review & approval by Purchaser. Unless referred to
in these listings, it will be assumed that all specifications are adhered to and that they do not
have implications with respect to cost, delivery and integrity of the plant. Only those
comments/exceptions that are accepted by the Company, in writing, shall be incorporated
into the Purchase Specification at time of order. Note that lead times will not be considered
by the Company as a justifiable reason for using alternate Vendors/deviations.

1.6

HEALTH, SAFEY AND ENVIRONMENT

The Vendor shall throughout the progress of the work have the strongest regard for the
Health Safety and Environment (HSE) of all persons and/or places upon and around the
worksite and shall keep the worksite and the work in an orderly state appropriate to the
avoidance of danger to all persons and properties and shall provide its personnel, at the
Vendors cost, with protective clothing and equipment as may be required for the work under
the PDO HSE regulations.

Page 9

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC


1.7

Revision: 1
Effective: Dec-12

SUMMARY OF MAIN CHANGES

This SP is a revision of the SP-2069 dated September 2008. Major Technical Changes are
listed in Appendix 9.

Page 10

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

2 APPLICABLE
CODES

STANDARDS,

Revision: 1
Effective: Dec-12

SPECIFICATIONS

AND

This SP shall be read in conjunction with the latest revision of the following Standards,
Specifications and Codes.
The Vendor shall also consider all other relevant SPs, DEPs, Shell Standard Drawings and
International Standards, which may not be mentioned here but are listed within these major
specifications, standards and codes. The applicable editions shall be the editions in force at
the date of the enquiry requisition / order or as mutually agreed during purchase order. The
international standards shall be read in conjuction with the corresponding DEP amendment.
It should be noted that references to DEP's and International standards within this SP are
based on the current revision of those standards at the time of publication of this SP. The
Vendor is deemed to be in possession and familiar with specifications, standards listed being
a regular supplier to Company. If any of the documents listed are not in the Vendors
possession, same shall be obtained from the Consultant / Purchaser. Not possessing the
referred standards / specifications shall not be a cause for deviation or non-compliance.
Including this SP the following engineering specifications shall be followed:

2.1

COMPANY STANDARDS

SP-1171

Specification for Quality Management System Requirements for


Product and Service

SP-1173

Welding of Metals

SP-1246 (Part 1 to 5)

Specification for Painting and Coating of Oil and Gas Production


Facilities

SP-1275

Specification for Civil and Works - Design Criteria Manual

SP-2020

Flange connections Bolts Torquing & Tensioning

SP-2041

Specification for Selection of Cracking-Resistant Materials for H2S


Containing Environments

SP-2047

Preparation and Contents of Engineering drawings

STD-2-3950-001

Foundation bolts (J type to be used for horizontal/vertical Vessels)

STD-4-0304-001

Earthing Boss of Steel Structures, Tanks, Vessels, etc.

2.2

SHELL GROUP STANDARDS

DEP 30.10.02.11-Gen

Metallic Materials-Selected Standards

DEP 30.10.02.15-Gen

Materials for use in H2S-containing environments in oil and gas


production (amendments and supplements to ISO 15156:2009)

DEP 30.10.02.16-Gen

Hydrogen induced cracking sensitivity test


(amendments/supplements to NACE TM0284)

DEP 30.10.02.17-Gen

Wet H2S requirements for Downstream pressure vessels and


piping

DEP 30.10.02.31-Gen

Metallic Materials-Prevention of Brittle Fracture in new assets

DEP 30.46.00.31-Gen

Thermal Insulation

DEP 30.48.40.31-Gen

Thermal Spray Coatings of Aluminium

DEP 31.10.00.10-Gen

Material Traceability and Positive Material Identification (PMI)

DEP 31.10.03.10-Gen

Symbols & Identification System Mechanical

Page 11

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Revision: 1
Effective: Dec-12

Petroleum Development Oman LLC

DEP 31.20.20.31-Gen

Internals for Columns

DEP 31.22.05.11-Gen

Gas/Liquid Separators Type selection and design rules

DEP 31.22.05.12-Gen

Liquid/Liquid and Gas/Liquid/Liquid (three-phase) Separators


The selection and design rules

DEP 31.22.10.35-Gen.

Manufacturing Reports for Pressure Vessels

DEP 31.22.20.31-Gen

Pressure Vessels(based on ASME Section VIII)

DEP 34.00.01.30-Gen

Structural design and engineering

DEP 34.19.20.11-Gen

Fire Proofing of Steel Structures

DEP 39.01.10.11-Gen

Selection of materials for life cycle performance (Upstream


facilities) - Materials selection process

DEP 39.01.10.12-Gen

Selection of materials for life cycle performance (Upstream


facilities) - Equipment

DEP 74.00.10.10

Shop and field pressure testing of piping systems

DEP 70.10.90.11-Gen.

Spare Parts.

2.3

SHELL STANDARD DRAWINGS

S 10.010

Vortex breakers for nozzles

S 10.016

Flanges for Non-Pressure Piping Connections Inside Vessels

S 10.030

Lifting lug for Top covers (material: carbon steel, low alloy steel or
stainless steel

S10.045

Anchor Bolt with sleeve for concrete foundations and structures

S10.056

Typical details for insulation collar for carbon, low-alloy steel and
stainless steel apparatus

S 10.070

Davit for ANSI or BS flanges, DN 300-600mm (12 24), classes


150-600 incl.

S 10.101

Equipment Nozzles

S 10.103

Typical details of bush-lined, overlay welded and clad steel


nozzles

S 10.114

Name plate with bracket for vessels and heat exchange


equipment

S 10.115

Typical details of lifting trunnion for vertical vessels

S 10.116

Bolting of Non-standard Flanges with Metric Screw Threads

S 10.119

Grab rungs and steps for Manways

S 20.001

Skirts, cylindrical and conical

S 20.002

Fireproof protection of Skirts

S 20.003

Support ring for insulation

S 20.004

Anchor bolt rings for lugs and base plate for columns

S 20.015

Typical details of Schoepentoeter (vane feed inlet) (type II)

S 20.016

Typical details of Schoepentoeter (vane feed inlet) (type III)

S 20.017

Typical details of Schoepentoeter (vane feed inlet) (type IV)

S 20.019

Typical details of Schoepentoeter (vane feed inlet) Vane ladder-

Page 12

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

supports and general notes


S 20.020

Typical details of schoepentoeter (vane feed inlet) with single section


vane ladder, max. height 800 mm (type 1A)

S 20.021

Typical details of schoepentoeter (vane feed inlet) with catcher cap


(type 1B)

S 20.022

Typical details of schoepentoeter (vane feed inlet) with multiple


section vane ladder (type 1C)

S 20.025

Typical details of schoepentoeter (vane feed inlet) (type Hi Fi)

S 20.026

Typical details of schoepentoeter (vane feed inlet) (type Hi Fi) vane


distribution and general notes

S 20.028

Typical details of Demisters

S 20.029

Typical details of Demister attachments

S 20.030

Typical details of Demister supports

S 22.001

Saddles for Horizontal vessels- Shell dia. Nom 150mm OD upto


and Including 1000mm OD.

S 22.002

Saddles for Horizontal vessels- Shell dia. 1050mm OD upto and


Including 3600mm OD.

S 22.003

Sliding plates for saddles of horizontal vessels.

S 22.005

Supports for Vertical vessels shell dia. 350mm OD upto and


Including 1500mm OD (half skirts).

S28.001

Stairways, general arrangement

S28.002

Stairways, stair details

S28.003

Stairways, hand railing connections

S28.004

Stairways, intermediate platform

S28.005

Stairways, top connections of stringers

S28.006

Hand railing, type A

S28.007

Hand railing, type B

S28.008

Hand railing, type C

S28.009

Hand railing, connection of railing to concrete type A

S28.010

Hand railing, connection of railing to concrete types B & C

S 28.011

Ladder General arrangement to columns, stacks and structures

S28.012

Ladder - typical details of sliding/fixed connections

S28.013

Platforms - cleats and brackets to columns (design load max 300


kg)

S28.014

Platforms - cleats and brackets to columns (design load over 300


kg)

S28.015

Davit general arrangement and typical details

S28.016

Grating typical of steel curb angles and cheqered plate

S28.020

Anchor bolts

S28.022-001

Grating, type I (sheet 1 of 3)

S28.022-002

Grating, type II (sheet 2 of 3)

S28.022-003

Grating, type III (sheet 3 of 3)

S28.022-004

Grating, type IV

Page 13

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

S28.022-005

Grating, type V

S28.023

Fastening of apparatus to fireproofed beams

2.4

Revision: 1
Effective: Dec-12

INTERNATIONAL STANDARDS

ASME Section VIII Div.1

ASME Boiler and Pressure Vessel Code Rules for Construction


of Pressure Vessels

ASME Section VIII Div.2

ASME Boiler and Pressure Vessel Code Alternative Rules for


Construction of Pressure Vessels

ASME Section V

Non-Destructive Examination

ASME Section IX

Welding and Brazing Qualification

ASME B 16.5

Pipe Flanges and Flanged Fittings

ASME B 16.47

Large diameter steel flanges NPS 26 thro NPS 60

NACE MR0175 / ISO Petroleum and natural gas industries - Materials for use in H2S
15156
containing environments in oil and gas production, Part1, 2 & 3.
ISO 10474

Steel and Steel Products inspection Documents.

BS/DS/DIN-EN 10204

Metallic products - Types of inspection documents

ISO 9001: 2008

ISO Quality Management System Requirements.

2.5

COMPANY AND SHELL GROUP STANDARD DATA / REQUISITION


SHEETS

DEP 30.10.01.92-Gen. -

Mass/Centre of Mass of Equipment

DEP 31.22.00.94-Gen. -

Pressure Vessels (columns, reactors, accumulators etc.)

DEP 31.22.00.98

Pressure vessels - ASME - User's design specification for


general service pressure vessel and engineered pressure
vessel

DEP 31.22.05.93-Gen. -

Demister Mat

DEP 31.20.41.93-Gen

Schoepentoeter

DEP 31.27.20.93-Gen. Strainers/Filters (use this datasheet instead of Pressure


Vessels datsheet only in case of Filters)

2.6

LIST OF COMPANY APPROVED SUB-VENDORS

The Vendor shall select sub-vendors from the list of relevant Company approved Vendors
list. The Vendor shall in respect of this order, procure third party material from sub-vendors
listed in the Companys approved list, unless the particular type of material is not covered by
the list, or a special dispensation to deviate from the list has been granted in writing by the
Company during the technical evaluation and award stages. Any item not covered in the
sub-vendors list shall be brought to the attention of the Company for agreement before any
sub-order is placed. The Vendor shall ensure that the equipment proposed to meet this
specification is designed and manufactured for the intended performance/service
requirements, for safe operation and to achieve the highest possible level of reliability and
availability of the package.

Page 14

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC


2.7

Revision: 1
Effective: Dec-12

COMPLIANCE WITH STANDARDS

The Vendor/ Supplier shall complete the Table of Compliance (Appendix-4) and highlight
deviations if any from standards and specifications. The Purchaser shall obtain the written
approval from the technical authority within the Company for any deviations from this
Specification.
Only those deviations that are approved by the Company shall be deemed to be part of the
scope. In all cases the Company shall determine the compliance of the design carried out
and works executed by the Vendor/Supplier in accordance with this Specification.

2.8

LANGUAGE AND UNITS OF MEASUREMENT

The English language and the SI system in accordance with DEP.00.00.20.10-Gen of units
shall be used throughout for all documentation and drawings. Where necessary for a specific
application, alternative units may be indicated in brackets together with the SI units.

2.9

CONFLICTING REQUIREMENTS

All conflicts between the requirements of this specification, related specifications, standards,
codes, requisition data sheets and data sheets shall be referred to the Company for
clarification before proceeding with the manufacture of the affected parts.
Vendor shall make a formal request with full supporting information when a deviation from
standard is required.
Vendor is requested to notify any inaccuracy or ambiguity encountered in this document.
Nothing contained in this specification and related documents shall be construed as relieving
the Vendor of the responsibility for designing and manufacturing the equipment to meet the
specified operating conditions.
The general hierarchy of documents shall be followed as below:
First priority

The Contract / Purchase order

Second priority

This specification with attached datasheets

Third priority

Company SPs

Fourth priority
drawings .

Company ERDs.Shell Group DEPs & Shell standard

Fifth priority

International standards & codes

In case of conflict among documents or sections relating to this specification, the more
stringent requirements shall apply, unless otherwise agreed in writing.
Where the Company technical specifications refer to or amend international codes and
standards, these international codes and standards shall be deemed to be part of the
specifications.
Where the technical specifications refer to other specifications, standards and codes, these
shall be deemed part of the specifications.

Page 15

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

3 SCOPE OF SUPPLY
The scope of supply shall include but not limited to the equipment and services defined below,
detailed in this specification, on the attached data or data/requisition sheets, standard
drawings and in accordance with the applicable standards, specifications and codes. The
Vendor shall supply complete, assembled and tested equipment including, but not limited to,
the scope of supply detailed below unless otherwise specified. Items which are optional and
required only if specified are marked with an asterisk (*) below. The Suppliers scope of supply
shall include, but not be limited to:-

3.1

MECHANICAL EQUIPMENT

a)

The equipment complete with all parts including supports, spares etc..

b)

All Internals viz. schoepentoeter, demister mat, internal dip/header pipe, vortex
breaker, baffles, column trays, plate packs etc. as applicable and specified in the
specification/datasheets including supports for internals.

c)

Manhole with davit arrangement.

d)

Lifting lugs / trunnions, cleats/clips for pipe support, ladder, platform, insulation, &
fireproofing (if required) etc.

e)

The vessels shall be provided with ASME code stamp.

f)

Fabrication, supply, certification & guarantee of the equipment and internals.

g)

Surface preparation and painting as per SP-1246 Part 1 to 5.

h)

Minimum 2 Nos. of Earthing bosses for each equipment.

i)

Nozzles with blind flanges and wherever counter flanges are in Vendors scope shall
be provided with gaskets and fasteners alongwith spares (10% bolts (min. 2nos.) and
200% gaskets).

j)

Nameplate & bracket for each Vessel.

k)

Foundation template for vertical skirt supported vessel.

l)

Special tools, if any, for installation, commissioning, maintenance and start-up.

m)

All buried vessel shall be supplied with external impressed current cathodic protection
(by others not by vessel vendor).

3.2

SERVICES

a)

Transportation & Delivery to Project Site or as agreed in Purchase Order specified


Location.

b)

Assistance/Supervision during installation & commissioning (*).

3.3

SPARE PARTS

a)

Installation & Commissioning spares 10% bolting (min. 2nos.) for each size and
200% gaskets for each blinded flange joints including internal joints. These spares
shall be part of vessel supply and to be included in vessel offer.

b)

Two years Trouble free operation spares 10% bolting (min. 2nos.) for each size and
300% gaskets for each blinded flange joints including internal joints.

The Vendor shall advise on the requirement of any additional spare parts & special tools and
shall state the lead times and costs in the offer. Vendor shall submit the same by filling in the
SPIR format, attached in Appendix-6.

Page 16

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

The Vendor shall provide a separate itemized price list of spare parts for two years Trouble
free operation along with the bid.
The Vendor shall also complete the E-SPIR (Electronic Spare Parts and Interchangeability
Record, DEP 70.10.90.11) data for 2 years of operation in accordance with the instructions
for use of E-SPIR information. The E-SPIR information shall be submitted within the period
indicated in the RED form to enable processing and ordering spare parts such that these can
be delivered within the period of the purchase order.

3.4

ENGINEERING SERVICES

This specification shall in no way relieve the Vendor from final guarantee as to material,
equipment, workmanship and performance of the vessel. The Vendor shall assume overall
responsibility for the design and engineering of all equipment supplied, as indicated in this
specification. This shall include, but not necessarily be limited to:
a)

Resolving engineering questions relating to equipment within the scope of supply.

b)

Providing / coordinating the complete detailed mechanical design as specified in this


specification and the referenced specification, standards and / or the datasheets for
all equipment & components within the scope of supply (including foundation loads,
design (size and number) of foundation bolts
and design of internals like
Schoepentoeter, demister etc. as per DEP/other standards).

c)

Inspection and Testing along with material certification.

d)

Company approved 3 party inspection agency to be appointed by the Purchaser for


inspection / testing & certification of all equipment and lifting appliances, in addition to
the authorized inspectors for design approval and code (ASME) stamping of vessels.

e)

Installation of internals at Vendors shop and then if feels necessary (due to criticality
and to avoid damage during transportation and installation) remove the internals and
deliver as loose supply in separate cratings, alongwith site installation procedure.

f)

Ensuring that all equipment supplied meet the requirements of the specifications and
standards referenced herein.

g)

Providing design parameters for foundations and overhead lifting facilities.

h)

Providing all documentation as per RED form attached in Appendix-3.

i)

Furnishing progress reports, third party inspection reports etc.

j)

Providing expediting services for all sub-Vendors and ensuring timely and proper
execution of the job.

k)

Attending Vendor coordination meeting / kick-off meeting / pre-inspection meeting at


Company / Purchaser / Consultant / Contractors office.

l)

Coordinating with the Purchasers design Consultant for all design / technical matters.

m)

Providing quality assurance for all sub-Vendors with respect to ISO 9001:2008.

n)

When ever sizing of vessel is not specified in data sheet OR specified as


preliminary/check, contractor/vendor shall perform sizing calculation as per relevant
DEPs.

rd

3.5

GUARANTEE / WARRANTY

The equipment shall perform satisfactorily under the operating conditions specified in this
Specification and datasheets and shall be fit for the purpose intended. The guarantee /
warranty requirements are as per the General Terms and Conditions. The Vendor shall
guarantee the equipment minimum as follows:

Page 17

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

i)

Process design (eg. Internals design) / performance as specified in data/requisition


sheet included in Appendix-2 of this specification.

ii)

Mechanical design, structural integrity, material and workmanship.

iii)

If any defect or mal-performance is observed during the guarantee period, the Vendor
shall make all necessary alteration, repair or replacement free of charge.

Unless a specific exception is given in the Vendors tender, it shall be understood that he
guarantees and agrees to the above.

3.6

EXCLUSIONS

The following are excluded from the Vendors scope of supply, however, shall be part of
Purchasers scope:

Concrete foundation design based on Vendor supplied technical data.

External access ladder / operation platform / grating / handrailing / pipe supports (but
Vendor shall provide suitable support clip/cleats for these parts. Vendor shall quote
unit price on per kg. basis for ladder, cleats, supports and per sq. metre basis for
platform).

Supply of Anchor bolts.(sizing is in Vendor scope)

Lifting & hoisting (but Vendor shall provide weight of all equipment parts which are to
be removed / installed during installation & maintenance).

Site installation and commissioning (optional).

Any instrumentation.

Any electrical connection.

Insulation (but cleats / supports for insulation attached to vessel shall be provided).

Fire proofing (but fire proofing supports attached to skirts/legs shall be provided).

Process piping from vessel nozzle flanges, unless otherwise specified.

Page 18

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

4 DESIGN
4.1

MECHANICAL REQUIREMENTS

4.1.1

The equipment shall be designed, fabricated and tested in-accordance with DEP
31.22.20.31-Gen., ASME VIII Div 1 / Div.2, as indicated on the datasheets attached
in Appendix-2. In addition to the design approval and code stamping by the
rd
authorized inspection agency, the Purchaser shall appoint a Company approved 3
party inspection agency, who are different from the authorized inspection agency for
certification of design and inspection.

4.1.2

Process design (calculation) for internals, mechanical design of all parts of the vessel
are responsibility of the Vendor.

4.1.3

All equipment shall be designed for a service life of 30 years OR as specified in


project design basis which ever is lower.

4.1.4

All the internals shall be assembled at the Vendors works to check for proper fit and
alignment. To avoid damage during transportation/installation, the internals shall be
removed prior to transportation and delivered loose in separate cratings alongwith
site installation procedure. Generally, internals shall be of removable type and should
be bolted to the internal supports and direct welding to equipment wall should be
avoided, but whenever internals are required to be welded to equipment wall, Vendor
to obtain necessary approval from the Company.

4.1.5

All of the equipment internals shall be designed and constructed so that it is possible
to remove them through the manhole.

4.1.6

All nozzle flanges and body flanges shall be welding neck raised face (WNRF) or
long weld neck raised face (LWNRF) type, 3.2-6.3 microns face finish as per ASME
B 16.5, unless otherwise specified on the datasheets.

4.1.7

Bolting and threads shall comply with ISO metric standards, except for ASME flange
connections, which shall be in-accordance ASME B16.5.

4.1.8

Bolt holes on all nozzle flanges shall straddle to natural centre line.

4.1.9

Lifting lugs shall be provided and attached to pressure containing parts via doubler
plates. The doubler/reinforcement plates shall be provided with NPT tapped telltale holes and these holes shall be closed by filling with non-corrosive compound
after testing and final painting. Lifting lugs and associated supports and bracing shall
be designed for transportation and installation of the equipment considering a
minimum impact factor of 2. Plates to which lifting lugs are attached shall be
ultrasonically examined over an area extending 100mm beyond the edges of the
attachment welds to ensure that it is free from laminations/defects. All lifting lugs and
the lifting lug welds (where possible) shall be ultrasonically tested, 100% MT/PT and
visual testing.

4.1.10 All nozzle openings shall be flush with the inside of the vessel and sharp edges shall
be rounded off to a radius of 3mm unless otherwise specified. Nozzles shall be
provided with reinforcing pads required as per design code and for the preliminary
allowable nozzle loads specified in Appendix-5. The Purchaser will advise the Vendor
on the actual nozzle loads during detailed design (after award of Purchase Order).
Vendor to design the nozzles/vessel for these loads.
4.1.11 Body flanges shall be provided for Compressor Scrubbers and vessels with
removable type internals, viz.Shoepentoeter, Mistmat, Swirldeck, trays, etc., which
are less than or equal to 1200mm vessel inside diameter and as specified in the
datasheet. Location of the body flange shall be agreed with the Company.
4.1.12 Horizontal vessels shall be saddle supported with one saddle fixed and the other
sliding alongwith sliding plate as per Shell standard drawing S.22.003. Vendor shall
consider saddle friction factor 0.3 for Steel plate to concrete/steel and 0.1 for Steel
plate to PTFE/NYLON plates in ZICK analysyis.

Page 19

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

4.1.13 Vertical vessels shall be either full skirt supported with inspection / access openings
and skirt vents or leg supported or lug/bracket supported as specified in the
datasheets.
4.1.14 All bottom head piping which penetrate vertical pressure vessels inside the skirt shall
be extended outside the skirt with pipe flanged in the horizontal run. Welding of
nozzles or piping to vessel skirts shall not be permitted. Skirt penetration point shall
be reinforced with a sleeve three (3) sizes larger than the bottom head piping.
Gusset plates shall be provided to the bottom head piping at the skirt penetration
point, and in no case shall the gusset plates be welded to the sleeve. Adequate
openings shall be provided for maintenance access to the Skirt
4.1.15 Flange inside diameter shall be same as that of mating nozzle neck/shell inside
diameter.
4.1.16 Nozzles shall not be located on longitudinal weld seams and shall avoid girth seams.
4.1.17 Nuts for all external flange joints shall be of heavy hexagonal type. Any external
coating requirements on fasteners shall be as per the applicable piping class.
4.1.18 The equipment supports shall be designed to withstand all induced stresses by
transportation & installation, wind load, operating conditions and pressure testing.
4.1.19 The material and inspection test certification shall be minimum according to ISO
10474 - 3.1B / EN 10204 3.1. All pressure retaining materials shall be certified to
ISO 10474, 3.1C/EN 10204, 3.2 for supplementaory tests viz. Impact, HIC, corrosion,
etc.
4.1.20 Vendor shall provide complete calculation to demonstrate the integrity of all
components including but not limited to Code calculations, nozzle local loading, lifting
lugs, hold down bolting, transportation and wind loading.
4.1.21 Asbestos in any form shall not be used as material for any item, including the
packaging. Molybdenum disulphide compounds shall not be used for any screwed
item.
4.1.22 Minimum nozzle size on all equipment shall be DN50. Smaller size requirement shall
be reduced in piping.
4.1.23 All equipment shall be fitted with two nos. of earthing boss each in accordance with
the drawing STD-4-0304-001.
4.1.24 Nameplate and nameplate bracket as per Shell standard drawing S.10.114. The
nameplate shall be clearly die-stamped with the tag number and other data as per
the standard drawing.
4.1.25 Manway/Access openings shall be provided with blind flange and davit arrangement
as per drawing S.10.070, unless the equipment is provided with cold insulation, in
which case hinge with handle shall be provided to facilitate blind flange/cover
opening. Internal ladder rungs and hand grip shall be provided for easy internal
access to the vessel through manholes.
4.1.26 Proper electrical isolation shall be provided between dissimilar metals (stainless steel
internals, if any, and mating carbon steel parts / supports) to prevent formation of
galvanic corrosion.
4.1.27 Vendor shall indicate the requirements of Impact testing, PWHT, and heat treatment
requirements for the entire equipment / dished ends, if any, in the quotation &
fabrication drawings.
4.1.28 Vendor shall follow the exact location & orientation of nozzles and
requirement/dimensions of cleats/clips for pipe supports, platform, ladder, if any,
provided by Purchaser later during detail engineering.
4.1.29 If a vessel is subject to PWHT then on completion of all painting activities the
following statement shall be stencilled onto the vessel adjacent to the manway(s) in
letters of 50mm high minimum. "Stress Relieved Vessel - No Welding Permitted".

Page 20

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

4.1.30 All gaskets fitted to the equipment shall be new and service gaskets shall be used for
hydrotesting. On no account gaskets shall be reused after hydro-testing.
4.1.31 For vessels with internal weld overlay, the undiluted chemical composition
requirement of the overlay shall be ensured by using a two-layer technique in which
the first layer is applied with a low heat input.
4.1.32 The equipment data sheets are included in Appendix-2. Vendor shall submit updated
completed data sheet along with the offer.
4.1.33 Vendor shall consider Project environmental wind data OR wind speed defined in
the environmental and site condition in Appendix-1 which ever is stringent. Wind
pressure shall be designed according to SP-1275 and DEP 34.00.01.30-Gen,
considering 3-second gust wind speed in the design.
4.1.34 Vendor shall consider sizing of anchor bolts with maximum allowable tensile stress
2
of bolt material as 100 N/mm only.
4.1.35 The Vendor shall provide all details required for the foundation design such as
foundation loads, lay-out and positioning of foundation bolts alongwith template,
requirement of leveling plates, etc. the Vendor shall provide clear drawings and
instructions well in advance.
4.1.36 The Vendor shall indicate the location, weight, and space requirements for
equipment parts, to be removed for normal maintenance. This will enable the design
of hoisting facilities above the equipment (by others).
4.1.37 Wherever corrosion allowance is specified in the datasheet for vessel, one corrosion
allowance thickness shall be added to vortex breaker specified in shell standard
drawing S.10.010.
4.1.38 The weld clearance between two adjacent pressure part welding shall be 2 times the
thickness of thinner part or 50mm, which ever is higher. For non pressure parts, the
weld clearance shall be 5 times thickness of thinner part or 50mm (max). The
distances are measured from the toe of the weld.
4.1.39 All vessels opearating at atmospheric pressure and designed for less than or equal
to 3.5 bar shall be designed as per the requirement of Minimum Service Pressure
Vessels as mentioned in DEP 31.22.20.31.
4.1.40 All other ASME section VIII div 1 pressure vessels shall be designed as per the
requirement of General Service Pressure Vessels as mentioned in DEP
31.22.20.31.
4.1.41 All ASME section VIII div 2 pressure vessels shall be designed as per the
requirement of Engineered Pressure Vessels as mentioned in DEP 31.22.20.31.
4.1.42 No backing strip welding is allowed in pressure parts.
4.1.43 Plates above 16mm and forgings above 50mm thick shall be subjected to UT to
check for any lamination defects.
4.1.44 Minimum of 1.5 mm (1/16 in) corrosion allowance shall be applied for skirt/leg
supports.
4.1.45 All pressure vessels shall be designed with 100% radiography.
4.1.46 All presure vessels designed according to ASME section VIII div 2 shall have integral
reinforced nozzles with extended lips to have butt weld joints to facilitate proper NDT.
4.1.47 Contractor/Consultant/Vendor shall Prepare User Defined Specification (UDS) for all
ASME Section VIII Div.2 designed pressure vessels/equipment. Required Input data
for UDS shall be provided by Purchaser/Company. Approval of UDS from Registered
Professional Engineer (RPE) is in contractors/Consultants/Vendor scope, however
Purchaser/Company shall endorse all input data before RPE approval.
4.1.48 All cold formed statinless steel dished heads shall be subjected to solution annealing.

Page 21

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Revision: 1
Effective: Dec-12

Petroleum Development Oman LLC


4.2

MATERIALS OF CONSTRUCTION

All materials shall be as specified in the datasheets with any additional Requirements
specified in material selection Report. Format of data sheet is attached in Appendix-2.
However, Consultant/ Contractor to confirm the suitability of the specified materials for the
process conditions.
All pressure retaining carbon steel materials shall be supplied in normalized condition.
All materials for sour service and HIC requirements shall be in accordance with requirements
of latest editions of NACE-MR-01-75/ISO 15156, DEP 30.10.02.15 and SP 2041.
All stainless steel and nickel based alloy materials shall be pickled and passivated as per
DEP 30.10.60.31 and SP-1173. Galvanized steel components shall not be used in the
proximity of stainless steel materials.
The material for the vessel and internals shall be fully in accordance with the materials
specified in the datasheet.
Vendor shall take all necessary steps to avoid change of materials during manufacturing and
shall do so only with Company / Purchasers approval.

4.3

SURFACE PREPARATION AND PAINTING

All equipment surfaces shall be prepared and painted in accordance with the requirements of
SP-1246 (Part 1 to 5) Specification for Painting and Coating of Oil and Gas Production
Facilities. For proprietary equipment, the Vendor may offer their standard painting system for
approval by the Company / Purchaser, but this shall be at least equal to the paint system
detailed in SP-1246 (Part 1 to 5) Specification for Painting and Coating of Oil and Gas
Production Facilities .
o

All exposed stainless steel/DSS parts subjected to temperatures above 60 C upto 100 C
shall be painted as per PCS-6 of SP-1246. For temperature more than 100C, SS/DSS parts
shall be protected against external pitting and crevice corrosion by means of coating with
Thermally Sprayed Aluminium (TSA) according to DEP 30.48.40.31.
The Equipment Tag numbers shall be clearly stenciled on all equipment, in a prominent
location.

Page 22

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

5 QUALITY ASSURANCE
5.1

GENERAL

The Vendor shall comply with the requirements of Companys Specification for Quality
Management System Requirements for Product and Service SP-1171.
The Vendor shall appoint an Authorized Inspection Agency. The Vendor shall submit with the
bid, the name of the Authorized Inspection (AI) agency that will be contracted to provide
inspection services, in accordance with the requirements of the specifications, codes and SP1171.
The Purchaser shall nominate a Third Party Inspection Authority (TPIA) to carry out the
Quality Assurance function on the Purchasers behalf. The Purchasers TPIA shall have the
same access as the Purchaser to the Vendors Quality System and the manufacturers
premises to carryout inspection activities.

5.2

QUALITY SYSTEM

The Vendor shall maintain and use a Quality System, which is based on ISO 9001:2008, to
control the work and assure the quality.
The Vendor selected sub-contractors, or suppliers-shall demonstrate that they operate
Quality Systems based on ISO 9001:2008.
The Vendor shall give his sub-contractors or suppliers assistance in attaining the required
standard if necessary. This shall not relieve the Vendor of his responsibility for the quality of
the finished work.
The Purchaser reserves the right to audit the Vendors Quality System and this can be
carried out by the Purchaser or its nominee.
The Vendor shall assign sufficient full time personnel to the project to ensure the Quality
Assurance / Quality Control System, documented in a Quality Assurance / Control manual, is
maintained and kept up-to-date throughout the duration of any purchase order.
A kick-off / co-ordination meeting shall be held between the Vendor and Purchaser, after the
purchaser order placement at design Consultants/Purchasers office in Oman.
At the discretion of the Purchaser the kick-off meeting may be waived.
At the kick-off meeting the Vendor and Purchaser shall review the Inspection and Test Plan
(ITP) submitted with the Tender and shall agree a date for issuing final ITP with Vendor.
The Vendor shall organize a prefabrication meeting to be attended by the Vendor, the
Vendors TPI, the Purchaser and the Purchasers TPIA.
A provisional notice of 10 working days is the minimum required by the Purchaser to attend
the inspection meetings.
Vendor shall keep a material control book, to which the Purchaser shall have access to any
time they wish. The book shall contain Sub-Vendors contact details, purchase orders,
equipment tag no., make/model nos., date of order, delivery and documentation required.

Page 23

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

6 INSPECTION & TESTING REQUIREMENTS


6.1

INSPECTION REQUIREMENTS

Inspection and testing requirements shall be in accordance with the applicable Company,
Shell Group and International standards, with the relevant sections of this specification and
the data sheets.
The Vendor shall specify all of the inspection and testing requirements in the ITP which shall
identify the activities requiring the Purchaser's approval, review, witnessing etc. Vendor shall
submit Separate ITP for sub-vendor activities for Purchaser's approval, review, witnessing
etc. For sour service company shall identify additional Witness/hold points in ITP without any
impact on delivery and purchase Terms and conditions. A typical general ITP is attached in
Appendix-8.
Purchaser reserves the right to inspect every component or item, which will form part of the
pressure vessel. The responsibility for the inspection, certification, etc. of all materials, parts,
etc. lies with the Vendor.
Not withstanding the above, the Purchaser or his authorized representative shall have free
access to all parts of the Vendor's and his Sub-Vendors works at all times during the
manufacturing period.
The Vendor shall be responsible for coordinating the inspection and testing of Sub-Vendor
supplied equipment, and for ensuring that the Purchaser's representatives are given the
necessary access for inspection, and adequate warning of inspection and witness tests.
The Vendor (and all Sub-Vendors) shall give the Company, as required, without charge, all
reasonable facilities for the purpose of inspecting the equipment to ensure that it is
manufactured in accordance with the requisition, drawings and technical specification and
QA/QC procedures and practices.
The Purchaser shall be given a minimum of 21 days notice prior to carrying out any tests on
the equipment covered by this specification.
All equipment shall be inspected for compliance with :

a.
b.
c.
d.
e.
f.

Approved for Construction drawings, latest revision.


Requirements of the Purchaser's requisition and correspondence thereafter.
Applicable standards, which shall also include the sub-referenced standards therein.
Inspection and Test plans (ITP) produced by the Vendor.
Approved process control procedures.
Welding of Metals as per SP-1173

Except as approved by the Purchaser, all equipment shall be presented for inspection in an
unpainted condition.
All measuring instruments required for shop testing shall be furnished by the Vendor, and be
supported by valid calibration certification.
All spare parts shall be subject to the same inspection standards and full material certification
as the purchase order.
Inspectors have the right to request additional inspections or tests to ensure that the
equipment complies with this specification and all relevant codes and standards.

Page 24

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

All welds shall be continuous and wherever sound back welding is not feasible due to
inaccessibility, single side welded joints with GTAW root pass shall be used.
All welding and welding consumables shall be in accordance with SP-1173, unless indicated
otherwise in this specification. Only Low Hydrogen welding consumables shall be used.
Diffusible Hydrogen level shall be less that 10ml/100g weld metal, unless agreed and
approved by the Purchaser. All welding consumables shall have specified mechanical
properties equal to or greater than the material being welded, unless agreed and approved by
the Purchaser.
The Vendor shall supply all necessary equipment and record welding variables during the
Procedure Qualification Record (PQR) Test, production welding and weld qualification tests.
Prior to the start of production welding all WPS with supporting PQR shall be submitted for
approval to the Purchaser. Wherever PWHT is specified, PQR shall be established with 3
cycle PWHT and results shall meet deisgn code requirements.
All pressure retaining butt welds shall be 100% radiographed/UT.
All components including plates, forgings, fittings, welding consumables etc. shall be
checked for impact test requirements to the specified lower design temperature (LDT) as the
minimum design metal temperature (MDMT) to meet the applicable codes and standards.
Vendor shall confirm with the material supplier the required impact test value at specified
LDT conform to the specified impact value as per DEP 30.10.02.31-Gen and applicable
codes and standards. Certified Material Test Report shall clearly specify the test results.
PWHT shall be performed as per the code requirements and as specified in the equipment
datasheet.
Positive Material Identification (PMI) shall be carried out on all wetted parts made of low alloy
and high alloy steels. Extent of PMI shall be carried out as per DEP 31.10.00.10-Gen.
Vendor shall submit PMI procedure with the bid for Company/Purchaser review. .
Vendor shall furnish Inspection Test Plan (ITP) specifying the responsibility, scope of
Authorized Inspection Agency in accordance with SP-1171. The minimum requirements of
inspections for Purchaser are:
a)

The verification of materials and certification of the equipment for conformity with the
specification requirements.

b)

The Hydrostatic test.

c)

The verification of welding procedures, welders qualifications, NDT personnel


qualification, NDT results, heat treatment charts.

d)

Visual examination.

e)

NDT witness / review.

f)

Witness / review of PWHT.

g)

The dimensional check of the equipment as per approved drawing.

h)

The surface preparation and painting application.

i)

The testing of the lifting frame for the transportation of the equipment. The lifting frame
shall be certified by TPIA.

j)

The completeness of shipment including checking of supply of spares and


accessories, Manufacturers Data Book, name plate details.

k)

Material test certification in accordance with ISO 10474/EN 10204 and any additional
requirements of the requisition.

Mill and shop inspection shall not relieve the Vendor from his contractual responsibility for
replacing any defective material and for repairing any defective workmanship that may be
discovered in the field.

Page 25

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

Any defects found by the TPIA shall be rectified in his presence. Where this is not possible or
practical, checklists shall be prepared and signed by the TPIA stating all 'pending items'.
Copies of these lists shall be sent to the Purchaser to enable their subsequent checking.
The equipment shall not be tested or leave the factory before all discovered defects have
been rectified.

6.2

TESTING REQUIREMENTS

This section describes the minimum requirements for the testing of the equipment. This
testing shall be performed in the Vendors works.
The Purchaser reserves the right to observe any of the testing, dismantling, inspection and
reassembly of equipment as specified.
Unless otherwise specified, all testing equipment required shall be provided by the Vendor.
Purchasers witnessing of shop test results shall not constitute a waiver of the Vendors
obligation to provide equipment which meets all specified operating conditions.
6.2.1

Hydrostatic Test

Hydro testing shall be as per the code, this specification, applicable DEPs, data sheets and
Inspection & Testing Plan. Inspector shall witness all hydrostatic tests. Drainage / flushing /
drying of the equipment shall strictly follow immediately after the hydrostatic testing as
specified in DEP 74.00.10.10. The water to be used for the hydrostatic test apart from the
requirements as to chloride content shall be free from sediment, i.e. un-dissolved solids of
any description and as specified in DEP 74.00.10.10.
The equipment shall be cleaned prior to final assembly and hydrostatic testing. After the
hydrostatic test, the equipment shall be drained, dried and cleaned thoroughly of all grease,
loose scale, rust, flux, etc.
6.2.2

Site Supervision for Testing & Commissioning

Purchaser will install and commission the equipment at site. The Vendor shall detail in the bid
the extent of specialist supervision and commissioning, if any, deemed necessary to satisfy
Vendor that installation and operation of the equipment meets the specification and warranty
requirements, the Vendor representative shall satisfy himself that the installation is
acceptable for commissioning of the equipment. For field tesing / commissioning, if any, the
Vendor shall provide the results of any shop tests executed prior to shipment.
The Vendor as an option shall include for supervision during pre-installation of the equipment
to ensure all quality requirements for the installation is within acceptable limits. These may
include but not be limited to
i)

Checking of foundations,

ii)

Anchor bolt type, installation & positioning in foundations.

The above measures should be reflected in the installation section of the manuals. The
Purchaser will commission the system under the direct supervision of the Vendors
specialists, if required. Provision of specialist services at site for installation checks and
commissioning for an estimated period if required, which will be subject to service contract
agreement with the Vendor. The Purchaser will give a minimum of 2 weeks advance notice
for the mobilization of the Vendors specialists in such cases.

Page 26

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Revision: 1
Effective: Dec-12

Petroleum Development Oman LLC

7 DOCUMENTATION REQUIREMENTS
Requirements for Vendor documentation are listed in the Requisition for Engineering
Documents (RED) form included in Appendix-3 and sections below. The Vendor shall prepare
a Vendor Document Register (VDR) or Suppliers Document Schedule (SDS) in the Company
standard format using the above information as a guide. The Vendor shall submit the
Document Register to Purchaser for review and approval together with document delivery
schedule after award and prior to submission of any other documentation. The Document
Register will thereafter form the basis of submission and control of all documents. The
Company title block/drawing number can be included on the front sheet. All documentation
shall be submitted for review/approval to the Purchaser within the committed schedule. It shall
be the responsibility of the Vendor to ensure that the production schedule takes into account
documentation submission, including a two weeks review period by the Purchaser, which
includes document delivery time.

7.1

INFORMATION TO BE SUBMITTED ALONGWITH THE BID

Vendor shall submit all the required documents as specified/identified in the RED form
attached in Appendix-3. In addition to this Vendor shall submit the following:
1. Table of Compliance, Appendix-4 duly completed, signed and stamped.
2. Unit rates for nozzles with flange rating as mentioned in datasheets for sizes NPS2
to NPS 24 and any higher sizes if specified in the datasheets.
2

3. Unit rate for cleats & ladders on per kg basis and platform on per m basis.
4. Commissioning assistance rate per day per person including mobilization and demobilisation charges.

7.2

INFORMATION TO BE SUBMITTED AFTER ORDER

7.2.1

Drawings and Documents to be submitted after Order

The documents/drawings shall be provided as outlined on the RED form, Appendix-3. It is the
Vendor's responsibility to ensure drawings are brought up to 'as built' level. Additional
drawings not specifically listed but of value, shall also be provided in the final package. All
drawings and documents shall be prepared in accordance with DEP 02.00.00.10.The
drawing shall be prepared in AutoCAD latest version and final drawings shall be submitted in
electronic form in addition to the hard copies as part of final document submission.
The text on all drawings and data shall be in English language. Text in the language of the
Vendor may also be shown, provided the English translation is shown in prominent location.
All data, calculations and drawings shall utilize SI metric units.
The design verification by TPIA is required and shall be the Vendors responsibility. The
verification agency shall be subject to Purchaser approval. The documents required by TPIA
are not covered under this specification. The Vendor shall provide all the drawings and
documents required by the TPIA for the approval of design and manufacturing in compliance
with the code.
7.2.2

Material Certificates

Material certificates shall be furnished in accordance with the relevant DEP, ASME, ASTM,
EN 10204 and ISO 10474 standards as amended by this specification and as identified in
RED form, Appendix-3. All pressure retaining materials shall be certified to ISO 10474,

Page 27

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

3.1C/EN 10204, 3.2 for vessels operating in high sour service with HIC testing and for high
alloy materials.

7.2.3

Test Certificates

Certificates for each mechanical, performance or calibration test, as applicable shall be


furnished, including hydrostatic test certificates and as identified in RED form, Appendix-3.

7.3

METHOD OF DOCUMENTATION TRANSMISSION

All documentation for review/approval shall be transmitted via internet (soft copy) or hard
copy by use of courier services and shall be sent to the Purchaser, the details of which shall
be discussed during the bid clarification meeting. Final documentation shall be in the form of
hard copy as well as electronic form as specified in RED form, Appendix-3.

7.4

IDENTIFICATION

Each drawing and document shall be identified with the following information (for drawings a
title block shall be used):
a)
Identity and signature of originator, checker and approver.
b)
Title
c)
Purchase order number
d)
The item/tag number or equipment number
e)
Official name of Vendors company
f)
Vendors drawing number.
g)
Latest revision by means of a number or letter in triangle with that number or letter
adjacent to the alterations.
h)
Company drawing number.

7.5

DATA

Vendor shall provide full information to enable completion of the data sheets, first for as
purchased, and then as built, within the confines of the supply. Preferably this should be
done by correcting and filling out the data sheet and submitting copies, both hard copy as
well as electronic copy (in CDs). Additional data as required by this specification shall also be
provided.
The Vendor shall maintain a record of shop test data for at least 36 months from date of
shipment.
All revised data must be resubmitted in its entirety. Revised data should state control
numbers and indicate, where appropriate, which drawings/data the revised document
supersedes. Revised data / changes shall be clearly highlighted by clouding and proper
revision mark for easy identification. The drawings / documents submitted without highlighting
the changes with clouding or identification revision mark, the documents shall be rejected
and returned to Vendor without checking / review.

7.6

TRANSMITTAL

All documentation for review/approval shall be transmitted via internet (soft copy) or hard
copy by use of courier services and shall be sent to the Purchaser.

Page 28

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

The Vendor shall submit the required documents and CDs for comment and approval by the
Purchaser under the cover of a transmittal form, Review Document Transmittal (RDT).
The Purchaser will review and may comment on all drawings, calculations and documents
submitted.
Corrections will be marked on the drawings. Marked-up copies of the drawings will be
returned to the Vendor under cover of the appropriate transmittal form.
The Vendor shall at all times be responsible for review and correction of Sub-Vendors
drawings and documents prior to submittal to Purchaser for approval.
The Purchaser will clearly indicate on the documents which parts, if any, are hold. The
Purchaser will inform the parties concerned, of the reasons for placing hold, and the date(s)
on which release of these holds can be expected. The Vendor shall not delay
manufacturing of released parts because of hold placed on other parts.
Upon approval of the Vendors drawings by the Purchaser, the Vendor shall forward to the
Purchaser the required number of approved documents, prints and diskettes as stated on the
RED form under cover of a transmittal form, Final Document Transmittal (FDT).
Manuals shall also be submitted to Purchaser under cover of a FDT.

7.7

MANUALS

The manual with all the relevant details to install, commission and operate/maintain the
equipment shall be provided, with all the applicable drawings and details. The manual shall
include all instructions on specific safety procedures for the installation and start-up of the
equipment.
Installation, operation and maintenance instructions including Sub-Vendor manuals.
Technical design data and test results (Manufacturer databook).
Certification data.
The information presented in the manual shall be specific to the equipment being supplied.
All manuals shall be A4 size. Drawings shall be reduced to A3 and folded to A4 size so that
the title block is visible. All manuals shall also be provided in software form on CD ROM
compatible with Microsoft Word for Windows application and all drawings on Auto CAD latest
version (version 2012 or higher).

7.8

RECORD CARDS

The Vendor shall submit duly completed SAP PM Master Data forms as per the Requisition
for Engineering Documents (RED form, Appendix-3). An electronic copy of these forms shall
be provided to the Vendor for completion and return to the Purchaser, during engineering
stage after order, as indicated in the RED forms.

Page 29

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

8 PACKAGING & PRESERVATION FOR SHIPMENT


The preparation for shipment of equipment and materials shall be in accordance with project
specific requirement, DEP 70.10.70.11-Gen and additional requirements as defined in this
section. Special care should be taken for the packaging of delicate equipments / parts.

8.1

PACKING REQUIREMENTS

All nozzles and open ends of the equipment shall be treated with Shell Ensis Fluid SDC and
closed off by wooden or plastic blanks and taped. Small bore connections shall be taped
over.
Preservation of the packages shall be suitable for a storage period of at least 6 months.
All equipment under sea shipment and those with Cr-Mo or higher alloy steel material shall
be cleaned, dried and then purged with nitrogen and sealed with nitrogen with a small
positive pressure not less than 0.7 bar(g). Nitrogen bottles shall be provided and secured to
the shipping saddles for refilling. All associated valves and gauges shall be provided to
monitor the nitrogen pressure inside the vessel.
The equipment shall be packed in a seaworthy close boarded case with a waterproof lining.
The case shall be sufficiently strong to withstand handling and storage.
For transportation of any equipment in Sultanate of Oman, the maximum height including the
trailer (standard height of low bed trailer 1.3 metres, special low bed trailer height 1 metre)
shall be 5.5 metres. The Vendor shall critically review this requirement and obtain necessary
approvals from local authorities / Purchaser prior to transportation. The equipment shall be
completely shop fabricated and transported in a single piece to site as far as possible.
All lifts should be single point unless adequately demonstrated by the Vendor that single point
lifts are not possible. Adequate lifting accessories such as lifting beam/frame, slings,
shackles etc. (as part of the shipment) shall be included, if required and agreed during order.
rd

Completeness of shipment shall be witnessed by the 3 party inspection agency and a


certificate of complete shipment issued by the Vendor will be verified against the packing
lists. A detailed, itemized packing list shall be sent to the Purchaser prior to dispatch. A copy
of the same signed packing list shall be included with the freight. Any shortages at site shall
be air freighted by Vendor at his expense within the scheduled delivery time.
Spares shall be packaged in a separate rigid box placed in the case containing the main
equipment.
All special tools are to be supplied in sectionalized purpose built cases with hinged lids.
In general, within Oman, all items shall be transported to site by truck. The majority of roads
are rough, corrugated, dusty desert graded roads. The equipment and packing must be able
to withstand rougher than normal treatment, with greater use made of shock absorbent
materials.

8.2

CRATING IDENTIFICATION

The exterior of all crated equipment shall be identified in accordance with the purchase order
and, as a minimum, shall include the following:

Crate dimensions and gross weight

Page 30

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Specific lifting and/or storage instructions

Crate identification

Supplier and Purchaser details

Brief material specification

Purchase order number

Final destination

Revision: 1
Effective: Dec-12

A complete packing list in a waterproof sleeve shall be firmly attached to the outside of each
crate. An identical list shall be attached to the inside of the crate.

Page 31

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

9 PLANNING & SCHEDULING


9.1

GENERAL

This section covers the minimum requirements of planning, scheduling, control and reporting
for the equipment.
The Vendor shall submit a project schedule indicating clearly the plan to meet the delivery
schedule required, including the required transportation time to installation site.
A network type project schedule representing all relevant activities and milestones, including
all Sub-Vendors equipment etc. shall be submitted by the Vendor within two (2) weeks after
receipt of the order.

9.2

MEETINGS

The following meetings shall be held between the Vendor and Purchaser:
Kick-off meeting.
Vendor pre-manufacturing meeting.
Any review meetings deemed necessary.
Certified minutes of meeting for all the meetings, recording all action items/parties shall be
prepared by the Vendor and faxed to the Purchaser for his approval/signature within two (2)
working days from the date of the meeting.
9.2.1

Kick-off Meeting

Kick-off meeting shall be held at Purchasers office. An agenda shall be prepared by the
Purchaser and distributed prior to this meeting and, as a minimum, shall include the following
items:
Schedules for transmittal of drawings, production and testing.
Inspection, expediting and testing, QA/QC.
Commercial aspects.
Schedule for future meetings.
Any other clarifications.
Certified minutes of meeting shall be prepared by the Vendor and faxed to the Purchaser for
his approval/signature within two (2) working days from the date of the meeting.
9.2.2

Vendor pre-manufacturing Meeting

The Vendor shall organize a pre-fabrication/inspection meeting with the Purchaser and the
Purchasers nominated inspection agency at Vendor facility. The following points represent
the minimum that will be discussed and on which total agreement of all parties will be
minuted:
Status and review of schedule for design deliverables.
Review of design engineering procedures and system.
Status and review welding procedures, NDT personnel qualification, NDT schedule.

Page 32

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

Ensure Purchaser/Company Representatives (engineers/INSPECTORS) have free


access to all fabrication areas at any reasonable time, including all times that fabrication
work is being performed.
Review the production program, including input from sub-contractors.
Review material substitution(s), if any.
Review scope of the overall inspection plan and define responsible parties regarding
interpretation, witnessing and reviewing.
Review any conflicts in codes/specifications and record which prevails.
Review any requirements to witness any particular inspection by Purchasers
Representative.
Review test program and procedures.
Review purchase order variation procedures and agree that any variation in design or
fabrication not approved by the Purchaser in writing shall be considered by the
INSPECTOR as non-acceptable.
Certified minutes of meeting shall be prepared by the Vendor and issued to the Purchaser
for his approval/signature within two (2) working days from the date of the meeting.
9.2.3

Review Meetings

Meeting agenda will be agreed upon and communicated no less than 10 working days before
the scheduled meeting date. Other meetings shall be held, as required, to perform the work
and complete all interface details.

9.3

REPORTING

Vendor shall report the progress of the job to the Purchaser during the entire period of the
contract. This shall be done as specified in the RED form, Appedix-3.

9.4

PURCHASE ORDERS

The Vendor shall supply to the Purchaser the un-priced copies of each purchase order for
major equipment / items ordered by the Vendor. Refer to RED forms (see Appendix-3) for
details.
The Vendor shall maintain and issue to the Purchaser as part of his Monthly Progress Report
an updated register of all purchase orders issued by the Vendor.

Page 33

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

APPENDICES :

Page 34

Specification for Pressure Vessels

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Revision: 1
Effective: Jun-12

Petroleum Development Oman LLC

APPENDIX-1

ENVIRONMENTAL & SITE CONDITIONS

The project specific environmental and site conditions shall be confirmed/provided by the
Purchaser based on the site location. The facilities shall be suitable for operation in the specified
environmental conditions in addition to the operating conditions.
The local environmental conditions are severe. There are frequent sandstorms, and the
atmosphere is heavily laden with airborne dust particles, some as small as 2 microns. It rains
rarely. The rain is often combined with hail and sandstorms.
Average Environmental conditions for the production stations are:
Relevant Ambient Data:
Barometric pressure

Ambient temperature

Summer

Maximum

98.9 kPa

Average

97.5 kPa

Minimum

95.7 kPa

Maximum

60 C **

Minimum

5 C

Black bulb temperature

Maximum

82 C

Relative humidity

Maximum

98 %

Minimum

30 %

Max. hourly avg.

26 meters/s

3 sec. Gust

35 meters/s

Wind speed

Prevailing wind direction

Rainfall

March - April

NW

May - June

SW

Remainder

SE

Design

25 mm/ hour

Average annual
Site elevation, above mean sea level

Negligible
185.5

meters

The above maximum shade temperature (60 deg C) occurs for short intervals only. Equipment
shall be designed to achieve its rated capacity with a shade temperature of 50 deg C. It shall
also be designed to function safely with a shade temperature of 60 deg C, but not necessarily
at its rated capacity. In addition, all instrumentation shall be designed to function correctly at
maximum temp. of 60C if shaded and 82C if unshaded.
Instrument supplied shall be suitable for the environmental conditions as per location class Dx
(4K6/4Z2/4Z4/4Z6/4C2/4S4/4M1) of IEC654-1 (IEC721-3-4 incl. Amendment 1)
4K6:

Tropical dry climate max. Ambient up to 60 degC

4Z2:

Negligible heat radiation from process sources

4Z4:

Air speed up to 30m/s

4Z6:

Negligible effects of water sources other than rain

4C2:

Effects of salts & other chemicals, including H2S also for coastal areas

4S4:

Effects of sand and dust

4M1:

Mechanical conditions (Vibration and shock)

Page 35

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

APPENDIX-2

Revision: 1
Effective: Dec-12

EQUIPMENT DATASHEETS & DRAWINGS

1. Pressure Vessel Datasheet (for ASME SEC VIII Div2 Vessels, refer DEP 31.22.00.98 also for
User Design Specification (UDS))
2. Demister Datasheet
3. Schoepentoeter Datasheet
4. Mass/Centre of Mass of Equipment Datasheet

Page 36

Specification for Pressure Vessels

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

SP-2069, Page : 37

SP-2069, Page 38

SP-2069, Page 39

SP-2069, Page 40

SP-2069, Page 41

SP-2069, Page 42

Data/requisition sheet for

Design book
Contr. Job
MESC

SCHOEPENTOETER

Top view of schoepentoeter

Inner diameter of column


Feed nozzle number
Nozzle inside diameter
Nozzle nominal diameter
Type
Applicable Standard Drawing
Catcher cap allowed
Split vane ladder allowed
Length of straight part of vanes
Vane radius
Number of vanes per side
Vane angle
Actual vane opening
Vane thickness
Schoepentoeter to pass through own nozzle
Schoepentoeter to pass through manhole ID
MATERIALS
Schoepentoeter material
Corrosion allowance

Made by:

mm
mm
inch/DN

YES/NO
YES/NO

Notes:
1) Design and construction shall be in accordance
w ith DEP 31.22.05.11-Gen.
2) The manufacturer shall check the information on
equipment requisition/draw ing and on the
standard draw ing for compatibility. He shall
indicate in the tender all missing information.

mm
mm
deg
mm
mm
YES/NO
mm

mm

Date

Rev.

EQUIPMENT:
Checked by:

Date

PLANT:
CONSIGNEE:

Approved by:

Date

SP-2069, Page 43

Sign.

P.D.O.

Eng. By :
Principal :

DEP 31.20.41.93-Gen., January 2002

Date

Equipment No.
Petroleum Development Oman LLC.

Datasheet No.

page:

SP-2069, Page 44

Petroleum Development Oman LLC

Revision: 1
Effective: Jun-12

APPENDIX-3
(RED FORMS)

REQUISITION FOR ENGINEERING DOCUMENTS

Page 45

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

SP-2069, Page 46

SP-2069, Page 47

SP-2069, Page 48

SP-2069, Page 49

SP-2069, Page 50

SP-2069, Page 51

SP-2069, Page 52

SP-2069, Page 53

SP-2069, Page 54

Revision: 1
Effective: Dec-12

Petroleum Development Oman LLC

APPENDIX-4

TABLE OF COMPLIANCE

The Vendor shall confirm below that the offer complies with all the clauses contained in this
specification or otherwise highlight deviation / exceptions under the clarification column. Vendor
can use separate sheets if space provided in the clarification column is insufficient. Words such
as Noted shall not be used.
Client : Petroleum Development Oman (PDO)

Vendor :

Client Ref. No. : PR No.

Vendor Ref. No :

Specification
Reference

Conforms

Alternative

Section

Yes / No

Yes / No

Clarification

1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
3
3.1
3.2
3.3
3.4
3.5
3.6
Page 55

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Revision: 1
Effective: Dec-12

Petroleum Development Oman LLC


Client : Petroleum Development Oman (PDO)

Vendor :

Client Ref. No. : PR No.

Vendor Ref. No :

Specification
Reference

Conforms

Alternative

Section

Yes / No

Yes / No

Clarification

4
4.1
4.2
4.3
5
5.1
5.2
6
6.1
6.2
6.2.1
6.2.2
7
7.1
7.2
7.2.1
7.2.2
7.2.3
7.3
7.4
7.5
7.6
7.7
7.8
8
8.1
8.2
9
9.1
Page 56

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Revision: 1
Effective: Dec-12

Petroleum Development Oman LLC


Client : Petroleum Development Oman (PDO)

Vendor :

Client Ref. No. : PR No.

Vendor Ref. No :

Specification
Reference

Conforms

Alternative

Section

Yes / No

Yes / No

Clarification

9.2
9.2.1
9.2.2
9.2.3
9.3
9.4
Appendix-1
Appendix-2
Appendix-3
Appendix-5
Appendix-6
Appendix-7
Appendix-8

Page 57

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

APPENDIX-5

Revision: 1
Effective: Dec-12

ALLOWABLE NOZZLE LOADS

Refer DEP SPECIFICATION FOR PRESSURE VESSELS (BASED ON ASME SECTION VIII)
DEP 31.22.20.31-Gen. February 2012,ECCN EAR99 - ANNEX VIII MINIMUM DESIGN VALUES
FOR NOZZLE FORCES AND MOMENTS.

1.

Page 58

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

APPENDIX-6

SPIR FORMAT

Page 59

Specification for Pressure Vessels SP-2069

Revision: 1
Effective: Dec-12

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

SP-2069, Page 60

SP-2069, Page 61

SP-2069, Page 62

Revision: 1
Effective: Dec-12

Petroleum Development Oman LLC

APPENDIX-7

USER FEEDBACK PAGE

SP- 2069 SPECIFICATION FOR PRESSURE VESSELS


USER FEEDBACK FORM
Any user who identifies an inaccuracy, error or ambiguity is requested to
notify the custodian so that appropriate action can be taken. The user is
requested to return this page fully completed, indicating precisely the
amendment(s) recommended.
Name:
Ref ID

Page Ref:

To:

Date:

Brief Description of Change Required and Reasons

UEP/12M
Custodian of Document

Page 63

Date:

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Jun-12

APPENDIX-8

INSPECTION AND TEST PLAN (ITP) FORMAT

Page 64

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Contractors Name
Quality Control Plan Ref.:
Discipline
Sl.
No

Project:
Element:
Pressure
Manufacture
Controlling
Document

Activity

1.

Design Calculations
and Drawings

Contract
Specifications

2.

Welding Procedures

Applicable Code
& relevant Shell
DEP

3.

Approval of
Procedures

NDT

Applicable Code
& SP 1176

4.

Review
of
operators
qualification
validity

NDT

ISO
9712
/
ASNT SNT TC
1A / CSWIP /
PCN

and

5.

Review of welder
qualification records

Applicable Code

6.

Approval of PWHT
Procedure
(if
applicable)
Material Inspection
Chemical, Physical,
Heat
treatment
condition (including
simulation
heat
treatment if any), UT

Applicable Code
& relevant Shell
DEP
Applicable
material
specification,
relevant
DEP
additional
requirements,

7.

TYPICAL INSPECTIN TEST PLAN


Revision No
0
Contract / P.O No.:
Vessel
Vessel Tag # :

Acceptance Criteria.
Frequency of Test.

Conformance to
manuf. code and
contract
specification
requirements

Approval - All
Approval All
WPS related to
pressure retaining
parts
Conformance to
relevant code &
spec
Minimum level II
valid qualifications
(Level I could be
used
as
only
assistant)
All welders shall
have
valid
qualifications
Conformance to
relevant code &
spec
Conformance to
the
controlling
documents
&
delivery conditions

Suppliers
Verification
Personnel

W Witness

R Review

EPC
Manufacturer Contractor
/ TPI

Authorised
Inspector

PDO

Design
Manager

Approved
calculations and
Drawings

H or
Review
as per
contract

Welding / QA
Engineer

Approved
for
construction
procedure

Welding / QA
Engineer

Approved NDT
procedures

QC Inspector

NDT
qualification
record

Welding / QA
Engineer

Valid
Qualification
records
Approved
PWHT
procedures
Material
inspection
report
&
material
heat
certificate

Welding / QA
Engineer
QC Inspector

LEGEND :
H Hold Point

Verification
Document

Page 65

S Surveillance

Contractors Name
Quality Control Plan Ref.:
Discipline
Sl.
No

Project:
Element:
Pressure
Manufacture
Controlling
Document

Activity

of plates, etc

8.

Verification
of
transfer of material
marking
on
cut
segments

9.

Cutting,
preparation
Forming

edge
&

10. Fit-up Inspection

11. Welding

12. Inspection of Back


gouging and NDT as
required
13. Visual Inspection of
welds
14. Positive
Material
Identification (PMI)

Approved
drawings, Data
Sheets, etc
Manufacturers
procedures

Manufacturers
procedures,
Applicable Code
& relevant Shell
DEP
Approved WPS,
code
and
relevant
Shell
DEP
Approved WPS

Approved WPS
and
relevant
spec
Applicable Code
& relevant Shell
DEP
Approved
Drawing
and
DEP
31.10.00.10

TYPICAL INSPECTIN TEST PLAN


Revision No
0
Contract / P.O No.:
Vessel
Vessel Tag # :

Acceptance Criteria.
Frequency of Test.

All cut material


shall bear the
material
details
including
heat
numbers
Dimension as per
approved
drawings
and
tolerance limits of
codes & DEP
As per approved
WPS, code and
relevant
Shell
DEP
Weld parameters
in accordance with
approved WPS
Conformance to
relevant spec
Conformance to
relevant code &
spec
Material
composition
in
accordance with
MTO
spec.
Frequency
in
accordance with

Suppliers
Verification
Personnel

W Witness

R Review

Verification
Document

EPC
Manufacturer Contractor
/ TPI

QC Inspector

Traceability
record

QC Inspector

Dimension
Inspection
report

QC Inspector

Fit-up
Inspection
Report

Welding
Supervisor &
Inspector
Welding
Supervisor &
Inspector
QC Inspector

Parameter log

Visual /
Reports

NDT

S/R

visual

QC Inspector

PMI Report

LEGEND :
H Hold Point

Page 66

S Surveillance

Weld
Report

Authorised
Inspector

PDO

Contractors Name
Quality Control Plan Ref.:
Discipline
Sl.
No

Controlling
Document

Activity

15. Ferrite check


required)
16. Dimensional
Inspection

Project:
Element:
Pressure
Manufacture

(as

Approved
Drawings
Data sheets

18. PWHT

Approved
PWHT
procedure
Relevant DEP

19. Hardness
measurement
20. Production control
Test
plates
(as
applicable) testing
21. NDT (Shall include
requirements
for
butt welds, nozzle
welds, attachment
welds, etc)
22. NDT and Chemical
analysis of weld
overlay for cladded
vessels
(if
applicable)
23. Repairs

Acceptance Criteria.
Frequency of Test.

API RP 582 &


AWS A4.2
Approved
drawings, code
and
relevant
DEP

17. Clearance
for
PWHT of the vessel

&

Relevant Code
and DEP
Applicable
Code, relevant
Shell DEP &
Approved NDT
Procedures
Code
and
relevant DEP

Code

TYPICAL INSPECTIN TEST PLAN


Revision No
0
Contract / P.O No.:
Vessel
Vessel Tag # :

and

DEP
API RP 582

Suppliers
Verification
Personnel

QC Inspector

QC Inspector

Clearance
Report

QC Inspector

PWHT chart

QC Inspector

QC Inspector

Hardness test
report
Test reports

Conformance
within
the
tolerance
limits
specified in the
controlling docs
All Welding (Hot
work)
works
completed
and
visually accepted
Conformance to
code
&
spec
requirements
Shall not exceed
248 HV10
Conformance to
Code and Spec
requirements
Conformance to
relevant code &
DEP

QC Inspector

QC Inspector

NDT Reports

Conformance to
relevant code &
DEP

QC Inspector

NDT
and
Chemical
analysis report

Conformance

QC Inspector

NDT report

to

W Witness

R Review

EPC
Manufacturer Contractor
/ TPI

Ferrite Check
Report
Dimensional
inspection
report

LEGEND :
H Hold Point

Verification
Document

Page 67

S Surveillance

Authorised
Inspector

PDO

Approval

Contractors Name
Quality Control Plan Ref.:
Discipline
Sl.
No

Activity

Project:
Element:
Pressure
Manufacture
Controlling
Document

relevant DEP
24. Clearance
for
Flushing / cleaning
& Pressure Test
25. Flushing / Cleaning

26. Pressure Testing

27. Inspection
of
internals Installation

28. Painting system

29. Surface preparation


(for
painting)
inspection
All
inspections listed in
Table 1 of SP-1246
Part 4 shall be
carried out

Approved
drawings (GA &
PEFS) & Data
sheets
Manufacturers
Procedure
&
contract Spec
Manufacturers
Procedure,
Code, approved
drawings & data
sheets
Manufacturers
Procedure,
Code, approved
drawings & data
sheets
and
internals
manufacturers
instructions
PDO Spec SP
1246 Part 1, 2 &
5
PDO Spec SP
1246 Part 4

TYPICAL INSPECTIN TEST PLAN


Revision No
0
Contract / P.O No.:
Vessel
Vessel Tag # :

Acceptance Criteria.
Frequency of Test.

relevant code &


DEP
All fabrication &
NDT in the vessel
completed
and
accepted
All internal surface
shall be dirt free

Suppliers
Verification
Personnel

W Witness

Clearance
Report

Fabrication
Supervisor &
QC inspector
QC Inspector

Flushing
Cleaning
Report
Pressure
Report

All
internal
installation
in
accordance with
approved
drawings

Fabrication
Supervisor &
QC inspector

Conformance to
SP 1246 Part 2 &
5
All test results in
accordance with
the
respective
painting
system
requirements
&
Table 1 of SP
1246 Part-4

Painting
Supervisor &
QC inspector
Painting
Supervisor &
QC inspector

R Review

Authorised
Inspector

PDO

of major
repairs

LEGEND :
H Hold Point

EPC
Manufacturer Contractor
/ TPI

Verification
Document

QC Inspector

Test
pressure
maintained as per
controlling
docs
and no leakages

Page 68

S Surveillance

Test

Installation
Inspection
Report

PDO Approved
painting system

Painting
Inspection
Report,
Holiday
Test
Report
&
Adhesion Test
Report

Contractors Name
Quality Control Plan Ref.:
Discipline
Sl.
No

Project:
Element:
Pressure
Manufacture

TYPICAL INSPECTIN TEST PLAN


Revision No
0
Contract / P.O No.:
Vessel
Vessel Tag # :

Controlling
Document

Acceptance Criteria.
Frequency of Test.

30. Painting inspection All inspections listed


in Table 1 of SP1246 Part 4 shall be
carried out

PDO Spec SP
1246 Part 4

31. Code Stamping /


Name Plate details

Manufacturing
Code

32. Review of MDB &


final Release

Contract
&
Code
requirements

All test results in


accordance with
the
respective
painting
system
requirements
&
Table 1 of SP
1246 Part-4
In
accordance
with
manufacturing
code requirements
Complete
in
accordance with
contract and code
requirements

Activity

Suppliers
Verification
Personnel

Painting
Supervisor &
QC inspector

QC Inspector

QAQC
Manager

LEGEND :
H Hold Point

W Witness

R Review

S Surveillance

Verification
Document

Page 69

EPC
Manufacturer Contractor
/ TPI

Painting
Inspection
Report,
Holiday
Test
Report
&
Adhesion Test
Report
Code stamp /
Name plate

MDB

Authorised
Inspector

PDO

Petroleum Development Oman LLC

APPENDIX-9

Revision: 1
Effective: Dec-12

DOCUMENT CHANGE IDENTIFICATION TABLE

Section

Major Changes List

1.1

All ERDs are obselete, reference to ERD is Removed.

1.3

Replaced Terminalogy with Definitions, Reference to ERD is Removed, LT


replaced with PT for Liquid Penentrant Testing.

1.6

New section Health, Safety and Environment added.

1.7

New section Summary of main changes added.

Reference to ERD is Removed.

2.1

Obselete standards are removed. Added SP-1173 and SP-2020 standard, SP2051 is replaced with DEP 74.00.10.10.

2.2

Some DEP standards are removed. DEP 30.10.60.18 is replaced by SP-1173.


NEW DEPs are added.

2.4

New International Standards are added.

2.3

Manway Rungs, Spere leg fire proofing, grating type IV and V Drawings added

2.5

DEP 31.22.00.98 and DEP 31.20.41.93 are added.

2.9

Reference to ERD is Removed.

3.1

Minimum 2 nos of earthing bosses specified, Foundation template for vertical


vessel and cathodic protection for buried vessel added.

3.2

Transportation location revised to project site OR as per Purchase Order specified


location.

3.3

Spares requirement elaborated.

3.4

Sub clause b) revised and sub clause n) added.

4.1

Sub clauses 4.1.3, 4.1.6, 4.1.11, 4.1.12, 4.1.14, 4.1.17, 4.1.19, 4.1.27, 4.1.33,
4.1.34 are revised. New sub clauses 4.1.37 to 4.1.48 are added.

4.2

Material of Construction requirements are revised.

4.3

External Painting for Stainless steel vessel parts is added.

5.2

ISO 9001: 2008 version added instead of 2000.

6.1

ITP requirements are elaborated. Subclause e) and f) added. 3 cycle PWHT for
PQR is added. 100% radiography for butt welds added. DEP 31.10.00.10 for PMI

Page 70

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 1
Effective: Dec-12

is added.
6.2.1

DEP 74.00.10.10 added instead of SP-2051.

7.1

Sub clause 4 is added.

7.2.1

ISO 10474 3.1C / EN 10204 3.2 certification requirements are added.

8.0

ERD-06-01 is replaced by project specific requirement.

Appendix 2

Data sheet for ASME Sec VIII, Div 2 vessel (UDS) and Schoepentoeter
Datasheet added.

Appendix 5

Removed and directed to DEP 31.22.20.31 Annex VIII.

Page 71

Specification for Pressure Vessels SP-2069

Printed 01/01/13

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.