A.
General
To adopt the best practice in building a VSP gun pit, the following
criteria should be observed:-
1.
2.
3.
The depth of the gun-pit should be 3m or more to reduce DownWave Multiples in the data-set, as well as for better energy
penetration.
[See Examples 1 and 2]
B.
Energy from the gun reaches the Down-hole receivers either directly
through the formation or along the mud-column (especially drilling with
heavy-drilling fluid) arriving with some delay. The gradient of the TubeWave is steeper than the gradient of the Direct First - arrivals, intercepting
at a point higher-up in the well. (Fig.1)