Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
"
You create and manage your project structure in SAP R/3 Project System, by means of work breakdown structures
and networks.The WBS describes individual phases and functions of a project. Network contains the individual
project tasks and the dependencies between them in the form of activities and relationships
Individual tasks required to carry out the project is called WBS elements.
Network
The network describes project processing. Thus the Network contains instructions on how to carry out activities
in a specific way, in a specific order and in a specific time period.Main elements of network are activities and
relationships. It forms the basis for planning, analyzing and monitoring time schedules, costs, & resources.
Activities
Activities are used to plan project staffing, capacity, material, PRTs, and service requirements. When
activities are assigned to WBS elements, detailed view of costs, dates, and capacities at WBS element
could be obtained. Its a task in a network which has a defined start and finish. An activity can be
broken down into activity elements.Three categories of activities in the Project System:
Internal Activities
External Activities
General Cost Activities
Activity element
Activity element is an activity which is subordinate to another activity. Activity elements contain the same information
as activities.Three categories of activity elements in the Project System:
Work elements
External Elements
General Cost Elements
Activity Type
Its a physical measure of activity output of a cost center .e.g. hours, number of units produced,
machine times, production times.
Milestones
Milestones are the events in the project to which particular importance is attached Or which trigger predefined
functions. In general they indicate transition between different departments or phases. Milestones are assigned to
activities and WBS elements:In PS milestones are used to:
Trigger predefined functions in network activities.
Carry out earned value analysis.
Determine dates in billing plan for sales orders.
Relationships
You use relationships to depict chronological and technical dependencies between activities. The relationship
determines the nature of the link between the individual activities. :
FS Relationship : An activity does not start until the preceding activity is completed.
SS Relationship : An activity can not start unless another activity has started.
FF Relationship : An activity can not be completed until another activity has been completed.
SF Relationship : An activity can not be completed until another succeeding activity has stared.
Confirmations
It is a part of network control. It documents the state of processing for the network activities and activity elements.
There are two types of confirmations Partial & Final.Confirmations are used to record:
The work center where the activity was carried out.
The person who carried out this activity.
The yield and scrap produced in an activity.
The actual values for the duration and dates.
Settlement
As a rule, projects are used to collect and monitor costs, but are not usually the final cost object. For this reason the
costs in atypical project will be settled at the end of the period.To this end, you store settlement rules in the activity /
WBS element requiring settlement. They contain information on settlement receivers, cost apportionment and control
data. Settlement receivers could be cost centers, G/L accounts. Etc.
Budget
The budget is the approved cost structure for an action or project in a particular period.Budgeting differs from cost
plan in that it is binding. In the approval phase you prescribe your project funds in the form of budget. It is possible to
allocate overall and annual budget in parallel.
Work Centers
Work center represents the resources responsible for executing an activity. In a work center, you can enter the
available capacity and an operating time. You can arrange the work centers in a hierarchy for capacity evaluation
purposes. Internal activities are assigned to work centers (resources) to be completed.A work center is a physical
unit within a company where an activity is performed.
Profit Center
It is subdivision of business organization which is set up for internal management control purposes. Profit centers
divide business up on a management basis. The basic aim of profit center accounting is to present areas of the
business as entities operating independently in the market.
Land Acquisition
Procurement
Construction
General
Above 4 activities should be done in sequence. As in second activity will start only after
request document for the land is completed and so on. Hence these activities have FS
Relationship between them.
- Now take WBS element Construction.
It could be sub divided in to floor wise tasks. Let say, we have four story building and each
floor has 4 flats. So under WBS element Construction we may create separate sub WBS
element for each floor. Each sub WBS element of floor may be divided further into last level
of WBS elements one for each flat on the floor. This way we will have hierarchy of the
WBS elements.Finally last level of WBS elements i.e. WBS elements of the flats will have
activities like
1. Plumbing
2.
3.
4.
5.
Electrical work
Flooring
Painting
Furniture
As I have said that Work center represents the resources responsible for executing an
activity For the above activities, work centers could be the company labor required for the
construction, labor provided by the external service center for plumbing and Electricity work.
while Profit Centers could be the finally constructed flats.
Sr NO
Project Elements
Examples
1
2
Project Def
WBS
Relationship
Milestones
Network
Thanks,
Runal
Jun 28, 2010 12:24 AM Kiran Kumar
Its Very easy to understand the basic flow of the PS module
Good attempt
Regards
Kiran
Jul 2, 2010 7:50 PM Muthuraman Govindasamy
Hello Sheetal
Very nicely presented the Project system
Muthu
Aug 23, 2010 5:17 AM mahesh A
Hi shital,
its very gr8 documentation for PS freash consultant.Hope if you have more documentation ,you will forwards to sdn
forum.
Regards,
Mahesh Amale
Aug 10, 2011 11:11 PM subhash sharma mahesh A in response to
The documents created are excellent and very useful to any PS module user.
Can you throw some ligt on how to import network activites from excel sheet. Similarily can i import Confirmation
from a excel sheet.
Regards
SCSharma
GM_Manufactuing systems (using SAP)
Hi Sheetal,
Regards,
Pranav
Hi Sheetal'
Thank you for giving such a valuable information for easy understanding of PS
basics.
Regards'
srikanth.
Its really a great thing.Such an effort to make the jargons and business flow comprehensible
is really commendable!!
Great job!