activities necessary to build an experimental model and related data are given in the
table on the next page. The project completion time using standard times is 14 weeks.
How much does it cost to reduce the duration of this project from 14 weeks to 10 weeks?
Activity Immediate Predec. Standard time Stand. Cost Crashtime(weeks) CrashCost
A 3 1,000
B 2 2,000
C 1 300
D A 7 1,300
E B 6 850
F C 2 4,000
G D,E 4 1,500