Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Tasks Types
Fixed Unit tasks
Unit refers to assignment Units as percentages. A
resource can be assigned to a task 100% or 50% i.e.
means resource is available for half his time.
Effort Driven
By default all fixed work task are effort driven
Task Dependency
Finish to start
First part is the related to predecessor and next part to
successor. This is most common. The predecessor task
must finish before the successor task can start. This is
created by using the LINK buttons on Taskbar.
Start to Start
Successor cannot start until predecessor starts
Finish to Finish
The successor task cannot finish until predecessor
Start to Finish
Successor task cannot finish until predecessor task
starts
Constraints type
As late as Possible
Project forces task to start on the last date possible,
so the tasks ends no later than the END Date.
Resources Types
Work
Usually People, based on Time
Material
Based on some unit of measurement, per/sq ft
Cost
Cost incurred not depended on amount of work
or duration. Like Cab fare, Hotel etc
Accrued At
Start (of task) End (of Task) or Prorated
(distributed evenly over the life of Task)
Master Project
Project A
Resources Pool
Project B
Project C