Sei sulla pagina 1di 40

MUNICIPALIDAD PROVINCIAL DEL CUSCO

GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

INFORME TECNICO MESUAL

OBRA
MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y
PEATONAL DE LA CALLE INCA YUPANQUI DE LA
ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO
DEL CUSCO, PROVINCIA DEL CUSCO

Residente de Obra :

ING. MOISES MAMANI APAZA

Supervisor de Obra :

ING. DINA CAROLINE TAPIA


FARFAN
2015

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y


PEATONAL DE LA CALLE INCA YUPANQUI DE LA
ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO DEL
CUSCO, PROVINCIA DEL CUSCO

FICHA TECNICA

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

FICHA TECNICA
CODIGO SNIP
NOMBRE DEL PROYECTO
DATOS GENERALES

COSTO TOTAL DEL


PROYECTO APROBADO

UBICACION

AVANCE FISICO ACUMULADO


AVANCE FISICO MENSUAL

252096
MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA
YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO DEL CUSCO,
PROVINCIA DEL CUSCO

UNIDAD EJECUTORA
FUNCION
PROGRAMA
SUB PROGRAMA
PROYECTO Y/O ACTIVIDAD
META
FUENTE DE FINANCIAMIENTO
MODALIDAD DE EJECUCION
NRO DE RESOLUCION DE
APROVACION DEL EXPEDIENTE
TECNICO
FECHA DE INICIO
TIEMPO DE EJECUCION
FECHA DE CONCLUCION
COSTO DIRECTO :
GASTOS DE SUPERVICION :
GASTOS DE LIQUIDACION :
EXPEDIENTE TECNICO :
COSTO TOTAL :
DEPARTAMENTO :
PROVINCIA
DISTRITO
LUGAR
AVANCE FISICO PROGRAMADO

MUNICIPALIDAD PROVINCIAL DEL CUSCO

20,000.00

.83 %

20,000.00

.83 %

15 TRANSPORTES
36 TRANSPORTE URBANO
74 VIAS URBANAS
004
44
CANON Y SOBRE CANON
ADMINISTRACION DIRECTA
RGM-701-GM-MPC-2013

2015-03-09
300
2016-01-03
2,408,070.50
52,528.18
11,431.68
13,719.63
2,485,750.25
CUSCO
CUSCO
CUSCO
APV. AYUDA MUTUA

AVANCE FISICO EJECUTADO


AVANCE FISICO ACUMULADO
AVANCE FISICO MENSUAL

104154.48

3.76 %

2253.82

.08 %

AVANCE FINANCIERO
0.0
0.0 %
AVANCE FINANCIERO
ACUMULADO
0.0 %
AVANCE FINANCIERO MENSUAL 0.0
INFORMACIO DEL PERSONA QUE ADMINISTRA LA OBRA
CARGO
NOMBRE
COLEGIATURA N
ING. OSCAR VILLAGARAY
JEFE DE LA DIVISION DE
SUPERVICION
ING. DINA CAROLINE TAPIA FARFAN
60282
SUPERVISOR DE OBRA
ING. MOISES MAMANI APAZA
112705
RESIDENTES DE OBRA
ALEXIS ZEA VIZCARRA
ASISTENTE TECNICO
JUAN CARLOS BORNAS
ASISTENTE ADMINISTRATIVO

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y


PEATONAL DE LA CALLE INCA YUPANQUI DE LA
ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO DEL
CUSCO, PROVINCIA DEL CUSCO

GENERALIDADES

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

A.1 INFORMACION DEL


PERSONAL
Nombre del Residente
Nombre del Inspector de Obra
A.2 FECHA REPORTADA
A.3 DATOS DEL PROYECTO
Unidad Ejecutora
Nombre de la Obra

Monto del Proyecto


Meta
Modalidad de Ejecucion
Plazo de ejecucion
A.4 FINANCIERO
Presupuesto Base
Presuspuesto Ejecutado Mes
Presupuesto Acumulado
Presupuesto Saldo
A.5 VALORIZACIONES
Valorizacion Mensual
Valorizacion Acumnulada
Valorizacion Saldos
A:6 CRONOGRAMA DE OBRA
Inicio
Programado
Dias Ejecutados
A.7 UBICACION
Lugar
Distrito
Provincia
Departamento

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

ING. MOISES MAMANI APAZA


ING. DINA CAROLINE TAPIA FARFAN
JUNIO
MUNICIPALIDAD PROVINCIAL DEL CUSCO
MEJORAMIENTO DE LA TRANSITABILIDAD
VEHICULAR Y PEATONAL DE LA CALLE
INCA YUPANQUI DE LA ASOCIACION
PROVIVIENDA AYUDA MUTUA, DISTRITO
DEL CUSCO, PROVINCIA DEL CUSCO
2,769,342.25
44
ADMINISTRACION DIRECTA
300 Dias calendarios
2,769,342.25
0.0

0.0 %

0.0

0.0 %

2,769,342.25
2,253.82
104,154.48
2,303,916.00

100.00 %
.08 %
3.76 %
96.24 %

2015-03-09
300 Dias calendarios
113 dias
APV. AYUDA MUTUA
CUSCO
CUSCO
CUSCO

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

B ASPECTOS TECNICOS
B RECURSOS UTILIZADOS
B.1.1 RECURSOS HUMANOS

CATEGORIA

MUNICIPALIDADD

RESIDENTE DE OBRA
INSPECTOR DE OBRA
ASISTENTE TECNICO
ASISTENTE ADMINISTRATIVO
ASISTENTE DE LIQUIDACION
ALMACENERO DE OBRA
TECNICO DE SUELOS
TOPOGRAFO
MAESTRO DE OBRA
OPERARIO
OFICIAL
PEON
GUARDIANES
TOTAL

0
0
0
0
0
0
0
0
0
0
0
0
0
0

B.1.2 PLANILLA DE TAREOS

DESCRIPCION

ANTERIOR

ACTUAL

ACUMULADO

MUNICIPALIDAD

0.0

0.0

0.0

TOTAL

0.0

0.0

0.0

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

B.2 RECURSOS DE MAQUINARIA Y EQUIPO


MAQUINARIA

MUNICIPALIDAD

B.2.1 VALORIZACION DE MAQUINARIA Y EQUIPO


PROGRAMADO
MAQUINARIA

ANTERIOR

PROGRAMADO

VALORIZADO

ACTUAL
%

VALORIZADO

ACUMULADO
%

VALORIZADO

SALDO
%

VALORIZADO

MAQUINARIA

0.0

0.0

0.0 %

0.0

0.0 %

0.0

0.0 %

0.0

0.0 %

TOTAL

0.0

0.0

0.0 %

0.0

0.0 %

0.0

0.0 %

0.0

0.0 %

B.3 AVANCE FISICO


B.3.1 VALORIZACION DE OBRA
PROGRAMADO
VALORIZACION

ANTERIOR

PRESUPUESTO

ACTUAL
%

VALORIZADO
S/.

ACUMULADO
%

VALORIZADO
S/.

SALDO
%

VALORIZADO
S/.

VALORIZADO
S/.

COSTO DIRECTO
COSTO TOTAL

2,408,070.50
2,769,342.25

101,900.65
117,188.32

4.23 %
4.23 %

2,253.82
2,591.95

.09 %
.09 %

104,154.48
119,780.28

MAYORES
METRADOS
TOTAL MAYORES
METRADOS

0.0

0.0

0.0 %

0.0

0.0 %

0.0

0.0 %

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0 %

0.0

0.0 %

0.0

0.0 %

80,507.35 51.47 %
80,507.35 51.47 %

7,335.63
7,335.63

4.69 %
4.69 %

PARTIDAS NUEVAS
TOTAL PARTIDAS
NUEVAS

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

156,410.00
156,410.00

4.33 % 2,303,916.00 95.67 %


4.33 % 2,649,561.75 95.67 %

87,842.98 56.16 %
87,842.98 56.16 %

68,567.02 43.84 %
68,567.02 43.84 %

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

B.3.3 MEMORIA DESCRIPTIVA VALORIZADA

ITEM
01
01.01
01.02
02
02.01
02.02
02.03
02.04
02.05
03
03.01
03.02
03.03
03.04
03.05
03.06
03.07
03.08
03.09
03.10
03.11
03.12
04
04.01
04.01.01
04.01.02
04.01.03
04.01.04
04.01.05
04.02

DESCRIPTION
OBRAS PROVISIONALES
CARTEL DE OBRA
ALMACEN Y RESIDENCIA DE OBRA
OBRAS PRELIMINARES
MOVILIZACION Y DESMOVILIZACION DE EQUIPOS
TRAZO, NIVELES Y REPLANTEO
SEALIZACION Y SEGURIDAD DE OBRA
LIMPIEZA MANUAL DE TERRENO
TRANSPORTE DE MATERIALES PARA LA OBRA
MOVIMIENTO DE TIERRAS
TRAZO, NIVELES Y REPLANTEO DURANTE EL
PROCESO DE CONSTRUCCION
NIVELACION DE BUZONES EN GENERAL
RECONEXIONES DOMICILIARIAS DE AGUA
RECONEXIONES DOMICILIARIAS DE DESAGUE
CORTE DE TERRENO A NIVEL DE SUB RASANTE
EXCAVACION MANUAL
PERFILADO Y COMPACTADO DE SUB RASANTE EN
ZONAS DE CORTE
RIEGO
RELLENO COMPACTADO CON MATERIAL PROPIO
RELLENO Y COMPACTADO CON MATERIAL PROPIO
(MANUAL)
TRANSPORTE DE MATERIAL EXCEDENTE MANUAL
(C/BUGUIE D=100M)
ELIMINACION MATERIAL EXCEDENTE
ESTRUCTURA DEL PAVIMENTO
BASE GRANULAR (e=0.20CM)
TRAZO, NIVELES Y REPLANTEO DURANTE EL
PROCESO DE CONSTRUCCION
EXTRACCION Y PREPARACION DE MATERIAL DE BASE
CARGUIO Y TRANSPORTE DE MATERIAL DE BASE
(Dmax=10KM)
EXTENDIDO Y COMPACTADO DE BASE
RIEGO
LOSA DE RODADURA

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

METRADO

COSTO

0.0
0.0

0.0
0.0

0.0
0.0
0.0
0.0
0.0

0.0
0.0
0.0
0.0
0.0

0.0

0.0

0.0
0.0
0.0
0.0
0.0
0.0

0.0
0.0
0.0
0.0
0.0
0.0

0.0
0.0
9.24

0.0
0.0
430.12

10.00

182.50

0.0

0.0

0.0

0.0

0.0
0.0

0.0
0.0

0.0
0.0

0.0
0.0

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

ITEM
04.02.01
04.02.02
04.02.03
04.02.04
04.02.05
04.02.06
04.02.07
04.02.08
04.02.09
04.02.10
04.03
04.03.01
04.03.02
04.03.03
05
05.01
05.01.01
05.01.02
05.01.03
05.01.04
05.01.05
05.02
05.02.01
05.02.02
05.02.03
05.02.04
05.02.05
05.02.06
05.02.07
05.02.08

DESCRIPTION
TRAZO, NIVELES Y REPLANTEO DURANTE EL
PROCESO DE CONSTRUCCION
ENCOFRADO Y DESENCOFRADO EN LOSA DE
PAVIMENTO
ACERO DE TEMPERATURA DE 1/4"
ACERO CORRUGADO G-60 DE 1/2" EN JUNTA
LONGITUDINAL
ACERO DE 3/4" EN JUNTA DE CONTRACCION
ACERO LISO DE 1" EN JUNTA DE DILATACION
CONCRETO F'C=210KG/CM2
CURADO DE LOSA DE CONCRETO
SELLADO DE JUNTAS DE CONTR. Y LONG
SELLADO DE JUNTAS DE DILATACION e=3/4", h=0.15M
ADOQUINADO
SUMINISTRO DE ADOQUINADO DE PIEDRA
COLOCADO DE ADOQUINES DE PIEDRA
SELLADO DE JUNTAS ENTRE ADOQUINES (C, F'C=210
KG/CM2)
SARDINELES Y VEREDAS
SARDINELES DE CONCRETO
TRAZO, NIVELES Y REPLANTEO DURANTE EL
PROCESO DE CONSTRUCCION
ENCOFRADO Y DESENCOFRADO DE SARDINELES
CONCRETO F'C=175KG/CM2
CURADO DE CONCRETO
SELLADO DE JUNTAS EN SARDINELES
VEREDAS
TRAZO, NIVELES Y REPLANTEO DURANTE EL
PROCESO DE CONSTRUCCION
NIVELACION Y COMPACTADO MANUAL
ENCOFRADO Y DESENCOFRADO PARA VEREDAS
HASTA H=0.20M
EMPEDRADO DE 6"
CONCRETO F'C=175KG/CM2
CURADO DE CONCRETO
SUMINISTRO DE LOSETAS DE PIEDRA
COLOCADO DE LOSETAS DE PIEDRA

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

METRADO

COSTO

0.0

0.0

0.0

0.0

0.0
0.0

0.0
0.0

0.0
0.0
0.0
0.0
0.0
0.0

0.0
0.0
0.0
0.0
0.0
0.0

0.0
0.0
0.0

0.0
0.0
0.0

0.0

0.0

0.0
0.0
0.0
0.0

0.0
0.0
0.0
0.0

0.0

0.0

0.0
0.0

0.0
0.0

0.0
0.0
0.0
0.0
0.0

0.0
0.0
0.0
0.0
0.0

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

ITEM
05.02.09
05.02.10
06
06.01
06.02
06.03
06.04
06.05
06.06
06.07
06.08
06.09
07
07.01
07.01.01
07.01.02
07.01.03
07.01.04
07.01.05
07.01.06
07.01.07
07.01.08
07.01.09
07.01.10
07.01.11
07.01.12
07.02
07.02.01
07.02.02
07.02.03

DESCRIPTION
EMBOQUILLADO ENTRE LOSETAS DE PIEDRA
CURADO DE CONCRETO
MUROS DE CONTENCION
TRAZO, NIVELES Y REPLANTEO DURANTE EL
PROCESO DE CONSTRUCCION
SOLADOS DE 2", MEZCLA 1:12
ENCOFRADO Y DESENCOFRADO DE MUROS DE
SOSTENIMIENTO
CONCRETO CICLOPEO F'C=140 KG/CM2 + 30% PG
FILTRO DE GRAVA
TUBERIA PVC SAL 3"
EMBOQUILLADO DE MURO (AREA VISIBLE) C:A 1:5,
e=0.02M
CURADO DE CONCRETO
JUNTAS ASFALTICAS 1"X0.06M, 1:4
SISTEMA DE EVACUACION DE AGUAS PLUVIALES
SUMIDEROS
TRAZO, NIVELES Y REPLANTEO DURANTE EL
PROCESO DE CONSTRUCCION
NIVELACION Y COMPACTADO MANUAL
EMPEDRADO DE 4"
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO DE REFUERZO G-60
CONCRETO F'C=210KG/CM2
REJILLA SUMIDERO PLAT 2 1/2"x 1/2" C/RIEL
TARRAJEO CON IMPERMEABILIZANTE MEZCLA 1:5
e=1.5 CM
CURADO DE CONCRETO
JUNTAS ASFALTICAS 1"X0.06M, 1:4
CAMA DE APOYO
TENDIDO DE TUBERIA DE 8"
CANAL CON TAPAS DE CONCRETO
TRAZO, NIVELES Y REPLANTEO DURANTE EL
PROCESO DE CONSTRUCCION
NIVELACION Y COMPACTADO MANUAL
EMPEDRADO DE 4"

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

METRADO

COSTO

0.0
0.0

0.0
0.0

0.0

0.0

0.0
33.50

0.0
1,461.60

0.0
0.0
11.70
0.0

0.0
0.0
179.60
0.0

0.0
0.0

0.0
0.0

0.0

0.0

0.0
0.0
0.0
0.0
0.0
0.0
0.0

0.0
0.0
0.0
0.0
0.0
0.0
0.0

0.0
0.0
0.0
0.0

0.0
0.0
0.0
0.0

0.0

0.0

0.0
0.0

0.0
0.0

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

ITEM
07.02.04
07.02.05
07.02.06
07.02.07
07.02.08
07.02.09
08
08.01
08.01.01
08.02
08.02.01
08.02.02
08.03
08.03.01
08.04
08.04.01
08.05
08.05.01
09
09.01
09.01.01
09.02
09.02.01
09.02.02
10
10.01
11
11.01
11.01.01
12

DESCRIPTION
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO DE REFUERZO G-60
CONCRETO F'C = 210 KG/CM2
TAPA DE CONCRETO ARMADO PREFABRICADO
TARRAJEO CON IMPERMEABILIZANTE MEZCLA 1:5
e=1.5 CM
CURADO DE CONCRETO
OBRAS COMPLEMENTARIAS
SEALIZACION
SEALES PREVENTIVAS
DEMARCACION
PINTADO DE SARDINELES AL BORDE DE LA VIA
PINTADO DE SEALES EN PISO
BANCAS
BANCAS DE MADERA CON ESTRUCTURA METALICA
PAPELERA
SUMINISTRO E INSTALACION DE CONTENEDOR TIPO
PAPELERA
ESTRUCTURAS VARIAS
BARANDAS METALICAS (SEGN DISEO)
CONTROL DE CALIDAD DE LA OBRA
DISEO DE MEZCLAS
DISEO DE MEZCLA DE CONCRETO
PRUEBA DE CONTROL
PRUEBA DE DENSIDAD DE CAMPO
ROTURA DE BRIQUETAS
INTERVENCION ARQUEOLOGICA
MONITOREO ARQUEOLOGICO
MITIGACION DE IMPACTOS
TRATAMIENTO DE AREAS VERDES
ACONDICIONAMIENTO DE AREAS VERDES
LIMPIEZA DE OBRA

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

METRADO

COSTO

0.0
0.0
0.0
0.0
0.0

0.0
0.0
0.0
0.0
0.0

0.0

0.0

0.0

0.0

0.0
0.0

0.0
0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0
0.0

0.0
0.0

0.0

0.0

0.0

0.0

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

ITEM
12.01
-

DESCRIPTION
LIMPIEZA DE OBRA
TOTAL

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

METRADO
0.0
-

COSTO
0.0
2,253.82

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y


PEATONAL DE LA CALLE INCA YUPANQUI DE LA
ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO DEL
CUSCO, PROVINCIA DEL CUSCO

RESUMEN DE VALORIZACION GENERAL

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

RESUMEN DE VALORIZACION GENERAL

ITEM

01

DESCRIPCION

PRESUPUESTO
PARCIAL

AVANCE
VALORIZADO
ANTERIOR

AVANCE
VALORIZADO
TOTAL JUNIO

AVANCE
ACUMULADO
TOTAL 2015

AVANCE
PORCENTUAL

MEJORAMIENTO DE LA TRANSITABILIDAD
VEHICULAR Y PEATONAL DE LA CALLE INCA
YUPANQUI DE LA ASOCIACION PROVIVIENDA
AYUDA MUTUA, DISTRITO DEL CUSCO,
PROVINCIA DEL CUSCO

2,408,070.50

101,900.65

2,253.82

104,154.47

4.33 %

COSTO DIRECTO

2,408,070.50

101,900.65

2,253.82

104,154.47

4.33 %

283,591.94

12,000.56

265.43

12,265.99

4.33 %

GASTOS DE SUPERVICION

52,528.18

2,222.80

49.16

2,271.96

4.33 %

GASTOS DE EXPEDIENTE TECNICO

13,719.63

580.56

12.84

593.40

4.33 %

LIQUIDACION DE OBRA

11,431.68

483.75

10.70

494.45

4.33 %

2,769,342.25

117,188.32

2,591.95

119,780.27

4.33 %

GASTOS GENERALES

COSTO TOTAL

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE


INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO
DEL CUSCO, PROVINCIA DEL CUSCO

RESUMEN DE VALORIZACION DE OBRA

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

RESUMEN DE VALORIZACION DE OBRA


OBRA : MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA
AYUDA MUTUA, DISTRITO DEL CUSCO, PROVINCIA DEL CUSCO
CORRESPONDIENTE AL MES DE : JUNIO

ITEM
1

PROGRAMADO
VALORIZACION
COSTO DIRECTO
COSTO TOTAL

MAYORES METRADOS
TOTAL MAYORES METRADOS

PARTIDAS NUEVAS
TOTAL PARTIDAS NUEVAS

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

PRESUPUESTO
2,408,070.50
2,769,342.25

ANTERIOR
VALORIZADO S/.
101,900.65
117,188.32

%
4.23 %
4.23 %

ACTUAL
VALORIZADO S/.
2,253.82
2,591.95

%
.09 %
.09 %

0.0
0.0

0.0
0.0

0.0 %
0.0 %

0.0
0.0

0.0 %
0.0 %

80,507.35 51.47 %
80,507.35 51.47 %

7,335.63
7,335.63

4.69 %
4.69 %

156,410.00
156,410.00

ACUMULADO
VALORIZADO S/.
%
104,154.48 4.33 %
119,780.28 4.33 %

0.0
0.0

0.0 %
0.0 %

87,842.98 56.16 %
87,842.98 56.16 %

SALDO
VALORIZADO S/.
%
2,303,916.00 95.67 %
2,649,561.75 95.67 %

0.0
0.0

0.0 %
0.0 %

68,567.02 43.84 %
68,567.02 43.84 %

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE


INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO
DEL CUSCO, PROVINCIA DEL CUSCO

VALORIZACION DE OBRA

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

VALORIZACION DE AVANCE DE OBRA PROGRAMADA


OBRA : MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA
AYUDA MUTUA, DISTRITO DEL CUSCO, PROVINCIA DEL CUSCO
CORRESPONDIENTE AL MES DE : JUNIO

PROGRAMADO
CODIGO

ANTERIOR

PARTIDA

UNID

METRADO

PRECIO
UNITARIO

PARCIAL

METRADO

COSTO

ACTUAL
%

METRADO

COSTO

ACUMULADO
%

METRADO

COSTO

SALDO
%

METRADO

COSTO

01

OBRAS PROVISIONALES

01.01

CARTEL DE OBRA

UND

2.00

652.12

1,304.24

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

2.00

1,304.24

100.00 %

01.02

ALMACEN Y RESIDENCIA DE OBRA

MES

10.00

150.00

1,500.00

3.00

450.00

30.00 %

0.0

0.0

0.0 %

3.0

450.00

30.00 %

7.00

1,050.00

70.00 %

02

OBRAS PRELIMINARES

02.01

MOVILIZACION Y DESMOVILIZACION DE EQUIPOS

GLB

02.02

TRAZO, NIVELES Y REPLANTEO

M2

02.03

SEALIZACION Y SEGURIDAD DE OBRA

UND

02.04

LIMPIEZA MANUAL DE TERRENO

M2

02.05

TRANSPORTE DE MATERIALES PARA LA OBRA

GLB

03

MOVIMIENTO DE TIERRAS

03.01

TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO


DE CONSTRUCCION

M2

03.02

NIVELACION DE BUZONES EN GENERAL

03.03

RECONEXIONES DOMICILIARIAS DE AGUA

03.04

1.00

2,433.44

2,433.44

0.60

1,460.06

60.00 %

0.0

0.0

0.0 %

0.6

1,460.06

60.00 %

0.40

973.38

40.00 %

7,935.74

.75

5,951.81

7,935.74

5,951.81

100.00 %

0.0

0.0

0.0 %

7935.74

5,951.81

100.00 %

0.0

0.0

0.0 %

1.00

720.80

720.80

1.00

720.80

100.00 %

0.0

0.0

0.0 %

1.0

720.80

100.00 %

0.0

0.0

0.0 %

7,935.34

.33

2,618.66

3,752.06

1,238.18

47.28 %

0.0

0.0

0.0 %

3752.06

1,238.18

47.28 %

4,183.28

1,380.48

52.72 %

1.00

5,000.00

5,000.00

1.00

5,000.00

100.00 %

0.0

0.0

0.0 %

1.0

5,000.00

100.00 %

0.0

0.0

0.0 %

7,935.74

.54

4,285.30

1,915.98

1,034.63

24.14 %

0.0

0.0

0.0 %

1915.98

1,034.63

24.14 %

6,019.76

3,250.67

75.86 %

UND

11.00

309.65

3,406.15

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

11.00

3,406.15

100.00 %

UND

44.00

283.35

12,467.40

13.00

3,683.55

29.55 %

0.0

0.0

0.0 %

13.0

3,683.55

29.55 %

31.00

8,783.85

70.45 %

RECONEXIONES DOMICILIARIAS DE DESAGUE

UND

44.00

283.35

12,467.40

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

44.00

12,467.40

100.00 %

03.05

CORTE DE TERRENO A NIVEL DE SUB RASANTE

M3

3,683.40

6.72

24,752.45

336.90

2,263.97

9.15 %

0.0

0.0

0.0 %

336.9

2,263.97

9.15 %

3,346.50

22,488.48

90.85 %

03.06

EXCAVACION MANUAL

M3

873.87

27.05

23,638.18

768.97

20,800.64

88.00 %

0.0

0.0

0.0 %

768.97

20,800.64

88.00 %

104.90

2,837.55

12.00 %

03.07

PERFILADO Y COMPACTADO DE SUB RASANTE EN


ZONAS DE CORTE

M2

5,497.33

4.77

26,222.26

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

5,497.33

26,222.26

100.00 %

03.08

RIEGO

M2

5,497.33

.47

2,583.75

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

5,497.33

2,583.75

100.00 %

03.09

RELLENO COMPACTADO CON MATERIAL PROPIO

M3

489.02

5.05

2,469.55

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

489.02

2,469.55

100.00 %

03.10

RELLENO Y COMPACTADO CON MATERIAL PROPIO


(MANUAL)

M3

230.58

46.55

10,733.50

204.17

9,504.11

88.55 %

9.24

430.12

4.01 %

213.41

9,934.24

92.55 %

17.17

799.26

7.45 %

03.11

TRANSPORTE DE MATERIAL EXCEDENTE MANUAL


(C/BUGUIE D=100M)

M3

1,092.34

18.25

19,935.20

363.50

6,633.88

33.28 %

10.00

182.50

.92 %

373.5

6,816.38

34.19 %

718.84

13,118.83

65.81 %

03.12

ELIMINACION MATERIAL EXCEDENTE

M3

5,696.59

15.25

86,873.00

374.00

5,703.50

6.57 %

0.0

0.0

0.0 %

374.0

5,703.50

6.57 %

5,322.59

81,169.49

93.43 %

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

PROGRAMADO
CODIGO

ANTERIOR

PARTIDA

UNID

METRADO

04

ESTRUCTURA DEL PAVIMENTO

04.01

BASE GRANULAR (e=0.20CM)

04.01.01

TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO


DE CONSTRUCCION

M2

5,497.33

04.01.02

EXTRACCION Y PREPARACION DE MATERIAL DE BASE

M3

1,099.47

04.01.03

CARGUIO Y TRANSPORTE DE MATERIAL DE BASE


(Dmax=10KM)

M3

1,374.33

04.01.04

EXTENDIDO Y COMPACTADO DE BASE

M2

5,497.33

04.01.05

RIEGO

M2

5,497.33

04.02

LOSA DE RODADURA

04.02.01

TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO


DE CONSTRUCCION

M2

04.02.02

ENCOFRADO Y DESENCOFRADO EN LOSA DE


PAVIMENTO

04.02.03
04.02.04

PRECIO
UNITARIO

METRADO

COSTO

ACTUAL
%

METRADO

COSTO

ACUMULADO
%

METRADO

COSTO

SALDO
%

METRADO

2,968.56

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

5,497.33

8.16

8,971.68

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

29.04

39,910.54

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

2.47

13,578.41

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

.47

2,583.75

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

5,497.33

.54

2,968.56

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

M2

784.10

38.91

30,509.33

0.0

0.0

0.0 %

0.0

0.0

0.0 %

ACERO DE TEMPERATURA DE 1/4"

KG

6,257.18

5.56

34,789.92

0.0

0.0

0.0 %

0.0

0.0

ACERO CORRUGADO G-60 DE 1/2" EN JUNTA


LONGITUDINAL

KG

990.02

5.99

5,930.22

0.0

0.0

0.0 %

0.0

0.0

04.02.05

ACERO DE 3/4" EN JUNTA DE CONTRACCION

KG

4,806.14

5.99

28,788.78

0.0

0.0

0.0 %

0.0

04.02.06

ACERO LISO DE 1" EN JUNTA DE DILATACION

KG

133.39

6.44

859.03

0.0

0.0

0.0 %

0.0

04.02.07

CONCRETO F'C=210KG/CM2

M3

934.55

415.01 387,847.59

0.0

0.0

0.0 %

04.02.08

CURADO DE LOSA DE CONCRETO

M2

5,497.33

.85

4,672.73

0.0

0.0

04.02.09

SELLADO DE JUNTAS DE CONTR. Y LONG

4,805.95

3.38

16,244.11

0.0

04.02.10

SELLADO DE JUNTAS DE DILATACION e=3/4", h=0.15M

77.00

7.69

592.13

04.03

ADOQUINADO

04.03.01

SUMINISTRO DE ADOQUINADO DE PIEDRA

M2

5,497.33

04.03.02

COLOCADO DE ADOQUINES DE PIEDRA

M2

5,497.33

04.03.03

SELLADO DE JUNTAS ENTRE ADOQUINES (C, F'C=210


KG/CM2)

M2

5,497.33

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

.54

PARCIAL

COSTO

2,968.56

100.00 %

1,099.47

8,971.67

100.00 %

1,374.33

39,910.54

100.00 %

0.0 %

5,497.33

13,578.41

100.00 %

0.0 %

5,497.33

2,583.75

100.00 %

0.0

0.0 %

5,497.33

2,968.56

100.00 %

0.0

0.0

0.0 %

784.10

30,509.33

100.00 %

0.0 %

0.0

0.0

0.0 %

6,257.18

34,789.92

100.00 %

0.0 %

0.0

0.0

0.0 %

990.02

5,930.22

100.00 %

0.0

0.0 %

0.0

0.0

0.0 %

4,806.14

28,788.78

100.00 %

0.0

0.0 %

0.0

0.0

0.0 %

133.39

859.03

100.00 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

934.55 387,847.59

100.00 %

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

5,497.33

4,672.73

100.00 %

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

4,805.95

16,244.11

100.00 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

77.00

592.13

100.00 %

147.00 808,107.50

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

5,497.33 808,107.50

100.00 %

18.48 101,590.66

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

5,497.33 101,590.66

100.00 %

21.20 116,543.40

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

5,497.33 116,543.40

100.00 %

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

PROGRAMADO
CODIGO

ANTERIOR

PARTIDA

UNID

METRADO

05

SARDINELES Y VEREDAS

05.01

SARDINELES DE CONCRETO

05.01.01

TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO


DE CONSTRUCCION

M2

149.27

05.01.02

ENCOFRADO Y DESENCOFRADO DE SARDINELES

M2

149.27

05.01.03

CONCRETO F'C=175KG/CM2

M3

89.56

05.01.04

CURADO DE CONCRETO

995.15

05.01.05

SELLADO DE JUNTAS EN SARDINELES

05.02

VEREDAS

05.02.01

TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO


DE CONSTRUCCION

M2

05.02.02

NIVELACION Y COMPACTADO MANUAL

M2

05.02.03

ENCOFRADO Y DESENCOFRADO PARA VEREDAS HASTA M


H=0.20M

05.02.04

EMPEDRADO DE 6"

M2

05.02.05

CONCRETO F'C=175KG/CM2

M3

05.02.06

CURADO DE CONCRETO

05.02.07

PRECIO
UNITARIO

.54

PARCIAL

METRADO

COSTO

ACTUAL
%

METRADO

COSTO

ACUMULADO
%

METRADO

COSTO

SALDO
%

METRADO

80.61

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

149.27

38.91

5,808.10

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

406.02

36,363.15

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

.39

388.11

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

149.40

9.27

1,384.94

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

931.88

.54

503.22

0.0

0.0

0.0 %

0.0

0.0

0.0 %

COSTO

80.61

99.99 %

149.27

5,808.10

100.00 %

89.56

36,363.15

100.00 %

0.0 %

995.15

388.11

100.00 %

0.0

0.0 %

149.40

1,384.94

100.00 %

0.0

0.0

0.0 %

931.88

503.22

100.00 %

931.88

1.47

1,369.86

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

931.88

1,369.86

100.00 %

1,014.15

20.18

20,465.55

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

1,014.15

20,465.55

100.00 %

931.88

22.31

20,790.24

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

931.88

20,790.24

100.00 %

69.89

406.02

28,376.74

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

69.89

28,376.74

100.00 %

M2

931.88

.85

792.10

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

931.88

792.10

100.00 %

SUMINISTRO DE LOSETAS DE PIEDRA

M2

86.00

94.50

8,127.00

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

86.00

8,127.00

100.00 %

05.02.08

COLOCADO DE LOSETAS DE PIEDRA

M2

86.00

18.51

1,591.86

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

86.00

1,591.86

100.00 %

05.02.09

EMBOQUILLADO ENTRE LOSETAS DE PIEDRA

M2

86.00

27.38

2,354.68

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

86.00

2,354.68

100.00 %

05.02.10

CURADO DE CONCRETO

M2

86.00

.85

73.10

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

86.00

73.10

100.00 %

06

MUROS DE CONTENCION

06.01

TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO


DE CONSTRUCCION

M2

225.67

.54

121.86

225.67

121.86

100.00 %

0.0

0.0

0.0 %

225.67

121.86

100.00 %

0.0

0.0

0.0 %

06.02

SOLADOS DE 2", MEZCLA 1:12

M2

225.67

14.51

3,274.47

225.67

3,274.47

100.00 %

0.0

0.0

0.0 %

225.67

3,274.47

100.00 %

0.0

0.0

0.0 %

06.03

ENCOFRADO Y DESENCOFRADO DE MUROS DE


SOSTENIMIENTO

M2

371.26

43.63

16,198.07

226.27

9,872.16

60.95 %

33.50

1,461.60

9.02 % 259.77002

11,333.77

69.97 %

111.49

4,864.31

30.03 %

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

PROGRAMADO
CODIGO

ANTERIOR

PARTIDA

UNID

METRADO

PRECIO
UNITARIO

PARCIAL

METRADO

COSTO

ACTUAL
%

METRADO

COSTO

ACUMULADO
%

METRADO

COSTO

SALDO
%

METRADO

COSTO

06.04

CONCRETO CICLOPEO F'C=140 KG/CM2 + 30% PG

M3

224.45

241.84

54,280.99

37.11

8,974.68

16.53 %

0.0

0.0

0.0 %

37.11

8,974.68

16.53 %

187.34

45,306.30

83.47 %

06.05

FILTRO DE GRAVA

M3

3.96

93.53

370.38

2.78

260.01

70.20 %

0.0

0.0

0.0 %

2.78

260.01

70.20 %

1.18

110.37

29.80 %

06.06

TUBERIA PVC SAL 3"

93.75

15.35

1,439.06

78.40

1,203.44

83.63 %

11.70

179.60

12.48 %

90.1

1,383.04

96.11 %

3.65

56.03

3.89 %

06.07

EMBOQUILLADO DE MURO (AREA VISIBLE) C:A 1:5,


e=0.02M

M2

313.11

27.34

8,560.43

155.29

4,245.63

49.60 %

0.0

0.0

0.0 %

155.29

4,245.63

49.60 %

157.82

4,314.80

50.40 %

06.08

CURADO DE CONCRETO

M2

371.26

.85

315.57

323.28

274.79

87.08 %

0.0

0.0

0.0 %

323.28

274.79

87.08 %

47.98

40.78

12.92 %

06.09

JUNTAS ASFALTICAS 1"X0.06M, 1:4

77.80

5.09

396.00

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

77.80

396.00

100.00 %

07

SISTEMA DE EVACUACION DE AGUAS PLUVIALES

07.01

SUMIDEROS

07.01.01

TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO


DE CONSTRUCCION

M2

15.40

.54

8.32

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

15.40

8.32

99.95 %

07.01.02

NIVELACION Y COMPACTADO MANUAL

M2

15.40

1.47

22.64

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

15.40

22.64

99.99 %

07.01.03

EMPEDRADO DE 4"

M2

15.40

15.88

244.55

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

15.40

244.55

100.00 %

07.01.04

ENCOFRADO Y DESENCOFRADO NORMAL

M2

22.40

26.35

590.24

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

22.40

590.24

100.00 %

07.01.05

ACERO DE REFUERZO G-60

KG

292.72

6.09

1,782.66

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

292.72

1,782.66

100.00 %

07.01.06

CONCRETO F'C=210KG/CM2

M3

5.13

415.01

2,129.00

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

5.13

2,129.00

100.00 %

07.01.07

REJILLA SUMIDERO PLAT 2 1/2"x 1/2" C/RIEL

M2

10.60

1,218.34

12,914.40

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

10.60

12,914.40

100.00 %

07.01.08

TARRAJEO CON IMPERMEABILIZANTE MEZCLA 1:5 e=1.5


CM

M2

32.80

20.73

679.94

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

32.80

679.94

100.00 %

07.01.09

CURADO DE CONCRETO

32.80

.39

12.79

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

32.80

12.79

100.02 %

07.01.10

JUNTAS ASFALTICAS 1"X0.06M, 1:4

44.00

5.09

223.96

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

44.00

223.96

100.00 %

07.01.11

CAMA DE APOYO

M3

12.03

139.84

1,682.28

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

12.03

1,682.28

100.00 %

07.01.12

TENDIDO DE TUBERIA DE 8"

240.50

100.91

24,268.86

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

240.50

24,268.86

100.00 %

07.02

CANAL CON TAPAS DE CONCRETO

07.02.01

TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO


DE CONSTRUCCION

M2

599.49

.54

323.72

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

599.49

323.72

100.00 %

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

PROGRAMADO
CODIGO

ANTERIOR

PARTIDA

UNID

METRADO

PRECIO
UNITARIO

PARCIAL

METRADO

COSTO

ACTUAL
%

METRADO

COSTO

ACUMULADO
%

METRADO

COSTO

SALDO
%

METRADO

COSTO

07.02.02

NIVELACION Y COMPACTADO MANUAL

M2

599.49

1.47

881.25

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

599.49

881.25

100.00 %

07.02.03

EMPEDRADO DE 4"

M2

599.49

15.88

9,519.90

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

599.49

9,519.90

100.00 %

07.02.04

ENCOFRADO Y DESENCOFRADO NORMAL

M2

1,005.57

26.35

26,496.77

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

1,005.57

26,496.77

100.00 %

07.02.05

ACERO DE REFUERZO G-60

KG

2,543.90

6.09

15,492.35

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

2,543.90

15,492.35

100.00 %

07.02.06

CONCRETO F'C = 210 KG/CM2

M3

179.94

415.01

74,676.90

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

179.94

74,676.90

100.00 %

07.02.07

TAPA DE CONCRETO ARMADO PREFABRICADO

UND

996.00

24.50

24,402.00

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

996.00

24,402.00

100.00 %

07.02.08

TARRAJEO CON IMPERMEABILIZANTE MEZCLA 1:5 e=1.5


CM

M2

1,398.81

20.73

28,997.33

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

1,398.81

28,997.33

100.00 %

07.02.09

CURADO DE CONCRETO

M2

1,398.81

.85

1,188.99

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

1,398.81

1,188.99

100.00 %

08

OBRAS COMPLEMENTARIAS

08.01

SEALIZACION

08.01.01

SEALES PREVENTIVAS

14.00

526.09

7,365.26

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

14.00

7,365.26

100.00 %

08.02

DEMARCACION

08.02.01

PINTADO DE SARDINELES AL BORDE DE LA VIA

1,990.30

6.37

12,678.21

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

1,990.30

12,678.21

100.00 %

08.02.02

PINTADO DE SEALES EN PISO

M2

49.50

6.51

322.25

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

49.50

322.25

100.00 %

08.03

BANCAS

08.03.01

BANCAS DE MADERA CON ESTRUCTURA METALICA

UND

5.00

1,477.90

7,389.50

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

5.00

7,389.50

100.00 %

08.04

PAPELERA

08.04.01

SUMINISTRO E INSTALACION DE CONTENEDOR TIPO


PAPELERA

UND

4.00

639.11

2,556.44

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

4.00

2,556.44

100.00 %

08.05

ESTRUCTURAS VARIAS

08.05.01

BARANDAS METALICAS (SEGN DISEO)

190.00

196.62

37,357.80

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

190.00

37,357.80

100.00 %

09

CONTROL DE CALIDAD DE LA OBRA

09.01

DISEO DE MEZCLAS

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

UND

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

PROGRAMADO
CODIGO

ANTERIOR

PARTIDA

09.01.01

DISEO DE MEZCLA DE CONCRETO

09.02

PRUEBA DE CONTROL

09.02.01
09.02.02
10

INTERVENCION ARQUEOLOGICA

10.01

MONITOREO ARQUEOLOGICO

11

MITIGACION DE IMPACTOS

11.01

TRATAMIENTO DE AREAS VERDES

11.01.01

ACONDICIONAMIENTO DE AREAS VERDES

12

LIMPIEZA DE OBRA

12.01

LIMPIEZA DE OBRA

UNID

METRADO

PRECIO
UNITARIO

PARCIAL

METRADO

UND

2.00

350.00

700.00

0.0

PRUEBA DE DENSIDAD DE CAMPO

UND

20.00

35.00

700.00

0.0

ROTURA DE BRIQUETAS

UND

25.00

25.00

625.00

10.00

MES

10.00

2,992.83

29,928.30

3.00

M2

365.00

14.56

5,314.40

M2

7,935.74

.80

6,348.59

COSTO

0.0

ACTUAL
%

METRADO

COSTO

ACUMULADO
%

METRADO

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

250.00

40.00 %

0.0

0.0

0.0 %

10.0

8,978.49

30.00 %

0.0

0.0

0.0 %

3.0

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

0.0

0.0

0.0 %

4.23 %

2,253.82

.09 %

COSTO

0.0

SALDO
%

METRADO

COSTO

0.0 %

2.00

700.00

100.00 %

0.0

0.0 %

20.00

700.00

100.00 %

250.00

40.00 %

15.00

375.00

60.00 %

8,978.49

30.00 %

7.00

20,949.81

70.00 %

0.0

0.0

0.0 %

365.00

5,314.40

100.00 %

0.0

0.0

0.0 %

7,935.74

6,348.59

100.00 %

104,154.48

4.33 %

2,303,916.
00

95.67 %

COSTO DIRECTO

2,408,070.
50

101,900.65

GASTOS GENERALES

283,591.94

12,000.56

265.43

12,265.99

271,325.97

GASTOS DE SUIPERVICION

52,528.18

2,222.80

49.16

2,271.96

50,256.22

GASTOS DE LIQUIDACION

11,431.68

483.75

10.70

494.45

10,937.23

GASTOS DE EXPEDIENTE TECNICO

13,719.63

580.56

12.84

593.40

13,126.23

GASTOS TOTAL PRESUPUESTO

2,769,342.
25

117,188.32

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

4.23 %

2,591.95

.09 %

119,780.28

4.33 %

2,649,561.
75

Ing. Moises Mamani Apaza


Residente de obra

95.67 %

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

PROGRAMADO
CODIGO

PARTIDA

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

ANTERIOR
UNID

METRADO

PRECIO
UNITARIO

PARCIAL

METRADO

COSTO

ACTUAL
%

METRADO

COSTO

ACUMULADO
%

METRADO

COSTO

SALDO
%

METRADO

COSTO

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE


INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO
DEL CUSCO, PROVINCIA DEL CUSCO

METRADO DIARIO DE AVANCE DE OBRA PROGRAMADA

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

METRADO DIARIO DE AVANCE DE OBRA PROGRAMADA


OBRA : MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA
AYUDA MUTUA, DISTRITO DEL CUSCO, PROVINCIA DEL CUSCO
CORRESPONDIENTE AL MES DE : JUNIO

CODIGO

PARTIDA

UNID

METRADO

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

TOTAL
MES

ACUMULAD
O

SALDO

01

OBRAS PROVISIONALES

01.01

CARTEL DE OBRA

UND

2.0

0.0

0.0

2.00

01.02

ALMACEN Y RESIDENCIA DE
OBRA

MES

10.0

0.0

3.00

7.00

02

OBRAS PRELIMINARES

02.01

MOVILIZACION Y
DESMOVILIZACION DE EQUIPOS

GLB

02.02

TRAZO, NIVELES Y REPLANTEO

M2

02.03

SEALIZACION Y SEGURIDAD DE
OBRA

UND

02.04

LIMPIEZA MANUAL DE TERRENO

M2

02.05

TRANSPORTE DE MATERIALES
PARA LA OBRA

GLB

03

MOVIMIENTO DE TIERRAS

03.01

TRAZO, NIVELES Y REPLANTEO


DURANTE EL PROCESO DE
CONSTRUCCION

M2

03.02

NIVELACION DE BUZONES EN
GENERAL

03.03

RECONEXIONES DOMICILIARIAS
DE AGUA

03.04

RECONEXIONES DOMICILIARIAS
DE DESAGUE

UND

03.05

CORTE DE TERRENO A NIVEL DE


SUB RASANTE

M3

03.06

EXCAVACION MANUAL

03.07

PERFILADO Y COMPACTADO DE
SUB RASANTE EN ZONAS DE
CORTE

03.08
03.09
03.10

1.0

0.0

0.60

0.40

7935.74

0.0

7,935.74

0.0

1.0

0.0

1.00

0.0

7935.34

0.0

3,752.06

4,183.2
8

1.0

0.0

1.00

0.0

7935.74

0.0

1,915.98

6,019.7
6

UND

11.0

0.0

0.0

11.00

UND

44.0

0.0

13.00

31.00

44.0

0.0

0.0

44.00

3683.4

0.0

336.90

3,346.5
0

M3

873.87

0.0

768.97

104.90

M2

5497.33

0.0

0.0

5,497.3
3

RIEGO

M2

5497.33

0.0

0.0

5,497.3
3

RELLENO COMPACTADO CON


MATERIAL PROPIO

M3

489.02

0.0

0.0

489.02

RELLENO Y COMPACTADO CON


MATERIAL PROPIO (MANUAL)

M3

230.58

9.24

9.24

213.41

17.17

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

CODIGO

PARTIDA

UNID

METRADO

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

TOTAL
MES

ACUMULAD
O

SALDO

03.11

TRANSPORTE DE MATERIAL
EXCEDENTE MANUAL (C/BUGUIE
D=100M)

M3

1092.34 10.00

10.00

373.50

718.84

03.12

ELIMINACION MATERIAL
EXCEDENTE

M3

5696.59

0.0

374.00

5,322.5
9

04

ESTRUCTURA DEL PAVIMENTO

04.01

BASE GRANULAR (e=0.20CM)

04.01.01

TRAZO, NIVELES Y REPLANTEO


DURANTE EL PROCESO DE
CONSTRUCCION

M2

5497.33

0.0

0.0

5,497.3
3

04.01.02

EXTRACCION Y PREPARACION
DE MATERIAL DE BASE

M3

1099.47

0.0

0.0

1,099.4
7

04.01.03

CARGUIO Y TRANSPORTE DE
M3
MATERIAL DE BASE (Dmax=10KM)

1374.33

0.0

0.0

1,374.3
3

04.01.04

EXTENDIDO Y COMPACTADO DE
BASE

M2

5497.33

0.0

0.0

5,497.3
3

04.01.05

RIEGO

M2

5497.33

0.0

0.0

5,497.3
3

04.02

LOSA DE RODADURA

04.02.01

TRAZO, NIVELES Y REPLANTEO


DURANTE EL PROCESO DE
CONSTRUCCION

M2

5497.33

0.0

0.0

5,497.3
3

04.02.02

ENCOFRADO Y DESENCOFRADO
EN LOSA DE PAVIMENTO

M2

784.1

0.0

0.0

784.10

04.02.03

ACERO DE TEMPERATURA DE
1/4"

KG

6257.18

0.0

0.0

6,257.1
8

04.02.04

ACERO CORRUGADO G-60 DE


1/2" EN JUNTA LONGITUDINAL

KG

990.02

0.0

0.0

990.02

04.02.05

ACERO DE 3/4" EN JUNTA DE


CONTRACCION

KG

4806.14

0.0

0.0

4,806.1
4

04.02.06

ACERO LISO DE 1" EN JUNTA DE


DILATACION

KG

133.39

0.0

0.0

133.39

04.02.07

CONCRETO F'C=210KG/CM2

M3

934.55

0.0

0.0

934.55

04.02.08

CURADO DE LOSA DE
CONCRETO

M2

5497.33

0.0

0.0

5,497.3
3

04.02.09

SELLADO DE JUNTAS DE CONTR. M


Y LONG

4805.95

0.0

0.0

4,805.9
5

04.02.10

SELLADO DE JUNTAS DE
DILATACION e=3/4", h=0.15M

77.0

0.0

0.0

77.00

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

CODIGO

PARTIDA

UNID

METRADO

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

TOTAL
MES

ACUMULAD
O

SALDO

04.03

ADOQUINADO

04.03.01

SUMINISTRO DE ADOQUINADO
DE PIEDRA

M2

5497.33

0.0

0.0

5,497.3
3

04.03.02

COLOCADO DE ADOQUINES DE
PIEDRA

M2

5497.33

0.0

0.0

5,497.3
3

04.03.03

SELLADO DE JUNTAS ENTRE


ADOQUINES (C, F'C=210
KG/CM2)

M2

5497.33

0.0

0.0

5,497.3
3

05

SARDINELES Y VEREDAS

05.01

SARDINELES DE CONCRETO

05.01.01

TRAZO, NIVELES Y REPLANTEO


DURANTE EL PROCESO DE
CONSTRUCCION

M2

149.27

0.0

0.0

149.27

05.01.02

ENCOFRADO Y DESENCOFRADO
DE SARDINELES

M2

149.27

0.0

0.0

149.27

05.01.03

CONCRETO F'C=175KG/CM2

M3

89.56

0.0

0.0

89.56

05.01.04

CURADO DE CONCRETO

995.15

0.0

0.0

995.15

05.01.05

SELLADO DE JUNTAS EN
SARDINELES

149.4

0.0

0.0

149.40

05.02

VEREDAS

05.02.01

TRAZO, NIVELES Y REPLANTEO


DURANTE EL PROCESO DE
CONSTRUCCION

M2

931.88

0.0

0.0

931.88

05.02.02

NIVELACION Y COMPACTADO
MANUAL

M2

931.88

0.0

0.0

931.88

05.02.03

ENCOFRADO Y DESENCOFRADO
PARA VEREDAS HASTA H=0.20M

1014.15

0.0

0.0

1,014.1
5

05.02.04

EMPEDRADO DE 6"

M2

931.88

0.0

0.0

931.88

05.02.05

CONCRETO F'C=175KG/CM2

M3

69.89

0.0

0.0

69.89

05.02.06

CURADO DE CONCRETO

M2

931.88

0.0

0.0

931.88

05.02.07

SUMINISTRO DE LOSETAS DE
PIEDRA

M2

86.0

0.0

0.0

86.00

05.02.08

COLOCADO DE LOSETAS DE
PIEDRA

M2

86.0

0.0

0.0

86.00

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

CODIGO

PARTIDA

UNID

METRADO

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

TOTAL
MES

ACUMULAD
O

SALDO

05.02.09

EMBOQUILLADO ENTRE
LOSETAS DE PIEDRA

M2

86.0

0.0

0.0

86.00

05.02.10

CURADO DE CONCRETO

M2

86.0

0.0

0.0

86.00

06

MUROS DE CONTENCION

06.01

TRAZO, NIVELES Y REPLANTEO


DURANTE EL PROCESO DE
CONSTRUCCION

M2

225.67

0.0

225.67

0.0

06.02

SOLADOS DE 2", MEZCLA 1:12

M2

225.67

0.0

225.67

0.0

06.03

ENCOFRADO Y DESENCOFRADO
DE MUROS DE SOSTENIMIENTO

M2

371.26 33.50

33.50

259.77

111.49

06.04

CONCRETO CICLOPEO F'C=140


KG/CM2 + 30% PG

M3

224.45

0.0

37.11

187.34

06.05

FILTRO DE GRAVA

M3

3.96

0.0

2.78

1.18

06.06

TUBERIA PVC SAL 3"

93.75 11.70

11.70

90.10

3.65

06.07

EMBOQUILLADO DE MURO (AREA M2


VISIBLE) C:A 1:5, e=0.02M

313.11

0.0

155.29

157.82

06.08

CURADO DE CONCRETO

M2

371.26

0.0

323.28

47.98

06.09

JUNTAS ASFALTICAS 1"X0.06M,


1:4

77.8

0.0

0.0

77.80

07

SISTEMA DE EVACUACION DE
AGUAS PLUVIALES

07.01

SUMIDEROS

07.01.01

TRAZO, NIVELES Y REPLANTEO


DURANTE EL PROCESO DE
CONSTRUCCION

M2

15.4

0.0

0.0

15.40

07.01.02

NIVELACION Y COMPACTADO
MANUAL

M2

15.4

0.0

0.0

15.40

07.01.03

EMPEDRADO DE 4"

M2

15.4

0.0

0.0

15.40

07.01.04

ENCOFRADO Y DESENCOFRADO
NORMAL

M2

22.4

0.0

0.0

22.40

07.01.05

ACERO DE REFUERZO G-60

KG

292.72

0.0

0.0

292.72

07.01.06

CONCRETO F'C=210KG/CM2

M3

5.13

0.0

0.0

5.13

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

CODIGO

PARTIDA

UNID

METRADO

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

TOTAL
MES

ACUMULAD
O

SALDO

07.01.07

REJILLA SUMIDERO PLAT 2 1/2"x


1/2" C/RIEL

M2

10.6

0.0

0.0

10.60

07.01.08

TARRAJEO CON
IMPERMEABILIZANTE MEZCLA
1:5 e=1.5 CM

M2

32.8

0.0

0.0

32.80

07.01.09

CURADO DE CONCRETO

32.8

0.0

0.0

32.80

07.01.10

JUNTAS ASFALTICAS 1"X0.06M,


1:4

44.0

0.0

0.0

44.00

07.01.11

CAMA DE APOYO

M3

12.03

0.0

0.0

12.03

07.01.12

TENDIDO DE TUBERIA DE 8"

240.5

0.0

0.0

240.50

07.02

CANAL CON TAPAS DE


CONCRETO

07.02.01

TRAZO, NIVELES Y REPLANTEO


DURANTE EL PROCESO DE
CONSTRUCCION

M2

599.49

0.0

0.0

599.49

07.02.02

NIVELACION Y COMPACTADO
MANUAL

M2

599.49

0.0

0.0

599.49

07.02.03

EMPEDRADO DE 4"

M2

599.49

0.0

0.0

599.49

07.02.04

ENCOFRADO Y DESENCOFRADO
NORMAL

M2

1005.57

0.0

0.0

1,005.5
7

07.02.05

ACERO DE REFUERZO G-60

KG

2543.9

0.0

0.0

2,543.9
0

07.02.06

CONCRETO F'C = 210 KG/CM2

M3

179.94

0.0

0.0

179.94

07.02.07

TAPA DE CONCRETO ARMADO


PREFABRICADO

UND

996.0

0.0

0.0

996.00

07.02.08

TARRAJEO CON
IMPERMEABILIZANTE MEZCLA
1:5 e=1.5 CM

M2

1398.81

0.0

0.0

1,398.8
1

07.02.09

CURADO DE CONCRETO

M2

1398.81

0.0

0.0

1,398.8
1

08

OBRAS COMPLEMENTARIAS

08.01

SEALIZACION

08.01.01

SEALES PREVENTIVAS

14.0

0.0

0.0

14.00

08.02

DEMARCACION

UND

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

CODIGO

PARTIDA

UNID

08.02.01

PINTADO DE SARDINELES AL
BORDE DE LA VIA

08.02.02

PINTADO DE SEALES EN PISO

M2

08.03

BANCAS

08.03.01

BANCAS DE MADERA CON


ESTRUCTURA METALICA

08.04

PAPELERA

08.04.01

SUMINISTRO E INSTALACION DE
CONTENEDOR TIPO PAPELERA

08.05

ESTRUCTURAS VARIAS

08.05.01

BARANDAS METALICAS (SEGN


DISEO)

09

CONTROL DE CALIDAD DE LA
OBRA

09.01

DISEO DE MEZCLAS

09.01.01

DISEO DE MEZCLA DE
CONCRETO

09.02

PRUEBA DE CONTROL

09.02.01

METRADO

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

TOTAL
MES

ACUMULAD
O

SALDO

1990.3

0.0

0.0

1,990.3
0

49.5

0.0

0.0

49.50

UND

5.0

0.0

0.0

5.00

UND

4.0

0.0

0.0

4.00

190.0

0.0

0.0

190.00

UND

2.0

0.0

0.0

2.00

PRUEBA DE DENSIDAD DE
CAMPO

UND

20.0

0.0

0.0

20.00

09.02.02

ROTURA DE BRIQUETAS

UND

25.0

0.0

10.00

15.00

10

INTERVENCION ARQUEOLOGICA

10.01

MONITOREO ARQUEOLOGICO

MES

10.0

0.0

3.00

7.00

11

MITIGACION DE IMPACTOS

11.01

TRATAMIENTO DE AREAS
VERDES

11.01.01

ACONDICIONAMIENTO DE AREAS M2
VERDES

365.0

0.0

0.0

365.00

12

LIMPIEZA DE OBRA

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

CODIGO

12.01

PARTIDA

LIMPIEZA DE OBRA

UNID

M2

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

METRADO

7935.74

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

TOTAL
MES

ACUMULAD
O

0.0

0.0

Ing. Moises Mamani Apaza


Residente de obra

SALDO

7,935.7
4

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE


INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO
DEL CUSCO, PROVINCIA DEL CUSCO

VALORZACION DE MAYORES METRADOS

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

VALORIZACION DE MAYORES METRADOS


OBRA : MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA
AYUDA MUTUA, DISTRITO DEL CUSCO, PROVINCIA DEL CUSCO
CORRESPONDIENTE AL MES DE : JUNIO

PROGRAMADO
CODIGO

PARTIDA

ANTERIOR
UNID

METRADO

PRECIO
UNITARIO

PARCIAL

METRADO

COSTO

ACTUAL
%

COSTO

COSTO

METRADO

COSTO

GASTOS GENERALES

0.0

0.0

0.0

0.0

0.0

GASTOS DE SUIPERVICION

0.0

0.0

0.0

0.0

0.0

GASTOS DE LIQUIDACION

0.0

0.0

0.0

0.0

0.0

GASTOS DE EXPEDIENTE TECNICO

0.0

0.0

0.0

0.0

0.0

GASTOS TOTAL PRESUPUESTO

0.0

0.0

Gerente de Infraestructura

0.0 %

0.0

SALDO
%

0.0

0.0

0.0 %

METRADO

0.0

0.0 %

0.0

ACUMULADO
%

COSTO DIRECTO

Ing. Tricia Santoyo Cruz

0.0 %

METRADO

0.0

0.0 %

0.0 %

0.0

0.0

Ing. Moises Mamani Apaza


Residente de obra

0.0 %

0.0 %

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE


INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO
DEL CUSCO, PROVINCIA DEL CUSCO

METRADO DIARIO DEMAYORES METRADOS

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

METRADO DIARIO DE MAYORES METRADOS


OBRA : MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA
AYUDA MUTUA, DISTRITO DEL CUSCO, PROVINCIA DEL CUSCO
CORRESPONDIENTE AL MES DE : JUNIO

CODIGO

PARTIDA

UNID

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

METRADO

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

TOTAL
MES

ACUMULAD
O

Ing. Moises Mamani Apaza


Residente de obra

SALDO

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE


INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO
DEL CUSCO, PROVINCIA DEL CUSCO

VALORIZACION DE PARTIDAS NUEVAS

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

VALORIZACION DE PARTIDAS NUEVAS


OBRA : MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA
AYUDA MUTUA, DISTRITO DEL CUSCO, PROVINCIA DEL CUSCO
CORRESPONDIENTE AL MES DE : JUNIO

PROGRAMADO
CODIGO

06.10

ANTERIOR

PARTIDA

CONCRETO CICLOPEO FC=140 +50%PG

UNID

PARCIAL

ACTUAL
%

METRADO

ACUMULADO
%

7,335.63

4.69 %

7,335.63

4.69 %

METRADO

SALDO
%

56.16 %

87,842.98

56.16 %

0.0

0.0

0.0

0.0

GASTOS DE SUIPERVICION

0.0

0.0

0.0

0.0

0.0

GASTOS DE LIQUIDACION

0.0

0.0

0.0

0.0

0.0

GASTOS DE EXPEDIENTE TECNICO

0.0

0.0

0.0

0.0

0.0

156,410.00

80,507.35

87,842.98

56.16 %

219.19

COSTO

0.0

4.69 %

87,842.98

METRADO

GASTOS GENERALES

7,335.63

280.81

COSTO

51.47 %

51.47 %

23.45

COSTO

80,507.35

Gerente de Infraestructura

257.36

COSTO

156,410.00

Ing. Tricia Santoyo Cruz

312.82 156,410.00

METRADO

51.47 %

GASTOS TOTAL PRESUPUESTO

500.0

PRECIO
UNITARIO

80,507.35

COSTO DIRECTO

M3

METRADO

68,567.02

43.84 %

68,567.02

43.84 %

68,567.02

Ing. Moises Mamani Apaza


Residente de obra

43.84 %

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE


INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO
DEL CUSCO, PROVINCIA DEL CUSCO

METRADO DIARIO DE PARTIDAS NUEVAS

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

Ing. Moises Mamani Apaza


Residente de obra

MUNICIPALIDAD PROVINCIAL DEL CUSCO


GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS

METRADO DIARIO DE PARTIDAS NUEVAS


OBRA : MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA
AYUDA MUTUA, DISTRITO DEL CUSCO, PROVINCIA DEL CUSCO
CORRESPONDIENTE AL MES DE : JUNIO

CODIGO

06.10

PARTIDA

CONCRETO CICLOPEO FC=140


+50%PG

UNID

M3

Ing. Tricia Santoyo Cruz


Gerente de Infraestructura

METRADO

500.0 23.45

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

TOTAL
MES

ACUMULAD
O

23.45

280.81

Ing. Moises Mamani Apaza


Residente de obra

SALDO

219.19