Ques: Draw a network diagram for a project having 9 activities
The inter-relationship is as follows:
1. C follows D but precedes F 2. C follows B but precedes H 3. G follows F but precedes I 4. E follows A but precedes I 5. D follows A 6. H & I terminate at the same time 7. A & B start at the same point