Ques: Draw a network diagram for a project having 9 activities

The inter-relationship is as follows:


1. C follows D but precedes F
2. C follows B but precedes H
3. G follows F but precedes I
4. E follows A but precedes I
5. D follows A
6. H & I terminate at the same time
7. A & B start at the same point

Ans: C follows D but precedes F

C follows B but precedes H

G follows F but precedes I

E follows A but precedes I

D follows A

H & I terminate at the same time

A & B start at the same point

So the final network diagram is: