Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
EDTP
6/29/15
After the track formation is ready, concrete sleeper are stacked along the formation
sides
Level & alignment control pegs are installed along the formation at interval of 10 m at
about 5.6 m from the center of formation
Centre of the track to be constructed is marked by paint on the formation
Ballast stock pile for bottom ballasting is stocked at nearby area and must be easily
excess by tipper truck and not obstructing construction machineries while the
construction of track in progress.
6/29/15
Tipper trucks are used to transport the ballast to the ballast box location
The ballast is unloaded to the ballast box to spread the ballast while moving along the
center of the track which are marked by paint at earlier stage.
6/29/15
The ballast box spread the bottom ballast at predetermined profile of 3.6m width
The distributed ballast then rolled by two passes of 10 tons vibratory roller compactor
following behind the ballast box at speed of between 2 5 Km/hr.
The ballast layer shall be up to 200mm thick and 4m wide after compaction.
6/29/15
The sleeper alignment corresponding to the track alignment to be built is marked on the
compacted bottom ballast to facilitate distribution of concrete sleeper onto it.
An excavator or any other suitable lifting plant then used to lift the sleepers.
A pair of spacer (of 600mm spacing for main lines & 650mm spacing for loop, siding or
spur line) and a spreader beam are used to lift 8 numbers of concreter sleeper at a
time.
6/29/15
6/29/15
RAIL THREADER
RAIL THREADER
6/29/15
13
6/29/15
14
6/29/15
15
On completion of rail distribution, rail strings are lifted by track jack, roller released
and rail positioned on the sleeper seat
6/29/15
16
6/29/15
1) PRIOR TO WELDING
650 mm from rail end
ground flush with web
using 100/125 mm hand
grinders to remove any
brand name, lettering, &
roll marks ensuring full
contact between welding
electrodes and the rail.
(cl 3.1.4 IN SITU FLASH BUTT WELDING
OF UIC 54KG RAILS DTP/MMCG(HQ)/N1N8/S1-S32/MS/WLD(EM)/0002)
6/29/15
18
6/29/15
19
20
2) POST WELDING
At full head profile (extending up to the lower corner of the rail head on either
side)
2mm
DTP/MMCG(HQ)/N1-N8/S1-S32/MS/WLD(EM)/0002)
At the
foot including the bottom fillet radius and also under the rail foot
1.5m
m
Final grinding carried out after the rail has cooled to ambient
temperature using rail profile grinder. The grinding shall be
limited to 400 mm from the weld over either or both rails to
prevent over grinding and provides smooth surface.
6/29/15
21
6/29/15
22
6/29/15
23
6/29/15
24
PROFILE GRINDING
Rail head alignment check using a meter gauge and filler gauge to
estimate the extent of profile grinding to be done and to check the
straightness of the of the joint
6/29/15
25
PROFILE GRINDING
26
27
6/29/15
28
6/29/15
29
6/29/15
30
0.3mm
6/29/15
31
Horizontal misalignment
reading
6/29/15
Vertical misalignment
reading
32
6/29/15
33
6/29/15
34
6/29/15
ANOTHER ROUND OF
TAMPING FOLLOWED BY
DTS SHOULD BE DONE IF
THE TRACK SETTLEMENT
IS MORE THAN 20mm ON
MINIMUM 250m OF THE
THE TRACK SHALL BE LIFTED AND TAMPED NEAR TO CORRECT LINE AND LEVEL
DURING SECOND TAMPING CYCLE GUIDED THROUGH THE TRACK SURVEY READING
INPUT GIVEN BY SURVEYOR
THE TRACK SURVEY READING UPON COMPLETION OF THE SECOND CYCLE TAMPING
IS RECORDED
BALLAST CUSHION UNDER THE TRACK SLEEEPER SHOULD NOT LESS THAN 250mm
WHICH CAN BE DETERMINED FROM THE TRACK SURVEY READING
THE TRACK IS THEN ALLOWED FOR ONE PASS OF DTS (DYNAMIC TRACK
STABILIZATION) MACHINE
HORIZONTAL OFFSET POINTS FOR THE TRACK ARE SET OUT AT EVERY 25m
FOR STRAIGHT STRETCH, 20m AT CURVES AND TRANSITION, AND AT EVERY
10m FOR CURVES WITH < 800m RADIUS
SURVEY READING OF TRACK LEVEL IS TAKEN WITH REFERENCE TO THE NEAREST TBM
SURVEY READINGS OF TRACK ARE TAKEN ON THE LEFT HAND RAIL (FACING NORTH), OR
ON THE LOWER SIDE FOR CURVES & TRANSITIONS
TRACK TOLERANCE
TARCK TOLERANCE
6/29/15
INTRODUCTION TO DE-STRESSING
49
6/29/15
50
51
52
53
2) INSERTION OF RAIL
ROLLER
RAIL SUPPORT
ROLLER
6/29/15
RAIL SIDE
ROLLER
54
2) INSERTION OF RAIL
ROLLER
INSTALLATION OF RAIL SIDE ROLLER
RAIL
PULL DIRECTION
55
3)
KNOCKIN
G
56
HIDRAULIC RAIL TENSORS ARE USED TO PULL THE RAILS DURING DESTRESSING.
IN STRAIGHT TRACK THE RAIL LENGTH FOR DESTRESSING IS LIMITED
TO < 1000 m, AND < 600 m FOR CURVED TRACK OF RADIUS < 1500 m.
WELDING GAP FOR ATW OF THE DE-STRESSING JOINT IS 25 mm 1
mm.
ADQUATE GAP SHOULD BE CREATED TO ACCOMMODATE WELDING GAP
AND RAIL EXTENSION PRIOR TO PULLING.
6/29/15
57
6/29/15
58
5) TENSIONING /
PULLING
DE-STRESSING JOINT
HYDRAULIC PUMP
IL
RA
SO
N
TE
5) TENSIONING /
PULLING
RAIL MOVEMENT/ ELONGATION IS CLOSELY MONITORED AT THE DESTRESSING JOINT AS WELL AS AT THE TELL TALE MARKS
ESTABLISHED EARLIER.
PULLING FORCE FROM THE TENSOR IS CONTINUOUSLY INCREASED
UNTIL THE DESIRED ELONGATION VALUE IS ACHIEVED AND THE
TENSOR WILL BE LOCKED ON ITS POSITION TO ALLOW FOR RE6/29/15
61
CLIPPING
& WELDING.
62
6/29/15
63
FILLER GAUGE
6/29/15
65
66
6/29/15
67
BUKIT MERTAJAM
UP MAIN
LINE
UP MAIN
LINE
BUKIT MERTAJAM
UP MAIN LINE CH72.048
PADANG BESAR
UP MAIN LINE CH78.874
BUKIT MERTAJAM
W
DO
UP MAIN
LINE
BUKIT
MERTAJAM
UP MAIN LINE CH78.874
AI
M
N
E
N
I
NL
UP MAIN
LINE
PADANG BESAR
UP MAIN LINE CH80.438
BUKIT MERTAJAM
SPUR UP
LEFT
SPUR UP
LEFT
BUKIT MERTAJAM
SPUR UP LEFT CH78.943
PADANG BESAR
SPUR UP LEFT CH79.943
BUKIT MERTAJAM
UP LOOP
LINE
UP LOOP
LINE
UP MAIN
LINE
BUKIT MERTAJAM
UP LOOP LINE CH79.291
PADANG BESAR
UP LOOP LINE CH80.200
BUKIT MERTAJAM
DO
WN
MA
IN
LIN
E
DOWN MAIN
LINE
UP MAIN
LINE
BUKIT MERTAJAM
DOWN MAIN LINE CH79.104
PADANG BESAR
DOWN MAIN LINE CH80.543
CUT & SLEW OF TRACK CONNECTING EXISTING KTMB TRACK WITH NEW
PERMANENT TRACK DONE DURING TRACK POSSESSION (LINE BLOCK).
PRE - LAID TEMPORARY TRACK PANELS SLEWED WITH SHOVEL MACHINE
NOMINALLY TO ITS FINAL ALIGNMENT TO MATCH WITH PERMANENT TRACK.
THE TRACK WILL BE BROUGHT TO FINAL LINE & LEVEL BY TAMPING MACHINE
THE TRACK PANELS JOINED WITH FISH PLATES SECURED WITH C-CLAMP
BEFORE TAMPING UNTIL DE-STRESSING & WELDING.
THE END
PRESENTED BY EE BOON HOE
SECTION HEAD QAQC N1-N3
6/29/15