ISSUES TO BE SOLVED THIS WEEK

ISSUES
GC-21 PACKAGE HOLD
BECAUSE OF COATING
REPORT (ONE SPOOL)
GC-20 PACKAGE
PREPARATION
3L-PE COATING REPAIR IN
SITE NCC DO NOT
SUPPLY THE MANPOWER
FOR REPAIR ACTIVITY

A1-1 SITE WORK FOR


SAND BLASTING SHBC
DO NOT WANT TO DO IN
THE SITE
WMS PREPARATION FOR
URGENT LOCATIONS
1. STF-A32A
2. GC-20
3. GC-22
4. BS-150
HBP COATING EXPIRATION
AFTER 10 MONTHS OF
COATED SPOOL

SOLUTION
DISCUSS W/ PMC AND
CHECK IN THE SITE

REMARKS
CLEARED

PREPARE IN URGENT
BASIS AND HAND OVER
TO QC0
TRAINING AND
APPROVAL OF IMCO
PERSONNEL
TRAINING AND
APPROVAL OF NCC
PERSONNEL

CLEARED

CHECK WITH PMC AND


ASK FOR THE ADVISE
OTHERWISE SUBMIT TQ
TO KOC
WMS PREPARATION UNTIL
14 APRIL AND DISCUSS TO
MICU

ON-GOING

CHECK THE SPOOL STATUS

ON-GOING

ON-GOING