733 days
20/8/13
Finish
Qtr 3, 2013
Qtr 4, 2013
Qtr 1, 2014
Qtr 2, 2014
Qtr 3, 2014
Qtr 4, 2014
Qtr 1, 2015
Qtr 2, 2015
Qtr 3, 2015
Qtr 4
A
S
O
N
D
J
F
M
A
M
J
J
A
S
O
N
D
J
F
M
A
M
J
J
A
S
O
31323334353637383940414243444546474849505152 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425262728293031323334353637383940414243444546474849505152 1 2 3 4 5 6 7 8 9 1011121314151617181920212223242526272829303132333435363738394041
21/9/15
91 days
13/8/14
11/11/14
15 days
25/2/15
15/3/15
42 days
19/2/14
1/4/14
29 days
14/5/14
11/6/14
14 days
20/8/13
2/9/13
Approval of IMP
7 days
3/9/13
9/9/13
21 days
10/9/13
30/9/13
28 days
1/10/13
28/10/13
10
7 days
29/10/13
4/11/13
11
14 days
5/11/13
18/11/13
12
ZONE 1
336 days
19/11/13
4/11/14
162 days
27/5/14
4/11/14
13
Task Name
Duration
Start
1-A
14
ROW 1 - 2 Teams
24 days
27/5/14
19/6/14
15
ROW 2 - 2 Teams
24 days
20/6/14
13/7/14
16
ROW 3 - 2 Teams
24 days
14/7/14
6/8/14
17
ROW 4 - 2 Teams
24 days
7/8/14
30/8/14
18
ROW 5 - 2 Teams
24 days
31/8/14
23/9/14
19
ROW 6 - 2 Teams
24 days
24/9/14
17/10/14
20
ROW 7 - 1 Teams
18 days
18/10/14
4/11/14
174 days
19/11/13
26/5/14
21
1-B
22
ROW 1 - 2 Teams
24 days
19/11/13
12/12/13
23
ROW 2 - 2 Teams
24 days
13/12/13
5/1/14
24
ROW 3 - 2 Teams
24 days
6/1/14
13/2/14
25
ROW 4 - 2 Teams
24 days
14/2/14
9/3/14
26
ROW 5 - 2 Teams
24 days
10/3/14
2/4/14
27
ROW 6 - 2 Teams
24 days
3/4/14
26/4/14
28
30 days
27/4/14
26/5/14
168 days
21/5/14
4/11/14
29
1-C
30
ROW 1 - 4 Teams
24 days
21/5/14
13/6/14
31
ROW 2 - 3 Teams
24 days
14/6/14
7/7/14
32
ROW 3 - 4 Teams
24 days
8/7/14
31/7/14
33
ROW 4 - 4 Teams
24 days
1/8/14
24/8/14
34
ROW 5 - 4 Teams
24 days
25/8/14
17/9/14
35
ROW 6 - 4 Teams
24 days
18/9/14
11/10/14
36
24 days
12/10/14
4/11/14
168 days
19/11/13
20/5/14
37
1-D
38
ROW 1 - 4 Teams
24 days
19/11/13
12/12/13
39
ROW 2 - 2 Teams
24 days
13/12/13
5/1/14
40
ROW 3 - 4 Teams
24 days
6/1/14
13/2/14
41
ROW 4 - 4 Teams
24 days
14/2/14
9/3/14
42
ROW 5 - 4 Teams
24 days
10/3/14
2/4/14
43
ROW 6 - 4 Teams
24 days
3/4/14
26/4/14
44
ROW 7 - 2 Teams
24 days
27/4/14
20/5/14
168 days
9/5/14
23/10/14
45
1-E
46
ROW 1 - 3 Teams
24 days
9/5/14
1/6/14
47
ROW 2 - 3 Teams
24 days
2/6/14
25/6/14
48
ROW 3 - 3 Teams
24 days
26/6/14
19/7/14
49
ROW 4 - 3 Teams
24 days
20/7/14
12/8/14
50
ROW 5 - 3 Teams
24 days
13/8/14
5/9/14
51
ROW 6 - 3 Teams
24 days
6/9/14
29/9/14
52
ROW 7 - 1 Teams
18 days
30/9/14
17/10/14
53
24 days
30/9/14
23/10/14
156 days
19/11/13
8/5/14
54
1-F
55
ROW 1 - 3 Teams
24 days
19/11/13
12/12/13
56
ROW 2 - 2 Teams
24 days
13/12/13
5/1/14
57
ROW 3 - 3 Teams
24 days
6/1/14
13/2/14
58
ROW 4 - 3 Teams
24 days
14/2/14
9/3/14
59
ROW 5 - 3 Teams
24 days
10/3/14
2/4/14
60
ROW 6 - 3 Teams
24 days
3/4/14
26/4/14
Task
Project: SHORT TERM PROGRAM
Split
Date: 20/8/13
Milestone
Summary
Project Summary
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Start-only
Finish-only
Deadline
Page 1
Progress
ID
Task Name
ROW 7 - 1 Teams
61
Start
12 days
27/4/14
Finish
Qtr 3, 2013
Qtr 4, 2013
Qtr 1, 2014
Qtr 2, 2014
Qtr 3, 2014
Qtr 4, 2014
Qtr 1, 2015
Qtr 2, 2015
Qtr 3, 2015
Qtr 4
A
S
O
N
D
J
F
M
A
M
J
J
A
S
O
N
D
J
F
M
A
M
J
J
A
S
O
31323334353637383940414243444546474849505152 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425262728293031323334353637383940414243444546474849505152 1 2 3 4 5 6 7 8 9 1011121314151617181920212223242526272829303132333435363738394041
8/5/14
144 days
27/4/14
17/9/14
63
ROW 1 - 3 Teams
24 days
27/4/14
20/5/14
64
ROW 2 - 3 Teams
24 days
21/5/14
13/6/14
65
ROW 3 - 3 Teams
24 days
14/6/14
7/7/14
66
ROW 4 - 3 Teams
24 days
8/7/14
31/7/14
67
ROW 5 - 3 Teams
24 days
1/8/14
24/8/14
68
ROW 6 - 3 Teams
24 days
25/8/14
17/9/14
144 days
19/11/13
26/4/14
62
69
1-G
Duration
1-H
70
ROW 1 - 3 Teams
24 days
19/11/13
12/12/13
71
ROW 2 - 3 Teams
24 days
13/12/13
5/1/14
72
ROW 3 - 3 Teams
24 days
6/1/14
13/2/14
73
ROW 4 - 3 Teams
24 days
14/2/14
9/3/14
74
ROW 5 - 3 Teams
24 days
10/3/14
2/4/14
75
ROW 6 - 3 Teams
24 days
3/4/14
26/4/14
306 days
12/6/14
28/4/15
84 days
12/6/14
3/9/14
76
77
ZONE 2
2-A
78
ROW 1 - 2 Teams
24 days
12/6/14
5/7/14
79
ROW 2 - 2 Teams
24 days
6/7/14
29/7/14
80
ROW 3 - 1 Teams
24 days
30/7/14
22/8/14
81
ROW 4 - 1 Teams
12 days
23/8/14
3/9/14
90 days
30/7/14
27/10/14
82
2-B
83
ROW 1 - 1 Teams
12 days
30/7/14
10/8/14
84
ROW 2 - 1 Teams
12 days
11/8/14
22/8/14
85
ROW 3 - 1 Teams
12 days
23/8/14
3/9/14
86
ROW 4 - 1 Teams
12 days
4/9/14
15/9/14
87
ROW 5 - 1 Teams
12 days
16/9/14
27/9/14
88
ROW 6 - 1 Teams
6 days
28/9/14
3/10/14
89
24 days
4/10/14
27/10/14
168 days
28/10/14
28/4/15
90
2-C
91
ROW 1 - 3 Teams
24 days
28/10/14
20/11/14
92
ROW 2 - 3 Teams
24 days
21/11/14
14/12/14
93
ROW 3 - 3 Teams
24 days
15/12/14
7/1/15
94
ROW 4 - 3 Teams
24 days
8/1/15
31/1/15
95
ROW 5 - 3 Teams
24 days
1/2/15
11/3/15
96
ROW 6 - 3 Teams
24 days
12/3/15
4/4/15
97
24 days
5/4/15
28/4/15
354 days
18/9/14
21/9/15
192 days
24/10/14
18/5/15
98
99
ZONE 3
3-A
100
ROW 1 - 3 Teams
24 days
24/10/14
16/11/14
101
ROW 2 - 3 Teams
24 days
17/11/14
10/12/14
102
ROW 3 - 3 Teams
24 days
11/12/14
3/1/15
103
ROW 4 - 3 Teams
24 days
4/1/15
27/1/15
104
ROW 5 - 3 Teams
24 days
28/1/15
7/3/15
105
ROW 6 - 3 Teams
24 days
8/3/15
31/3/15
106
ROW 7 - 3 Teams
24 days
1/4/15
24/4/15
107
ROW 8 - 1 Teams
12 days
25/4/15
6/5/15
108
24 days
25/4/15
18/5/15
126 days
5/11/14
25/3/15
109
3-B
110
ROW 1 - 2 Teams
24 days
5/11/14
28/11/14
111
ROW 2 - 2 Teams
24 days
29/11/14
22/12/14
112
ROW 3 - 2 Teams
24 days
23/12/14
15/1/15
113
ROW 4 - 2 Teams
24 days
16/1/15
8/2/15
114
ROW 5 - 2 Teams
24 days
9/2/15
19/3/15
115
ROW 6 - 1 Teams
6 days
20/3/15
25/3/15
180 days
26/3/15
21/9/15
116
3-C
117
ROW 1 - 2 Teams
24 days
26/3/15
18/4/15
118
ROW 2 - 2 Teams
24 days
19/4/15
12/5/15
119
ROW 3 - 2 Teams
24 days
13/5/15
5/6/15
120
ROW 4 - 2 Teams
24 days
6/6/15
29/6/15
121
ROW 5 - 1 Teams
24 days
30/6/15
23/7/15
Task
Project: SHORT TERM PROGRAM
Split
Date: 20/8/13
Milestone
Summary
Project Summary
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Start-only
Finish-only
Deadline
Page 2
Progress
ID
Task Name
122
Start
60 days
24/7/15
Finish
Qtr 3, 2013
Qtr 4, 2013
Qtr 1, 2014
Qtr 2, 2014
Qtr 3, 2014
Qtr 4, 2014
Qtr 1, 2015
Qtr 2, 2015
Qtr 3, 2015
Qtr 4
A
S
O
N
D
J
F
M
A
M
J
J
A
S
O
N
D
J
F
M
A
M
J
J
A
S
O
31323334353637383940414243444546474849505152 1 2 3 4 5 6 7 8 9 10111213141516171819202122232425262728293031323334353637383940414243444546474849505152 1 2 3 4 5 6 7 8 9 1011121314151617181920212223242526272829303132333435363738394041
21/9/15
150 days
18/9/14
14/2/15
124
ROW 1 - 3 Teams
24 days
18/9/14
11/10/14
125
ROW 2 - 3 Teams
24 days
12/10/14
4/11/14
126
ROW 3 - 3 Teams
24 days
5/11/14
28/11/14
127
ROW 4 - 3 Teams
24 days
29/11/14
22/12/14
128
ROW 5 - 3 Teams
24 days
23/12/14
15/1/15
129
ROW 6 - 3 Teams
24 days
16/1/15
8/2/15
130
ROW 7 - 1 Teams
6 days
9/2/15
14/2/15
192 days
2/3/15
9/9/15
123
131
3-D
Duration
3-E
132
ROW 1 - 3 Teams
24 days
2/3/15
25/3/15
133
ROW 2 - 3 Teams
24 days
26/3/15
18/4/15
134
ROW 3 - 3 Teams
24 days
19/4/15
12/5/15
135
ROW 4 - 3 Teams
24 days
13/5/15
5/6/15
136
ROW 5 - 3 Teams
24 days
6/6/15
29/6/15
137
ROW 6 - 3 Teams
24 days
30/6/15
23/7/15
138
ROW 7 - 3 Teams
24 days
24/7/15
16/8/15
139
ROW 8 - 2 Teams
24 days
17/8/15
9/9/15
216 days
5/11/14
23/6/15
140
3-F
141
ROW 1 - 4 Teams
24 days
5/11/14
28/11/14
142
ROW 2 - 4 Teams
24 days
29/11/14
22/12/14
143
ROW 3 - 4 Teams
24 days
23/12/14
15/1/15
144
ROW 4 - 4 Teams
24 days
16/1/15
8/2/15
145
ROW 5 - 4 Teams
24 days
9/2/15
19/3/15
146
ROW 6 - 4 Teams
24 days
20/3/15
12/4/15
147
ROW 7 - 4 Teams
24 days
13/4/15
6/5/15
148
ROW 8 - 4 Teams
24 days
7/5/15
30/5/15
149
ROW 9 - 2 Teams
24 days
31/5/15
23/6/15
364 days
19/11/13
2/12/14
160 days
19/11/13
12/5/14
150
151
ZONE 4
4-A
152
ROW S1 - 4 Teams
24 days
19/11/13
12/12/13
153
ROW S2 - 4 Teams
24 days
13/12/13
5/1/14
154
ROW S3 - 3 Teams
24 days
6/1/14
13/2/14
155
ROW W - 4 Teams
28 days
14/2/14
13/3/14
156
ROW S4 - 4 Teams
24 days
14/3/14
6/4/14
157
ROW S5 - 2 Teams
24 days
7/4/14
30/4/14
158
ROW S6 - 1 Teams
12 days
1/5/14
12/5/14
204 days
13/5/14
2/12/14
159
4-B
160
ROW 1 - 3 Teams
24 days
13/5/14
5/6/14
161
ROW 2 - 3 Teams
24 days
6/6/14
29/6/14
162
ROW 3 - 3 Teams
24 days
30/6/14
23/7/14
163
ROW 4 - 3 Teams
24 days
24/7/14
16/8/14
164
ROW 5 - 3 Teams
24 days
17/8/14
9/9/14
165
ROW 6 - 3 Teams
24 days
10/9/14
3/10/14
166
ROW 7 - 3 Teams
24 days
4/10/14
27/10/14
167
36 days
28/10/14
2/12/14
Task
Project: SHORT TERM PROGRAM
Split
Date: 20/8/13
Milestone
Summary
Project Summary
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Start-only
Finish-only
Deadline
Page 3
Progress