Sei sulla pagina 1di 17

PT.

WIJAYA KARYA REKAYASA KONSTRUKSI

NON CONFORMANCE REPORT

Form No.
Rev
Date
Dept

: ISO-QA/QC/01/VIII/14
: 00
:
: QA / QC

Element ISO 9001 : 2000

BOILER
STAG

Corrosive pipe Water Wall Siklon


ELECTRICAL & I / C
No.

01/BLR/QA/QC/VIII/14

Date

CONTENT OF NON CONFORMANCE :

Pipa
korosive

PROPOSED CORRECTIVE ACTION :

Proposed Completion date :

COMMENT :
Pipa Korosif

Comment by : .
NCR CLOSED :
(Name & Sign)

Date of Comment : ..
YES

NO
Date :

PT. WIJAYA KARYA REKAYASA KONSTRUKSI

NON CONFORMANCE REPORT

Form No.
Rev
Date
Dept

: ISO-QA/QC/01/VIII/14
: 00
:
: QA / QC

Element ISO 9001 : 2000

BOILER
STAG

Corrosive Pipe
ELECTRICAL & I / C
No.

01/BLR/QA/QC/VIII/14

Date

CONTENT OF NON CONFORMANCE :

Pipa Korosif

PROPOSED CORRECTIVE ACTION :

Proposed Completion date :

Brushing

COMMENT :

Comment by : .
NCR CLOSED :
(Name & Sign)

Date of Comment : ..
YES

NO
Date :

PT. WIJAYA KARYA REKAYASA KONSTRUKSI

NON CONFORMANCE REPORT

Form No.
Rev
Date
Dept

: ISO-QA/QC/01/VIII/14
: 00
:
: QA / QC

Element ISO 9001 : 2000

BOILER
STAG

Dented Pipe(penyok) LP Heater


ELECTRICAL & I / C
No.

01/BLR/QA/QC/VIII/14

Date

CONTENT OF NON CONFORMANCE :

Dented Pipe

PROPOSED CORRECTIVE ACTION :

Proposed Completion date :

COMMENT :

Comment by : .
NCR CLOSED :
(Name & Sign)

Date of Comment : ..
YES

NO
Date :

PT. WIJAYA KARYA REKAYASA KONSTRUKSI

NON CONFORMANCE REPORT

Form No.
Rev
Date
Dept

: ISO-QA/QC/01/VIII/14
: 00
:
: QA / QC

Element ISO 9001 : 2000

BOILER
STAG

Dented Pipe(penyok) LP Heater


ELECTRICAL & I / C
No.

01/BLR/QA/QC/VIII/14

Date

CONTENT OF NON CONFORMANCE :

Dented Pipe

PROPOSED CORRECTIVE ACTION :

Proposed Completion date :

COMMENT :

Comment by : .
NCR CLOSED :
(Name & Sign)

Date of Comment : ..
YES

NO
Date :

PT. WIJAYA KARYA REKAYASA KONSTRUKSI

NON CONFORMANCE REPORT

Form No.
Rev
Date
Dept

: ISO-QA/QC/01/VIII/14
: 00
:
: QA / QC

Element ISO 9001 : 2000

BOILER
STAG

Dented Pipe(penyok) LP Heater


ELECTRICAL & I / C
No.

01/BLR/QA/QC/VIII/14

Date

Dented Pipe

CONTENT OF NON CONFORMANCE :

PROPOSED CORRECTIVE ACTION :

Proposed Completion date :

COMMENT :

Comment by : .
NCR CLOSED :
(Name & Sign)

Date of Comment : ..
YES

NO
Date :

PT. WIJAYA KARYA REKAYASA KONSTRUKSI

NON CONFORMANCE REPORT

Form No.
Rev
Date
Dept

: ISO-QA/QC/01/VIII/14
: 00
:
: QA / QC

Element ISO 9001 : 2000

BOILER
STAG

Dented Pipe(penyok) LP Heater


ELECTRICAL & I / C
No.

01/BLR/QA/QC/VIII/14

Date

Dented Pipe

CONTENT OF NON CONFORMANCE :

PROPOSED CORRECTIVE ACTION :

Proposed Completion date :

COMMENT :

Comment by : .
NCR CLOSED :
(Name & Sign)

Date of Comment : ..
YES

NO
Date :

PT. WIJAYA KARYA REKAYASA KONSTRUKSI

NON CONFORMANCE REPORT

Form No.
Rev
Date
Dept

: ISO-QA/QC/01/VIII/14
: 00
:
: QA / QC

Element ISO 9001 : 2000

BOILER
STAG

Dented Pipe(penyok) LP Heater


ELECTRICAL & I / C
No.

01/BLR/QA/QC/VIII/14

Date

Dented Pipe

CONTENT OF NON CONFORMANCE :

PROPOSED CORRECTIVE ACTION :

Proposed Completion date :

COMMENT :

Comment by : .
NCR CLOSED :
(Name & Sign)

Date of Comment : ..
YES

NO
Date :

PT. WIJAYA KARYA REKAYASA KONSTRUKSI

NON CONFORMANCE REPORT

Form No.
Rev
Date
Dept

: ISO-QA/QC/01/VIII/14
: 00
:
: QA / QC

Element ISO 9001 : 2000

BOILER
STAG

Dented Pipe(penyok) LP Heater


ELECTRICAL & I / C
No.

01/BLR/QA/QC/VIII/14

Date

Dented Pipe

CONTENT OF NON CONFORMANCE :

PROPOSED CORRECTIVE ACTION :

Proposed Completion date :

COMMENT :

Comment by : .
NCR CLOSED :
(Name & Sign)

Date of Comment : ..
YES

NO
Date :

PT. WIJAYA KARYA REKAYASA KONSTRUKSI

NON CONFORMANCE REPORT

Form No.
Rev
Date
Dept

: ISO-QA/QC/01/VIII/14
: 00
:
: QA / QC

Element ISO 9001 : 2000

BOILER
STAG

Dented Pipe(penyok) LP Heater


ELECTRICAL & I / C
No.

01/BLR/QA/QC/VIII/14

Date

Dented Pipe

CONTENT OF NON CONFORMANCE :

PROPOSED CORRECTIVE ACTION :

Proposed Completion date :

COMMENT :

Comment by : .
NCR CLOSED :
(Name & Sign)

Date of Comment : ..
YES

NO
Date :

PT. WIJAYA KARYA REKAYASA KONSTRUKSI

NON CONFORMANCE REPORT

Form No.
Rev
Date
Dept

: ISO-QA/QC/01/VIII/14
: 00
:
: QA / QC

Element ISO 9001 : 2000

BOILER
STAG

Dented Pipe(penyok) LP Heater


ELECTRICAL & I / C
No.

01/BLR/QA/QC/VIII/14

Date

Dented Pipe

CONTENT OF NON CONFORMANCE :

PROPOSED CORRECTIVE ACTION :

Proposed Completion date :

COMMENT :

Comment by : .
NCR CLOSED :
(Name & Sign)

Date of Comment : ..
YES

NO
Date :

PT. WIJAYA KARYA REKAYASA KONSTRUKSI

NON CONFORMANCE REPORT

Form No.
Rev
Date
Dept

: ISO-QA/QC/01/VIII/14
: 00
:
: QA / QC

Element ISO 9001 : 2000

BOILER
STAG

Dented Pipe(penyok) LP Heater


ELECTRICAL & I / C
No.

01/BLR/QA/QC/VIII/14

Date

Dented Pipe

CONTENT OF NON CONFORMANCE :

PROPOSED CORRECTIVE ACTION :

Proposed Completion date :

COMMENT :

Comment by : .
NCR CLOSED :
(Name & Sign)

Date of Comment : ..
YES

NO
Date :

PT. WIJAYA KARYA REKAYASA KONSTRUKSI

NON CONFORMANCE REPORT

Form No.
Rev
Date
Dept

: ISO-QA/QC/01/VIII/14
: 00
:
: QA / QC

Element ISO 9001 : 2000

BOILER
STAG

Dented Pipe(penyok) LP Heater


ELECTRICAL & I / C
No.

01/BLR/QA/QC/VIII/14

Date

Dented Pipe

CONTENT OF NON CONFORMANCE :

PROPOSED CORRECTIVE ACTION :

Proposed Completion date :

COMMENT :

Comment by : .
NCR CLOSED :
(Name & Sign)

Date of Comment : ..
YES

NO
Date :

PT. WIJAYA KARYA REKAYASA KONSTRUKSI

NON CONFORMANCE REPORT

Form No.
Rev
Date
Dept

: ISO-QA/QC/01/VIII/14
: 00
:
: QA / QC

Element ISO 9001 : 2000

BOILER
STAG

Dented Pipe(penyok) LP Heater


ELECTRICAL & I / C
No.

01/BLR/QA/QC/VIII/14

Date

Dented Pipe

CONTENT OF NON CONFORMANCE :

PROPOSED CORRECTIVE ACTION :

Proposed Completion date :

COMMENT :

Comment by : .
NCR CLOSED :
(Name & Sign)

Date of Comment : ..
YES

NO
Date :

PT. WIJAYA KARYA REKAYASA KONSTRUKSI

NON CONFORMANCE REPORT

Form No.
Rev
Date
Dept

: ISO-QA/QC/01/VIII/14
: 00
:
: QA / QC

Element ISO 9001 : 2000

BOILER
STAG

Dented Pipe(penyok) LP Heater


ELECTRICAL & I / C
No.

01/BLR/QA/QC/VIII/14

Date

Dented Pipe

CONTENT OF NON CONFORMANCE :

PROPOSED CORRECTIVE ACTION :

Proposed Completion date :

COMMENT :

Comment by : .
NCR CLOSED :
(Name & Sign)

Date of Comment : ..
YES

NO
Date :

PT. WIJAYA KARYA REKAYASA KONSTRUKSI

NON CONFORMANCE REPORT

Form No.
Rev
Date
Dept

: ISO-QA/QC/01/VIII/14
: 00
:
: QA / QC

Element ISO 9001 : 2000

BOILER
STAG

Dented Pipe(penyok) LP Heater


ELECTRICAL & I / C
No.

01/BLR/QA/QC/VIII/14

Date

Dented pipe

CONTENT OF NON CONFORMANCE :

PROPOSED CORRECTIVE ACTION :

Proposed Completion date :

COMMENT :

Comment by : .
NCR CLOSED :
(Name & Sign)

Date of Comment : ..
YES

NO
Date :

PT. WIJAYA KARYA REKAYASA KONSTRUKSI

NON CONFORMANCE REPORT

Form No.
Rev
Date
Dept

: ISO-QA/QC/01/VIII/14
: 00
:
: QA / QC

Element ISO 9001 : 2000

BOILER
STAG

Dented Pipe(penyok) LP Heater


ELECTRICAL & I / C
No.

01/BLR/QA/QC/VIII/14

Date

Dented Pipe

CONTENT OF NON CONFORMANCE :

PROPOSED CORRECTIVE ACTION :

Proposed Completion date :

COMMENT :

Comment by : .
NCR CLOSED :
(Name & Sign)

Date of Comment : ..
YES

NO
Date :