Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
PROYECTO
:"MEJORAMIENTO Y REHABILITACIN DEL CAMINO VECINAL DE USPACHACA CHAUPIMARCA, DISTRITO DE TAPUC, PROVINCIA DE DANIEL ALCIDES CARRIN, DEPARTAMENTO DE PASCO"
Modalidad de Ejecucion
CONTRATISTA
Residente de Obra
Supervisor de Obra
MONTO CONTRATO
ADICIONAL DE OBRA
DEDUCTIVO DE OBRA
MONTO DE CONTRATO VIGENTE
S/.
S/.
S/.
S/.
2,068,747.54
517,054.09
287,588.94
2,298,212.69
9/24/2014
120 Das Calend
32 Das Calend
2/22/2015
CRONOGRAMA REPROGRAMADO
ITEM
DESCRIPCION
UND
METRADO
P.UND
TOTAL
PRIMER MES
SEGUNDO MES
TERCER MES
CUARTO MES
QUINTO MES
Nov-14
VALORIZ
Dec-14
VALORIZ
Jan-15
VALORIZ
Feb-15
VALORIZ
EJECUTADO
PARTIDAS CONTRACTUALES
01
01.01
01.02
01.03
01.04
01.05
02
02.01
02.02
03
03.01
03.02
03.03
03.04
03.05
03.06
03.07
04
04.01
04.01.01
04.02
04.02.01
04.02.02
04.02.03
04.02.04
04.03
04.03.01
04.03.02
04.03.03
04.03.04
04.04
04.04.01
04.04.02
S/.
PROGRAMADO
1,656,456.67
OBRAS PROVISIONALES
CARTEL DE OBRA EN MADERA DE 3.60m x 2.40m
LETRINA PROVICIONAL DE OBRA
CAMPAMENTO DE OBRA
FLETE TERRESTRE
PLACA RECORDATORIA 0.60 x 0.80 - BRONCE
797.90
600.00
7,500.00
###
500.00
797.90
1,800.00
7,500.00
29,156.59
500.00
797.90
1,800.00
7,500.00
23,325.27
-
und
und
GLB
GLB
und
1.00
3.00
1.00
1.00
1.00
m3
m3
98.00
73.07
32.58
259.44
3,192.84
18,957.28
und
und
und
und
und
und
und
1.00
1.00
1.00
4.00
2.00
2.00
2.00
4,000.00
4,000.00
4,000.00
1,800.00
4,000.00
4,000.00
1,440.00
4,000.00
4,000.00
4,000.00
7,200.00
8,000.00
8,000.00
2,880.00
2,000.00
-
KM
12.79
505.57
6,466.24
4,651.24
1,815.00
m3
m3
m3
m3
24,997.00
2,063.50
721.70
32,188.00
4.82
8.14
15.93
5.28
120,485.54
16,796.89
11,496.68
169,952.64
78,315.60
13,431.00
9,197.34
-
28,920.00
3,365.89
2,299.34
45,791.33
m3
m3
m3
m3
8,632.58
8,632.58
8,632.58
11,222.35
3.09
3.90
2.01
6.77
26,674.67
33,667.06
17,351.49
75,975.31
m3
m3
11,510.10
11,510.10
0.69
5.16
7,941.97
59,392.12
2,915.66
-
2,915.66
500.00
DEMOLICION
EXCAVACION PARA ESTRUCTURAS MANUAL
DEMOLICION DE CONCRETO ARMADO
3,192.84
3,702.21
15,255.07
Y
Y
Y
Y
Y
Y
Y
DESMOVILIZACION
DESMOVILIZACION
DESMOVILIZACION
DESMOVILIZACION
DESMOVILIZACION
DESMOVILIZACION
DESMOVILIZACION
DE
DE
DE
DE
DE
DE
DE
TRACTOR ORUGA
CARGADOR FRONTAL
RETO EXCAVADORA
VOLQUETES
MOTONIVELADORA
RODILLO VIB. LISO AUTOPROPULSADO
CISTERNA
2,000.00
2,000.00
1,600.00
3,600.00
4,000.00
4,000.00
1,440.00
2,000.00
2,000.00
400.00
3,600.00
4,000.00
4,000.00
1,440.00
PAVIMENTO
TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO
EXPLANACIONES
EXCAVACION HASTA SUB RASANTE MATERIAL SUELTO CON TRACTOR 140-160
CORTE EN ROCA SUELTA
CORTE EN ROCA FIJA
CONFORMACION DE TERRAPLENES
MATERIAL PARA AFIRMADO
MATERIAL DE CANTERA
APILAMIENTO DE MATERIAL
CARGUIO DE MATERIAL
ZARANDEADO
ESCARIFICADO PAVIMENTO ANTIGUO
ESCARIFICADO
CONFORMACION DE TERRAPLEN
13,249.94
80,444.02
4,371.73
19,813.08
25,006.80
12,888.12
56,609.05
686.16
866.03
446.34
1,936.63
5,899.04
44,114.54
1,527.76
(0.00)
(0.00)
39,345.56
6,175.43
7,794.23
4,017.03
17,429.63
2,042.93
13,749.82
:"MEJORAMIENTO Y REHABILITACIN DEL CAMINO VECINAL DE USPACHACA CHAUPIMARCA, DISTRITO DE TAPUC, PROVINCIA DE DANIEL ALCIDES CARRIN, DEPARTAMENTO DE PASCO"
Modalidad de Ejecucion
CONTRATISTA
Residente de Obra
Supervisor de Obra
MONTO CONTRATO
ADICIONAL DE OBRA
DEDUCTIVO DE OBRA
MONTO DE CONTRATO VIGENTE
S/.
S/.
S/.
S/.
2,068,747.54
517,054.09
287,588.94
2,298,212.69
9/24/2014
120 Das Calend
32 Das Calend
2/22/2015
CRONOGRAMA REPROGRAMADO
ITEM
DESCRIPCION
UND
METRADO
P.UND
TOTAL
PRIMER MES
SEGUNDO MES
TERCER MES
CUARTO MES
QUINTO MES
Nov-14
VALORIZ
Dec-14
VALORIZ
Jan-15
VALORIZ
Feb-15
VALORIZ
EJECUTADO
04.05
04.05.01
04.05.02
04.05.03
04.05.04
04.05.05
05
05.01
05.01.01
05.01.01.01
05.01.02
05.01.02.01
05.01.02.02
05.01.02.03
05.01.02.04
05.01.03
05.01.03.01
05.01.03.02
05.01.04
05.01.04.01
05.01.04.02
05.01.04.03
05.01.05
05.01.05.01
05.01.06
05.01.06.01
05.02
05.02.01
05.02.01.01
05.02.02
05.02.02.01
05.02.02.02
05.02.02.03
05.02.02.04
05.02.03
05.02.03.01
05.02.03.02
05.02.04
05.02.04.01
05.02.04.02
05.02.04.03
05.02.05
05.02.05.01
SUPERFICIE DE RODADURA
CARGUIO DE MATERIAL
TRANSPORTE DE MATERIAL R=139.53 TRAMO Km 11+800 - 0+000
TRANSPORTE DE MATERIAL R=645.57 TRAMO Km 11+800 - 12+569
TRANSPORTE DE MATERIAL R=312.05 TRAMO Km 0+000 - 0+220
BASE GRANULAR E=0.15m REND.=2240 m2/DIA.
m3
m3
m3
m3
m2
8,632.58
7,965.00
519.08
148.50
57,550.50
2.01
26.63
5.77
5.77
2.11
17,351.49
212,107.95
2,995.09
856.85
121,431.56
PROGRAMADO
12,888.78
157,547.07
90,195.45
446.27
5,456.09
3,123.61
OBRAS DE ARTE
ALCANTARILLAS TMC D=24" (46 und)
TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO
MOVIMIENTO DE TIERRAS
EXCAVACION DE T./ NORMAL CON RETROEXCAVADORA
RELLENO Y COMPACTADO CON MATERIAL PROPIO
REFINE NIVEL. Y COMPACTACION
ELIMINACION DE MATERIAL CON VOLQUETE R=409
CONCRETO SIMPLE
ENCOFRADO Y DESENCOFRADO
MAMPOSTERIA DE PIEDRA F'C= 140 KG/CM2 + 30% DE PM.
CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO
CONCRETO F'C=210 KG/CM2
ACERO F'y=4200 KG/CM2
COLOCACION DE ALCANTARILLA
ALCANTARILLA TMC CIRCULAR DE 1.8 mm. D=24"
PINTURA
PINTURA EN CABEZALES DE ALCANTARILLA
m2
828.92
9.81
8,131.71
8,131.71
m3
m3
M2.
m3
812.26
201.20
521.64
763.83
4.28
16.59
3.56
3.05
3,476.47
3,337.91
1,857.04
2,329.68
1,889.41
1,814.12
1,857.04
1,266.12
m2
m3
27.60
48.99
28.55
275.30
787.98
13,486.95
m2
m3
kg
1,239.70
164.97
11,698.09
28.55
329.65
4.46
35,393.44
54,382.36
52,173.48
28,355.16
248.40
260.61
64,735.52
64,735.52
12.68
1,339.13
m
m2
105.61
1,133.42
1,088.47
759.69
21,543.83
33,102.73
17,126.40
453.65
435.32
303.87
236.39
4,046.09
13,058.77
19,930.64
-
790.84
1,348.99
6,691.92
m2
218.88
9.81
2,147.21
m3
m3
M2.
m3
205.09
19.65
158.76
231.79
4.28
16.59
3.56
3.05
877.79
325.99
565.19
706.96
m2
m3
5.40
8.50
28.55
275.30
154.17
2,340.05
m2
m3
kg
500.13
63.32
5,755.12
28.55
329.65
4.46
14,278.71
20,873.44
25,667.84
m2
20.66
12.68
261.97
4,016.44
49,104.79
2,995.09
856.85
28,112.50
(0.01)
(0.00)
(0.00)
551.59
9,440.87
0.00
0.00
1,339.13
2,147.21
877.79
325.99
565.19
706.96
154.17
2,340.05
14,278.71
20,873.44
25,667.84
261.97
:"MEJORAMIENTO Y REHABILITACIN DEL CAMINO VECINAL DE USPACHACA CHAUPIMARCA, DISTRITO DE TAPUC, PROVINCIA DE DANIEL ALCIDES CARRIN, DEPARTAMENTO DE PASCO"
Modalidad de Ejecucion
CONTRATISTA
Residente de Obra
Supervisor de Obra
MONTO CONTRATO
ADICIONAL DE OBRA
DEDUCTIVO DE OBRA
MONTO DE CONTRATO VIGENTE
S/.
S/.
S/.
S/.
2,068,747.54
517,054.09
287,588.94
2,298,212.69
9/24/2014
120 Das Calend
32 Das Calend
2/22/2015
CRONOGRAMA REPROGRAMADO
ITEM
DESCRIPCION
UND
METRADO
P.UND
TOTAL
PRIMER MES
SEGUNDO MES
TERCER MES
CUARTO MES
QUINTO MES
Nov-14
VALORIZ
Dec-14
VALORIZ
Jan-15
VALORIZ
Feb-15
VALORIZ
EJECUTADO
05.03
05.03.01
05.03.01.01
05.03.01.01.01
05.03.01.02
05.03.01.02.01
05.03.01.02.02
05.03.01.02.03
05.03.01.02.04
05.03.01.02.05
05.03.01.03
05.03.01.03.01
05.03.01.04
05.03.01.04.0
05.03.01.04.01.
1
05.03.01.04.01.
01
05.03.01.04.01.
02
05.03.01.04.0
03
05.03.01.04.02.
2
05.03.01.04.02.
01
05.03.01.04.02.
02
03
05.04
05.04.01
05.04.01.01
05.04.02
05.04.02.01
05.04.02.02
05.04.02.03
05.04.03
05.04.03.01
05.04.03.02
05.04.03.03
05.04.04
05.04.04.01
06
06.01
06.01.01
06.01.02
06.02
06.02.01
06.02.02
06.02.03
06.02.04
PROGRAMADO
MUROS DE CONTENCION
ESTRUCTURA
TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO
MOVIMIENTO DE TIERRAS
EXCAVACION DE T./ NORMAL CON RETROEXCAVADORA
REFINE NIVEL. Y COMPACTACION
RELLENO Y COMPACTADO CON MATERIAL PROPIO
MATERIAL GRANULAR
ELIMINACION DE MATERIAL CON VOLQUETE R=409
CONCRETO SIMPLE
SOLADO E=4" FC=100 Kg/cm2
CONCRETO ARMADO
ZAPATAS
CONCRETO F'C= 210 EN ZAPATA KG/CM2
ENCOFRADO Y DESENCOFRADO PARA ZAPATA
ACERO F'y=4200 KG/CM2
MURO
CONCRETO F'C= 210 KG/CM2
ENCOFRADO Y DESENCOFRADO
ACERO F'y=4200 KG/CM2
m2
324.80
9.81
3,186.29
2,966.54
2,098.23
338.91
4,131.74
3,708.52
919.54
(1,812.88)
(0.01)
0.00
(0.00)
(0.60)
(0.01)
(0.01)
(0.01)
(50.44)
0.03
3.35
(59.64)
(0.01)
m3
M2.
m3
m3
m3
1,672.58
324.80
849.70
167.50
1,028.60
4.28
3.56
16.59
75.53
3.05
7,158.64
1,156.29
14,096.52
12,651.28
3,137.23
m2
324.80
26.93
8,746.86
2,563.74
m3
m2
kg
129.92
97.28
5,756.23
327.58
22.03
4.46
42,559.19
2,143.08
25,672.79
12,474.25
649.66
7,536.37
m3
m2
kg
121.48
871.87
6,801.74
348.20
28.55
4.46
42,299.34
24,891.89
30,335.76
12,395.92
7,320.51
16,031.92
BADEN
TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO
MOVIMIENTO DE TIERRAS
EXCAVACION DE TERRENO SUELTO
REFINE Y NIVEL. Y COMPAC./PLANCHA COMPACTADORA
ELIMINACION DE MATERIAL CON VOLQUETE R=409
OBRAS DE CONCRETO SIMPLE
CONCRETO F'C= 175 KG/CM2
CONCRETO F'C= 175 KG/CM2 + 30% PM
ENCOFRADO Y DESENCOFRADO
OTROS
JUNTAS ASFALTICAS DE e=1" (DILATACION)
m2
135.00
9.81
1,324.35
m3
M2.
m3
32.40
123.00
40.50
37.56
3.82
3.05
1,216.94
469.86
123.53
m3
m3
m2
32.40
41.80
17.70
352.71
296.59
28.55
11,427.80
12,397.46
505.34
117.00
20.87
2,441.79
SEALIZACION
SEALES PREVENTIVAS
FABRICACION DE SEALES (0.60 X 0.60m.)
EXCAVACION Y COLOCACION
SEALES INFORMATIVAS
FABRICACION DE SEALES (0.60 X 0.90m.)
EXCAVACION Y COLOCACION
POSTES KILOMETRICOS
EXCAVACION Y COLOCACION DE POSTES KILOMETRICOS
und
und
26.00
26.00
235.46
93.47
6,121.96
2,430.22
und
und
und
und
2.00
2.00
14.00
14.00
158.41
93.47
25.00
136.73
316.82
186.94
350.00
1,914.22
2,032.63
5,060.42
817.38
9,964.78
8,943.36
2,217.70
6,183.13
30,084.95
1,543.86
18,136.39
29,900.07
17,631.02
14,303.85
1,324.35
1,216.94
469.86
123.53
11,427.80
12,397.46
505.34
2,441.79
6,121.96
2,430.22
316.82
186.94
350.00
1,914.22
:"MEJORAMIENTO Y REHABILITACIN DEL CAMINO VECINAL DE USPACHACA CHAUPIMARCA, DISTRITO DE TAPUC, PROVINCIA DE DANIEL ALCIDES CARRIN, DEPARTAMENTO DE PASCO"
Modalidad de Ejecucion
CONTRATISTA
Residente de Obra
Supervisor de Obra
MONTO CONTRATO
ADICIONAL DE OBRA
DEDUCTIVO DE OBRA
MONTO DE CONTRATO VIGENTE
S/.
S/.
S/.
S/.
2,068,747.54
517,054.09
287,588.94
2,298,212.69
9/24/2014
120 Das Calend
32 Das Calend
2/22/2015
CRONOGRAMA REPROGRAMADO
ITEM
DESCRIPCION
UND
METRADO
P.UND
TOTAL
PRIMER MES
SEGUNDO MES
TERCER MES
CUARTO MES
QUINTO MES
Nov-14
VALORIZ
Dec-14
VALORIZ
Jan-15
VALORIZ
Feb-15
VALORIZ
EJECUTADO
07
07.01
07.02
07.03
08
08.01
08.01.01
09
09.01
10
10.01
ENSAYOS
ENSAYO DENSIDAD DE CAMPO
ENSAYO PROCTOR Y CBR
ENSAYO RESISTENCIA COMPRESION CONCRETO
und
und
und
05.01
05.01.01
05.01.01.01
05.01.02
05.01.02.01
05.01.02.02
05.01.02.03
05.01.02.04
05.01.03
05.01.03.01
05.01.03.02
05.01.04
05.01.04.01
05.01.04.02
05.01.04.03
40.00
450.00
30.00
12,789.20
450.00
1,650.00
360.00
12,789.20
450.00
1,290.00
IMPACTO AMBIENTAL
CONSIDERACIONES AMBIENTALES
IMPACTO AMBIENTAL
GLB
1.00
und
1.00
KM
12.79
62,300.00
2,492.00
59,808.00
8,225.00
8,225.00
6,168.75
2,056.25
95.46
1,220.93
###
SEGURIDAD EN OBRA
SEGURIDAD EN OBRA
OTROS
LIMPIEZA GENERAL DE LA OBRA
ADICIONAL DE OBRA
05
319.73
1.00
55.00
PROGRAMADO
S/.
414,007.84
S/.
322,203.28
19.45%
19.45%
S/.
156,946.10
9.47%
28.93%
S/.
582,221.71
35.15%
64.07%
S/.
41,058.15
2.48%
66.55%
PROGRAMADO
OBRAS DE ARTE
ALCANTARILLAS TMC D=24"
TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO
MOVIMIENTO DE TIERRAS
EXCAVACION DE T./ NORMAL CON RETROEXCAVADORA
RELLENO Y COMPACTADO CON MATERIAL PROPIO
REFINE NIVEL. Y COMPACTACION
ELIMINACION DE MATERIAL CON VOLQUETE R=409
CONCRETO SIMPLE
ENCOFRADO Y DESENCOFRADO
MAMPOSTERIA DE PIEDRA F'C= 140 KG/CM2 + 30% DE PM.
CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO
CONCRETO F'C=210 KG/CM2
ACERO F'y=4200 KG/CM2
m2
m3
m3
M2.
m3
24.84
14.90
16.56
12.42
9.81
4.28
16.59
3.56
3.05
m2
m3
28.55
275.30
m2
m3
kg
28.55
329.65
4.46
106.32
247.26
58.95
37.88
-
1,220.93
S/.
554,027.43
33.45%
100.00%
106.32
247.26
58.95
37.88
:"MEJORAMIENTO Y REHABILITACIN DEL CAMINO VECINAL DE USPACHACA CHAUPIMARCA, DISTRITO DE TAPUC, PROVINCIA DE DANIEL ALCIDES CARRIN, DEPARTAMENTO DE PASCO"
Modalidad de Ejecucion
CONTRATISTA
Residente de Obra
Supervisor de Obra
MONTO CONTRATO
ADICIONAL DE OBRA
DEDUCTIVO DE OBRA
MONTO DE CONTRATO VIGENTE
S/.
S/.
S/.
S/.
2,068,747.54
517,054.09
287,588.94
2,298,212.69
9/24/2014
120 Das Calend
32 Das Calend
2/22/2015
CRONOGRAMA REPROGRAMADO
ITEM
DESCRIPCION
UND
METRADO
P.UND
TOTAL
PRIMER MES
SEGUNDO MES
TERCER MES
CUARTO MES
QUINTO MES
Nov-14
VALORIZ
Dec-14
VALORIZ
Jan-15
VALORIZ
Feb-15
VALORIZ
EJECUTADO
05.01.05
05.01.05.01
05.01.06
05.01.06.01
05.02
05.02.01
05.02.01.01
05.02.02
05.02.02.01
05.02.02.02
05.02.02.03
05.02.02.04
05.02.03
05.02.03.01
05.02.03.02
05.02.04
05.02.04.01
05.02.04.02
05.02.04.03
05.02.05
05.02.05.01
05.02.06
05.02.06.01
05.03
05.03.01
05.03.01.01
05.03.01.01.01
05.03.01.02
05.03.01.02.01
05.03.01.02.02
05.03.01.02.03
05.03.01.02.04
05.03.01.02.05
05.03.01.03
05.03.01.03.01
COLOCACION DE ALCANTARILLA
ALCANTARILLA TMC CIRCULAR DE 1.8 mm. D=24"
PINTURA
PINTURA EN CABEZALES DE ALCANTARILLA
m
m2
25.00
-
290.61
12.68
m2
162.18
9.81
m3
m3
M2.
m3
101.41
117.45
136.62
20.05
4.28
16.59
3.56
3.05
m2
m3
7.56
9.59
28.55
275.30
m2
m3
kg
291.15
34.19
2,356.07
28.55
329.65
4.46
52.20
405.11
m2
20.66
20.66
MUROS DE CONTENCION
ESTRUCTURA
TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO
MOVIMIENTO DE TIERRAS
EXCAVACION DE T./ NORMAL CON RETROEXCAVADORA
REFINE NIVEL. Y COMPACTACION
RELLENO Y COMPACTADO CON MATERIAL PROPIO
MATERIAL GRANULAR
ELIMINACION DE MATERIAL CON VOLQUETE R=409
CONCRETO SIMPLE
SOLADO E=4" FC=100 Kg/cm2
m2
259.60
9.81
m3
M2.
m3
1,904.47
259.60
1,031.96
4.28
3.56
16.59
m3
627.01
3.05
m2
259.60
26.93
7,265.25
-
PROGRAMADO
7,265.25
1,590.99
434.04
1,948.50
486.37
61.14
215.84
2,638.75
8,312.33
11,270.32
10,508.09
21,146.74
426.92
636.39
173.62
779.40
194.55
24.46
86.34
1,055.50
3,324.93
4,508.13
4,203.24
8,458.70
170.77
954.59
260.43
1,169.10
291.82
36.69
129.50
1,583.25
4,987.40
6,762.19
6,304.85
12,688.05
256.15
2,546.68
8,151.11
924.18
17,120.22
1,912.37
6,991.03
1,018.67
3,260.44
369.67
6,848.09
764.95
2,796.41
1,528.01
4,890.67
554.51
10,272.13
1,147.42
4,194.62
:"MEJORAMIENTO Y REHABILITACIN DEL CAMINO VECINAL DE USPACHACA CHAUPIMARCA, DISTRITO DE TAPUC, PROVINCIA DE DANIEL ALCIDES CARRIN, DEPARTAMENTO DE PASCO"
Modalidad de Ejecucion
CONTRATISTA
Residente de Obra
Supervisor de Obra
MONTO CONTRATO
ADICIONAL DE OBRA
DEDUCTIVO DE OBRA
MONTO DE CONTRATO VIGENTE
S/.
S/.
S/.
S/.
2,068,747.54
517,054.09
287,588.94
2,298,212.69
9/24/2014
120 Das Calend
32 Das Calend
2/22/2015
CRONOGRAMA REPROGRAMADO
ITEM
DESCRIPCION
UND
METRADO
P.UND
TOTAL
PRIMER MES
SEGUNDO MES
TERCER MES
CUARTO MES
QUINTO MES
Nov-14
VALORIZ
Dec-14
VALORIZ
Jan-15
VALORIZ
Feb-15
VALORIZ
EJECUTADO
05.03.01.04
05.03.01.04.01
05.03.01.04.01.0
05.03.01.04.01.0
05.03.01.04.01.0
05.03.01.04.02
05.03.01.04.02.0
05.03.01.04.02.0
05.03.01.04.02.0
CONCRETO ARMADO
ZAPATAS
CONCRETO F'C= 210 EN ZAPATA KG/CM2
ENCOFRADO Y DESENCOFRADO PARA ZAPATA
ACERO F'y=4200 KG/CM2
MURO
CONCRETO F'C= 210 KG/CM2
ENCOFRADO Y DESENCOFRADO
ACERO F'y=4200 KG/CM2
m3
m2
kg
168.32
103.76
13,718.17
327.58
22.03
4.46
m3
m2
kg
234.24
1,475.86
15,090.28
348.20
28.55
4.46
DEDUCTIVO DE OBRA
02
02.02
05
05.02
05.02.01
05.02.01.01
05.02.02
05.02.02.01
05.02.02.02
05.02.02.03
05.02.02.04
05.02.03
05.02.03.01
05.02.03.02
05.02.04
05.02.04.01
05.02.04.02
05.02.04.03
05.02.05
05.02.05.01
S/.
55,138.27
2,285.83
61,183.04
81,560.98
42,135.80
67,302.66
230,273.92
PROGRAMADO
22,055.31
914.33
24,473.21
32,624.39
16,854.32
26,921.07
S/.
170,232.53
41.12%
41.12%
33,082.96
1,371.50
36,709.82
48,936.59
25,281.48
40,381.60
S/.
243,775.31
58.88%
100.00%
PROGRAMADO
DEMOLICION
DEMOLICION DE CONCRETO ARMADO
m3
58.80
259.44
OBRAS DE ARTE
ALCANTARILLA DE CONCRETO (9 und)
TRABAJOS
PRELIMINARES
TRAZO Y REPLANTEO
m2
218.88
9.81
m3
m3
M2.
m3
205.09
19.65
158.76
231.79
4.28
16.59
3.56
3.05
m2
m3
5.40
8.50
28.55
275.30
m2
m3
kg
500.13
63.32
5,755.12
28.55
329.65
4.46
m2
20.66
12.68
MOVIMIENTO DE TIERRAS
EXCAVACION DE T./ NORMAL CON RETROEXCAVADORA
RELLENO Y COMPACTADO CON MATERIAL PROPIO
REFINE NIVEL. Y COMPACTACION
ELIMINACION DE MATERIAL CON VOLQUETE R=409
CONCRETO SIMPLE
ENCOFRADO Y DESENCOFRADO
MAMPOSTERIA DE PIEDRA F'C= 140 KG/CM2 + 30% DE PM.
CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO
CONCRETO F'C=210 KG/CM2
ACERO F'y=4200 KG/CM2
PINTURA
PINTURA EN CABEZALES DE ALCANTARILLA
15,255.07
(15,255.07)
-
2,147.21
877.79
325.99
565.19
706.96
154.17
2,340.05
14,278.71
20,873.44
25,667.84
261.97
(2,147.21)
(877.79)
(325.99)
(565.19)
(706.96)
(154.17)
(2,340.05)
(14,278.71)
(20,873.44)
(25,667.84)
(261.97)
-
:"MEJORAMIENTO Y REHABILITACIN DEL CAMINO VECINAL DE USPACHACA CHAUPIMARCA, DISTRITO DE TAPUC, PROVINCIA DE DANIEL ALCIDES CARRIN, DEPARTAMENTO DE PASCO"
Modalidad de Ejecucion
CONTRATISTA
Residente de Obra
Supervisor de Obra
MONTO CONTRATO
ADICIONAL DE OBRA
DEDUCTIVO DE OBRA
MONTO DE CONTRATO VIGENTE
S/.
S/.
S/.
S/.
2,068,747.54
517,054.09
287,588.94
2,298,212.69
9/24/2014
120 Das Calend
32 Das Calend
2/22/2015
CRONOGRAMA REPROGRAMADO
ITEM
DESCRIPCION
UND
METRADO
P.UND
TOTAL
PRIMER MES
SEGUNDO MES
TERCER MES
CUARTO MES
QUINTO MES
Nov-14
VALORIZ
Dec-14
VALORIZ
Jan-15
VALORIZ
Feb-15
VALORIZ
EJECUTADO
05.03
MUROS DE CONTENCION
05.03.01
05.03.01.01
ESTRUCTURA
TRABAJOS PRELIMINARES
05.03.01.01.01
05.03.01.02
TRAZO Y REPLANTEO
05.03.01.02.01
05.03.01.02.02
05.03.01.02.03
05.03.01.02.04
05.03.01.02.05
05.03.01.03
207.20
9.81
m3
M2.
m3
m3
m3
1,182.34
229.60
600.65
118.41
727.11
4.28
3.56
16.59
75.53
3.05
m2
229.60
26.93
m3
m2
kg
91.84
70.08
4,066.45
327.58
22.03
4.46
m3
m2
kg
85.87
617.55
3,207.14
348.20
28.55
4.46
CONCRETO SIMPLE
05.03.01.03.01
05.03.01.04
05.03.01.04.0
m2
MOVIMIENTO DE TIERRAS
CONCRETO ARMADO
ZAPATAS
05.03.01.04.01.0
05.03.01.04.01.0
05.03.01.04.01.0
05.03.01.04.0
MURO
05.03.01.04.02.0
05.03.01.04.02.0
05.03.01.04.02.0
COSTO DIRECTO
PORCENTAJE DE AVANCE
C.D.
GASTOS GENERALES
G.G.=
UTILIDADES
U.=
SUB TOTAL
S.T.= G.G. + U
I.G.V.
IGV
S.T. + I.G.V.
Factor de Relacin Fr = 0.90000
###
(2,032.63)
(5,060.42)
(817.38)
(9,964.78)
(8,943.36)
(2,217.70)
(6,183.13)
(30,084.95)
(1,543.86)
(18,136.39)
(29,900.07)
(17,631.02)
(14,303.85)
322,203.28
17.51%
156,946.10
8.53%
582,221.71
31.64%
211,290.68
11.48%
567,528.82
30.84%
176,636.25
30,927.65
15,064.94
55,886.31
20,281.38
54,475.97
147,215.24
25,776.26
12,555.69
46,577.74
16,903.25
45,402.30
378,907.19
184,566.73
684,685.76
248,475.31
667,407.09
68,203.30
33,222.02
123,243.44
44,725.55
120,133.27
###
447,110.49
217,788.75
807,929.20
293,200.86
787,540.36
###
402,399.45
196,009.88
727,136.28
263,880.77
708,786.32
###
18% del S.T.
PROGRAMADO
2,032.63
5,060.42
817.38
9,964.78
8,943.36
2,217.70
6,183.13
30,084.95
1,543.86
18,136.39
29,900.07
17,631.02
14,303.85
389,527.57
17.51%
17.51%
8.53%
26.04%
31.64%
57.68%
11.48%
69.16%
30.84%
100.00%
CURVA "S"
REAL
(al 22-feb-2015)
INCLUIDO LOS COSTOS ADICIONALES Y DEDUCIDOS
OBRA
:
:
:
:
###
###
###
### (en trmite)
100.00%
90.00%
86.07%
PROGRAMADO
CONTRACTUAL
80.00%
80.00%
76.29%
EJECUTADO REAL
70.00%
AL 80% DEL
PROGRAMADO
69.16%
60.00%
57.68%
57.68%
55.33%
50.00%
46.14%
40.00%
30.00%
26.04%
26.04%
20.00%
17.51%
17.51%
20.83%
14.01%
10.00%
0.00%
0.00%
-
1.23%
0.98%
41906
41943
41973
42004
42035
42057
80%
0.98%
###
###
###
###
###
:"MEJORAMIENTO Y REHABILITACIN DEL CAMINO VECINAL DE USPACHACA CHAUPIMARCA, DISTRITO DE TAPUC, PROVINCIA DE DANIEL ALCIDES CARRIN, DEPARTAMENTO DE PASCO"
Modalidad de Ejecucion
CONTRATISTA
Residente de Obra
Supervisor de Obra
MONTO CONTRATO
ADICIONAL DE OBRA
DEDUCTIVO DE OBRA
MONTO DE CONTRATO VIGENTE
S/.
S/.
S/.
S/.
2,068,747.54
517,054.09
287,588.94
2,298,212.69
9/24/2014
120 Das Calend
32 Das Calend
2/22/2015
CRONOGRAMA REPROGRAMADO
ITEM
DESCRIPCION
UND
METRADO
P.UND
TOTAL
PRIMER MES
SEGUNDO MES
TERCER MES
CUARTO MES
QUINTO MES
Nov-14
VALORIZ
Dec-14
VALORIZ
Jan-15
VALORIZ
Feb-15
VALORIZ
EJECUTADO
ADICIONAL DE OBRA
05
05.01
05.01.01
05.01.01.01
05.01.02
05.01.02.01
05.01.02.02
05.01.02.03
05.01.02.04
05.01.03
05.01.03.01
05.01.03.02
05.01.04
05.01.04.01
05.01.04.02
05.01.04.03
05.01.05
05.01.05.01
05.01.06
05.01.06.01
05.02
05.02.01
05.02.01.01
05.02.02
05.02.02.01
05.02.02.02
05.02.02.03
05.02.02.04
S/.
414,007.84
PROGRAMADO
PROGRAMADO
OBRAS DE ARTE
ALCANTARILLAS TMC D=24"
TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO
MOVIMIENTO DE TIERRAS
EXCAVACION DE T./ NORMAL CON RETROEXCAVADORA
RELLENO Y COMPACTADO CON MATERIAL PROPIO
REFINE NIVEL. Y COMPACTACION
ELIMINACION DE MATERIAL CON VOLQUETE R=409
CONCRETO SIMPLE
ENCOFRADO Y DESENCOFRADO
MAMPOSTERIA DE PIEDRA F'C= 140 KG/CM2 + 30% DE PM.
CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO
CONCRETO F'C=210 KG/CM2
ACERO F'y=4200 KG/CM2
COLOCACION DE ALCANTARILLA
ALCANTARILLA TMC CIRCULAR DE 1.8 mm. D=24"
PINTURA
PINTURA EN CABEZALES DE ALCANTARILLA
m2
m3
m3
M2.
m3
24.84
14.90
16.56
12.42
9.81
4.28
16.59
3.56
3.05
m2
m3
28.55
275.30
m2
m3
kg
28.55
329.65
4.46
m
m2
25.00
-
290.61
12.68
m2
162.18
9.81
m3
m3
M2.
m3
101.41
117.45
136.62
20.05
4.28
16.59
3.56
3.05
106.32
247.26
58.95
37.88
7,265.25
1,590.99
434.04
1,948.50
486.37
61.14
106.32
247.26
58.95
37.88
7,265.25
636.39
173.62
779.40
194.55
24.46
954.59
260.43
1,169.10
291.82
36.69
:"MEJORAMIENTO Y REHABILITACIN DEL CAMINO VECINAL DE USPACHACA CHAUPIMARCA, DISTRITO DE TAPUC, PROVINCIA DE DANIEL ALCIDES CARRIN, DEPARTAMENTO DE PASCO"
Modalidad de Ejecucion
CONTRATISTA
Residente de Obra
Supervisor de Obra
MONTO CONTRATO
ADICIONAL DE OBRA
DEDUCTIVO DE OBRA
MONTO DE CONTRATO VIGENTE
S/.
S/.
S/.
S/.
2,068,747.54
517,054.09
287,588.94
2,298,212.69
9/24/2014
120 Das Calend
32 Das Calend
2/22/2015
CRONOGRAMA REPROGRAMADO
ITEM
DESCRIPCION
UND
METRADO
P.UND
TOTAL
PRIMER MES
SEGUNDO MES
TERCER MES
CUARTO MES
Nov-14
Dec-14
Jan-15
Feb-15
VALORIZ
VALORIZ
VALORIZ
VALORIZ
VALORIZ
EJECUTADO
05.02.03
05.02.03.01
05.02.03.02
05.02.04
05.02.04.01
05.02.04.02
05.02.04.03
05.02.05
05.02.05.01
05.02.06
05.02.06.01
05.03
05.03.01
05.03.01.01
05.03.01.01.01
05.03.01.02
05.03.01.02.01
05.03.01.02.02
05.03.01.02.03
05.03.01.02.04
05.03.01.02.05
05.03.01.03
05.03.01.03.01
05.03.01.04
05.03.01.04.01
05.03.01.04.01.
05.03.01.04.01.
05.03.01.04.01.
CONCRETO SIMPLE
ENCOFRADO Y DESENCOFRADO
MAMPOSTERIA DE PIEDRA F'C= 140 KG/CM2 + 30% DE PM.
CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO
CONCRETO F'C=210 KG/CM2
ACERO F'y=4200 KG/CM2
COLOCACION DE ALCANTARILLA
ALCANTARILLA TMC CIRCULAR DE 1.8 mm. D=36"
PINTURA
PINTURA EN CABEZALES DE ALCANTARILLA
m2
m3
7.56
9.59
28.55
275.30
m2
m3
kg
291.15
34.19
2,356.07
28.55
329.65
4.46
52.20
405.11
m2
20.66
20.66
MUROS DE CONTENCION
ESTRUCTURA
TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO
MOVIMIENTO DE TIERRAS
EXCAVACION DE T./ NORMAL CON RETROEXCAVADORA
REFINE NIVEL. Y COMPACTACION
RELLENO Y COMPACTADO CON MATERIAL PROPIO
MATERIAL GRANULAR
ELIMINACION DE MATERIAL CON VOLQUETE R=409
CONCRETO SIMPLE
SOLADO E=4" FC=100 Kg/cm2
CONCRETO ARMADO
ZAPATAS
CONCRETO F'C= 210 EN ZAPATA KG/CM2
ENCOFRADO Y DESENCOFRADO PARA ZAPATA
ACERO F'y=4200 KG/CM2
m2
259.60
9.81
m3
M2.
m3
1,904.47
259.60
1,031.96
4.28
3.56
16.59
m3
627.01
3.05
m2
259.60
26.93
m3
m2
kg
168.32
103.76
13,718.17
327.58
22.03
4.46
QUINTO MES
PROGRAMADO
215.84
2,638.75
8,312.33
11,270.32
10,508.09
21,146.74
426.92
86.34
1,055.50
3,324.93
4,508.13
4,203.24
8,458.70
170.77
129.50
1,583.25
4,987.40
6,762.19
6,304.85
12,688.05
256.15
2,546.68
8,151.11
924.18
17,120.22
1,912.37
6,991.03
55,138.27
2,285.83
61,183.04
1,018.67
3,260.44
369.67
6,848.09
764.95
2,796.41
22,055.31
914.33
24,473.21
1,528.01
4,890.67
554.51
10,272.13
1,147.42
4,194.62
33,082.96
1,371.50
36,709.82
:"MEJORAMIENTO Y REHABILITACIN DEL CAMINO VECINAL DE USPACHACA CHAUPIMARCA, DISTRITO DE TAPUC, PROVINCIA DE DANIEL ALCIDES CARRIN, DEPARTAMENTO DE PASCO"
Modalidad de Ejecucion
CONTRATISTA
Residente de Obra
Supervisor de Obra
MONTO CONTRATO
ADICIONAL DE OBRA
DEDUCTIVO DE OBRA
MONTO DE CONTRATO VIGENTE
S/.
S/.
S/.
S/.
2,068,747.54
517,054.09
287,588.94
2,298,212.69
9/24/2014
120 Das Calend
32 Das Calend
2/22/2015
CRONOGRAMA REPROGRAMADO
ITEM
DESCRIPCION
UND
METRADO
P.UND
TOTAL
PRIMER MES
SEGUNDO MES
TERCER MES
CUARTO MES
QUINTO MES
Nov-14
VALORIZ
Dec-14
VALORIZ
Jan-15
VALORIZ
Feb-15
VALORIZ
EJECUTADO
05.03.01.04.02
05.03.01.04.02.
05.03.01.04.02.
05.03.01.04.02.
COSTO DIRECTO
MURO
CONCRETO F'C= 210 KG/CM2
ENCOFRADO Y DESENCOFRADO
ACERO F'y=4200 KG/CM2
C.D.
m3
m2
kg
234.24
1,475.86
15,090.28
348.20
28.55
4.46
81,560.98
42,135.80
67,302.66
###
GASTOS GENERALES
G.G.=
39,739.79
UTILIDADES
U.=
33,120.63
SUB TOTAL
S.T.= G.G. + U
I.G.V.
IGV
S.T. + I.G.V.
S/.
32,624.39
16,854.32
26,921.07
170,232.53
16,340.29
S/.
48,936.59
25,281.48
40,381.60
243,775.31
23,399.50
13,618.60
19,502.03
200,191.42
286,676.84
36,034.46
51,601.83
###
236,225.88
338,278.67
###
212,603.29
304,450.80
###
18% del S.T.
PROGRAMADO
87,636.29
41.12%
41.12%
58.88%
100.00%
:"MEJORAMIENTO Y REHABILITACIN DEL CAMINO VECINAL DE USPACHACA CHAUPIMARCA, DISTRITO DE TAPUC, PROVINCIA DE DANIEL ALCIDES CARRIN, DEPARTAMENTO DE PASCO"
Modalidad de Ejecucion
CONTRATISTA
Residente de Obra
Supervisor de Obra
MONTO CONTRATO
ADICIONAL DE OBRA
DEDUCTIVO DE OBRA
MONTO DE CONTRATO VIGENTE
S/.
S/.
S/.
S/.
2,068,747.54
517,054.09
287,588.94
2,298,212.69
9/24/2014
120 Das Calend
32 Das Calend
2/22/2015
33 Das Calend
DESCRIPCION
UND
METRADO
P.UND
TOTAL
PRIMER MES
SEGUNDO MES
TERCER MES
CUARTO MES
QUINTO MES
SEXTO MES
Nov-14
Dec-14
Jan-15
Feb-15
Mar-15
EJECUTADO
PARTIDAS CONTRACTUALES
01
01.01
01.02
01.03
01.04
01.05
02
02.01
02.02
03
03.01
03.02
03.03
03.04
03.05
03.06
03.07
04
04.01
04.01.01
04.02
04.02.01
04.02.02
04.02.03
04.02.04
04.03
04.03.01
04.03.02
04.03.03
04.03.04
S/.
3/27/2015
PROGRAMADO
1,656,456.67
OBRAS PROVISIONALES
CARTEL DE OBRA EN MADERA DE 3.60m x 2.40m
LETRINA PROVICIONAL DE OBRA
CAMPAMENTO DE OBRA
FLETE TERRESTRE
PLACA RECORDATORIA 0.60 x 0.80 - BRONCE
797.90
600.00
7,500.00
###
500.00
797.90
1,800.00
7,500.00
29,156.59
500.00
797.90
1,800.00
7,500.00
23,325.27
-
und
und
GLB
GLB
und
1.00
3.00
1.00
1.00
1.00
m3
m3
98.00
73.07
32.58
259.44
3,192.84
18,957.28
und
und
und
und
und
und
und
1.00
1.00
1.00
4.00
2.00
2.00
2.00
4,000.00
4,000.00
4,000.00
1,800.00
4,000.00
4,000.00
1,440.00
4,000.00
4,000.00
4,000.00
7,200.00
8,000.00
8,000.00
2,880.00
2,000.00
-
KM
12.79
505.57
6,466.24
4,651.24
1,815.00
m3
m3
m3
m3
24,997.00
2,063.50
721.70
32,188.00
4.82
8.14
15.93
5.28
120,485.54
16,796.89
11,496.68
169,952.64
78,315.60
13,431.00
9,197.34
-
28,920.00
3,365.89
2,299.34
45,791.33
m3
m3
m3
m3
8,632.58
8,632.58
8,632.58
11,222.35
3.09
3.90
2.01
6.77
26,674.67
33,667.06
17,351.49
75,975.31
2,915.66
-
2,915.66
500.00
DEMOLICION
EXCAVACION PARA ESTRUCTURAS MANUAL
DEMOLICION DE CONCRETO ARMADO
3,192.84
3,702.21
0.00
15,255.07
Y
Y
Y
Y
Y
Y
Y
DESMOVILIZACION
DESMOVILIZACION
DESMOVILIZACION
DESMOVILIZACION
DESMOVILIZACION
DESMOVILIZACION
DESMOVILIZACION
DE
DE
DE
DE
DE
DE
DE
TRACTOR ORUGA
CARGADOR FRONTAL
RETO EXCAVADORA
VOLQUETES
MOTONIVELADORA
RODILLO VIB. LISO AUTOPROPULSADO
CISTERNA
2,000.00
2,000.00
1,600.00
3,600.00
4,000.00
4,000.00
1,440.00
2,000.00
2,000.00
400.00
3,600.00
4,000.00
4,000.00
1,440.00
PAVIMENTO
TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO
EXPLANACIONES
EXCAVACION HASTA SUB RASANTE MATERIAL SUELTO CON TRACTOR 140-160
CORTE EN ROCA SUELTA
CORTE EN ROCA FIJA
CONFORMACION DE TERRAPLENES
MATERIAL PARA AFIRMADO
MATERIAL DE CANTERA
APILAMIENTO DE MATERIAL
CARGUIO DE MATERIAL
ZARANDEADO
13,249.94
80,444.02
19,813.08
25,006.80
12,888.12
56,609.05
8,743.46
6,861.59
8,660.26
4,463.37
19,366.26
34,973.83
(0.00)
(0.00)
0.00
(0.00)
:"MEJORAMIENTO Y REHABILITACIN DEL CAMINO VECINAL DE USPACHACA CHAUPIMARCA, DISTRITO DE TAPUC, PROVINCIA DE DANIEL ALCIDES CARRIN, DEPARTAMENTO DE PASCO"
Modalidad de Ejecucion
CONTRATISTA
Residente de Obra
Supervisor de Obra
MONTO CONTRATO
ADICIONAL DE OBRA
DEDUCTIVO DE OBRA
MONTO DE CONTRATO VIGENTE
S/.
S/.
S/.
S/.
2,068,747.54
517,054.09
287,588.94
2,298,212.69
9/24/2014
120 Das Calend
32 Das Calend
2/22/2015
33 Das Calend
DESCRIPCION
UND
METRADO
P.UND
TOTAL
PRIMER MES
SEGUNDO MES
TERCER MES
CUARTO MES
QUINTO MES
SEXTO MES
Nov-14
Dec-14
Jan-15
Feb-15
Mar-15
EJECUTADO
04.04
04.04.01
04.04.02
04.05
04.05.01
04.05.02
04.05.03
04.05.04
04.05.05
05
05.01
05.01.01
05.01.01.01
05.01.02
05.01.02.01
05.01.02.02
05.01.02.03
05.01.02.04
05.01.03
05.01.03.01
05.01.03.02
05.01.04
05.01.04.01
05.01.04.02
05.01.04.03
05.01.05
05.01.05.01
05.01.06
05.01.06.01
05.02
05.02.01
05.02.01.01
05.02.02
05.02.02.01
05.02.02.02
3/27/2015
m3
m3
11,510.10
11,510.10
0.69
5.16
7,941.97
59,392.12
5,899.04
44,114.54
m3
m3
m3
m3
m2
8,632.58
7,965.00
519.08
148.50
57,550.50
2.01
26.63
5.77
5.77
2.11
17,351.49
212,107.95
2,995.09
856.85
121,431.56
12,888.78
157,547.07
90,195.45
m2
828.92
9.81
8,131.71
8,131.71
m3
m3
M2.
m3
812.26
201.20
521.64
763.83
4.28
16.59
3.56
3.05
3,476.47
3,337.91
1,857.04
2,329.68
1,889.41
1,814.12
1,857.04
1,266.12
m2
m3
27.60
48.99
28.55
275.30
787.98
13,486.95
m2
m3
kg
1,239.70
164.97
11,698.09
28.55
329.65
4.46
35,393.44
54,382.36
52,173.48
28,355.16
248.40
260.61
64,735.52
64,735.52
m2
105.61
12.68
1,339.13
m2
218.88
9.81
m3
m3
205.09
19.65
4.28
16.59
PROGRAMADO
2,042.93
15,277.57
4,462.70
54,560.88
2,995.09
856.85
-
(0.00)
0.01
6,247.22
0.01
0.00
(0.00)
0.01
24,988.89
OBRAS DE ARTE
ALCANTARILLAS TMC D=24" (46 und)
TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO
MOVIMIENTO DE TIERRAS
EXCAVACION DE T./ NORMAL CON RETROEXCAVADORA
RELLENO Y COMPACTADO CON MATERIAL PROPIO
REFINE NIVEL. Y COMPACTACION
ELIMINACION DE MATERIAL CON VOLQUETE R=409
CONCRETO SIMPLE
ENCOFRADO Y DESENCOFRADO
MAMPOSTERIA DE PIEDRA F'C= 140 KG/CM2 + 30% DE PM.
CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO
CONCRETO F'C=210 KG/CM2
ACERO F'y=4200 KG/CM2
COLOCACION DE ALCANTARILLA
ALCANTARILLA TMC CIRCULAR DE 1.8 mm. D=24"
PINTURA
PINTURA EN CABEZALES DE ALCANTARILLA
1,133.42
1,088.47
759.69
21,543.83
33,102.73
17,126.40
13,058.77
19,930.64
-
2,147.21
877.79
325.99
453.42
435.32
303.89
790.84
1,348.99
6,691.92
-
0.22
(0.00)
(0.02)
472.79
8,092.17
315.19
5,394.78
0.00
(0.00)
0.00
1,339.13
2,147.21
877.79
325.99
:"MEJORAMIENTO Y REHABILITACIN DEL CAMINO VECINAL DE USPACHACA CHAUPIMARCA, DISTRITO DE TAPUC, PROVINCIA DE DANIEL ALCIDES CARRIN, DEPARTAMENTO DE PASCO"
Modalidad de Ejecucion
CONTRATISTA
Residente de Obra
Supervisor de Obra
MONTO CONTRATO
ADICIONAL DE OBRA
DEDUCTIVO DE OBRA
MONTO DE CONTRATO VIGENTE
S/.
S/.
S/.
S/.
2,068,747.54
517,054.09
287,588.94
2,298,212.69
9/24/2014
120 Das Calend
32 Das Calend
2/22/2015
33 Das Calend
DESCRIPCION
UND
METRADO
P.UND
TOTAL
PRIMER MES
SEGUNDO MES
TERCER MES
CUARTO MES
QUINTO MES
SEXTO MES
Nov-14
Dec-14
Jan-15
Feb-15
Mar-15
EJECUTADO
05.02.02.03
05.02.02.04
05.02.03
05.02.03.01
05.02.03.02
05.02.04
05.02.04.01
05.02.04.02
05.02.04.03
05.02.05
05.02.05.01
05.03
05.03.01
05.03.01.01
05.03.01.01.01
05.03.01.02
05.03.01.02.01
05.03.01.02.02
05.03.01.02.03
05.03.01.02.04
05.03.01.02.05
05.03.01.03
05.03.01.03.01
05.03.01.04
05.03.01.04.0
1
05.03.01.04.01.
01
05.03.01.04.01.
02
05.03.01.04.01.
03
05.03.01.04.0
2
05.03.01.04.02.
01
05.03.01.04.02.
02
05.03.01.04.02.
03
05.04
05.04.01
05.04.01.01
3/27/2015
M2.
m3
158.76
231.79
3.56
3.05
565.19
706.96
m2
m3
5.40
8.50
28.55
275.30
154.17
2,340.05
m2
m3
kg
500.13
63.32
5,755.12
28.55
329.65
4.46
14,278.71
20,873.44
25,667.84
m2
20.66
12.68
261.97
m2
324.80
9.81
3,186.29
2,966.54
m3
M2.
m3
m3
m3
1,672.58
324.80
849.70
167.50
1,028.60
4.28
3.56
16.59
75.53
3.05
7,158.64
1,156.29
14,096.52
12,651.28
3,137.23
2,098.23
338.91
4,131.74
3,708.52
919.54
m2
324.80
26.93
8,746.86
2,563.74
m3
m2
kg
129.92
97.28
5,756.23
327.58
22.03
4.46
42,559.19
2,143.08
25,672.79
12,474.25
649.66
7,536.37
m3
m2
kg
121.48
871.87
6,801.74
348.20
28.55
4.46
42,299.34
24,891.89
30,335.76
12,395.92
7,320.51
16,031.92
m2
135.00
9.81
1,324.35
PROGRAMADO
565.19
706.96
154.17
2,340.05
14,278.71
20,873.44
25,667.84
261.97
MUROS DE CONTENCION
ESTRUCTURA
TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO
MOVIMIENTO DE TIERRAS
EXCAVACION DE T./ NORMAL CON RETROEXCAVADORA
REFINE NIVEL. Y COMPACTACION
RELLENO Y COMPACTADO CON MATERIAL PROPIO
MATERIAL GRANULAR
ELIMINACION DE MATERIAL CON VOLQUETE R=409
CONCRETO SIMPLE
SOLADO E=4" FC=100 Kg/cm2
CONCRETO ARMADO
ZAPATAS
CONCRETO F'C= 210 EN ZAPATA KG/CM2
ENCOFRADO Y DESENCOFRADO PARA ZAPATA
ACERO F'y=4200 KG/CM2
MURO
CONCRETO F'C= 210 KG/CM2
ENCOFRADO Y DESENCOFRADO
ACERO F'y=4200 KG/CM2
(1,812.89)
(0.01)
(0.60)
(0.01)
(50.45)
0.02
3.34
(59.64)
(0.01)
2,032.64
5,060.42
817.38
9,964.78
8,943.36
2,217.70
6,183.12
30,084.94
1,543.87
18,136.40
29,900.08
17,631.02
14,303.85
BADEN
TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO
1,324.35
:"MEJORAMIENTO Y REHABILITACIN DEL CAMINO VECINAL DE USPACHACA CHAUPIMARCA, DISTRITO DE TAPUC, PROVINCIA DE DANIEL ALCIDES CARRIN, DEPARTAMENTO DE PASCO"
Modalidad de Ejecucion
CONTRATISTA
Residente de Obra
Supervisor de Obra
MONTO CONTRATO
ADICIONAL DE OBRA
DEDUCTIVO DE OBRA
MONTO DE CONTRATO VIGENTE
S/.
S/.
S/.
S/.
2,068,747.54
517,054.09
287,588.94
2,298,212.69
9/24/2014
120 Das Calend
32 Das Calend
2/22/2015
33 Das Calend
DESCRIPCION
UND
METRADO
P.UND
TOTAL
3/27/2015
PRIMER MES
SEGUNDO MES
TERCER MES
CUARTO MES
QUINTO MES
SEXTO MES
Nov-14
Dec-14
Jan-15
Feb-15
Mar-15
EJECUTADO
05.04.02
05.04.02.01
05.04.02.02
05.04.02.03
05.04.03
05.04.03.01
05.04.03.02
05.04.03.03
05.04.04
05.04.04.01
06
06.01
06.01.01
06.01.02
06.02
06.02.01
06.02.02
06.02.03
06.02.04
07
07.01
07.02
07.03
08
08.01
08.01.01
09
09.01
10
10.01
MOVIMIENTO DE TIERRAS
EXCAVACION DE TERRENO SUELTO
REFINE Y NIVEL. Y COMPAC./PLANCHA COMPACTADORA
ELIMINACION DE MATERIAL CON VOLQUETE R=409
OBRAS DE CONCRETO SIMPLE
CONCRETO F'C= 175 KG/CM2
CONCRETO F'C= 175 KG/CM2 + 30% PM
ENCOFRADO Y DESENCOFRADO
OTROS
JUNTAS ASFALTICAS DE e=1" (DILATACION)
m3
M2.
m3
32.40
123.00
40.50
37.56
3.82
3.05
1,216.94
469.86
123.53
m3
m3
m2
32.40
41.80
17.70
352.71
296.59
28.55
11,427.80
12,397.46
505.34
11,427.80
12,397.46
505.34
117.00
20.87
2,441.79
2,441.79
und
und
26.00
26.00
235.46
93.47
6,121.96
2,430.22
und
und
und
und
2.00
2.00
14.00
14.00
158.41
93.47
25.00
136.73
316.82
186.94
350.00
1,914.22
6,121.96
2,430.22
316.82
186.94
350.00
1,914.22
und
und
und
319.73
1.00
55.00
40.00
450.00
30.00
12,789.20
450.00
1,650.00
360.00
450.00
600.00
690.00
GLB
1.00
62,300.00
2,492.00
23,923.20
35,884.80
und
1.00
8,225.00
8,225.00
6,168.75
1,028.13
1,028.13
KM
12.79
95.46
1,220.93
PROGRAMADO
1,216.94
469.86
123.53
SEALIZACION
SEALES PREVENTIVAS
FABRICACION DE SEALES (0.60 X 0.60m.)
EXCAVACION Y COLOCACION
SEALES INFORMATIVAS
FABRICACION DE SEALES (0.60 X 0.90m.)
EXCAVACION Y COLOCACION
POSTES KILOMETRICOS
EXCAVACION Y COLOCACION DE POSTES KILOMETRICOS
ENSAYOS
ENSAYO DENSIDAD DE CAMPO
ENSAYO PROCTOR Y CBR
ENSAYO RESISTENCIA COMPRESION CONCRETO
12,789.20
IMPACTO AMBIENTAL
CONSIDERACIONES AMBIENTALES
IMPACTO AMBIENTAL
###
SEGURIDAD EN OBRA
SEGURIDAD EN OBRA
OTROS
LIMPIEZA GENERAL DE LA OBRA
S/.
322,203.28
19.45%
19.45%
S/.
156,946.10
9.47%
28.93%
S/.
582,221.71
35.15%
64.07%
S/.
134,546.69
8.12%
72.20%
S/.
55,483.77
3.35%
75.55%
S/.
1,220.93
405,055.11
24.45%
100.00%
:"MEJORAMIENTO Y REHABILITACIN DEL CAMINO VECINAL DE USPACHACA CHAUPIMARCA, DISTRITO DE TAPUC, PROVINCIA DE DANIEL ALCIDES CARRIN, DEPARTAMENTO DE PASCO"
Modalidad de Ejecucion
CONTRATISTA
Residente de Obra
Supervisor de Obra
MONTO CONTRATO
ADICIONAL DE OBRA
DEDUCTIVO DE OBRA
MONTO DE CONTRATO VIGENTE
S/.
S/.
S/.
S/.
2,068,747.54
517,054.09
287,588.94
2,298,212.69
9/24/2014
120 Das Calend
32 Das Calend
2/22/2015
33 Das Calend
DESCRIPCION
UND
METRADO
P.UND
TOTAL
PRIMER MES
SEGUNDO MES
TERCER MES
CUARTO MES
QUINTO MES
SEXTO MES
Nov-14
Dec-14
Jan-15
Feb-15
Mar-15
EJECUTADO
ADICIONAL DE OBRA
05
05.01
05.01.01
05.01.01.01
05.01.02
05.01.02.01
05.01.02.02
05.01.02.03
05.01.02.04
05.01.03
05.01.03.01
05.01.03.02
05.01.04
05.01.04.01
05.01.04.02
05.01.04.03
05.01.05
05.01.05.01
05.01.06
05.01.06.01
05.02
05.02.01
05.02.01.01
05.02.02
05.02.02.01
05.02.02.02
05.02.02.03
05.02.02.04
05.02.03
05.02.03.01
05.02.03.02
S/.
3/27/2015
PROGRAMADO
414,007.84
PROGRAMADO
OBRAS DE ARTE
ALCANTARILLAS TMC D=24"
TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO
MOVIMIENTO DE TIERRAS
EXCAVACION DE T./ NORMAL CON RETROEXCAVADORA
RELLENO Y COMPACTADO CON MATERIAL PROPIO
REFINE NIVEL. Y COMPACTACION
ELIMINACION DE MATERIAL CON VOLQUETE R=409
CONCRETO SIMPLE
ENCOFRADO Y DESENCOFRADO
MAMPOSTERIA DE PIEDRA F'C= 140 KG/CM2 + 30% DE PM.
CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO
CONCRETO F'C=210 KG/CM2
ACERO F'y=4200 KG/CM2
COLOCACION DE ALCANTARILLA
ALCANTARILLA TMC CIRCULAR DE 1.8 mm. D=24"
PINTURA
PINTURA EN CABEZALES DE ALCANTARILLA
m2
24.84
14.90
16.56
12.42
4.28
16.59
3.56
3.05
106.32
247.26
58.95
37.88
106.32
247.26
58.95
37.88
25.00
290.61
7,265.25
7,265.25
m2
162.18
9.81
1,590.99
m3
m3
M2.
m3
101.41
117.45
136.62
20.05
4.28
16.59
3.56
3.05
m2
m3
7.56
9.59
28.55
275.30
1,590.99
434.04
1,948.50
486.37
61.14
215.84
2,638.75
m3
m3
M2.
m3
m2
m3
m2
m3
kg
m
m2
434.04
1,948.50
486.37
61.14
86.34
1,055.50
129.50
1,583.25
:"MEJORAMIENTO Y REHABILITACIN DEL CAMINO VECINAL DE USPACHACA CHAUPIMARCA, DISTRITO DE TAPUC, PROVINCIA DE DANIEL ALCIDES CARRIN, DEPARTAMENTO DE PASCO"
Modalidad de Ejecucion
CONTRATISTA
Residente de Obra
Supervisor de Obra
MONTO CONTRATO
ADICIONAL DE OBRA
DEDUCTIVO DE OBRA
MONTO DE CONTRATO VIGENTE
S/.
S/.
S/.
S/.
2,068,747.54
517,054.09
287,588.94
2,298,212.69
9/24/2014
120 Das Calend
32 Das Calend
2/22/2015
33 Das Calend
DESCRIPCION
UND
METRADO
P.UND
TOTAL
3/27/2015
PRIMER MES
SEGUNDO MES
TERCER MES
CUARTO MES
QUINTO MES
SEXTO MES
Nov-14
Dec-14
Jan-15
Feb-15
Mar-15
EJECUTADO
05.02.04
05.02.04.01
05.02.04.02
05.02.04.03
05.02.05
05.02.05.01
05.02.06
05.02.06.01
05.03
05.03.01
05.03.01.01
05.03.01.01.01
05.03.01.02
05.03.01.02.01
05.03.01.02.02
05.03.01.02.03
05.03.01.02.04
05.03.01.02.05
05.03.01.03
05.03.01.03.01
05.03.01.04
05.03.01.04.01
05.03.01.04.01.
05.03.01.04.01.
05.03.01.04.01.
05.03.01.04.02
05.03.01.04.02.
05.03.01.04.02.
05.03.01.04.02.
CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO
CONCRETO F'C=210 KG/CM2
ACERO F'y=4200 KG/CM2
COLOCACION DE ALCANTARILLA
ALCANTARILLA TMC CIRCULAR DE 1.8 mm. D=36"
PINTURA
PINTURA EN CABEZALES DE ALCANTARILLA
m2
m3
kg
291.15
34.19
2,356.07
28.55
329.65
4.46
52.20
405.11
m2
20.66
20.66
MUROS DE CONTENCION
ESTRUCTURA
TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO
MOVIMIENTO DE TIERRAS
EXCAVACION DE T./ NORMAL CON RETROEXCAVADORA
REFINE NIVEL. Y COMPACTACION
RELLENO Y COMPACTADO CON MATERIAL PROPIO
MATERIAL GRANULAR
ELIMINACION DE MATERIAL CON VOLQUETE R=409
CONCRETO SIMPLE
SOLADO E=4" FC=100 Kg/cm2
CONCRETO ARMADO
ZAPATAS
CONCRETO F'C= 210 EN ZAPATA KG/CM2
ENCOFRADO Y DESENCOFRADO PARA ZAPATA
ACERO F'y=4200 KG/CM2
MURO
CONCRETO F'C= 210 KG/CM2
ENCOFRADO Y DESENCOFRADO
ACERO F'y=4200 KG/CM2
m2
259.60
9.81
m3
M2.
m3
1,904.47
259.60
1,031.96
4.28
3.56
16.59
m3
627.01
3.05
m2
259.60
26.93
m3
m2
kg
168.32
103.76
13,718.17
327.58
22.03
4.46
m3
m2
kg
234.24
1,475.86
15,090.28
348.20
28.55
4.46
PROGRAMADO
8,312.33
11,270.32
10,508.09
21,146.74
426.92
8,312.33
11,270.32
10,508.09
21,146.74
426.92
2,546.68
8,151.11
924.18
17,120.22
2,546.68
8,151.11
420.08
1,912.37
6,991.03
55,138.27
2,285.83
61,183.04
81,560.98
42,135.80
67,302.66
504.10
6,848.09
10,272.13
1,912.37
S/.
3,177.74
3,813.29
28,171.88
1,035.41
28,426.75
18,876.47
875.30
22,929.40
8,089.92
375.13
9,826.89
15,139.74
23,733.90
33,696.01
207,973.47
50.23%
50.23%
26,568.50
7,360.76
13,442.66
102,360.39
24.72%
74.96%
39,852.74
11,041.14
20,163.99
S/.
103,673.97
25.04%
100.00%
S/.
:"MEJORAMIENTO Y REHABILITACIN DEL CAMINO VECINAL DE USPACHACA CHAUPIMARCA, DISTRITO DE TAPUC, PROVINCIA DE DANIEL ALCIDES CARRIN, DEPARTAMENTO DE PASCO"
Modalidad de Ejecucion
CONTRATISTA
Residente de Obra
Supervisor de Obra
MONTO CONTRATO
ADICIONAL DE OBRA
DEDUCTIVO DE OBRA
MONTO DE CONTRATO VIGENTE
S/.
S/.
S/.
S/.
2,068,747.54
517,054.09
287,588.94
2,298,212.69
9/24/2014
120 Das Calend
32 Das Calend
2/22/2015
33 Das Calend
DESCRIPCION
UND
METRADO
P.UND
TOTAL
PRIMER MES
SEGUNDO MES
TERCER MES
CUARTO MES
QUINTO MES
SEXTO MES
Nov-14
Dec-14
Jan-15
Feb-15
Mar-15
EJECUTADO
DEDUCTIVO DE OBRA
02
02.02
05
05.02
05.02.01
05.02.01.01
05.02.02
05.02.02.01
05.02.02.02
05.02.02.03
05.02.02.04
05.02.03
05.02.03.01
05.02.03.02
05.02.04
05.02.04.01
05.02.04.02
05.02.04.03
05.02.05
05.02.05.01
05.03
05.03.01
05.03.01.01
05.03.01.01.01
05.03.01.02
05.03.01.02.01
05.03.01.02.02
05.03.01.02.03
05.03.01.02.04
05.03.01.02.05
05.03.01.03
05.03.01.03.01
S/.
230,273.92
3/27/2015
PROGRAMADO
PROGRAMADO
DEMOLICION
DEMOLICION DE CONCRETO ARMADO
m3
58.80
259.44
OBRAS DE ARTE
ALCANTARILLA DE CONCRETO (9 und)
TRABAJOS
PRELIMINARES
TRAZO Y REPLANTEO
m2
218.88
9.81
m3
m3
M2.
m3
205.09
19.65
158.76
231.79
4.28
16.59
3.56
3.05
m2
m3
5.40
8.50
28.55
275.30
m2
m3
kg
500.13
63.32
5,755.12
28.55
329.65
4.46
m2
20.66
12.68
MOVIMIENTO DE TIERRAS
EXCAVACION DE T./ NORMAL CON RETROEXCAVADORA
RELLENO Y COMPACTADO CON MATERIAL PROPIO
REFINE NIVEL. Y COMPACTACION
ELIMINACION DE MATERIAL CON VOLQUETE R=409
CONCRETO SIMPLE
ENCOFRADO Y DESENCOFRADO
MAMPOSTERIA DE PIEDRA F'C= 140 KG/CM2 + 30% DE PM.
CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO
CONCRETO F'C=210 KG/CM2
ACERO F'y=4200 KG/CM2
PINTURA
PINTURA EN CABEZALES DE ALCANTARILLA
MUROS DE CONTENCION
ESTRUCTURA
TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO
m2
207.20
9.81
m3
M2.
m3
m3
m3
1,182.34
229.60
600.65
118.41
727.11
4.28
3.56
16.59
75.53
3.05
m2
229.60
26.93
MOVIMIENTO DE TIERRAS
EXCAVACION DE T./ NORMAL CON RETROEXCAVADORA
REFINE NIVEL. Y COMPACTACION
RELLENO Y COMPACTADO CON MATERIAL PROPIO
MATERIAL GRANULAR
ELIMINACION DE MATERIAL CON VOLQUETE R=409
CONCRETO SIMPLE
SOLADO E=4" FC=100 Kg/cm2
15,255.07
2,147.21
877.79
325.99
565.19
706.96
154.17
2,340.05
14,278.71
20,873.44
25,667.84
261.97
2,032.63
5,060.42
817.38
9,964.78
8,943.36
2,217.70
6,183.13
(15,255.07)
(2,147.21)
(877.79)
(325.99)
(565.19)
(706.96)
(154.17)
(2,340.05)
(14,278.71)
(20,873.44)
(25,667.84)
(261.97)
(2,032.63)
(5,060.42)
(817.38)
(9,964.78)
(8,943.36)
(2,217.70)
(6,183.13)
:"MEJORAMIENTO Y REHABILITACIN DEL CAMINO VECINAL DE USPACHACA CHAUPIMARCA, DISTRITO DE TAPUC, PROVINCIA DE DANIEL ALCIDES CARRIN, DEPARTAMENTO DE PASCO"
Modalidad de Ejecucion
CONTRATISTA
Residente de Obra
Supervisor de Obra
MONTO CONTRATO
ADICIONAL DE OBRA
DEDUCTIVO DE OBRA
MONTO DE CONTRATO VIGENTE
S/.
S/.
S/.
S/.
2,068,747.54
517,054.09
287,588.94
2,298,212.69
9/24/2014
120 Das Calend
32 Das Calend
2/22/2015
33 Das Calend
DESCRIPCION
UND
METRADO
P.UND
TOTAL
PRIMER MES
SEGUNDO MES
TERCER MES
CUARTO MES
QUINTO MES
SEXTO MES
Nov-14
Dec-14
Jan-15
Feb-15
Mar-15
EJECUTADO
05.03.01.04
05.03.01.04.0
CONCRETO ARMADO
ZAPATAS
05.03.01.04.01.
05.03.01.04.01.
05.03.01.04.01.
05.03.01.04.0
MURO
05.03.01.04.02.
05.03.01.04.02.
05.03.01.04.02.
m3
m2
kg
91.84
70.08
4,066.45
327.58
22.03
4.46
m3
m2
kg
85.87
617.55
3,207.14
348.20
28.55
4.46
COSTO DIRECTO
PORCENTAJE DE AVANCE
C.D.
GASTOS GENERALES
G.G.=
UTILIDADES
U.=
SUB TOTAL
S.T.= G.G. + U
I.G.V.
IGV
S.T. + I.G.V.
VALORIZACION REAL
Avance Programado Parcial
Avance Programado Acumulado
(30,084.95)
(1,543.86)
(18,136.39)
(29,900.07)
(17,631.02)
(14,303.85)
322,203.28
17.51%
156,946.10
8.53%
582,221.71
31.64%
342,520.17
18.61%
157,844.16
8.58%
278,455.17
15.13%
176,636.25
30,927.65
15,064.94
55,886.31
32,877.83
15,151.15
26,728.37
147,215.24
25,776.26
12,555.69
46,577.74
27,401.61
12,627.53
22,276.41
378,907.19
184,566.73
684,685.76
402,799.61
185,622.84
327,459.95
68,203.30
33,222.02
123,243.44
72,503.92
33,412.11
58,942.79
###
447,110.49
217,788.75
807,929.20
475,303.52
219,034.95
386,402.74
###
402,399.45
196,009.88
727,136.28
427,773.16
197,131.45
347,762.46
###
Fr = 0.90000
PROGRAMADO
30,084.95
1,543.86
18,136.39
29,900.07
17,631.02
14,303.85
###
3/27/2015
389,527.57
17.51%
17.51%
8.53%
26.04%
31.64%
57.68%
18.61%
76.29%
8.58%
84.87%
15.13%
100.00%
Anexo N 01
Para la reprogramacin de la Curva "S" incluidos los Avances Programados del Contrato Principal y los Avances de la
Prestacin Adicional N 01 en conjunto.
OBRA
###
24-Sep-14
21-Jan-15
AMPLIACION N 01 :
ueva fecha de Vencimiento :
###
22-Feb-15
AMPLIACION N 02 :
ueva fecha de Vencimiento :
###
27-Mar-15
(Concentido)
(Concentido)
Meses
Sep - 2014
Oct - 2014
Nov - 2014
Dec - 2014
Jan - 2015
Feb - 2015
Mar - 2015
Totales:
Avance Programado
Del Contrato
Adicional
Deductivo
Principal
de Obra
de Obra
S/.
28,167.96 S/.
S/.
S/.
374,231.48 S/.
S/.
S/.
196,009.87 S/.
S/.
S/.
727,136.27 S/.
S/.
S/.
168,035.27 S/.
259,737.92 S/.
S/.
69,293.64 S/.
127,837.82 S/.
S/.
505,873.05 S/.
129,478.35 S/.
-287,588.94
S/.
2,068,747.54 S/.
517,054.09
S/.
-287,588.94 S/.
Avances Ejecutados
Del Contrato
Adicional
Principal
de Obra
S/.
28,167.96 S/.
S/.
374,231.49 S/.
S/.
196,009.88 S/.
S/.
727,136.28 S/.
S/.
168,035.28 S/.
259,737.93
S/.
57,428.41 S/.
167,395.27
Total Avance
Programado
S/.
28,167.96
S/.
374,231.48
S/.
196,009.87
S/.
727,136.27
S/.
427,773.19
S/.
197,131.46
S/.
347,762.46
Total Avance
Programado
S/.
28,167.96
S/.
374,231.49
S/.
196,009.88
S/.
727,136.28
S/.
427,773.21
S/.
224,823.68
S/.
-
2,298,212.69
CURVA "S"
REAL
:
:
:
:
###
###
###
### Concentido
100.00%
100.00%
90.00%
86.07%
84.87%
PROGRAMADO
CONTRACTUAL
80.00%
80.00%
76.29%
76.29%
EJECUTADO REAL
70.00%
AL 80% DEL
PROGRAMADO
67.89%
60.00%
57.68%
57.68%
61.03%
50.00%
46.14%
40.00%
30.00%
26.04%
26.04%
20.00%
17.51%
17.51%
20.83%
14.01%
10.00%
0.00%
0.00%
-
1.23%
0.98%
24-Sep-14
31-Oct-14
30-Nov-14
31-Dec-14
31-Jan-15
28-Feb-15
16-Mar-15
80%
0.98%
###
###
###
###
###
###