Homework 3
1
4
2
3
3
-
4
6
5
-
6
1
7
1
8
1
9
-
10
3
1
1225
2
325
1
875
1
500
2
1800
1
1500
1
435
1
2220
2
770
1
850
7775
8175
1152
5
6000
1030
0
9500
9565
8280
1133
0
8650
The operation runs 2 shift or 16 hours of intended working time (breaks and lunch are taken outside of this
16 hours. The machine was designed to produce 6000 parts in 8 hours.
a) What are the quality, performance, and availability rates and Overall Equipment efficiency? (4 pt)
b) How many orders (i.e. number of units) would not be filled during this 10 day period. (2 pts)
The manufacturing Engineer has suggested a project to replace the machine so increasing its production
rate to 7000 parts per shift. He is also stated that a new machine may not breakdown as often and produces
better quality parts. The lead time will be several months and cost $50,000 USD but he is confident that it
will solve the production problems.
c) What do you think? Is the additional capacity required? Is there anything you can start working on
today? (2 pts)