Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Guidance by:
Mr. IQBAL HAFIS KHAN
CERTIFICATE
This is certify that the project entitled. Estimate and Costing of Double
storey Building submitted by Brajesh verma, Rajesh Pawar, Ravi kumar
Pathak, Rohit Tiwari, Shaurabh Shukla, Shailendra Malviya, Shreyansh Jain,
Subhendra Gurjar, Vijay Sheel Mishra, Wasim Akram Ansari, Neeraj Jatav
and Neeraj Dahayat in partial fulfillments for the requirements for the
award of Bachelor of Technology
Degree in Civil Engineering at NRI Institute of Science and Technology,
Bhopal
( Rajeev Gandhi Technical University ) is an authentic work carried out by
them under my super vision and guidance.
To the best of my knowledge, the matter embodied in the thesis has not been
submitted to any other university / Institute for the awarded of any Degree.
DECLARATION
NAME:Brajesh Verma
0115ce101017
Rajesh Pawar
0115ce101041
Ravi kumar Pathak 0115ce101044
Rohit Tiwari
0115ce101045
Saurabh Shukla
0115ce101050
Shailendra malviya 0115ce101051
Shreyansh Jain
0115ce101053
Subhendra Gurjar 0115ce101054
Vijaya sheel Mishra 0115ce101061
Wasim Akram Ansari 0115ce101064
Neeraj Jatav
0115ce091038
Neeraj Dahayat
0115ce091037
ACKNOWLEDGEMENT
A
PROJECT REPORT
On
ESTIMATE & COSTING OF DOUBLE STOREY BUILDING
For
Department of Civil Engineering
By
BRAJESH VERMA
SHAILENDRA MALVIYA
ROHIT TIWARI
RAVI KUMAR PATHAK
SOURABH SHUKLA
SHUBHENDRA GURJAR
SHREYANSH JAIN
VIJAY SHEEL MISHRA
RAJESH PAWAR
WA
IN PARTIAL FULFILLMENT OF
GRADUATE PROGRAM IN CIVIL ENGINEERING
NRI INSTITUTE OF SCIENCE AND TECHNOLOGY
BHOPAL
(2010-2014)
INDEX
INTRODUCTION
IMPORTANCE OF ESTIMATION
TYPE OF ESTIMATION
DATA USES FOR ESTIMATION
METHOD OF ESTIMATION
ESTIMATION OF DOUBLE STORY BUILDING
ABSTRACT
TOTAL AMOUNT
INTRODUCTION
IMPORTANCE OF ESTIMATING
TYPES OF ESTIMATION
estimate
estimate
Revised estimate
Supplementary estimate
te
1. Building
(i) Per student for school and hostels,
Per classroom for school,
Per bad for hospitals,
Per site for cinema,
Per bay for factories etc.
(ii) On Plinth area basis (per sqm)
On cubic content basis (per cubic metre)
2. Roads and Highways Par KM length.
3. Irrigation channels Per KM basis depending upon the
capacity of channel or area of land
commanded.
4.Bridges and Culverts - per running meter of span,
depending upon the road way.
5.Sewerage project and water supply project per head
of population.
6.Over head water tank on the basis of capacity per
liter of tank ; etc.
of work.
Detail drawings, (plan, site plan, layout plan,
elevations, sectional elevations,cross section.
Calculation and design of various items such as Beam,
Slabs, Irrigation channels etc.
Schedule of rates followed and premium if any.
Analysis of rates for non schedule rate items.
Revised estimate
The Revised estimate should be
accompanied by all the papers as in case of
detailed estimate and also should include the
comparative statement, showing the variation
ineach item of work, its quantity rate and cost
original and revised, excess or saving and giving
the reasons of excess or saving in case of each
item.
Supplementary estimate
This estimate is a detailed estimate and is prepared when
additional works are required to supplement the original
works or when further development is required during the
programs of works.
When some additions are done in the original work, a
fresh detailed estimate is prepared to supplement the
original work. this estimate is called supplementary
estimate. It is also accompanied by all the papers is
required in the detail estimate.
PLOT AREA
SIZE
FOUNDATION EXCAVATION
HEIGHT OF BUILDING
PLAN
SECTION
ELEVATION
METHOD OF ESTIMATING
For the length of the first footing or first step of the brick
wall, subtract two offsets (2x6"=12") in foundation concrete
from the length of the trench or concrete.
For the second footing subtract from the length of the 1st
Footing two (2x2.25"= 4.5"), for 3rd footing subtract from
the length of the 2nd footing 2 offsets (4.5") and in this way
deal with the long walls up to the super-structure.
In the figure, the double crosshatched areas marked P,Q,R, & S come twice, while
ESTIMATE OF
DOUBLE STOREYED BULILDING
EXP.Prepare a detailed estimate of double storeyed residential
building consisting four two roomed quarters (two quarters
in each storey) from the showing drawing and general
specifications. the astimate of ground floor and first floor
should be prepared separately. The estimate of the Mumty
room (staircase room in the 2nd floor) should be included in
the estimate of the first floor. Assume suitable
rates.Workout also Plinth Area rate of the building.
GENERAL SPECIFICATIONS :Foundation & Plinth- Foundation,
concrete shall be of lime concrete with over burnt
brick ballast. Foundation and plinth masonry shall be
first class brickwork in lime mortar.
PLAN
SECTION
ELEVATION
ABSTRACT
Work
Total Cost in
2.Concrete
34485.15
3.Brickwork
54382.58
4.Wood work
31732.43
30235.25
12326.86
5644.02
2030.31
9.Misscellaneous items
2322.07
TOTAL AMOUNT
Total =
216718.64
Total
=251393.54
3% for contingencies
= 7541.80
2%for work charged establishment
= 5027.87
Total
Say
= 263963.21
= 263963.00