To

SDE Electical,
O/o GMTD,
Patiala.
No: JTO/AT/PA/1
Sub: Regarding A/T pending points of DG set of Ajnauda Kalan site..

Dated: 16.07.2014.

Acceptance Testing of DG set under Phase-VII for Ajnauda Kalan site of Patiala SSA has
been conducted as per T&D Circle Test schedule TD/SW/KVA-6322/TS dated 25.04.2008.The
following pending points have been observed :1. The plinth with approved plan has not been provided(Test item 1.1 of Test schedule).
2. Approved earth layout/distribution diagram has not been provided for location of earth check for
3.
4.
5.
6.
7.
8.
9.

E/A set.(Test item 3.1 of Test schedule).


Capacity of Battery is 88AH instead of 120AH( Test item 4.2 of Test schedule).
Temperature rise Test for the Alternator has not been provided(Test item 6.1 of Test schedule).
Insulation check has not been provided(Test item 7.1 and 7.2 of Test schedule).
Regulation Test on 110% over load condtion is out of specified limits (Test item 8 of Test schedule).
Provision of Fire Extinguishers/ Fire Buckets are not available on site(Test item 10 of Test schedule)
Fuel level indication couldnt be checked( Test item 11.1 of Test schedule).
Extension of alarms have not been provided(Test item 13.2 of Test schedule).

JTO A/T
Patiala
Copy to:- DET A/T Patiala

JTO A/T

Patiala