PROJECT

WATERFRONT INTEGRATED PROJECT

REPORT

DAILY PROGRESS REPORT (00:00 - 20:00)

DATE

12/1/2014

Bored Pile Progress


Boring
Commenced
Building 2
2-339 @ 01:40
2-44 @ 12:15
2-246 @ 17:30

Boring
Continued

Piles
Terminated

R/F Cage
Installation

2-28
2-194

2-387 @ 04:15

2-187 @ 01:30
2-25 @ 18:45

Building 5
5-64 @ 11:45

Total No of Piles
Concreted
Building 2

Concreting
2-187 @ 15:20

244/532
Building 5

5-110 @ 06:10

119/121

Building 4

Building 4
4-25

005/30

Defective Piles
Pile No Dia (mm)
2-320 1500
2-496 1500
2-316 1500

Deffect
Not vertically aligned
concrete hardened
Not vertically aligned

Rectification
Rectified
filled with grade 15 / additional piles will require
Rectified

2-468

1500

Not vertically aligned

Rectified

2-282

1500

Concrete hardened

casing has been removed before rectification works carry out

2-58

1200

error in setting out coordiantes (586mm


deviation)

2-240

1500

4-09

1200

5-48

1500

Rectified
ascending of R/F cage during concreting
Bottom plate of cleaning bucket stucked inside
borehole @ 150mm above the terminate level
concrete hardened and kelly bar stuck in concre filled with grade 15 / additional piles will require

Piling Machine Records


Machine No

BG 24-04 BG 24-05 BG 24-08 BG 28-06 BG 30-01 BG 28-09


5-64

Piles

2-28

2-44

2-194

M-06
2-246

Problesms & Delays


BG-06 under repair.
Boring work stopped in Pile No: 2-339 since M-08 was under service.
BG-04 under repair.
M-09 moved to Pile No: 2-28 after breakdown of BG-08.

Sheet Pile Progress


PRD-DH-608
PRD-IPD-100
PRD-DH-120

B#4
B#6
B#6

Pre-boring in Grid A10-A11


Moving to building #02
Under Repair (Rotary Repair)

Sewer Pump Station


Block work continued

Engineer's Site Office Building


No work carried out

M-07

M-08 M-09
2-339

2-28